About this file
Demolition of Residential Building at 3 Bacon Street, Wellesley, Massachusetts
This is an Invitation for Bid (IFB) issued by the Town of Wellesley, Massachusetts for the complete demolition of a 1,300 square-foot, one-story wood-frame ranch-style residential building located at 3 Bacon Street. The project encompasses removal of the entire structure, including a five-room dwelling with two bedrooms, one full bathroom, full basement, approximately 180 square-foot enclosed frame porch, approximately 441 square-foot frame garage, and approximately 39 square-foot open porch situated on a 23,600 square-foot lot. The contractor must remove all materials and debris, backfill the foundation cavity with clean gravel, and leave the site level and properly graded. A pre-bid site visit is scheduled for August 17, 2026 at 10:00 AM at the project location. Sealed bids are due by September 9, 2026 at 11:00 AM, with the bid opening held in the Great Hall at Wellesley Town Hall. Work is scheduled to begin in or around October 1, 2026 and must be completed by October 30, 2026, with all work conducted during normal business hours of 7:00 AM to 5:00 PM. No bidder may withdraw their bid for thirty (30) days after the opening date.
Bid security in the amount of five percent (5%) of the total bid price is required in the form of a certified check or bid bond. A Payment Bond equal to fifty percent (50%) of the total contract price with a surety company licensed to do business in Massachusetts is required before contract execution. The project is subject to Massachusetts prevailing wage rates as determined by the Department of Labor and Workforce Development under M.G.L. Chapter 149, Sections 26-27D. The Town will waive or pay all necessary permit fees, handle utility disconnections and capping, perform hazardous material abatement prior to demolition, and provide any required fire watch. The contractor is responsible for obtaining all other necessary permits and licenses, providing dust control measures, installing silt fencing to protect the wetland and Morses Pond, constructing temporary perimeter fencing, notifying adjacent properties within 300 feet, securing the site, and conducting a thorough building search prior to demolition. Liquidated damages of $500 per day may be assessed if the project is not completed by the specified deadline. The estimated project value is $50,000. Awards will be made to the lowest responsible and eligible bidder possessing the necessary skill, ability, and integrity to complete the work within the specified timeframe and in accordance with M.G.L. Chapter 149, Section 44A and M.G.L. Chapter 30, Section 39S.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BID (IFB)
#SB-2026-01
DEMOLITION OF RESIDENTIAL BUILDING LOCATED
AT 3 BACON STREET, WELLESLEY
(M.G.L. c. 149)
August 12, 2026
BIDS DUE:
September 9, 2026 at 11:00 am Late Proposals Will Be Rejected
DELIVER COMPLETED SUBMISSIONS TO:
Town of Wellesley, MA Town Hall, Select Board Office
Attn: Meghan Jop 525 Washington Street, Wellesley, MA
Phone: 781-431-1019 x 2201 e-mail: mjop@wellesleyma.gov
TOWN OF WELLESLEY
MASSACHUSETTS
INVITATION TO BID
Sealed bids for furnishing the following will be received at the Select Board Office, Wellesley Town Hall, 525 Washington Street, Wellesley, Massachusetts 02482 until the time specified below at which time the bids will be publicly opened and read.
ITEM BID OPENING
SB-2026-01 September 9, 2026 Demolition of Residential Building located at 11:00 AM 3 Bacon Street, Wellesley, MA 02482
Bid Documents and bid forms may be obtained at the Select Board Office, Wellesley Town Hall, 525 Washington Street, Wellesley, MA, or on the Town’s webpage at https://www.wellesleyma.gov/Bids.aspx
Bids will be opened in the Great Hall, Wellesley Town Hall, 525 Washington Street, Wellesley, MA 02482.
Each bid must be accompanied by a bid security of CERTIFIED CHECK, or BID BOND issued by a responsible bank or trust company licensed to do business in the State of Massachusetts in the amount of 5% of the total bid. Work under this project includes the demolition of a residential structure with an estimated value of the project of $50,000
A Pre-Bid Site Visit will be held for all interested parties on August 17, 2026 at 10:00 AM, at the site location, 3 Bacon Street, Wellesley, MA 02482
No bidder may withdraw his bid for a period of thirty (30) days, after the date set for the opening thereof.
Attention is directed to the minimum wage rates to be paid as determined by the Department of Labor and Workforce Development under the provisions of Massachusetts General Laws, Chapter 149, Sections 26 to 27D inclusive.
A Payment Bond of an amount equal to 50 per cent of the total amount of the bid with a surety company satisfactory to the Town, as surety, will be required for the payment for all labor and materials used in the work. Such bond shall be prepared on forms provided by the Owner and supplied by a surety company licensed to do business in the Commonwealth of Massachusetts
The bidding and award of this Contract will be under the provisions of M.G. L. Chapter 149, Section 44A, et seq. and the provisions of M.G.L. Chapter 30, Section 39S.
Wellesley is an affirmative action/equal opportunity purchaser. The Town reserves the right to accept or reject, in whole or in part, any or all bids or take whatever other action may be deemed necessary to be in the best interest of the Town.
Meghan Jop Executive Director
ADV: Wellesley Townsman – August 13, 2026 Central Register – August 12, 2026 https://www.wellesleyma.gov/Bids.aspx
#SB-2026-01
Town of Wellesley, Massachusetts
Select Board Office
COVER SHEET
The Town of Wellesley reserves the right to reject any or all Bids, to omit any item or items called for, or to accept the bids(s) deemed in the best interest of the Town. One Original and One (1) copy of the bids must be submitted before 11:00 AM on September 9, 2026 to:
Meghan Jop Select Board Office
Town Hall 525 Washington Street
Wellesley, Massachusetts 02482
The envelope containing the Bid and required information must be sealed and marked with Proposer’s name, title of proposal, Bid number, and date of opening. The Proposer must sign all required signature pages in order for the proposal to be considered.
The Proposer acknowledges receipt of the following ADDENDA #
BUSINESS/INDIVIDUAL NAME_______________________________________________________
ADDRESS __________________________________________________________
CITY, STATE, ZIP CODE __________________________________________________________
TELEPHONE __________________________________________________________
EMAIL __________________________________________________________
INDIVIDUAL/AUTHORIZED SIGNATURE ______________________________________
AUTHORIZED OFFICER NAME (print) ______________________________________
DATE ______________________________________
By signing above, the authorized officer is certifying that a complete examination of all bid/IFB documents has been made and that the goods/services will be delivered within the time specified and at the prices stated.
All bidders must sign and submit with their bid the attached Certificate of Good Faith and Tax Attestation Form. Failure to do so will result in the bid being unresponsive and rejected.
If bidder/proposer is a co-partnership, all partners must execute both copies of the bid/proposal, unless one partner has been authorized to sign for the co-partnership, in which case evidence of such authority shall be submitted.
If bidder/proposer is a corporation, the authorized agent shall execute both copies of the bid/proposal.
Evidence of authority to sign must be submitted.
The Town of Wellesley reserves the right to reject any or all bids/proposals and waive any informalities deemed to be in the best interests of the Town.
INSTRUCTIONS TO BIDDERS
BID NO. SB-2026-01
1.01 - PROPOSAL
1. Sealed proposals will be received at the time and place as designated by the Owner in the “Invitation For
Bid”.
2. If, at the time of the scheduled bid opening, the Town Hall is closed due to inclement weather or other unforeseeable events, the bid opening will be postponed until the same time as specified in the bid documents on the next normal business day. Bids will be accepted until that date and time.
3. Proposal envelopes shall be clearly marked “Sealed Bid” and addressed to: Att.: Meghan Jop, Town of
Wellesley, Select Board Office, Town Hall, 525 Washington Street, Wellesley, MA 02482.
4. Proposals shall be submitted in duplicate. Proposal envelopes shall have bidder’s company name and address on the outside.
5. No claims for immunity or exceptions predicated upon misunderstanding or failure to correctly interpret the “Invitation for Bid” or the contract Documents will be allowed.
1.02 - BID SETS
Bid sets will be available at the Select Board Office, Wellesley Town Hall, 525 Washington Street, Wellesley, Massachusetts as well as on https://www.wellesleyma.gov/Bids.aspx There is no cost for copies of the bid sets.
1.03 – PRE-BID CONFERENCES AND SITE VISITS
A Pre-Bid Site Visit will be held for all interested parties on August 17, 2026, at 10:00 AM, at the site location, 3 Bacon Street, Wellesley, MA, 02482.
1.04 - QUALIFICATION AND LICENSING
1. All Bidders are notified that they must be licensed under prevailing state and local laws and regulations governing the proposed work.
2. All work and materials shall comply in every respect with the building laws, state and town regulations, and the directions of the inspector of buildings and such building laws, regulations and directions are to be considered as a part of the Contract to which it relates.
1.05- BID WITHDRAWAL
1. Withdrawal or modifications to bids will be allowed only if written notice of a Bidder’s desire to withdraw or modify his/her bid is filed prior to the time of bid opening and at the place specified in the request for bids. A notice of a Bidder’s desire to withdraw or modify a bid must be signed by the Bidder or his/her designated representative.
1. No bid may be withdrawn for a period of thirty (30) days after the scheduled closing time for the receipt of bids. The Owner reserves the right to accept or reject in whole or in part any or all bids, or take whatever other action that may be deemed to be in its best interest.
1.06 - LOCATION OF SITE
1. The site for this project is 3 Bacon Street, Wellesley, MA 02482.
1.07 – BID/CONTRACT DOCUMENTS
1. The Contract Documents consist of the following:
https://www.wellesleyma.gov/Bids.aspx
1. Specifications.
2. Drawings as indicated in the Specifications, if applicable.
3. Addenda to Specifications and drawings, if any.
4. The sample construction contract agreement and contract supplement “C”.
5. The Town issued Purchase Order.
6. Town of Wellesley Board of Survey Report
1.08- OWNER
1. Where the term Owner is used in these Specifications, and other Contract Documents, same refers to
Town of Wellesley, Massachusetts, or its authorized representative.
1.09 – ENGINEER/ARCHITECT
1. Where the term Engineer/Architect appears in these Specifications, same refers to Town of Wellesley, or their authorized representative.
1.10- CONTRACTOR
1. Where the term Contractor or General Contractor is used in the Specifications, it shall mean the Contractor mentioned as such in the Agreement.
2. Where reference is made to Subcontractors, such reference is intended for reasons of clarification and the relationship between the Contractor and said Subcontractors shall be in accordance with the General Conditions.
1.11 - EXPLANATION TO BIDDERS
1. No oral interpretation will be made. Any interpretations made to bidders will be in the form of an addendum to the Specifications and Drawings that will be forwarded to all bidders.
2. Discrepancies, omissions or doubts as to the meaning of Specifications and drawings should be communicated at once to the Town of Wellesley for interpretation. This request for clarification must be made in writing, via email (mjop@wellesleyma.gov), prior to the bid opening. Bidders should act promptly and allow sufficient time for a reply to reach them before the submission of their bids and any interpretation made by the Select Board Office and/or the Engineer/Architect prior to receipt of bids shall be made a part of the Contract.
3. Requests for clarifications by a prospective Bidder regarding the specifications, or other bid documents must be presented in writing, via email (mjop@wellesleyma.gov), to the Select Board Office before the bids are opened. Requests shall include the project specification name and date, and shall be directed to the Purchasing Agent.
4. Verbal explanations or instructions will not be binding during the bidding process. Only written addenda are binding. Written addenda resulting from requests for clarifications will be delivered to all listed holders of the Bid Documents no later than (3) business days prior to the bid opening. Addenda may be issued after this date if deemed to be in the best interests of the Town by the Purchasing Agent.
All Bidders shall acknowledge the receipt of all addenda when submitting their bids.
5. In the absence of an interpretation by the Select Board Office and/or Engineer/Architect should the Specifications disagree in themselves or with the drawings, the better quality or the greater quantity of work or materials shall be estimated upon and, unless otherwise ordered, shall be furnished.
1.12- CONDITIONS OF WORK
1. Each bidder shall carefully examine the Contract Documents, shall visit the site, and fully inform himself as to all existing and controlling conditions and limitations. The submission of a bid shall be conclusive evidence that the Bidder is familiar with all such conditions, including the nature, amount, and location of the work, the type of facilities needed preliminary to and during the execution of the work, the general and local conditions, labor conditions, and all other matters which might in any way affect or have a bearing on the work or its cost.
2. The Contractor shall include all charges for labor, material, tools, staging, equipment and supervision that he/she deems necessary in order to complete, in a thoroughly professional and expeditious manner, all the work described hereafter. All work shall be according to code and approved by the proper authority. All other material and debris accumulated as a result of this operation shall become the property of the contractor and shall be removed from the premises by him/her. The premises are to be clean and neat, to the satisfaction of the Town of Wellesley and/or designated Consultant.
1.13 - PERMITS, FEES AND NOTICES
1. The successful bidder shall secure all permits and licenses necessary for the proper execution and completion of the work including the filing of a Request for Determination of Applicability with the Wellesley Wetland Protection Committee.
2. The Owner will waive or pay for, as applicable, fees for all necessary permits.
3. The Town will waive or provide the survey.
1.14 - COOPERATION AND COORDINATION
1. The Owner has entered, or may enter, into separate contracts for work related to the work under this specification.
2. The successful bidder shall cooperate with said contractors and coordinate his work with the work of other trades so that construction will proceed in a rapid and orderly fashion.
1.15 - TIMELY COMPLETION AND LIQUIDATED DAMAGES
The Contractor shall start the work under this Contract on written notice from and on date set by the Owner. The Contractor shall start the work at the building on the date set by the Owner and shall continue, without interruption, to completion with all the practical dispatch and regularity. Work is to begin in or around October 1, 2026, and shall be completed in full by October 30, 2026. All work to be completed during normal business hours of 7:00 AM to 5:00 PM.
1. Liquidated damages in the amount of $500 per day may be assessed if the project is not complete by the set completion date.
1.16 - CONTRACT FORM
1. The successful Bidder will be notified of the award of the Contract in writing, and shall properly execute a contract in accordance with the construction contract agreement and contract supplement “C” provided herein, within five (5) working days after receipt of such notification.
1.17 - ADDENDA
1. The Owner may, during the bidding period, advise the Bidders by addenda of additions, omissions, or alterations in the Specifications and drawings. All such changes shall become a part of the contract and shall be included in the work covered by the Proposal.
2. No addenda will be issued later than two (2) days prior to the date set for receipt of bids, unless deemed to be in the public’s best interest to do so by the Purchasing Agent.
1.18 - TAXES
1. The Owner is exempt from all purchaser taxes. Tax Exempt Number will be supplied to the successful bidder.
1.19 - PROPOSAL SECURITY
1. Each Bidder shall submit with his bid a Bid Security in the amount of five percent (5%) of the total bid price. The Bid Security shall consist of Certified Check, or Bidder’s Bond.
1.20 - LABOR & MATERIALS PAYMENT BOND
1. Before Contract signing, the Contractor shall furnish the Owner with a Labor & Materials Payment
Bond in the amount of fifty percent (50%) of the Contract price, to insure completion of work and payment for all labor and materials furnished on the project.
2. All bonds shall be written conformance with Massachusetts General Laws, Chapter 149, Section 29, as amended.
1.21 – CONTRACTOR’S LIABILITY INSURANCE
2. See the insurance requirements and minimum coverage amounts listed in both the specifications and Contract Supplement “C”.
1.22 – COMPETENCY OF BIDDERS AND REFERENCES
1. No contract will be awarded to any person, firm, or corporation that is in arrears or is in default to the
Owner upon any debt or contract, or that is a defaulter, as surety or otherwise, upon any obligation to the Owner, or has failed to perform faithfully any previous contract with the Owner.
2. All Bidders must supply a list of references for similar projects performed over the last three years providing names, addresses and contract person with telephone number on each project. This reference list is to be submitted with the bid.
1.23 - AWARD OF CONTRACT
1. This contract shall be awarded to the lowest responsible and eligible bidder based upon the base bid amount as in accordance with MGL Ch. 149. Such a bidder must possess the skill, ability and integrity necessary for the faithful performance of the work and shall establish his ability to comply with the schedule of work outlined in the Contract section. The term “lowest responsible and eligible bidder” as used herein shall mean the bidder whose bid is the lowest of those bidders possessing the skill, ability and integrity necessary for the faithful performance of the work within the time limit allowed.
TOWN OF WELLESLEY
SPECIFICATIONS
General Plot
General Description of 3 Bacon Street: 1,300 square-foot, one-story wood-frame ranch-style residence constructed in 1959. The dwelling contains five rooms, two bedrooms, one full bathroom, a full basement, an approximately 180 square-foot enclosed frame porch, an approximately 441 square-foot frame garage, and an approximately 39 square-foot open porch. The property is situated on a 23,600 square-foot lot.
Bidders to field verify during pre-bid site visit.
The current building is a one story wood framed building sitting on a concrete foundation. The building measures approximately 44 feet x 34 feet. All utilities, including the existing water, sewer, electricity and natural gas will be disconnected and capped by the Town of Wellesley. Town will abate any hazardous material prior to demolition.
The building must be removed in its entirety, excluding existing foundation and slab-on-grade. The foundation walls and floor slab can remain, however drainage must be provided in floor slab. After demolition and removal of materials, the site will need to be back filled with clean gravel and left with a level gravel base adjacent to the surrounding asphalt elevations.
The contractor shall include in the lump sum bid price demolition, removal and proper disposal of all demolition debris and rubble. Foundation wall and floor slab can remain with drainage, backfilling of the foundation cavity and rough grading and compaction of the backfill to prevent erosion or surface water nuisance on this cleared lot, removing trash, rubbish and debris, leaving the lot clean and leveled to a uniform grade. No demolition work shall begin until all proper permits have been issued.
A. The Contractor shall remove and properly dispose of all remaining petroleum products and any aboveground or underground oil storage tanks in accordance with all applicable laws and regulations.
B. Demolition shall proceed in a systemic manner, from top to bottom.
C. Locate demolition equipment throughout the site and remove materials so not to impose excessive loads to supporting walls of adjacent structures.
D. Contractor is to ensure that the area to be backfilled is free of standing water, frost, frozen materials, trash and debris. Properly dispose of debris away from the site in approved disposal areas.
E. The Contractor must not leave the site in an unsafe condition. The site must be properly fenced off during the duration of the work.
F. Dust Control: The Contractor shall wet down the debris to prevent air pollution by dust rising from the demolition work and to prevent fires caused by vandals. Also employ tarpaulins on trucks carrying debris to prevent spreading dust and debris. In addition, clean up loose debris daily to prevent the wind from spreading dust and debris.
G. Install silt fencing to protect the wetland and Morses Pond from sediment.
H. Install construction fencing in order to protect the existing trees at the front entrance of the building.
In addition, the entire site shall have temporary construction fencing around the perimeter of the site.
I. Bid price to include any required fire watch by the Wellesley Fire Department.
Ability & Experience of Bidder
The Town of Wellesley reserves the right not to award the contract to any bidder who does furnish evidence of prior experience and current capabilities, including manpower and equipment, necessary to enable him to prosecute the required demolition and to successfully complete the work in the time named in the contract. The bidders must submit their qualification statement with their bid package. The Contractor must submit a list of references of at least three similar past projects completed within the past three years. This reference list must be submitted with the bid.
Permits
The Contractor shall obtain all necessary permits at the Contractor’s expense before commencing the work, including all arrangements with utility companies and Town of Wellesley Departments, if necessary, however, the Town has already capped or discontinued all utilities. Building permit fees will be waived by the Town.
Demolition & Disposal Fees
The Contractor shall assure that the Town of Wellesley is aware of their demolition operations at all times. The Contractor shall submit evidence of such legal removal and disposal, in the form of trucking slips and manifests, as part of their payment request from the Town of Wellesley. The Contractor prior to the start of work shall provide details for proposed material disposal, dump fees and locations.
Rodent Control
The Town of Wellesley shall perform rodent control measures prior to demolition.
Notification of Adjacent Properties
The Contractor shall provide notification to and protection of all adjacent properties within 300 feet. All demolition is to be confined to the property boundaries. No demolition activities are to be conducted on any public way without the prior consent and/or permits from the Town of Wellesley. All adjacent streets and sidewalks must be protected during demolition activities.
Building Search
The Contractor shall conduct a thorough search of the building structure and site immediately prior to the demolition to assure that the work site is clear of any person and/or pets.
Secure Site
The Contractor shall secure the site of the building to be demolished, including, but not limited to the construction fencing or other protective barriers, police protection and protection of area residents from any and all hazards during the demolition as deemed necessary to ensure public safety. The Contractor is also responsible for any and all police details where applicable.
Investigation of Conditions
All bidders must note in their submittals that they have inspected the sites, read all of the contract documents, including insurance requirements, and are fully acquainted with the work to be performed and have all the resources to perform the work in compliance with all laws and regulations within the specified time frame of the Contract.
Prevailing Wage Rates
THE COMMONWEALTH OF MASSACHUSETTS
EXECUTIVE OFFICE OF LABOR AND WORKFORCE DEVELOPMENT
DEPARTMENT OF LABOR STANDARDS
Prevailing Wage Rates
MAURA HEALEY
Governor
KIM DRISCOLL
Lt. Governor
As determined by the Director under the provisions of the Massachusetts General Laws, Chapter 149, Sections 26 to 27H
LAUREN JONES
Secretary
MICHAEL FLANAGAN
Director
Awarding Authority: Wellesley City/Town: WELLESLEY
Contract Number: SB-2026-01
Description of Work: Demolition of a 1300 square foot, one story wood frame ranch style residence constructed in 1959 with an enclosed frame porch and a 441 square foot garage.
Job Location: 3 Bacon Street
Information about Prevailing Wage Schedules for Awarding Authorities and Contractors
The wage rates will remain in effect for the duration of the project, except in the case of multi-year public construction projects. For construction projects lasting longer than one year, awarding authorities must request an updated wage schedule no later than two weeks before the anniversary of the date the contract was executed by the awarding authority and the general contractor. For multi-year CM AT RISK projects, the awarding authority must request an annual update no later than two weeks before the anniversary date, determined as the earlier of: (a) the execution date of the GMP Amendment, or (b) the execution date of the first amendment to permit procurement of construction services. The updated wage schedule must be provided to all contractors, including general and sub-contractors, working on the construction project.
This annual update requirement is generally not applicable to 27F “rental of equipment” contracts. For such contracts, the prevailing wage rates issued by DLS shall remain in effect for the duration of the contract term. However, if the prevailing wage rate sheet issued does not contain wage rates for each year covered by the contract term, the Awarding Authority must request updated rate sheets from DLS and provide them to the contractor to ensure the correct rates are being paid throughout the duration of the contract. Additionally, if an Awarding Authority exercises an option to renew or extend the contract term, they must request updated rate sheets form DLS and provide them to the contractor.
This wage schedule applies only to the specific project referenced at the top of this page and uniquely identified by the “Wage Request Number” on all pages of this schedule.
An Awarding Authority must request an updated wage schedule if it has not opened bids or selected a contractor within 90 days of the date of issuance of the wage schedule. For CM AT RISK projects (bid pursuant to G.L. c.149A), the earlier of: (a) the execution date of the GMP Amendment, or (b) the bid for the first construction scope of work must be within 90-days of the wage schedule issuance date.
The wage schedule shall be incorporated in any advertisement or call for bids for the project as required by M.G.L. c. 149, § 27. The wage schedule shall be made a part of the contract awarded for the project. The wage schedule must be posted in a conspicuous place at the work site for the life of the project in accordance with M.G.L. c. 149 § 27. The wages listed on the wage schedule must be paid to employees performing construction work on the project whether they are employed by the prime contractor, a filed sub-bidder, or a sub-contractor.
Apprentices working on the project are required to be registered with the Massachusetts Division of Apprentice Standards (DAS). Apprentices must keep their apprentice identification card on their persons during all work hours on the project. An apprentice registered with DAS may be paid the lower apprentice wage rate at the applicable step as provided on the prevailing wage schedule. Any apprentice not registered with DAS regardless of whether they are registered with another federal, state, local, or private agency must be paid the journeyworker's rate.
Every contractor or subcontractor working on the construction project must submit weekly payroll reports and a Statement of Compliance directly to the awarding authority by mail or email and keep them on file for three years. Each weekly payroll report must contain: the employee’s name, address, occupational classification, hours worked, and wages paid. Do not submit weekly payroll reports to DLS. For a sample payroll reporting form go to http://www.mass.gov/dols/pw.
Contractors with questions about the wage rates or classifications included on the wage schedule have an affirmative obligation to inquire with DLS at (617)
626-6953.
Contractors must obtain the wage schedules from awarding authorities. Failure of a contractor or subcontractor to pay the prevailing wage rates listed on the wage schedule to all employees who perform construction work on the project is a violation of the law and subjects the contractor or subcontractor to civil and criminal penalties.
Employees not receiving the prevailing wage rate set forth on the wage schedule may file a complaint with the Fair Labor Division of the office of the Attorney
General at (617) 727-3465.
Page 1 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Construction
Classification Effective Date Base Wage Health Pension Annuity Supplemental
Unemployment Total Rate
6/1/2026 $41.95 $16.17 $21.78 $0.00 $0.00 $79.90
12/1/2026 $41.95 $16.17 $23.52 $0.00 $0.00 $81.64
(2 AXLE) DRIVER - EQUIPMENT
TEAMSTERS JOINT COUNCIL NO. 10
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
1/1/2027 $41.95 $16.77 $23.52 $0.00 $0.00 $82.24
6/1/2026 $42.02 $16.17 $21.78 $0.00 $0.00 $79.97
12/1/2026 $42.02 $16.17 $23.52 $0.00 $0.00 $81.71
(3 AXLE) DRIVER - EQUIPMENT
TEAMSTERS JOINT COUNCIL NO. 10
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
1/1/2027 $42.02 $16.77 $23.52 $0.00 $0.00 $82.31
6/1/2026 $42.14 $16.17 $21.78 $0.00 $0.00 $80.09
12/1/2026 $42.14 $16.17 $23.52 $0.00 $0.00 $81.83
(4 & 5 AXLE) DRIVER - EQUIPMENT
TEAMSTERS JOINT COUNCIL NO. 10
TEAMSTERS JOINT COUNCIL NO. 10 ZONE B
1/1/2027 $42.14 $16.77 $23.52 $0.00 $0.00 $82.43
ADS/SUBMERSIBLE PILOT
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 1)
1/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53
For apprentice rates see "Apprentice- PILE DRIVER"
6/1/2026 $42.41 $10.90 $9.75 $9.11 $0.00 $72.17
12/1/2026 $43.85 $10.90 $9.75 $9.11 $0.00 $73.61
6/1/2027 $45.30 $10.90 $9.75 $9.11 $0.00 $75.06
12/1/2027 $46.75 $10.90 $9.75 $9.11 $0.00 $76.51
6/1/2028 $48.25 $10.90 $9.75 $9.11 $0.00 $78.01
AIR TRACK OPERATOR
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.75 $10.90 $9.75 $9.11 $0.00 $79.51
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $42.41 $10.90 $9.75 $9.21 $0.00 $72.27AIR TRACK OPERATOR (HEAVY & HIGHWAY)
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $43.85 $10.90 $9.75 $9.21 $0.00 $73.71
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
ASBESTOS REMOVER - PIPE / MECH. EQUIPT.
HEAT & FROST INSULATORS LOCAL 6
HEAT & FROST INSULATORS LOCAL 6 (BOSTON)
12/1/2025 $44.80 $14.50 $4.30 $6.75 $0.00 $70.35
6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67
12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11
6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01
6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51
ASPHALT RAKER
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $41.91 $10.90 $9.75 $9.21 $0.00 $71.77ASPHALT RAKER (HEAVY & HIGHWAY)
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $43.35 $10.90 $9.75 $9.21 $0.00 $73.21
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03ASPHALT/CONCRETE/CRUSHER PLANT-ON SITE
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
Page 2 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03BACKHOE/FRONT-END LOADER
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67
12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11
6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01
6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51
BARCO-TYPE JUMPING TAMPER
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $42.41 $10.90 $9.75 $9.11 $0.00 $72.17
12/1/2026 $43.85 $10.90 $9.75 $9.11 $0.00 $73.61
6/1/2027 $45.30 $10.90 $9.75 $9.11 $0.00 $75.06
12/1/2027 $46.75 $10.90 $9.75 $9.11 $0.00 $76.51
6/1/2028 $48.25 $10.90 $9.75 $9.11 $0.00 $78.01
BLOCK PAVER, RAMMER / CURB SETTER
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.75 $10.90 $9.75 $9.11 $0.00 $79.51
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $42.41 $10.90 $9.75 $9.21 $0.00 $72.27BLOCK PAVER, RAMMER / CURB SETTER (HEAVY &
HIGHWAY)
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $43.85 $10.90 $9.75 $9.21 $0.00 $73.71
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
BOILER MAKER
BOILERMAKERS LOCAL 29
BOILERMAKERS LOCAL 29
1/1/2024 $48.12 $7.07 $14.60 $6.00 $0.00 $75.79
8/1/2026 $70.15 $12.84 $15.57 $8.02 $0.00 $106.58BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY
WATERPROOFING)
BRICKLAYERS LOCAL 3
BRICKLAYERS LOCAL 3 (NEWTON)
2/1/2027 $71.55 $12.84 $15.57 $8.02 $0.00 $107.98
Apprentice: BOILER MAKER
Effective Date: 1/1/2024
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57
2 65.00 $31.28 $7.07 $9.32 $3.90 $0.00 $51.57
3 70.00 $33.68 $7.07 $10.03 $4.20 $0.00 $54.98
4 75.00 $36.09 $7.07 $10.74 $4.50 $0.00 $58.40
5 80.00 $38.50 $7.07 $11.45 $4.80 $0.00 $61.82
6 85.00 $40.90 $7.07 $12.18 $5.10 $0.00 $65.25
7 90.00 $43.31 $7.07 $12.88 $5.40 $0.00 $68.66
8 95.00 $45.71 $7.07 $13.62 $5.70 $0.00 $72.10
Apprentice to Journeyworker Ratio: 1:4
Page 3 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35BULLDOZER/GRADER/SCRAPER
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
6/1/2026 $50.40 $10.90 $9.75 $9.80 $0.00 $80.85CAISSON & UNDERPINNING BOTTOM MAN
LABORERS
LABORERS - FOUNDATION AND MARINE
12/1/2026 $51.90 $10.90 $9.75 $9.80 $0.00 $82.35
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $49.25 $10.90 $9.75 $9.80 $0.00 $79.70CAISSON & UNDERPINNING LABORER
LABORERS
LABORERS - FOUNDATION AND MARINE
12/1/2026 $50.75 $10.90 $9.75 $9.80 $0.00 $81.20
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $49.58 $10.90 $9.75 $9.80 $0.00 $80.03CAISSON & UNDERPINNING TOP MAN
LABORERS
LABORERS - FOUNDATION AND MARINE
12/1/2026 $51.08 $10.90 $9.75 $9.80 $0.00 $81.53
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67
12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11
6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01
6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51
CARBIDE CORE DRILL OPERATOR
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)
Effective Date: 8/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $35.08 $12.84 $15.57 $8.02 $0.00 $71.51
2 60.00 $42.09 $12.84 $15.57 $8.02 $0.00 $78.52
3 70.00 $49.11 $12.84 $15.57 $8.02 $0.00 $85.54
4 80.00 $56.12 $12.84 $15.57 $8.02 $0.00 $92.55
5 90.00 $63.14 $12.84 $15.57 $8.02 $0.00 $99.57
Apprentice: BRICK/STONE/ARTIFICIAL MASONRY (INCL. MASONRY WATERPROOFING)
Effective Date: 2/1/2027
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $35.78 $12.84 $15.57 $8.02 $0.00 $72.21
2 60.00 $42.93 $12.84 $15.57 $8.02 $0.00 $79.36
3 70.00 $50.09 $12.84 $15.57 $8.02 $0.00 $86.52
4 80.00 $57.24 $12.84 $15.57 $8.02 $0.00 $93.67
5 90.00 $64.40 $12.84 $15.57 $8.02 $0.00 $100.83
Apprentice to Journeyworker Ratio: 1:5
Page 4 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
3/1/2026 $50.85 $11.08 $11.47 $8.50 $0.00 $81.90
9/1/2026 $52.10 $11.08 $11.47 $8.50 $0.00 $83.15
CARPENTER
CARPENTERS
CARPENTERS -ZONE 2 (Eastern Massachusetts) 3/1/2027 $53.35 $11.08 $11.47 $8.50 $0.00 $84.40
10/1/2025 $27.37 $7.38 $4.47 $1.00 $0.00 $40.22CARPENTER WOOD FRAME
CARPENTERS
CARPENTERS-ZONE 3 (Wood Frame) 10/1/2026 $28.47 $7.38 $4.47 $1.00 $0.00 $41.32
All Aspects of New Wood Frame Work
Apprentice: CARPENTER
Effective Date: 3/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69
2 45.00 $22.88 $11.08 $0.00 $1.73 $0.00 $35.69
3 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45
4 55.00 $27.97 $11.08 $0.00 $3.40 $0.00 $42.45
5 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19
6 70.00 $35.60 $11.08 $11.41 $5.10 $0.00 $63.19
7 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00
8 80.00 $40.68 $11.08 $11.44 $6.80 $0.00 $70.00
Apprentice: CARPENTER
Effective Date: 9/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26
2 45.00 $23.45 $11.08 $0.00 $1.73 $0.00 $36.26
3 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14
4 55.00 $28.66 $11.08 $0.00 $3.40 $0.00 $43.14
5 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06
6 70.00 $36.47 $11.08 $11.41 $5.10 $0.00 $64.06
7 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00
8 80.00 $41.68 $11.08 $11.44 $6.80 $0.00 $71.00
Apprentice to Journeyworker Ratio: 1:5
Apprentice: CARPENTER WOOD FRAME
Effective Date: 10/1/2025
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80
2 60.00 $16.42 $7.38 $0.00 $0.00 $0.00 $23.80
3 65.00 $17.79 $7.38 $0.00 $1.00 $0.00 $26.17
4 70.00 $19.16 $7.38 $0.00 $1.00 $0.00 $27.54
5 75.00 $20.53 $7.38 $3.80 $1.00 $0.00 $32.71
6 80.00 $21.90 $7.38 $3.80 $1.00 $0.00 $34.08
Page 5 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
7/1/2026 $54.49 $13.35 $16.43 $7.78 $1.80 $93.85
1/1/2027 $55.94 $13.35 $16.43 $7.78 $1.80 $95.30
7/1/2027 $57.29 $13.35 $16.43 $7.78 $1.80 $96.65
CEMENT MASONRY/PLASTERING
PLASTERERS AND CEMENT MASONS LOCAL 534
Plasterers and Cement Masons - Zone 1
1/1/2028 $58.64 $13.35 $16.43 $7.78 $1.80 $98.00
Apprentice: CARPENTER WOOD FRAME
Effective Date: 10/1/2025
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
7 85.00 $23.26 $7.38 $3.80 $1.00 $0.00 $35.44
8 90.00 $24.63 $7.38 $3.80 $1.00 $0.00 $36.81
Apprentice: CARPENTER WOOD FRAME
Effective Date: 10/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46
2 60.00 $17.08 $7.38 $0.00 $0.00 $0.00 $24.46
3 65.00 $18.51 $7.38 $0.00 $1.00 $0.00 $26.89
4 70.00 $19.93 $7.38 $0.00 $1.00 $0.00 $28.31
5 75.00 $21.35 $7.38 $3.80 $1.00 $0.00 $33.53
6 80.00 $22.78 $7.38 $3.80 $1.00 $0.00 $34.96
7 85.00 $24.20 $7.38 $3.80 $1.00 $0.00 $36.38
8 90.00 $25.62 $7.38 $3.80 $1.00 $0.00 $37.80
Apprentice to Journeyworker Ratio: 1:5
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 7/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $27.25 $13.35 $16.43 $0.00 $0.00 $57.03
2 60.00 $32.69 $13.35 $16.43 $7.78 $1.80 $72.05
3 65.00 $35.42 $13.35 $16.43 $7.78 $1.80 $74.78
4 70.00 $38.14 $13.35 $16.43 $7.78 $1.80 $77.50
5 75.00 $40.87 $13.35 $16.43 $7.78 $1.80 $80.23
6 80.00 $43.59 $13.35 $16.43 $7.78 $1.80 $82.95
7 90.00 $49.04 $13.35 $0.00 $7.78 $0.00 $70.17
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 1/1/2027
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $27.97 $13.35 $16.43 $0.00 $0.00 $57.75
2 60.00 $33.56 $13.35 $16.43 $7.78 $1.80 $72.92
Page 6 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
6/1/2026 $41.91 $10.90 $9.75 $9.11 $0.00 $71.67
12/1/2026 $43.35 $10.90 $9.75 $9.11 $0.00 $73.11
6/1/2027 $44.80 $10.90 $9.75 $9.11 $0.00 $74.56
12/1/2027 $46.25 $10.90 $9.75 $9.11 $0.00 $76.01
6/1/2028 $47.75 $10.90 $9.75 $9.11 $0.00 $77.51
CHAIN SAW OPERATOR
LABORERS
LABORERS - ZONE 2
12/1/2028 $49.25 $10.90 $9.75 $9.11 $0.00 $79.01
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $60.61 $17.05 $13.35 $3.25 $0.00 $94.26CLAM SHELLS/SLURRY BUCKETS/HEADING MACHINES
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $62.09 $17.05 $13.35 $3.25 $0.00 $95.74
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
6/1/2026 $37.63 $17.05 $13.35 $3.25 $0.00 $71.28COMPRESSOR OPERATOR
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $38.58 $17.05 $13.35 $3.25 $0.00 $72.23
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
DELEADER (BRIDGE)
PAINTERS LOCAL 35
PAINTERS LOCAL 35 - ZONE 2
1/1/2026 $59.56 $10.35 $12.00 $12.60 $0.00 $94.51
6/1/2026 $49.30 $10.90 $9.75 $9.65 $0.00 $79.60DEMO: ADZEMAN
Apprentice: CEMENT MASONRY/PLASTERING
Effective Date: 1/1/2027
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
3 65.00 $36.36 $13.35 $16.43 $7.78 $1.80 $75.72
4 70.00 $39.16 $13.35 $16.43 $7.78 $1.80 $78.52
5 75.00 $41.96 $13.35 $16.43 $7.78 $1.80 $81.32
6 80.00 $44.75 $13.35 $16.43 $7.78 $1.80 $84.11
7 90.00 $50.35 $0.00 $16.43 $0.00 $0.00 $66.78
Apprentice to Journeyworker Ratio: 1:5
Apprentice: DELEADER (BRIDGE)
Effective Date: 1/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $29.78 $10.35 $0.00 $0.00 $0.00 $40.13
2 55.00 $32.76 $10.35 $0.00 $6.93 $0.00 $50.04
3 60.00 $35.74 $10.35 $0.00 $7.56 $0.00 $53.65
4 65.00 $38.71 $10.35 $0.00 $8.19 $0.00 $57.25
5 70.00 $41.69 $10.35 $12.00 $8.82 $0.00 $72.86
6 75.00 $44.67 $10.35 $12.00 $9.45 $0.00 $76.47
7 80.00 $47.65 $10.35 $12.00 $10.08 $0.00 $80.08
8 90.00 $53.60 $10.35 $12.00 $11.34 $0.00 $87.29
Apprentice to Journeyworker Ratio: 1:1
Page 7 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
12/7/2026 $50.80 $10.90 $9.75 $9.65 $0.00 $81.10
6/7/2027 $52.40 $10.90 $9.75 $9.65 $0.00 $82.70
12/6/2027 $54.00 $10.90 $9.75 $9.65 $0.00 $84.30
6/5/2028 $55.68 $10.90 $9.75 $9.65 $0.00 $85.98
LABORERS
LABORERS - ZONE 2
12/4/2028 $57.35 $10.90 $9.75 $9.65 $0.00 $87.65
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $50.30 $10.90 $9.75 $9.65 $0.00 $80.60
12/7/2026 $51.80 $10.90 $9.75 $9.65 $0.00 $82.10
6/7/2027 $53.40 $10.90 $9.75 $9.65 $0.00 $83.70
12/6/2027 $55.00 $10.90 $9.75 $9.65 $0.00 $85.30
6/5/2028 $56.68 $10.90 $9.75 $9.65 $0.00 $86.98
DEMO: BACKHOE/LOADER/HAMMER OPERATOR
LABORERS
LABORERS - ZONE 2
12/4/2028 $58.35 $10.90 $9.75 $9.65 $0.00 $88.65
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $50.05 $10.90 $9.75 $9.65 $0.00 $80.35
12/7/2026 $51.55 $10.90 $9.75 $9.65 $0.00 $81.85
6/7/2027 $53.15 $10.90 $9.75 $9.65 $0.00 $83.45
12/6/2027 $54.75 $10.90 $9.75 $9.65 $0.00 $85.05
6/5/2028 $56.43 $10.90 $9.75 $9.65 $0.00 $86.73
DEMO: BURNERS
LABORERS
LABORERS - ZONE 2
12/4/2028 $58.10 $10.90 $9.75 $9.65 $0.00 $88.40
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $50.30 $10.90 $9.75 $9.65 $0.00 $80.60
12/7/2026 $51.80 $10.90 $9.75 $9.65 $0.00 $82.10
6/7/2027 $53.40 $10.90 $9.75 $9.65 $0.00 $83.70
12/6/2027 $55.00 $10.90 $9.75 $9.65 $0.00 $85.30
6/5/2028 $56.68 $10.90 $9.75 $9.65 $0.00 $86.98
DEMO: CONCRETE CUTTER/SAWYER
LABORERS
LABORERS - ZONE 2
12/4/2028 $58.35 $10.90 $9.75 $9.65 $0.00 $88.65
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $50.05 $10.90 $9.75 $9.65 $0.00 $80.35
12/7/2026 $51.55 $10.90 $9.75 $9.65 $0.00 $81.85
6/7/2027 $53.15 $10.90 $9.75 $9.65 $0.00 $83.45
12/6/2027 $54.75 $10.90 $9.75 $9.65 $0.00 $85.05
6/5/2028 $56.43 $10.90 $9.75 $9.65 $0.00 $86.73
DEMO: JACKHAMMER OPERATOR
LABORERS
LABORERS - ZONE 2
12/4/2028 $58.10 $10.90 $9.75 $9.65 $0.00 $88.40
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $49.30 $10.90 $9.75 $9.65 $0.00 $79.60
12/7/2026 $50.80 $10.90 $9.75 $9.65 $0.00 $81.10
6/7/2027 $52.40 $10.90 $9.75 $9.65 $0.00 $82.70
12/6/2027 $54.00 $10.90 $9.75 $9.65 $0.00 $84.30
6/5/2028 $55.68 $10.90 $9.75 $9.65 $0.00 $85.98
DEMO: WRECKING LABORER
LABORERS
LABORERS - ZONE 2
12/4/2028 $57.35 $10.90 $9.75 $9.65 $0.00 $87.65
For apprentice rates see "Apprentice- LABORER"
6/1/2026 $58.70 $17.05 $13.35 $3.25 $0.00 $92.35DIRECTIONAL DRILL MACHINE OPERATOR
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.14 $17.05 $13.35 $3.25 $0.00 $93.79
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
Page 8 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
DIVER
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 1)
8/1/2024 $78.11 $10.08 $11.62 $10.04 $0.00 $109.85 as of 8-1-24, Apprentices with diving licenses begin at second year. % of Diver wage 70/80/90 2A $69.83, 3A $91.79,4A $102.14 Total Rate
DIVER TENDER
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 1)
8/1/2024 $55.79 $10.08 $11.62 $12.67 $0.00 $90.16 as of 8-1-24, Apprentices with diving licenses begin at second year. % of Piledriver wage 70/80/90 2A $54.20, 3A $73.93,4A $82.05 Total Rate
DIVER TENDER (EFFLUENT)
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 1)
8/1/2024 $83.69 $10.08 $11.62 $12.67 $0.00 $118.06
For apprentice rates see "Apprentice- PILE DRIVER"
DIVER/SLURRY (EFFLUENT)
PILE DRIVER LOCAL 56
PILE DRIVER LOCAL 56 (ZONE 1)
8/1/2024 $117.16 $10.08 $11.62 $12.67 $0.00 $151.53
For apprentice rates see "Apprentice- PILE DRIVER"
DRAWBRIDGE OPERATOR (Construction)
DRAWBRIDGE - SEIU LOCAL 888
DRAWBRIDGE - SEIU LOCAL 888
7/1/2020 $26.77 $6.67 $3.93 $0.00 $0.16 $37.53
3/1/2026 $66.86 $13.00 $14.64 $9.00 $0.00 $103.50
9/1/2026 $68.78 $13.00 $14.69 $9.00 $0.00 $105.47
3/1/2027 $69.97 $13.00 $14.73 $9.00 $0.00 $106.70
9/1/2027 $71.88 $13.00 $14.79 $9.00 $0.00 $108.67
ELECTRICIAN
ELECTRICIANS LOCAL 103
ELECTRICIANS LOCAL 103
3/1/2028 $73.08 $13.00 $14.82 $9.00 $0.00 $109.90
Apprentice: ELECTRICIAN
Effective Date: 3/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 40.00 $26.74 $13.00 $0.80 $0.00 $0.00 $40.54
2 40.00 $26.74 $13.00 $0.80 $0.00 $0.00 $40.54
3 45.00 $30.09 $13.00 $13.53 $4.05 $0.00 $60.67
4 45.00 $30.09 $13.00 $13.53 $4.05 $0.00 $60.67
5 50.00 $33.43 $13.00 $13.63 $4.50 $0.00 $64.56
6 55.00 $36.77 $13.00 $13.73 $4.95 $0.00 $68.45
7 60.00 $40.12 $13.00 $13.83 $5.40 $0.00 $72.35
8 65.00 $43.46 $13.00 $13.93 $5.85 $0.00 $76.24
9 70.00 $46.80 $13.00 $14.03 $6.30 $0.00 $80.13
10 75.00 $50.15 $13.00 $14.13 $6.75 $0.00 $84.03
Apprentice: ELECTRICIAN
Effective Date: 9/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
Page 9 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
1/1/2026 $77.26 $16.38 $11.06 $10.70 $0.00 $115.40ELEVATOR CONSTRUCTOR
ELEVATOR CONSTRUCTORS LOCAL 4
ELEVATOR CONSTRUCTORS LOCAL 4
1/1/2027 $80.55 $16.48 $11.16 $11.00 $0.00 $119.19
1/1/2026 $54.08 $16.38 $11.06 $10.07 $0.00 $91.59ELEVATOR CONSTRUCTOR HELPER
Apprentice: ELECTRICIAN
Effective Date: 9/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 40.00 $27.51 $13.00 $0.83 $0.00 $0.00 $41.34
2 40.00 $27.51 $13.00 $0.83 $0.00 $0.00 $41.34
3 45.00 $30.95 $13.00 $13.56 $4.05 $0.00 $61.56
4 45.00 $30.95 $13.00 $13.56 $4.05 $0.00 $61.56
5 50.00 $34.39 $13.00 $13.66 $4.50 $0.00 $65.55
6 55.00 $37.83 $13.00 $13.76 $4.95 $0.00 $69.54
7 60.00 $41.27 $13.00 $13.87 $5.40 $0.00 $73.54
8 65.00 $44.71 $13.00 $13.97 $5.85 $0.00 $77.53
9 70.00 $48.15 $13.00 $14.07 $6.30 $0.00 $81.52
10 75.00 $51.59 $13.00 $14.18 $6.75 $0.00 $85.52
Apprentice Notes
Apprentice to Journeyworker Ratio: 2:3
Apprentice: ELEVATOR CONSTRUCTOR
Effective Date: 1/1/2026
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $38.63 $0.00 $0.00 $0.00 $0.00 $38.63
2 55.00 $42.49 $16.38 $11.06 $10.70 $0.00 $80.63
3 65.00 $50.22 $16.38 $11.06 $10.70 $0.00 $88.36
4 70.00 $54.08 $16.38 $11.06 $10.70 $0.00 $92.22
5 80.00 $61.81 $16.38 $11.06 $10.70 $0.00 $99.95
Apprentice: ELEVATOR CONSTRUCTOR
Effective Date: 1/1/2027
Step Percent Apprentice Base Wage Health Pension Annuity
Supplemental Unemployment
Total Rate
1 50.00 $40.28 $0.00 $0.00 $0.00 $0.00 $40.28
2 55.00 $44.30 $16.48 $11.16 $11.00 $0.00 $82.94
3 65.00 $52.36 $16.48 $11.16 $11.00 $0.00 $91.00
4 70.00 $56.39 $16.48 $11.16 $11.00 $0.00 $95.03
5 80.00 $64.44 $16.48 $11.16 $11.00 $0.00 $103.08
Page 10 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
ELEVATOR CONSTRUCTORS LOCAL 4
ELEVATOR CONSTRUCTORS LOCAL 4
1/1/2027 $56.39 $16.48 $11.16 $11.00 $0.00 $95.03
For apprentice rates see "Apprentice - ELEVATOR CONSTRUCTOR"
6/1/2026 $41.91 $10.90 $9.75 $9.21 $0.00 $71.77FENCE & GUARD RAIL ERECTOR (HEAVY & HIGHWAY)
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $43.35 $10.90 $9.75 $9.21 $0.00 $73.21
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
5/1/2026 $54.40 $16.55 $13.35 $3.25 $0.00 $87.55
11/1/2026 $55.69 $16.55 $13.35 $3.25 $0.00 $88.84
FIELD ENG.INST.PERSON-BLDG,SITE,HVY/HWY
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
5/1/2027 $57.12 $16.55 $13.35 $3.25 $0.00 $90.27
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
5/1/2026 $56.02 $16.55 $13.35 $3.25 $0.00 $89.17
11/1/2026 $57.32 $16.55 $13.35 $3.25 $0.00 $90.47
FIELD ENG.PARTY CHIEF-BLDG,SITE,HVY/HWY
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
5/1/2027 $58.77 $16.55 $13.35 $3.25 $0.00 $91.92
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
5/1/2026 $26.28 $16.55 $13.35 $3.25 $0.00 $59.43
11/1/2026 $27.04 $16.55 $13.35 $3.25 $0.00 $60.19
FIELD ENG.ROD PERSON-BLDG,SITE,HVY/HWY
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
5/1/2027 $27.89 $16.55 $13.35 $3.25 $0.00 $61.04
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
3/1/2026 $66.86 $13.00 $14.64 $9.00 $0.00 $103.50
9/1/2026 $68.78 $13.00 $14.69 $9.00 $0.00 $105.47
3/1/2027 $69.97 $13.00 $14.73 $9.00 $0.00 $106.70
9/1/2027 $71.88 $13.00 $14.79 $9.00 $0.00 $108.67
FIRE ALARM INSTALLER
ELECTRICIANS LOCAL 103
ELECTRICIANS LOCAL 103
3/1/2028 $73.08 $13.00 $14.82 $9.00 $0.00 $109.90
For apprentice rates see "Apprentice- ELECTRICIAN"
3/1/2026 $53.49 $13.00 $14.23 $7.20 $0.00 $87.92
9/1/2026 $55.02 $13.00 $14.28 $7.20 $0.00 $89.50
3/1/2027 $55.98 $13.00 $14.31 $7.20 $0.00 $90.49
9/1/2027 $57.50 $13.00 $14.36 $7.20 $0.00 $92.06
FIRE ALARM REPAIR / MAINTENANCE
/ COMMISSIONING
ELECTRICIANS LOCAL 103
ELECTRICIANS LOCAL 103
3/1/2028 $58.46 $13.00 $14.38 $7.20 $0.00 $93.04
For apprentice rates see "Apprentice- TELECOMMUNICATIONS TECHNICIAN"
6/1/2026 $47.55 $17.05 $13.35 $3.25 $0.00 $81.20FIREMAN (ASST. ENGINEER)
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $48.73 $17.05 $13.35 $3.25 $0.00 $82.38
For apprentice rates see "Apprentice- OPERATING ENGINEERS"
6/1/2026 $29.21 $10.90 $9.75 $9.21 $0.00 $59.07FLAGGER & SIGNALER (HEAVY & HIGHWAY)
LABORERS
LABORERS - ZONE 2 (HEAVY & HIGHWAY)
12/1/2026 $29.21 $10.90 $9.75 $9.21 $0.00 $59.07
For apprentice rates see "Apprentice- LABORER (Heavy and Highway)
3/1/2026 $59.24 $10.33 $11.47 $8.80 $0.00 $89.84
9/1/2026 $60.74 $10.33 $11.47 $8.80 $0.00 $91.34
FLOORCOVERER
FLOORCOVERERS LOCAL 2168
FLOORCOVERERS LOCAL 2168 ZONE I
3/1/2027 $62.24 $10.33 $11.47 $8.80 $0.00 $92.84
Page 11 of 31Wage Request Number: 20260804195525Issue Date: 08/06/2026
Supplemental
Unemployment Total Rate
6/1/2026 $59.38 $17.05 $13.35 $3.25 $0.00 $93.03FORK LIFT/CHERRY PICKER
OPERATING ENGINEERS LOCAL 4
OPERATING ENGINEERS LOCAL 4
12/1/2026 $60.83 $17.05 $13.35 $3.25 $0.00 $94.48
For apprentice rates see…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .