Scope of Work ISD Remove Tree at Main~1.docx
DOCX document 19 KB Posted
- Contract number
- 27-444DHS-ISDIS-P-102793
- Issued by
- Illinois
About this file
This is a Scope of Work document for the Illinois School for the Deaf (ISD), a state agency located in Jacksonville, Illinois. The project is identified as contract number 27-444DHS-ISDIS-R-339302 and concerns tree removal services at the institution's Main Building facility.
The project scope requires the contractor to cut down and remove one tree located in the front of the Main Building, grind the stump to a depth of six inches, and remove all associated debris. The contractor must backfill the area with dirt and apply grass seed and straw or other suitable ground cover, while taking care to avoid damage to sidewalks, structures, and existing landscaping. All debris, including stumps, stump grindings, and branches, must be hauled away daily and upon job completion. The contractor must supply all necessary tools, equipment, and labor to complete the work and is prohibited from using subcontractors. A mandatory pre-bid meeting is scheduled for Monday, September 21, 2026, at 10:00 a.m. at the facility's Main Building first-floor conference room. The project must be completed by June 30, 2027, marking the end of Fiscal Year 2027. Inquiries should be directed to Chris Fairfield, Chief Engineer, at (217) 370-6145 or (217) 479-4253.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Standard Terms and Conditions v23.2~49.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work Illinois School for the Deaf
27-444DHS-ISDIS-R-339302
1.1 Name of Project: Tree Removal at Main Building
1.2 Description of Project: -- ISD is looking for bidders to cut down and remove 1 tree.
1.3 Bidders Must : Cut down 1 tree in the front of Main Building, grind the stump to a depth of 6” and remove all debris related to tree removal. Backfill with dirt and cover area with grass seed and straw or other suitable cover. Avoid damaging sidewalks, structures, and existing area as much as possible. Remove all debris daily and upon completion of the job. All debris resulting from tree removal and stump grindings must be hauled away including stumps, stump grindings, branches, etc.
1.4 Additional Requirements and/or Conditions: Supply all tools, equipment, and manpower to complete the job.
1.5 No subcontractors allowed.
1.6 There is a mandatory pre-bid meeting to be held on Monday, 09/21/26, at 10:00am at Illinois School for the Deaf, address 125 S Webster Ave Jacksonville IL 62650. Main Building 1sf floor conference room.
1.7 Timeline of Project: Completed by the end of FY27, 06/30/2027
Chris Fairfield Chief Engineer Illinois School for the Deaf
(217) 370-6145 work cell (217)479-4253 office
File details come from the government source that posted it. Updated .