About this file
This is a Performance Bond template document applicable to the Merimere Dike Seepage Control project (B027-03) in Meriden, Connecticut, administered by the State of Connecticut. The bond serves as a financial guarantee that the contractor will faithfully perform all work in accordance with the contract terms and conditions. The bond covers subsurface pressure injection grouting operations, site preparation, and site restoration activities at the Merimere Dike located on Reservoir Road. The bond amount is to be determined and specified by the contracting parties at execution. The contractor and surety are jointly and severally liable to the owner for completion of the work. Any legal action under the bond must be initiated within two years from the date final payment under the contract becomes due.
The Performance Bond establishes remedies available to the owner should the contractor default, including the option to complete the contract using the surety's funds or to obtain competitive bids for completion work. The bond protects only the named owner and does not extend rights of action to other parties. The contract is funded by the Environmental Protection Agency, and Federal Labor Standards Provisions, including Davis-Bacon prevailing wage requirements, will be enforced as applicable to this work.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS, that (here insert full name and address or legal title of Contractor) as Principal herinafter called contractor and (here insert full name and address or legal title of Surety
As Surety, hereinafter called Surety, are held and firmly bound unto (here insert full name and address or legal title of Owner)
As Obligee, hereinafter called Owner, in the amount of
Dollars $___________________________ for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS,
Contractor has by written agreement dated 20 , entered into a contract with Owner for (here insert full name, address and description of project)
In accordance with Drawings and Specifications prepared by (here insert full name and address or legal title of Engineer/Architect)
Which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
PERFORMANCE BOND
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor, shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
The Surety hereby waives, notice of any alteration or defaults, under the contract or contracts of completion extension of time made by the Owner. arranged under this paragraph sufficient funds to pay the cost of completion less the balance of the contract price;
Whenever Contractor shall be, and declared by Owner but not exceeding, including other costs and damages to be in default under the Contract, the Owner having for which the Surety may be liable hereunder, the amount performed Owner’s obligations thereunder, the surety set forth in the first paragraph hereof. The term “balance may promptly remedy the default, or shall promptly of the contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor
1) Complete the Contract in accordance with its terms under the Contract and any amendments thereto, less and conditions, or the amount properly paid by Owner to Contractor.
2) Obtain a bid or bids for completing the Contract in Any suit under this bond must be instituted before accordance with its terms and conditions, and upon de- the expiration of two (2) years from the date on which termination by Surety of the lowest responsible bidder, final payment under the Contract falls due.
or, if the Owner elects, upon determination by the Owner and the Surety jointly of the lowest responsible No right of action shall accrue on this bond to or for bidder, arrange for a contract between such bidder and the use of any person or corporation other than the Owner, and make available as Work progresses (even Owner named herein or the heirs, executors, adminis-though there should be a default of a succession of trators or successors of the Owner.
Signed and sealed this day of 20
(Principal) (Witness) (Title)