This document is a Solicitation (SF 1442) for the fabrication and replacement of the North Fork Bridge for the Stehekin District of North Cascades National Park. The work consists of constructing a bridge abutment, fabricating a steel truss bridge, using a helicopter to transport the bridge to the site, constructing an approach ramp, and completing installation of decking and handrail.
This is a 100% small business set-aside with a firm-fixed-price contract to be awarded. The magnitude of construction is between $750,000 and $1,000,000. A site visit is planned for May 14, 2024, and proposals are due by June 3, 2024. The performance period is 270 days after notice to proceed. A 20% bid bond is required with the proposal, and payment and performance bonds at 100% of the contract price are required within 10 days of award. Subcontracting is limited to 85% of the contract value, excluding materials.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8324R0009_Amd_0002.pdf | ||
| Sol_140P8324R0009_Amd_0001.pdf | ||
| Attachment_F_Drawings_Revised_0001.pdf | ||
| Attachment_E_North_Fork_Bridge_Questions_and_Answers_0001.pdf | ||
| Attachment_A_Project_Specifications_DIV_I_II.pdf | ||
| Attachment_C__DOL_Wage_Determination.pdf | ||
| Form_4_-_Limitations_on_Subcontracting_compliance_worksheet.xlsx | XLSX spreadsheet | |
| Attachment_B__Drawings.pdf | ||
| Attachment_D_Forms_to_Return_with_Proposal.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION CALL
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040654851
NPS, PWR - OLYM MABO
600 E. Park Avenue
Port Angeles WA 98362-6757
PPY
Submit proposal electronically (by email) to michael_beatty@nps.gov. per instructions in
Section L
Michael Beatty 3608547219
1x 05/01/2024
140P8324R0009
INVITATION FOR BID
REQUEST FOR PROPOSAL
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Request for Proposals #140P8324R0009 is for the fabrication and replacement of the
North Fork Bridge for the Stehekin District of North Cascades NP.
THIS IS NOT A GOVERNMENT ESTIMATE" In accordance with FAR 36.204 the Magnitude of
Construction: between $750,000 and $1,000,000.
This project is subject to Construction Wage Rate Requirements
Set-Aside: This procurement is 100% set-aside for Small Business concerns in accordance with FAR part 19.5.
Site Visit: A site visit is planned for Tuesday May 14, 2024 at 08:00 am PDT.
Kindly RSVP to lacey_cunningham@nps.gov by noon on May 10, 2024.
Location: Prospective contractors will meet NPS staff at the Stehekin Landing at 8 am on Tuesday, May 14th, rain or shine. Everyone will be shuttled to the end of the
Stehekin Valley Road to begin the hike. It is a six-mile hike from the end of the road to the bridge site, and a six -mile hike back out to the vehicles at the end of the Stehekin Valley Road.
Continued ...
11. The Contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 270 calendar days and complete it within ________________ ________________ calendar days after receiving
See Section F
06/03/2024
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 12/2022)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES CODE AT
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, PWR - OLYM MABO
600 E. Park Avenue
Port Angeles WA 98362-6757
PPY
Michael Beatty
28. NEGOTIATED AGREEMENT 29. AWARD
and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations,certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
10 U.S.C. 3204(a) 41 U.S.C. 3304(a)
STANDARD FORM 1442 (REV. 12/2022) BACK
Continued...
and return
(Contractor is not required to sign this document.) Your offer on this
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 32
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
140P8324R0009
Type of Contract: a Firm-Fixed-Price contract will be awarded.
A Bid Guarantee is required with your proposal(IAW FAR clause 52.228-1 Bid Guarantee)
Instructions: To complete this SF1442, write the business name, address, UEI number, and point of contact in Block 14 and complete Blocks 15 through 20C, including acknowledging all amendments in Block 19. Complete Price Schedule and return with documents listed in Section L.
Additional instructions and a list of forms are provided in Section L. Blank price schedule and other required and optional documents are hyperlinked to the solicitation at SAM.gov.
Delivery: 270 Days After Notice to Proceed
Delivery Location Code: 0004506041
See Award
99999 US
Period of Performance: 07/04/2024 to 03/28/2025
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
RFP #140P8324R0009
Replace North Fork Bridge North Cascades NP
SECTION A: Solicitation/contract form (Standard Form 1442) (Pages 1-3)
SECTION B: Supplies or services and price/cost
Contract Price Schedule All work shall be performed in accordance with the attached specifications, drawings, and wage determination. Refer to Attachment 1 for line item definitions; all items are lump sum.
Unit Q Price/ Unit Subtotal
Line Item #1- Fabrication of Steel Truss Bridge and Delivery to Sling Load Location
EA 1
Line Item #2 – Demolition of Existing Bridge and Preparing Backhaul Loads
LS 1
Line Item #3 – Transportation and Delivery of Tools and Materials to Bridge Site
LS 1
Line Item #4 – Site Earthwork and Construction of Abutments
LS 1
Line Item #5 – Delivery of Bridge Superstructure to Site Via Helicopter
LS 1
Line Item #6 - Finish Assembly including approach ramps, decking, handrails
LS 1
Line Item #7 - Preparing Loads, Site Cleanup, and Backhauling Via Helicopter
LS 1
Total Line Items #1- #7 LS
52.252-2 FAR Clauses Incorporated By Reference (Feb 1998) This contract incorporates one or more Federal Acquisition Regulation (FAR) and Department of the Interior Acquisition Regulation (DIAR) clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at these addresses:
FAR - https://www.acquisition.gov/?q=browsefar DIAR - http://www.ecfr.gov/cgi-bin/text-idx?SID=e3fdab2f32e71039c0f3823dcff65823&tpl=/ecfrbrowse/Title48/48chapter14.tpl Clauses that are from the DIAR begin with “14”.
SECTION C: Description/Specifications
Project Location: Bridge Creek Trail, part of the Pacific Crest Trail, within the Stehekin District, North Cascades NP, Stehekin, WA; Chelan County.
The project is for the replacement of the North Fork Trail Bridge that collapsed under heavy snow load. The work of this contract consists of constructing a bridge abutment, fabricating a steel truss bridge, using a helicopter to transport the bridge to the site, constructing an approach ramp, and completing installation decking and handrail.
The contractor shall perform all work in accordance with the documents listed in Section J, which are attached and incorporated into this solicitation/contract.
SECTION D: Packaging and Marking (not used)
SECTION E: Inspection and Acceptance
52.246-12 Inspection of Construction. (AUG 1996) 52.246-13 Inspection-Dismantling, Demolition, or Removal of Improvements (Aug 1996) https://www.acquisition.gov/?q=browsefar
SECTION F: Deliveries or Performance
52.236-15 Schedules for Construction Contracts (APR 1984) 52.242-14 Suspension of Work. (APR 1984)
52.211-10 Commencement, Prosecution, and Completion of Work, Alternate I. (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the entire work within 270 calendar days after issuance of the NTP. The time stated for completion shall include final cleanup of the premises.
F.1 Period of Performance Dates and Seasonal Conditions Although NPS does not intend to suspend work during contract performance, seasonal weather conditions may restrict the contractor’s construction activities. The Contractor’s construction schedule should take into account historic weather patterns when planning the work sequence. Precipitation, both rain and snow, is heaviest November through January.
SECTION G: Contract Administration Data
1452.201-70 Authorities and Delegations (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum.
The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
1452.204-70 Release of Claims—Department of the Interior (JUL 1996) After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI-137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
G.1 Appointment of Contractor Representative / Superintendent Prior to commencement of work on this contract, the contractor shall provide to the Contracting Officer and COR the name and telephone number of at least one responsible individual who will serve to respond to operational problems and/or emergencies on a daily basis. The contractor agrees that notice to the designated representative shall constitute notice to the contractor and agrees to be bound by any commitments or representations made by the representative.
G.2 Electronic Invoicing and Payment Requirements - Internet Payment Platform (IPP) (Feb 2021) P Payment requests must be submitted electronically through the U.S. Department of the Treasury's Internet Payment Platform System (IPP; https://www.ipp.gov).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions- Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice (upload your business invoice as an attachment to the IPP invoice before you click “submit” in IPP):
1. Contractor’s standard business invoice,
2. Signed certification required by FAR clause 52.232-5,
3. Schedule of values for work being invoiced, and
4. If submitting a final invoice, also attach a signed copy of the Release of Claims form.
Contractor’s failure to attach the required documentation as specified above will result in the IPP invoice being rejected and cause a delay in payment.
The Contractor must use the IPP website for submitting requests for payment. The Contractor Government Business Point of Contact (as listed SAM) will receive enrollment instructions via email from the Federal Reserve Bank of St.
Louis (FRBSTL) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email IPPCustomerSupport@fiscal.treasury.gov or phone
(866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation
G.3 NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (Dec 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The
Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 10 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
1. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
2. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
3. All information provided should be reviewed for accuracy prior to submission.
4. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
5. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
6. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
G.4 NPS Contact Information Contracting Officer: Michael Beatty 360-854-7219 michael_beatty@nps.gov Contracting Officer’s Representative: Lacey Cunningham 360-390-2788 lacey_cunningham@nps.gov
SECTION H: SPECIAL CONTRACT REQUIREMENTS
H.1 Wage Determination U.S. Department of Labor General Wage Decision no. WA20240065 (Chelan County, WA), is incorporated into this solicitation/contract, as shown in Section J.
H.2 Progress Meetings The Contracting Officer will convene periodic meetings described in Attachment 1; the contractor will be required to attend in person or by phone. The Contracting Officer will provide specific details regarding the date, time, and location of the preconstruction conference, any need for attendance by subcontractors, and information regarding the items to be discussed.
H.3 Notice of Required Bonds A Bid Bond, using Standard Form 24, for 20% of the offered amount is required with proposal submission. The awardee shall furnish a payment bond, using Standard Form 25, and a performance bond, using Standard Form 25A, within 10 days after contract award. The penal sum of the payment and performance bonds shall be 100% of the contract price.
H.4 Interpretations of Contract: Notice of Ambiguities This written contract and any and all identified writings or documents incorporated by reference herein or physically attached hereto constitute the parties' complete agreement and no other prior or contemporaneous agreements either written or oral shall be considered to change, modify, or contradict it. Any ambiguity in the contract will not be https://www.cpars.csd.disa.mil/ https://www.cpars.gov/ strictly construed against the drafter of the contract language but shall be resolved by applying the most reasonable interpretation under the circumstances, giving full consideration to the intentions of the parties at the time of contracting.
The Contractor shall exercise due diligence to discover and to bring to the attention of the Contracting Officer at the earliest possible time any ambiguities, discrepancies, inconsistencies, or conflicts in or between the specifications and the applicable drawings or other documents incorporated. Failure to comply with such obligation may be deemed a waiver and release of any and all claims for extra costs or delay arising out of such ambiguities, discrepancies, inconsistencies, and conflicts.
H.5 Worker’s Compensation Insurance Requirements The Contractor shall maintain compensation insurance for employees engaged in the work complying with the worker's compensation laws of the State in which the work is to be performed and shall maintain liability insurance protecting the Contractor from claims because of bodily injury (including death) and property damage arising under this Contract.
H.6 Limitations on Subcontracting Requirements The prime contractor agrees to pay not more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count toward the 85 percent subcontract amount that cannot be exceeded. Refer to Paragraph (e)(4) of FAR clause 52.219-14, Limitations on Subcontracting. Prior to submitting the final invoice, the contractor shall complete and submit a report demonstrating compliance with the clause. Non-compliance with the limitations on subcontracting requirements will be noted in the CPARS evaluation (see G.3). The reporting form will be provided after contract award.
H.7 Archeological Findings Petroglyphs, artifacts, burial grounds or remains, structural features, ceremonial, domestic, and archeological objects of any nature, historic or prehistoric, found within the construction area, are the property of and will be removed only by the Government. Should Contractor's operations uncover or their employees find any archeological remains, Contractor shall suspend operations at the site of discovery; notify Contracting Officer immediately of the findings;
and continue operations in other areas. Included with the notification shall be a brief statement of the location and details of the findings. Should the temporary suspension of work at the site result in delays, or the discovery site require archeological studies resulting in delays or additional work for Contractor, s/he will be compensated by an equitable adjustment under the General Provisions of the Contract.
H.8 Conduct of Operations At all times the Contractor shall conduct their organization in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and with such appropriate regulations as the Superintendent may prescribe. The park compendium is available at Superintendent's Compendium – North Cascades (U.S. National Park Service) (nps.gov).
In addition, work on Saturdays, Sundays, Federal holidays or at night may be performed only with the prior consent of the Contracting Officer. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park except with prior approval of the Contracting Officer. Rowdy, disruptive behavior and/or sexual harassment will not be tolerated, and the offending individual(s) will be removed from the site. Amplified playing of music or talk programs is prohibited on site or in buildings.
SECTION I: Federal Acquisition Regulation (FAR) Contract Clauses
52.202-1 Definitions. (JUN 2020) 52.203-3 Gratuities. (APR 1984) 52.203-5 Covenant Against Contingent Fees. (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government. (JUN 2020) 52.203-7 Anti-Kickback Procedures. (JUN 2020) https://www.nps.gov/noca/learn/management/superintendent-compendium.htm https://www.nps.gov/noca/learn/management/superintendent-compendium.htm
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity. (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity. (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions. (JUN 2020) 52.203-17 Contractor Employee Whistleblower Rights and Requirement to Inform Employees of Whistleblower
Rights (JUN 2020) 52.203-19 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or
Statements (JAN 2017) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (MAY 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUN 2020) 52.204-13 System for Award Management Maintenance. (OCT 2018) 52.204-14 Service Contract Reporting Requirements (OCT 2016) 52.204-18 Commercial and Government Entity Code Maintenance (AUG 2020) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (NOV 2021) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky
Lab and Other Covered Entities (NOV 2021) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or
Equipment (NOV 2021) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or
Proposed for Debarment. (NOV 2021) 52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (NOV 2015) 52.215-2 Audit and Records—Negotiation (JUN 2020) 52.215-8 Order of Precedence - Uniform Contract Format. (OCT 1997) 52.215-17 Waiver of Facilities Capital Cost of Money (Oct 1997) [Will be included in the contract only if the prospective contractor does not propose facilities capital cost of money in its offer. Refer to provision 52.215- 16 in Section L.5.]
52.215-19 Notification of Ownership Changes (OCT 1997) 52.215-21 Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data—
Modifications (NOV 2021) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2020) 52.219-8 Utilization of Small Business Concerns. (FEB 2024) 52.219-14 Limitations on Subcontracting (OCT 2022) 52.219-28 Post-Award Small Business Program Rerepresentation. (MAR 2023) 52.222-3 Convict Labor. (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation. (MAR 2018) 52.222-6 Construction Wage Rate Requirements (AUG 2018) 52.222-7 Withholding of Funds. (MAY 2014) 52.222-8 Payrolls and Basic Records. (JUL 2021) 52.222-9 Apprentices and Trainees. (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. (MAY 2014)
52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of Segregated Facilities. (APR 2015) 52.222-26 Equal Opportunity. (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction. (APR 2015) 52.222-35 Equal Opportunity for Veterans. (JUN 2020) 52.222-36 Equal Opportunity for Workers with Disabilities. (JUN 2020) 52.222-37 Employment Reports on Veterans. (JUN 2020) 52.222-40 Notification of Employee Rights Under the National Labor Relations Act. (DEC 2010) 52.222-50 Combating Trafficking in Persons. (NOV 2021) 52.222-54 Employment Eligibility Verification. (MAY 2022) 52.222-55 Minimum Wages Under Executive Order 13658 (JAN 2022) 52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2022) 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (AUG 2018) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (JUN 2020) 52.225-13 Restrictions on Certain Foreign Purchases. (FEB 2021) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity--Construction Contracts. (DEC 2007) 52.228-2 Additional Bond Security. (OCT 1997) 52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-11 Individual Surety Pledges of Assets. (FEB 2021) (DEVIATION APR 2020) 52.228-12 Prospective Subcontractor Requests for Bonds. (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds - Construction. (JUN 2020) (DEVIATION APR 2020) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.229-12 Tax on Certain Foreign Procurements- Notice and Representation (FEB 2021) 52.232-5 Payments under Fixed-Price Construction Contracts. (JUN 2020) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts. (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes, Alt. 1. (MAY 2014, DEC 1991) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984)
52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-8 Other Contracts. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.236-17 Layout of Work. (APR 1984) 52.236-21 Specifications and Drawings for Construction. (FEB 1997) 52.236-26 Preconstruction Conference. (FEB 1995) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.244-6 Subcontracts for Commercial Products and Commercial Services. (FEB 2024) 52.246-21 Warranty of Construction. (MAR 1994) - Alternate I (APR 1984) 52.248-3 Value Engineering - Construction. (OCT 2022) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) - Alternate I (SEP 1996) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.252-6 Authorized Deviations in Clauses (NOV 2020) (b) Department of the Interior (48 CFR 14) 52.253-1 Computer Generated Forms. (JAN 1991) 1452.215-70 Examination of Records by the Department of the Interior (APR 1984)
52.211-3 Availability of Specifications Not Listed in the GSA Index of Federal Specifications, Standards and Commercial Item Descriptions. (June 1988)
Unless the Contract Documents include more stringent requirements, applicable construction industry standards have the same force and effect as if bound or copied directly into the Contract Documents to the extent referenced.
Such standards are made a part of the Contract Documents by reference. The specifications cited in this solicitation may be obtained from Industry Organizations listed in the Specifications Document at:
02 41 00 – Part 1, para 1.5 03 30 00 – Part 1, para 1.2 05 50 50 – Part 1, para 1.2 06 10 00 – Part 1, para 1.03 31 23 00 – Part 1, para 1.2 03 31 00 – Part 1, para 1.2
(End of clause)
52.219-14 Limitations on Subcontracting. (OCT 2022)
a) This clause does not apply to the unrestricted portion of a partial set-aside.
(b) Definition. Similarly situated entity, as used in this clause, means a first-tier subcontractor, including an independent contractor, that—
(1) Has the same small business program status as that which qualified the prime contractor for the award (e.g., for a small business set-aside contract, any small business concern, without regard to its socioeconomic status); and
(2) Is considered small for the size standard under the North American Industry Classification System (NAICS) code the prime contractor assigned to the subcontract.
(c) Applicability. This clause applies only to—
(1) Contracts that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(2) Part or parts of a multiple-award contract that have been set aside for any of the small business concerns identified in 19.000(a)(3);
(3) Contracts that have been awarded on a sole-source basis in accordance with subparts 19.8, 19.13, 19.14, and 19.15;
(4) Orders expected to exceed the simplified acquisition threshold and that are—
(i) Set aside for small business concerns under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to small business concerns under multiple-award contracts as described in 19.504(c)(1)(ii);
(5) Orders, regardless of dollar value, that are—
(i) Set aside in accordance with subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 8.405-5 and 16.505(b)(2)(i)(F); or
(ii) Issued directly to concerns that qualify for the programs described in subparts 19.8, 19.13, 19.14, or 19.15 under multiple-award contracts, as described in 19.504(c)(1)(ii); and
(6) Contracts using the HUBZone price evaluation preference to award to a HUBZone small business concern unless the concern waived the evaluation preference.
(d) Independent contractors. An independent contractor shall be considered a subcontractor.
(e) Limitations on subcontracting. By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—
(1) Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract;
(2) Supplies (other than procurement from a nonmanufacturer of such supplies), it will not pay more than 50 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both supplies and services, the 50 percent limitation shall apply only to the supply portion of the contract;
(3) General construction, it will not pay more than 85 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 85 percent subcontract amount that cannot be exceeded; or
(4) Construction by special trade contractors, it will not pay more than 75 percent of the amount paid by the Government for contract performance, excluding the cost of materials, to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 75 percent subcontract amount that cannot be exceeded.
(f) The Contractor shall comply with the limitations on subcontracting as follows:
(1) For contracts, in accordance with paragraphs (c)(1), (2), (3) and (6) of this clause— [Contracting Officer check as appropriate.] X By the end of the base term of the contract and then by the end of each subsequent option period; or
□ By the end of the performance period for each order issued under the contract.
(2) For orders, in accordance with paragraphs (c)(4) and (5) of this clause, by the end of the performance period for the order.
(g) A joint venture agrees that, in the performance of the contract, the applicable percentage specified in paragraph
(e) of this clause will be performed by the aggregate of the joint venture participants.
(1) In a joint venture comprised of a small business protégé and its mentor approved by the Small Business Administration, the small business protégé shall perform at least 40 percent of the work performed by the joint venture. Work performed by the small business protégé in the joint venture must be more than administrative functions.
(2) In an 8(a) joint venture, the 8(a) participant(s) shall perform at least 40 percent of the work performed by the joint venture. Work performed by the 8(a) participants in the joint venture must be more than administrative functions.
52.225-9 Buy American - Construction Materials. (OCT 2022)
(a) Definitions. As used in this clause— Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is–
(i) A commercial product (as defined in paragraph (1) of the definition of “commercial product” at
Federal Acquisition Regulation (FAR) 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.
"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means—
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Critical component means a component that is mined, produced, or manufactured in the United States and deemed critical to the U.S. supply chain. The list of critical components is at FAR 25.105.
Critical item means a domestic construction material or domestic end product that is deemed critical to U.S.
supply chain resiliency. The list of critical items is at FAR 25.105.
Domestic construction material means—
(1) For construction material that does not consist wholly or predominantly of iron or steel or a combination of both-
(i) An unmanufactured construction material mined or produced in the United States; or
(ii) A construction material manufactured in the United States, if– (A)The cost of its components mined, produced, or manufactured in the United States exceeds
60 percent of the cost of all its components, except that the percentage will be 65 percent for items delivered in calendar years 2024 through 2028 and 75 percent for items delivered starting in calendar year 2029.
Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic. Components of unknown origin are treated as foreign; or
(B) The construction material is a COTS item; or
(2) For construction material that consists wholly or predominantly of iron or steel or a combination of both, a construction material manufactured in the United States if the cost of foreign iron and steel constitutes less than 5 percent of the cost of all components used in such construction material. The cost of foreign iron and steel includes but is not limited to the cost of foreign iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the construction material and a good faith estimate of the cost of all foreign iron or steel components excluding COTS fasteners. Iron or steel components of unknown origin are treated as foreign. If the construction material contains multiple components, the cost of all the materials used in such construction material is calculated in accordance with the definition of "cost of components".
Fastener means a hardware device that mechanically joins or affixes two or more objects together. Examples of fasteners are nuts, bolts, pins, rivets, nails, clips, and screws.
Foreign construction material means a construction material other than a domestic construction material.
Foreign iron and steel means iron or steel products not produced in the United States. Produced in the United
States means that all manufacturing processes of the iron or steel must take place in the United States, from the initial melting stage through the application of coatings, except metallurgical processes involving refinement of steel additives. The origin of the elements of the iron or steel is not relevant to the determination of whether it is domestic or foreign.
Predominantly of iron or steel or a combination of both means that the cost of the iron and steel content exceeds 50 percent of the total cost of all its components. The cost of iron and steel is the cost of the iron or steel mill products (such as bar, billet, slab, wire, plate, or sheet), castings, or forgings utilized in the manufacture of the product and a good faith estimate of the cost of iron or steel components excluding COTS fasteners.
Steel means an alloy that includes at least 50 percent iron, between 0.02 and 2 percent carbon, and may include other elements.
"United States" means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference. (1) This clause implements 41 U.S.C.chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the domestic content test of the Buy American statute is waived for construction material that is a COTS item, except that for construction material that consists wholly or predominantly of iron or steel or a combination of both, the domestic content test is applied only to the iron and steel content of the construction materials, excluding COTS fasteners. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial product or to the construction materials or components listed by the Government as follows:
________________________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that- (i)The cost of domestic construction material would be unreasonable.
(A) For domestic construction material that is not a critical item or does not contain critical components.
(1)The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent;
(2)For construction material that is not a COTS item and does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that is manufactured in the United States and does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest offer of foreign construction material that exceeds 55 percent domestic content as a domestic offer and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(A)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(A)(2) of this clause will no longer apply as of January 1, 2030.
(B) For domestic construction material that is a critical item or contains critical components.
(1)The cost of a particular domestic construction material that is a critical item or contains critical components, subject to the requirements of the Buy American statute, is unreasonable when the cost of such material exceeds the cost of foreign material by more than 20 percent plus the additional preference factor identified for the critical item or construction material containing critical components listed at FAR 25.105.
(2)For construction material that does not consist wholly or predominantly of iron or steel or a combination of both, if the cost of a particular domestic construction material is determined to be unreasonable or there is no domestic offer received, and the low offer is for foreign construction material that does not exceed 55 percent domestic content, the Contracting Officer will treat the lowest foreign offer of construction material that is manufactured in the United States and exceeds 55 percent domestic content as a domestic offer, and determine whether the cost of that offer is unreasonable by applying the evaluation factor listed in paragraph (b)(3)(i)(B)(1) of this clause.
(3)The procedures in paragraph (b)(3)(i)(B)(2) of this clause will no longer apply as of January 1, 2030.
(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American statute. (1) (i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including-
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable…