This is a Standard Form of Agreement between the City of Meriden, Connecticut and a contractor for the B027-03 Merimere Dike Seepage Control project. The work involves subsurface pressure injection grouting at Merimere Dike located on Reservoir Road in Meriden, Connecticut, including site preparation, grouting operations, and site restoration to preconstruction conditions. AECOM has been designated as the engineer and Owner's representative for the project. The contractor must achieve substantial completion within 120 days from the contract commencement date and final completion within 180 days. The contract documents include general conditions, supplemental general conditions, specifications, and drawings (Sheets G-001 through C-102) on file with the City of Meriden's Purchasing Department. The contractor's bid proposal, qualification statement, and non-collusive bid statement constitute part of the contract documents and must be submitted as Attachment C.

The contract price consists of a lump sum amount for all work other than unit price work, with unit price work to be paid at established unit prices multiplied by actual quantities as determined by the engineer. Liquidated damages are assessed at $1,000 per day for delays beyond the substantial completion date and an additional $1,000 per day for failure to complete remaining work within the specified timeframe. The project is funded by the Environmental Protection Agency, requiring compliance with Federal Labor Standards Provisions and prevailing wage requirements under the Davis-Bacon and Related Acts. The contractor must provide performance and payment bonds (Attachment A) and insurance certificates (Attachment B). Connecticut Department of Labor Wage and Workplace Standards Division requirements apply. The contractor's representations confirm site familiarity, compliance with applicable laws and regulations, and satisfaction with subsurface condition reports and drawings provided.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Merimere Dike Agreement August, 2026 Seepage Control 1

STANDARD FORM OF AGREEMENT

BETWEEN OWNER AND CONTRACTOR

ON THE BASIS OF A STIPULATED PRICE

B027-03

THIS AGREEMENT is dated as of the _________ day of _______________ 2026 by and between the City of Meriden, 142 East Main Street Meriden, CT 06450 hereinafter called OWNER and ____________________________ hereinafter called CONTRACTOR.

OWNER and CONTRACTOR, in consideration of the mutual covenants hereinafter set forth, agree as follows:

Article 1. WORK.

CONTRACTOR shall complete all Work as specified or indicated in the Contract Documents. The Work is generally described as follows: See Section 01010, Summary of Work

The Project for which the Work under the Contract Documents may be the whole or only a part is generally described as follows:

B027-03- Merimere Dike Seepage Control

Article 2. ENGINEER.

The Project has been designed by AECOM, who is hereinafter called ENGINEER and who is to act as Owner’s representative, assume all duties and responsibilities and has the rights and authority assigned to ENGINEER in the Contract Documents in connection with completion of the Work in accordance with the contract Documents.

Article 3. CONTRACT TIMES.

3.1 The Work will be substantially completed within One Hundred Twenty (120) days after the date when the Contract Times commence to run as provided in paragraph 2.03 of the General Conditions, and completed and ready for final payment in accordance with paragraph 14.07B of the General Conditions within One Hundred Eighty (180) days after the date when the Contract Times commence to run.

3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the essence of this Agreement and that OWNER will suffer financial loss if the Work is not completed within the times specified in paragraph

3.1 above, plus any extensions thereof allowed in accordance with Article 12 of the General Conditions. They also recognize the delays, expense and difficulties involved in proving the actual loss suffered by OWNER if the Work is not completed on time. Accordingly, instead of requiring any such proof, OWNER and CONTRACTOR agree that as liquidated damages for delay (but not as a penalty) CONTRACTOR shall pay OWNER One Thousand dollars ($1,000.00) for each day that expires after the time specified in paragraph 3.1 for Substantial Completion until the Work is substantially complete. After Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete the remaining Work within the time specified in paragraph 3.1 for completion and readiness for final payment or any proper extension thereof granted by OWNER, CONTRACTOR shall pay OWNER One Thousand dollars ($1,000.00) for each day that expires after the time specified in paragraph 3.1 for completion and readiness for final payment.

Seepage Control 2

Article 4. CONTRACT PRICE.

OWNER shall pay CONTRACTOR for completion of the Work in accordance with the Contract Documents an amount in current funds equal to the sum of the amounts determined pursuant to paragraphs 4.1 and 4.2 below:

4.1. For all Work, other than Unit Price Work, a Lump Sum of:

Figures

______________________________________________________________________________ Dollars Written

All specific cash allowances are included in the above price and have been computed in accordance with 11.02 of the General Conditions;

plus

4.2. For all Unit Price Work, an amount equal to the sum of the established unit price for each separately identified item of Unit Price Work times the estimated quantity of that item as indicated in this paragraph 4.2:

UNIT PRICE WORK

ESTIMATED UNIT TOTAL

NO. ITEM UNIT QUANTITY PRICE ESTIMATED

TOTAL OF ALL UNIT PRICES:

Written Figures

Bid Attached.

As provided in paragraph 11.03 of the General Conditions estimated quantities are not guaranteed, and determinations of actual quantities and classification are to be made by ENGINEER as provided in paragraph

9.07 of the General Conditions. Unit prices have been computed as provided in paragraph 11.03C of the General Conditions.

(The Bid may be attached. Any attachments and/or exhibits attached should be listed in Article 8).

Seepage Control 3

If adjustment prices for variations from stipulated Base Bid quantities have been agreed to, insert appropriate provisions.

Article 5. Deleted in its entirety.

Article 6. Deleted in its entirety.

Article 7. CONTRACTOR’S REPRESENTATIONS.

In order to induce OWNER to enter into this Agreement CONTRACTOR makes the following representations:

7.1. CONTRACTOR has examined and carefully studied the Contract Documents including the Addenda listed in paragraph 8 and the other related data identified in the Bidding Documents including “technical data.”

7.2. CONTRACTOR has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance or furnishing of the Work.

7.3. CONTRACTOR is familiar with and is satisfied as to all federal, state and local Laws and Regulations that may affect cost, progress, performance and furnishing of the Work.

7.4. CONTRACTOR has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except Underground Facilities) which have been identified in the Supplementary Conditions as provided in paragraph 4.02 of the General Conditions. CONTRACTOR accepts the determination of the extent of the “technical data” contained in such reports and drawings upon which CONTRACTOR is entitled to rely. CONTRACTOR acknowledges that such reports and drawings are not Contract Documents and may not be complete for Contractor’s purposes. CONTRACTOR acknowledges that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to Underground Facilities at or contiguous to the site. CONTRACTOR has obtained and carefully studied assumes responsibility for having done so) all such additional supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the site or otherwise which may affect cost, progress, performance or furnishing of the Work or which relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by CONTRACTOR and safety precautions and programs incident thereto. CONTRACTOR does not consider that any additional examinations, investigations, explorations, tests, studies or data are necessary for the performance and furnishing of the Work at the Contract Price, within the Contract Times and in accordance with the other terms and conditions of the contract Documents.

7.5. CONTRACTOR is aware of the general nature of work to be performed by OWNER and others at the site that relates to the Work as indicated in the Contract Documents.

7.6. CONTRACTOR has correlated the information known to CONTRACTOR, information and observation obtained from visits to the site, reports and drawings identified in the Contract Documents and all additional examinations, investigations, explorations, tests, studies and data with the Contract Documents.

7.7. CONTRACTOR has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that CONTRACTOR has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to CONTRACTOR, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

Seepage Control 4

Article 8. CONTRACT DOCUMENTS.

The Contract Documents, which comprise the entire agreement between OWNER and CONTRACTOR concerning the Work, consist of the following:

8.1. This Agreement.

8.2. General Conditions and Supplemental General Conditions.

8.3. Performance, Payment, and other Bonds – Attachment A.

8.4. Insurance certificate – Attachment B.

8.5. Contractor’s Bid Proposal, Non-Collusive Bid Statement, Bidder’s Qualification Stmt – Attachment C.

8.6. Connecticut Department of Labor – Wage and Workplace Standards Division.

8.7. Davis-Bacon Act which requires payment of prevailing wages to laborers and mechanics employed on federal and federally assisted construction projects.

8.8. “By Reference”: The complete Specifications as included in the bidding documents bearing the title, Merimere Dike Seepage Control

8.9. “By Reference”: List of Drawings: Sheet No’s. G-001 through C-102 included in the bidding

The above documents are on file in the City of Meriden’s Purchasing Department.

8.10. Addenda numbers and .

(Those addenda which pertain exclusively to the bidding process need not be listed.)

8.11. The following which may be delivered or issued after the Effective Date of the Agreement and are not attached hereto: All-Written Amendments and other documents amending, modifying or supplementing the Contract Documents pursuant to paragraphs 3.04 and 3.05 of the General Conditions.

There are no Contract Documents other than those listed above. The Contract Documents may only be amended, modified or supplemented as provided in paragraphs 3.04 and 3.05 of the General Conditions.

Article 9. MISCELLANEOUS.

9.1. Terms used in this Agreement which are defined in Article I of the General Conditions will have the meanings indicated in the General Conditions.

9.2. No assignment by a party hereto of any rights under or interests in the Contract Documents will be binding on another party hereto without the written consent of the party sought to be bound; and, specifically but without limitation, moneys that may become due and moneys that are due may not be assigned without such consent (except to the extent that the effect of this restriction may be limited by law), and unless specifically stated to the contrary in any written consent to an assignment no assignment will release or discharge the assignor from any duty or responsibility under the Contract Documents.

Seepage Control 5

9.3. OWNER and CONTRACTOR each binds itself, its partners, successors, assigns and legal representatives to the other party hereto, its partners, successors, assigns and legal representatives in respect to all covenants, agreements and obligations contained in the Contract Documents.

9.4. Any provision or part of the Contract Documents held to be void or unenforceable under any Law or Regulation shall be deemed stricken, and all remaining provisions shall continue to be valid and binding upon OWNER and CONTRACTOR, who agree that the Contract Documents shall be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.

WITNESS WHEREOF, the parties hereto have affixed their names and seals.

THE CITY OF MERIDEN CONTRACTOR:

Brian P. Daniels Duly Authorized Duly Authorized

Date:_________________________ Date:__________________________

END OF SECTION

Seepage Control 6

“Page Intentionally Left Blank”