File Type Posted
RFI.pdf PDF
NCIC form.pdf PDF
2D8G - Statement of Work (Security Upgrade)_1.pdf PDF
davis bacon.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BBR021Q00000011 Page 1 of 36

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15BBR021Q00000011

SEALED BID (IFB)

NEGOTIATED (RFP)

2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

1 36

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

2D8G

CODE BBRO

Federal Bureau of Prisons MDC Brooklyn 80 29th Street Brooklyn, NY 11232

7. ISSUED BY

Federal Bureau of Prisons MDC Brooklyn 80 29th Street

8. ADDRESS OFFER TO

9. FOR INFORMATION CALL: a. NAME b. TELEPHONE NUMBER (Include area code)(NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

SECURITY UPGRADE PROJECT. Please refer to the Statement of Work for details.

The contractor receiving the award shall provide all materials, labor, and equipment to complete the work outlined in the Statement of Work in accordance with the requirements of solicitation 15BBR021Q00000011.

**INCLUDE THE FOLLOWING INFORMATION WHEN SUBMITTING***

DUNS NUMBER: ____________________

TIN NUMBER: _______________________

CAGE CODE: _______________________

EMAIL:_____________________________

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 120 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

12:00a.

07/12/2021

b. An offer guarantee is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

60d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

15BBR021Q00000011 Page 2 of 36

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

X 29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

15BBR021Q00000011 Page 3 of 36

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (June 1996) 52.21-603-70 Contracting Officer's Representative (COR) (June 2012) 52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)

52.27-103-72 DOJ CONTRACTOR RESIDENCY REQUIREMENT BUREAU OF PRISONS (JUNE

2004) FAO-0001 Bonds FAO-0002 Magnitude FAO-0003 Required Insurance FAO-0004 Pre-Construction Conference FAO-0005 Submittals FAO-0006 Contractor Use of Premises FAO-0007 Payment Services FAO-0008 Request for Final Inspection FAO-0009 Contract Security (Program Statement 3000.03 Human Resource Management Manual) FAO-0012 Progress Meetings FAO-0014 Contract Closeout Procedures (for construction contracts $150,000 or less)

4 Contract Clauses 52.203-12 Limitation On Payments To Influence Certain Federal Transactions (Oct 2010) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017) 52.204-2 Alt I Security Requirements (Aug 1996) - Alternate I (Apr 1984) 52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Oct 2018) 52.204-13 System for Award Management Maintenance (Oct 2018) 52.204-18 Commercial and Government Entity Code Maintenance (Jul 2016) 52.204-19 Incorporation by Reference of Representations and Certifications (Dec 2014) 52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018) 52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (Aug 2019) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (Oct 2015) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015) 52.219-6 Notice of Total Small Business Set-Aside (Mar 2020) 52.219-14 Limitations on Subcontracting (Mar 2020) 52.222-8 Payrolls and Basic Records (Aug 2018) 52.222-9 Apprentices and Trainees (July 2005) 52.222-10 Compliance with Copeland Act Requirements (Feb 1988) 52.222-11 Subcontracts (Labor Standards) (May 2014) 52.222-12 Contract Termination - Debarment (May 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014) 52.222-14 Disputes Concerning Labor Standards (Feb 1988) 52.222-15 Certification of Eligibility (May 2014) 52.222-21 Prohibition of Segregated Facilities (Apr 2015) 52.222-26 Equal Opportunity (Sept 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (Apr 2015) 52.222-35 Equal Opportunity for Veterans (Oct 2015) 52.222-36 Equal Opportunity for Workers with Disabilities (Jul 2014) 52.222-37 Employment Reports on Veterans (Feb 2016) 52.222-50 Combating Trafficking in Persons (Jan 2019) 52.222-55 Minimum Wages Under Executive Order 13658 (Dec 2015)

15BBR021Q00000011 Page 4 of 36

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (Aug 2011) 52.227-4 Patent Indemnity-Construction Contracts (Dec 2007) 52.225-13 Restrictions on Certain Foreign Purchases (June 2008) 52.228-2 Additional Bond Security (Oct 1997) 52.228-11 Pledges of Assets (Aug 2018) 52.232-23 Assignment of Claims (May 2014) 52.232-5 Payments under Fixed-Price Construction Contracts (May 2014) 52.232-27 Prompt Payment for Construction Contracts (Jan 2017) 52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct 2018) 52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Dec 2013) 52.233-1 Disputes (May 2014) 52.233-3 Protest after Award (Aug 1996) 52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004) 52.236-2 Differing Site Conditions (Apr 1984) 52.236-5 Material and Workmanship (Apr 1984) 52.236-7 Permits and Responsibilities (Nov 1991) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984) 52.236-12 Cleaning Up (Apr 1984) 52.236-13 Accident Prevention (Nov 1991) 52.236-26 Preconstruction Conference (Feb 1995) 52.242-14 Suspension of Work (Apr 1984) 52.243-5 Changes and Changed Conditions (Apr 1984) 52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984) 52.249-10 Default (Fixed-Price Construction) (Apr 1984) 52.204-21 Basic Safeguarding of Covered Contractor Information Systems (June 2016) 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) 52.211-12 Liquidated Damages-Construction (Sept 2000) 52.211-13 Time Extensions (Sept 2000) 52.225-9 Buy American-Construction Materials (May 2014) 52.228-5 Insurance-Work on a Government Installation (Jan 1997) 52.228-15 Performance and Payment Bonds - Construction (Oct 2010) FAO-0015 Changes FAO-0016 Equitable Adjustments: Waiver and Release of Claims FAO-0019 Contractor's Signature

5 Attachments 6 Solicitation Provisions

52.252-1 Solicitation Provisions Incorporated by Reference (Feb 1998) 52.216-1 Type of Contract (Apr 1984) 52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work (May 2014) 52.225-10 Notice of Buy American Requirement-Construction Materials (May 2014) 52.236-27 Site Visit (Construction) (Feb 1995) 52.204-7 System for Award Management (Oct 2018) 52.204-16 Commercial and Government Entity Code Reporting (Jul 2016) 52.204-22 Alternative Line Item Proposal (Jan 2017)

7 Representations and Certifications 52.225-25 Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran--Representation and Certifications (Aug 2018) 52.204-8 Annual Representations and Certifications (Mar 2020) 52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (Dec 2019) FAO-0020 List of References and Bank Information

15BBR021Q00000011 Page 5 of 36

Section 2 - Commodity or Services Schedule

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 The contractor shall provide all labor, materials and equipment necessary to construct and upgrade specific security elements to include (36) K4 rated bollards around (3) perimeter officer's booths to provide protection from vehicular attacks, upgrade the

(2) vehicle gates and (1) pedestrian gate in the staff parking lot so that they can be completely secured against unauthorized vehicular or pedestrian entrance which includes filling the gaps above/below gates and adding razor wire to the top of the fencing gates. The contractor is also responsible for installing razor wire along the 30th Street fence to prevent access to the secured area on 30th Street.

PSC: Y1FF

1 $________ $_________________

15BBR021Q00000011 Page 6 of 36

Section 3 - Special Contract Requirements

Clauses By Full Text

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (June 1996)

(a) "Unsafe condition" as used in this clause means the actual or potential exposure of contractor or Government employees to a hazardous material as defined in Federal Standard No. 313, and any revisions thereto during the term of this contract, or any other material or working condition designated by the Contracting Officer's Technical Representative (COTR) as potentially hazardous and requiring safety controls.

(b) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.

(c) Prior to commencement of work, contractors are required to inspect for and report to the contracting officer or designee the presence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.

(d) If during the performance of the work under this contract, the contractor or any of its employees, or subcontractor employees, discovers the existence of an unsafe condition, the contractor shall immediately notify the contracting officer, or designee, (with written notice provided not later than three (3) working days thereafter) of the existence of an unsafe condition. Such notice shall include the contractor's recommendations for the protection and the safety of Government, contractor and subcontractor personnel and property that may be exposed to the unsafe condition.

(e) When the Government receives notice of an unsafe condition from the contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will constitute a dispute under the Disputes clause of this contract.

(f) Nothing contained in this clause shall relieve the contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.

(End of Clause)

52.21-603-70 Contracting Officer's Representative (COR) (June 2012)

(a)Paul ,Brady , General,Foreman, is hereby designated as the Contracting Officer's Representative (COR) under this contract.

(b) The COR is responsible, as applicable, for: receiving all deliverables, inspecting and accepting the supplies or services provide hereunder in accordance with the terms and conditions of this contract; providing direction to the contractor which clarifies the contractor effort, fills in details or otherwise serves to accomplish the contractual Scope of Work; evaluating performance; and certifying all invoices/vouchers for acceptance of the supplies or services furnished for payment.

(c) The COR does not have the authority to alter the contractor's obligations under the contract, and/or modify any of the expressed terms, conditions, specifications, or cost of the agreement. If as a result of technical discussions it is desirable to alter/change contractual obligations or the Scope of Work, the Contracting Officer shall issue such changes.

52.24-403-70 Notice of Contractor Personnel Security Requirements (OCT 2005)

Compliance with Homeland Security Presidential Directive-12 (HSPD-12) and Federal Information Processing Standard Publication

201 (FIPS 201) 1 entitled "Personal Identification Verification (PIV) for Federal Employees and Contractors," Phase I.

1. Long-Term Contractor Personnel:

In order to be compliant with HSPD-12/PIV I, the following investigative requirements must be met for each new long-term 2 contractor employee whose background investigation (BI) process begins on or after October 27, 2005:

a. Contractor Personnel must present two forms of identification in original form prior to badge issuance (acceptable documents are listed in Form I-9, OMB No. 1615-0047, "Employment Eligibility Verification," and at least one document must be a valid State or Federal government-issued picture ID);

15BBR021Q00000011 Page 7 of 36

b. Contractor Personnel must appear in person at least once before a DOJ official who is responsible for checking the identification documents. This identity proofing must be completed sometime during the clearance process but prior to badge issuance and must be documented by the DOJ official;

c. Contractor Personnel must undergo a BI commensurate with the designated risk level associated with the duties of each position.

Outlined below are the minimum BI requirements for each risk level:

* High Risk - Background Investigation (5 year scope)

* Moderate Risk - Limited Background Investigation (LBI) or Minimum Background Investigation (MBI)

* Low Risk - National Agency Check with Inquiries (NACI) investigation

d. The pre-appointment BI waiver requirements for all position sensitivity levels are a:

1) Favorable review of the security questionnaire form;

2) Favorable fingerprint results;

3) Favorable credit report, if required;3

4) Waiver request memorandum, including both the Office of Personnel Management schedule date and position sensitivity/risk level;

and

5) Favorable review of the National Agency Check (NAC) 4 portion of the applicable BI that is determined by position sensitivity/risk level.

A badge may be issued following approval of the above waiver requirements.

If the NAC is not received within five days of OPM's scheduling date, the badge can be issued based on a favorable review of the Security Questionnaire and the Federal Bureau of Investigation Criminal History Check (i.e., fingerprint check results).

e. Badge re-validation will occur once the investigation is completed and favorably adjudicated. If the BI results so justify, badges issued under these procedures will be suspended or revoked.

2. Short-Term Contractor Personnel:

It is the policy of the DOJ that short-term contractors having access to DOJ information systems and/or DOJ facilities or space for six months or fewer are subject to the identity proofing requirements listed in items 1a. and 1b. above. The pre-appointment waiver requirements for short-term contractors are:

a. Favorable review of the security questionnaire form;

b. Favorable fingerprint results;

c. Favorable credit report, if required;5 and

d. Waiver request memorandum indicating both the position sensitivity/risk level and the duration of the appointment. The commensurate BI does not need to be initiated.

A badge may be issued following approval of the above waiver requirements and the badge will expire six months from the date of issuance. This process can only be used once for a short-term contractor in a twelve month period. This will ensure that any consecutive short-term appointments are subject to the full PIV-I identity proofing process.

For example, if a contractor employee requires daily access for a three or four-week period, this contractor would be cleared according to the above short-term requirements. However, if a second request is submitted for the same contractor employee within a twelve-month period for the purpose of extending the initial contract or for employment under a totally different contract for another three or four-week period, this contractor would now be considered "long-term" and must be cleared according to the long-term requirements as stated in this interim policy.

3. Intermittent Contractors:

An exception to the above-mentioned short-term requirements would be intermittent contractors.

a. For purposes of this policy, "intermittent" is defined as those contractor employees needing access to DOJ information systems and/or DOJ facilities or space for a maximum of one day per week, regardless of the duration of the required intermittent access. For example, the water delivery contractor that delivers water one time each week and is working on a one-year contract.

b. Contractors requiring intermittent access should follow the Department's escort policy. Please reference the August 11, 2004, and January 29, 2001, Department Security Officer policy memoranda that conveys the requirements for contractor facility escorted access.

c. Due to extenuating circumstances, if a component requests unescorted access or DOJ IT system access for an intermittent contractor, the same pre-employment background investigation waiver requirements that apply to short-term contractors are required.

d. If an intermittent contractor is approved for unescorted access, the contractor will only be issued a daily badge. The daily badge will be issued upon entrance into a DOJ facility or space and must be returned upon exiting the same facility or space.

e. If an intermittent contractor is approved for unescorted access, the approval will not exceed one year. If the intermittent contractor requires unescorted access beyond one year, the contractor will need to be re-approved each year.

4. An individual transferring from another department or agency shall not be re-adjudicated provided the individual has a current (within the last five years), favorably adjudicated BI meeting HSPD-12 and DOJ's BI requirements.

5. The DOJ's current escorted contractor policy remains unchanged by this acquisition notice.

Notes:

1. FIPS 201 is available at: www.csrc.nist.gov/publications/fips/fips201/FIPS-201-022505.pdf

15BBR021Q00000011 Page 8 of 36

2. Under HSPD-12, long-term contractors are contractors having access to DOJ information systems and/or DOJ facilities or space for six months or longer. The PIV-I identity proofing process, including initiation and adjudication of the required background investigation, is required for all new long-term contractors regardless of whether it is the current practice to issue a badge. The second phase of HSPD-12 implementation (PIV-II) requires badge issuance to all affected long-term contractors.

3. For contractors in position sensitivity/risk levels above level 1, a favorable review of a credit check is required as part of the pre-appointment waiver package.

4. In order to avoid a delay in the hiring process, components should request an Advance NAC Report when initiating investigations to OPM. Per OPM ' s instructions, to obtain an Advance NAC Report, a Code " 3" must be placed in block " B " of the " Agency Use Only " section of the investigative form. This report is available for all case types.

5.For contractors in position sensitivity/risk levels above level 1, a favorable review of a credit check is required as part of the pre-appointment waiver package.

[End of Clause]

52.27-103-72 DOJ CONTRACTOR RESIDENCY REQUIREMENT BUREAU OF PRISONS (JUNE 2004)

For three of the five years immediately prior to submission of an offer/bid/quote, or prior to performance under a contract or commitment, individuals or contractor employees providing services must have:

1. Legally resided in the United States (U.S.);

2. worked for the U.S. overseas in a Federal or military capacity; or

3. been a dependent of a Federal or military employee serving overseas.

If the individual is not a U.S. citizen, they must be from a country allied with the U.S. The following website provides current information regarding allied countries: http://www.opm.gov/employ/html/citizen.htm By signing this contract or commitment document, or by commencing performance, the contractor agrees to this restriction.

[End of Clause]

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows; a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $30,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements

15BBR021Q00000011 Page 9 of 36 from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0002 Magnitude

The magnitude of this project is between $100,000.00 and $250,000.00.

FAO-0003 Required Insurance

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the

Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

15BBR021Q00000011 Page 10 of 36

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered.

The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.

FAO-0005 Submittals

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

FAO-0006 Contractor Use of Premises

Work Hours

15BBR021Q00000011 Page 11 of 36

The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site.

Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form; however, it shall contain similar information as the AIA Form G-702. The Contracting Officer will approve the amount of payment by signing and forwarding the application and certificate as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

FAO-0008 Request for Final Inspection

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0009 Contract Security (Program Statement 3000.03 Human Resource Management Manual)

The following security measures will be applied to all contract employees who will be working under the terms of the contract:

National Crime Information Center (NCIC) Check Name Check Fingerprint Check (FD-258)

15BBR021Q00000011 Page 12 of 36

OF-306, Declaration for Federal Employment, and Appropriate Resume or Optional Application Contract Pre-employment Form Release of Information

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/ Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0014 Contract Closeout Procedures (for construction contracts $150,000 or less)

Contract Closeout must be completed upon receipt of property and final payment.

Prior to payment of final invoice:

The Contractor shall submit the following documentation:

(1) Guarantees and warranties;

15BBR021Q00000011 Page 13 of 36

(2) All operation/maintenance manuals;

(3) Consent of Surety to Final Payment (AIA Document G707), if the contractor furnished a bond;

(4) Release of Claims (GSA Form 1142);

(5) Evidence of no pending labor disputes;

(6) As-built drawings/shop drawings, (if applicable);

(7) Contractor’s final invoice.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

15BBR021Q00000011 Page 14 of 36

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.246-12 Inspection of Construction (Aug 1996)

52.203-12 Limitation On Payments To Influence Certain Federal Transactions

(Oct 2010)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017)

52.204-2 Alt I Security Requirements (Aug 1996) - Alternate I (Apr 1984)

52.204-9 Personal Identity Verification of Contractor Personnel (Jan 2011)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards

(Oct 2018)

52.204-13 System for Award Management Maintenance (Oct 2018)

52.204-18 Commercial and Government Entity Code Maintenance (Jul 2016)

52.204-19 Incorporation by Reference of Representations and Certifications (Dec

2014)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services

Developed or Provided by Kaspersky Lab and Other Covered Entities

(Jul 2018)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment (Aug 2019)

52.209-6 Protecting the Government's Interest When Subcontracting with

Contractors Debarred, Suspended, or Proposed for Debarment (Oct

2015)

15BBR021Q00000011 Page 15 of 36

Clause Title Fill-ins (if applicable)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov

2015)

52.219-6 Notice of Total Small Business Set-Aside (Mar 2020)

52.219-14 Limitations on Subcontracting (Mar 2020)

52.222-8 Payrolls and Basic Records (Aug 2018)

52.222-9 Apprentices and Trainees (July 2005)

52.222-10 Compliance with Copeland Act Requirements (Feb 1988)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related

Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-21 Prohibition of Segregated Facilities (Apr 2015)

52.222-26 Equal Opportunity (Sept 2016)

52.222-27 Affirmative Action Compliance Requirements for Construction (Apr

2015)

52.222-35 Equal Opportunity for Veterans (Oct 2015)

52.222-36 Equal Opportunity for Workers with Disabilities (Jul 2014)

52.222-37 Employment Reports on Veterans (Feb 2016)

52.222-50 Combating Trafficking in Persons (Jan 2019)

52.222-55 Minimum Wages Under Executive Order 13658 (Dec 2015)

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan 2017)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving

(Aug 2011)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.225-13 Restrictions on Certain Foreign Purchases (June 2008)

52.228-2 Additional Bond Security (Oct 1997)

52.228-11 Pledges of Assets (Aug 2018)

52.232-23 Assignment of Claims (May 2014)

15BBR021Q00000011 Page 16 of 36

Clause Title Fill-ins (if applicable)

52.232-5 Payments under Fixed-Price Construction Contracts (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for Award Management

(Oct 2018)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors

(Dec 2013)

52.233-1 Disputes (May 2014)

52.233-3 Protest after Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions (Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and

Improvements (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-13 Accident Prevention (Nov 1991)

52.236-26 Preconstruction Conference (Feb 1995)

52.242-14 Suspension of Work (Apr 1984)

52.243-5 Changes and Changed Conditions (Apr 1984)

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short

Form) (Apr 1984)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

Clauses By Full Text

52.252-2 Clauses Incorporated by Reference (Feb 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/ these address(es):

www.acquisition.gov

15BBR021Q00000011 Page 17 of 36

[Insert one or more Internet addresses]

(End of clause)

52.204-21 Basic Safeguarding of Covered Contractor Information Systems (June 2016)

(a) Definitions. As used in this clause--

"Covered contractor information system" means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.

"Federal contract information" means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.

"Information" means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction

(CNSSI) 4009).

"Information system" means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).

"Safeguarding" means measures or controls that are prescribed to protect information systems.

(b) Safeguarding requirements and procedures.

(1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:

(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).

(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.

(iii) Verify and control/limit connections to and use of external information systems.

(iv) Control information posted or processed on publicly accessible information systems.

(v) Identify information system users, processes acting on behalf of users, or devices.

(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.

(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.

(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.

(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.

(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.

15BBR021Q00000011 Page 18 of 36

(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.

(xii) Identify, report, and correct information and information system flaws in a timely manner.

(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.

(xiv) Update malicious code protection mechanisms when new releases are available.

(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.

(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.

(c) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (c), in subcontracts under this contract (including subcontracts for the acquisition of commercial items, other than commercially available off-the-shelf items), in which the subcontractor may have Federal contract information residing in or transiting through its information system.

(End of clause)

52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within 10 [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 45 Days.* The time stated for completion shall include final cleanup of the premises.

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

52.211-12 Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $999.52 [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.211-13 Time Extensions (Sept 2000)

Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.

(End of clause)

52.225-9 Buy American-Construction Materials (May 2014)

(a) Definitions. As used in this clause--

"Commercially available off-the-shelf (COTS) item"--

15BBR021Q00000011 Page 19 of 36

(1) Means any item of supply (including construction material) that is--

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.