This is a Statement of Work for the procurement of Vicon motion tracking cameras and supporting equipment to replace aging hardware at NASA Langley Research Center's Flight Dynamics Research Facility.
The contractor shall purchase Valkyrie Cameras, VICON Standard PC (US), Netgear MS324TXUP switch, Lock+, and related hardware from VICON. The specified equipment includes cameras with 720 frames per second capability, 2816 H x 2176 V sensor resolution, VK6 base model, 9.8-18.8mm varifocal lens, and 32.5w PoE++ power specifications. Additional requirements include 30-meter Vicon Valkyrie Camera Cables, first-year hardware warranty, a 24-port POE++ 720W managed switch, and on-site installation, setup, and training services. The work shall be performed at NASA Langley Research Center, Building 2105, Hampton, Virginia. The period of performance extends from the date of purchase through delivery, with an anticipated 4-6 week lead time based on the manufacturer's quote.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SATPC0042333 Tab 06 RDSS..pdf | ||
| SATPC0042333 Tab 07 Capability Statement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
1. Objective/Requirements
Purchase Vicon Motion tracking cameras and supporting equipment to replace existing aging Vicon hardware for the Flight Dynamics Research Facility.
2. Characteristics, Scope, and Specs
The contractor shall perform the following duties:
• Purchase a Purchase Valkyrie Cameras, VICON Standard PC (US), Netgear
MS324TXUP, Lock+, and supporting hardware from VICON with the following specs:
o FPS: 720 o Sensor resolution (pixels): 2816 H x 2176 V o Base Model: VK6 o Varifocal lens: 9.8 - 18.8 mm o 32.5w PoE++ o Vicon Valkyrie Camera Cable - 30 m o 1st Year Hardware Warranty o 24 port switch POE++ 720W managed o On-site Install, Setup and Training
3. Place of Performance
NASA Langley Research Center, Building 2105, Hampton, VA
4. Period of Performance
From date of purchase to date of delivery assuming 4-6 week lead time per manufacturer’s quote.