FINAL SAMPLE TASK ORDER.docx
DOCX document 16 KB Posted
- Solicitation number
- SB1341-11-RP-0060
About this file
Sample Task Order
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FINAL TECHNICAL SPECIFICATION NBSR-AP-2.docx | DOCX document | |
| FINAL TECHNICAL SPECIFICATION NBSR-CSP-1.docx | DOCX document | |
| FINAL 4 FBO POST.docx | DOCX document | |
| Drawings for sample task order.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAMPLE TASK ORDER:
NOTE: The Sample Task Order is merely a sample of the type of welding services anticipated by NIST. This Sample Task Order does not constitute actual work.
1. Sample Task Order: On-site Pipe welding Requirements
Title: Fabrication and Installation of a Fuel Element Hydraulic Flow Test Piping System
Attached please find the drawing E-04-002 (12 sheets) which depicts the piping arrangement with all equipment and piping components. Sheet 1 of 12 of this drawing shows piping assembly with tank support stand. The following components and subassemblies will be supplied by the Government: (Refer to sheet 1 of 12 of E-04-002)
1. 4”x3” Centrifugal Pump with 15 HP electric motor (item 25)
2. Plate type Heat Exchanger (Item 7)
3. Orifice plate for flow measurement (Item 23)
4. Fuel Canister Section (Item 13)
5. 6” diameter Sight Glass (Item 14) and
6. 6” Fuel access canister section (Item 15) with blind flange (Item 35)
Please disregard sheets 7 through 12 of drawing E-04-002 for your estimate as the “Fuel Canister Section Assembly” will be government supplied.
Installation of system components and subassemblies described above is contractor’s responsibility.
Please disregard all notes listed on drawing E-40-002 (sheet 1 thru 12) and replace with the following information:
1 Do not scale this drawing. The Offeror shall verify dimensions in the field prior to cutting and/or welding any piping components.
2 Pipe and piping components shall be furnished by Offeror.
3 Certified welders and welding procedures shall be used in accordance with specifications.
4 Applicable codes and standards (use most recent version).
5 Disregard materials shown in the “Bill of Materials”. Consider all components are made of carbon steel.
File details come from the government source that posted it. Updated .