Schedule of Services.xls
XLS spreadsheet 42 KB Posted
- Attached to
- USCGC RESOLUTE DRYDOCK FY22 Federal contract opportunity
- Solicitation number
- 70Z080-22-Q-P4503300
About this file
This document contains a pricing schedule for drydock availability services for the USCGC RESOLUTE (WMEC-210B). The schedule lists over 40 line items of work to be performed including hull plating testing and preservation, propulsion system maintenance and overhaul, sea valves and waste pieces overhaul, rudder and appendage inspection and repair, superstructure preservation, and tank preservation. Pricing is provided for labor rates and individual line items, as well as total pricing for definite, optional, and combined definite and optional items. The related federal contract opportunity is solicitation number 70Z080-22-Q-P4503300 for the USCGC RESOLUTE drydock FY22, issued by the Department of Homeland Security Coast Guard with a point of contact of Kaity George.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Schedule of Services UPDATED.xls | XLS spreadsheet | |
| Amendment 3.docx | DOCX document | |
| Specification Rev 1.pdf | ||
| Amendment 2 Questions.docx | DOCX document | |
| Amendment 2 Page 1 of 2.docx | DOCX document | |
| Amendment 1.pdf | ||
| Statement of Work _Specification.pdf | ||
| 70Z080-22-Q-P4503300.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOS&S
| PRICING SCHEDULE FOR: | |||||
| USCGC RESOLUTE (WMEC-210B) DRYDOCK AVAILABILITY FY2021 | |||||
| ITEM | DESCRIPTION | UNIT PRICE | UNIT | QTY | EXTENDED PRICE |
| D-001 | Hull Plating (U/W Body), Ultrasonic Testing | JOB | 1 | ||
| D-002 | Hull Plating Freeboard, Preserve – Partial | JOB | 1 | ||
| D-003 | Appendages (U/W), Preserve (Internal) and Leak Test | JOB | 1 | ||
| D-004 | Propulsion Shaft Fairwaters And Rope Guards, Inspect | JOB | 1 | ||
| D-005 | Voids (Non-Accessible), Preserve (Internal) and Leak Test | JOB | 1 | ||
| D-006 | Propulsion Shafting; Remove, Inspect, and Reinstall | JOB | 1 | ||
| D-007 | Propulsion Intermediate Shaft(s); Remove, Inspect, and Reinstall | JOB | 1 | ||
| O-008 | Propulsion Shaft Coating, Renew | JOB | 1 | ||
| O-009 | Propulsion Shafting, Straighten | EA | 4 | ||
| O-010 | Propeller Shaft Sleeve(s), Renew | JOB | 1 | ||
| O-011 | Propulsion Shafting, Optical or Laser Alignment Check | JOB | 1 | ||
| D-012 | Propulsion Shaft Seal (Mechanical And Inflatable) Assemblies, Inspect And Repair Or Renew | JOB | 1 | ||
| O-013 | Propulsion Shaft Bearings (External), Renew | JOB | 1 | ||
| O-014 | Propulsion Stern Tube Bearings, Renew | JOB | 1 | ||
| O-015 | Stern Tube Interior Surfaces, Preserve 100% | JOB | 1 | ||
| D-016 | Controllable Pitch Propellers, Clean and Inspect | JOB | 1 | ||
| D-017 | Controllable Pitch Propeller (CPP) Hubs, Remove, Inspect and Reinstall | JOB | 1 | ||
| D-018 | Fathometer Transducer, General Maintenance | JOB | 1 | ||
| D-019 | Sea Valves and Waster Pieces, Overhaul Or Renew | JOB | 1 | ||
| D-020 | Sea Strainers - Duplex (All Sizes), Overhaul | JOB | 1 | ||
| D-021 | Rudder Assembly; Remove, Inspect And Reinstall | JOB | 1 | ||
| D-022 | Superstructure, Preserve “Partial” | JOB | 1 | ||
| D-023 | Cathodic Protection, Zinc Anodes, Renew, | JOB | 1 | ||
| D-024 | Drydock | JOB | 1 | ||
| D-025 | Temporary Services, Provide - Cutter | JOB | 1 | ||
| D-026 | Raw Water Condensate Cooling Pump, Upgrade | JOB | 1 | ||
| D-027 | Hull and Structural Plating, Renew | JOB | 1 | ||
| D-028 | Vertical Ladder, Modify | JOB | 1 | ||
| D-029 | JP-5 Service Tank Plating, Renew | JOB | 1 | ||
| D-030 | Main Engine/Reduction Gear Alignment, Check | JOB | 1 | ||
| D-031 | Fuel Manifold, Overhaul | JOB | 1 | ||
| D-032 | Reefer R/W Piping, Renew | JOB | 1 | ||
| D-033 | Doppler Speed Log, Replace | JOB | 1 | ||
| D-034 | Deep Water Sounder, Remove | JOB | 1 | ||
| D-035 | U/W Body, Preserve (100%) | JOB | 1 | ||
| D-036 | Propulsion Shafting, Strain Gage Alignment, Inspect | JOB | 1 | ||
| D-037 | Sea Trial Performance, Support, Provide | JOB | 1 | ||
| D-038 | Controllable Pitch Propeller (CPP) System, Inspect and Service | JOB | 1 | ||
| D-039 | Hull Plating (Side Scan), Ultrasonic Testing | JOB | 1 | ||
| D-040 | Tanks (Potable Water), Preserve "100%" | JOB | 1 | ||
| O-00A | Composite Labor Rate | Hour | 1 | ||
| D-00B | GFP Report | NSP | EA | NSP | |
| O-00Z | Laydays | Day | 5 | ||
| Total Price of Definite Items | |||||
| Total Price of Option Items | |||||
| Total Price of Definite and Optional Items |
&C(10/14/2020) Draft-00 - Page &P of &N
File details come from the government source that posted it. Updated .