S02 - Specifications - 607-19-106.pdf
PDF 3 MB Posted
- Solicitation number
- 36C25220B0027
About this file
This presolicitation notice announces a forthcoming solicitation for construction services. The project involves modernizing the hot water system in C-wing at the William S. Middleton Memorial Veterans Hospital in Madison, Wisconsin. Work includes installing a new mechanical chase and risers, a new heating water supply station, a new steam pressure reducing station, replacing various mechanical lines including hot water distribution lines, steam supply lines, chilled water lines, and replacing steam convectors/radiators with heating water units. A pre-bid conference will be held. The solicitation, specifications and drawings will be posted on Contact Opportunities. The procurement is set aside for Service-Disabled Veteran-Owned Small Businesses. Offerors must represent their SDVOSB eligibility and small business size status at time of submission. The estimated value is between $2-5 million. The NAICS code is 236220 with a $39.5 million size standard. The period of performance is 365 days after notice to proceed. The solicitation will be issued on or about August 25, 2020 with bids due September 24, 2020. Amendments will be posted to Contact Opportunities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| S06 - SF1442.pdf | ||
| S06 - Pre-Bid Attendance List.pdf | ||
| 36C25220B0027 0002.docx | DOCX document | |
| S06 - Wage Determination.pdf | ||
| 36C25220B0027 0001.docx | DOCX document | |
| S02 - Drawings - VOL2 607-19-106.pdf | ||
| S02 - Drawings - VOL3 607-19-106.pdf | ||
| S02 - Drawings - VOL4 607-19-106.pdf | ||
| P07 - Wage Determination.pdf | ||
| S02 - Drawings - VOL1 607-19-106.pdf | ||
| 36C25220B0027_1.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT SPECIFICATIONS
FOR 100% CONSTRUCTION DOCUMENTS
Specifications (Div: 00- 26)
PROJECT TITLE: Modernize C-Wing HWS VA PROJECT NO.: Project 607-19-106
Wm S. Middleton VA Medical Center Madison, Wisconsin
05-01-19
00 01 10-1
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15 00 01 16 Submittal Register
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-13 01 33 23 Shop Drawings, Product Data, and Samples 05-17 01 35 26 Safety Requirements 02-17 01 42 19 Reference Standards 05-16 01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17 02 82 11 Traditional Asbestos Abatement 09-15 02 82 13.13 Glovebag Asbestos Abatement 09-15 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15 02 82 13.31 Asbestos Transite Abatement 09-15 02 83 33.13 Lead-Based Paint Removal and Disposal 08-16
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 02-16
DIVISION 05 – METALS
05 50 00 Metal Fabrications 08-18
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 60 00 Flashing and Sheet Metal 07-14 07 84 00 Firestopping 02-16 07 92 00 Joint Sealants 10-17
DIVISION 08 - OPENINGS
08 31 13 Access Doors and Frames 02-16 08 71 00 Door Hardware 01-16
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 04-15 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 09-18 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 02-16 09 91 00 Painting 01-16
00 01 10-2
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 10-15
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 08-17
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16 22 05 23 General-Duty Valves for Plumbing Piping 09-15 22 07 11 Plumbing Insulation 09-15 22 11 00 Facility Water Distribution 09-15 22 13 00 Facility Sanitary and Vent Piping 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 08-17
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment
02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15 23 07 11 HVAC and Boiler Plant Insulation 02-15 23 08 00 Commissioning of HVAC Systems 11-16 23 08 11 Demonstrations and Tests for Boiler Plant 08-17 23 09 23 Direct-Digital Control System for HVAC 09-11 23 11 23 Facility Natural-Gas Piping 08-17 23 21 13 Hydronic Piping 08-17 23 21 23 Hydronic Pumps 08-17 23 22 13 Steam and Condensate Heating Piping 08-17 23 25 00 HVAC Water Treatment 02-15 23 31 00 HVAC Ducts and Casings 03-13 23 51 00 Breechings, Chimneys, and Stacks 08-17 23 52 25 Low-Pressure Water Heating Boilers 08-17 23 82 00 Convection Heating and Cooling Units 04-11 23 82 16 Air Coils 04-11
DIVISION 25 – INTEGRATED AUTOMATION
25 13 00 Building Automation System (BAS) Integration 08-13
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16 26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17 26 05 26 Grounding and Bonding for Electrical Systems 01-17
00 01 10-3
26 05 33 Raceway and Boxes for Electrical Systems 01-18 26 24 16 Panelboards 01-18 26 29 11 Motor Controllers 01-18 26 29 21 Enclosed Switches and Circuit Breakers 01-17 26 51 00 Interior Lighting 01-18
07-01-15
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title General
GI001 Title Sheet
GI002 General Infection Control and Phasing Notes, and Symbols
Environmental HA100 Basement Floor- C-Wing Asbestos Abatement
HA10G Ground Floor- Ab C-Wing Asbestos Abatement
HA101 First Floor- C-Wing Asbestos Abatement
HA102 Second Floor- C-Wing Asbestos Abatement
HA103 Third Floor- C-Wing Asbestos Abatement
HA104 Fourth Floor- C-Wing Asbestos Abatement
ARCHITECTURAL
AD100 Basement Floor- Demolition Plan
AD10G Ground Floor- Demolition Plan
AD101 First Floor- Demolition Plan
AD102 Second Floor- Demolition Plan
AD103 Third Floor- Demolition Plan
AD104 Fourth Floor- Demolition Plan
A100 Basement Floor- Construction Plan
A10G Ground Floor- Construction Plan
A101 First Floor- Construction Plan
A102 Second Floor- Construction Plan
A103 Third Floor- Construction Plan
A104 Fourth Floor- Construction Plan
A105 Fifth Floor – Penthouse Roof- New Work Plan
A500 Details for Shaft Wall Construction, Ceiling and Soffit Details
Structural S001 Structural – General Notes
SD100 Basement Floor- Demolition Plan
00 01 15 - 2
SD10G Ground Floor- Demolition Plan
SD101 First Floor- Demolition Plan
SD102 Second Floor- Demolition Plan
SD103 Third Floor- Demolition Plan
SD104 Fourth Floor- Demolition Plan
SD105 Fourth Floor- Demolition Plan
S105 Fifth Floor – New Work Plan
Plumbing P000 Plumbing Details, Notes, Symbols and
Abbreviations
P100 Partial Floor Plans C-Wing Plumbing
Fire Protection FP000 Fire Protection Symbols and Abbreviations
FP100 Basement Floor C-Wing Fire Protection
MECHANICAL
MOOO Mechanical Notes, Symbols and Abbreviations
MD100 Basement Floor- C-Wing HVAC Piping Demolition
MD10G Ground Floor- C-Wing HVAC Piping and Ductwork Demolition
MD101 First Floor- C-Wing HVAC Piping and Ductwork Demolition
MD102 Second Floor- C-Wing HVAC Piping and Ductwork Demolition
MD103 Third Floor- C-Wing HVAC Piping and Ductwork Demolition
MD104 Fourth Floor- C-Wing HVAC Piping and Ductwork Demolition
MD105 Fifth Floor- C-Wing HVAC Piping and Ductwork Demolition
MD300 Fifth Floor – C-Wing - Enlarged Penthouse Plan - Piping Demolition
M100 Basement Floor- C-Wing HVAC Piping New Work
M10G Ground Floor- C-Wing HVAC Piping and Ductwork New Work
M101 First Floor- C-Wing HVAC Piping and Ductwork Demolition
M102 Second Floor- C-Wing HVAC Piping and Ductwork New Work
M103 Third Floor- C-Wing HVAC Piping and Ductwork New
00 01 15 - 3
Work
M104 Fourth Floor- C-Wing HVAC Piping and Ductwork New Work
M105 Fifth Floor- C-Wing HVAC Piping and Ductwork New Work
M300 Fifth Floor – C-Wing - Enlarged Penthouse Plan - Piping New Work
M301 Enlarged Plans
M400 Mechanical Risers
M401 Mechanical Risers
M402 Mechanical Risers
M500 Mechanical Details
M501 Mechanical Details
M502 Mechanical Details
M503 Mechanical Photos
M600 Mechanical Controls
M601 Mechanical Controls
M700 Mechanical Schedules
M701 Mechanical Schedules
Electrical E001 Electrical Symbols, Abbreviations and Notes
E100 Basement Floor Plan – Electrical Demolition/ New Work
E10G Ground Floor Plan – Electrical Demolition/ New Work
E101 First Floor Plan – Electrical Demolition/ New Work
E102 Second Floor Plan – Electrical Demolition/ New Work
E103 Third Floor Plan – Electrical Demolition/ New Work
E104 Fourth Floor Plan – Electrical Demolition/ New Work
E105 Fifth Floor Plan – Electrical Power Demolition/New Work
EP600 Electrical Lighting Panel Distribution Schedules and Equipment New Work
00 01 15 - 4
- - - E N D - - -
SECTION 00 01 16
SUBMITTAL REGISTER
# Section # Title Due
1 01 32 16.15 Project Schedule 15 days from NTP, Before work on site
2 01 32 16.15 Schedule of Values 15 days from NTP, Before work on site
3 01 35 26 Construction Safety & Health Plan Before work on site
4 01 35 26 Activity Hazard Analyses As Needed
5 01 35 26 Lift Plan As Needed
6 01 74 19 Waste Management Plan Before work on site
7 01 74 19 Final summary of construction and demolition debris diversion and disposal Post-construction
8 03 30 53 Cast In Place Concrete: Mix Design Pre-Construction
DIV 05 - METALS
9 05 50 00 Shop Drawings Pre-construction
10 05 50 00 Certificates of Compliance and Test Reports Pre-construction
11 05 50 00 Manufacturer's Literature and Data Pre-construction
12 07 60 00 Manufacturer's Literature and Data Pre-construction
13 07 60 00 Shop Drawings Pre-construction
14 07 60 00 Certificates of Compliance and Test Reports Pre-construction
15 07 84 00 Manufacturer's Literature and Data Pre-construction
16 07 84 00 List of FM, UL, or WH Classification Pre-construction
17 07 92 00 Joint Sealants: Literature Pre-construction
18 07 92 00 Certificates and qualifications Pre-construction
19 07 92 00 Warranty Pre-construction
20 08 31 13 Shop Drawings Pre-construction
21 08 31 13 Manufacturer's Literature and Data Pre-construction
22 08 71 00 Hardware Schedule Pre-construction
23 08 71 00 Samples and Manufacturers' Literature Pre-construction
24 08 71 00 Certificates of Compliance and Test Reports Pre-construction
25 09 22 16 Shop Drawings Pre-construction
26 09 22 16 Manufacturer's Literature and Data Pre-construction
27 09 22 16 Test Results Pre-construction
28 09 29 00 Manufacturer's Literature and Data Pre-construction
29 09 29 00 Shop Drawings Pre-construction
30 09 29 00 Samples Pre-construction
31 09 29 00 Test Results Pre-construction
32 09 29 00 Certificates of Compliance and Test Reports Pre-construction
33 09 51 00 Shop Drawings Pre-construction
34 09 51 00 Samples Pre-construction
35 09 51 00 Manufacturer's Literature and Data Pre-construction
36 09 51 00 Manufacturer's Certificates Pre-construction
37 09 65 13 Manufacturer's Literature and Data Pre-construction
DIV 07 - THERMAL AND MOISTURE PROTECTION
DIV 08 - OPENINGS
DIV 09 - FINISHES
DIV 01 - GENERAL REQUIREMENTS
DIV 03 - CONCRETE
00 01 16 -1
# Section # Title Due
38 09 65 13 Samples Pre-construction
39 09 65 13 Warranty Pre-construction
40 09 91 00 Manufacturer's Literature and Data Pre-construction
41 09 91 00 Sample Panels Pre-construction
42 09 91 00 Manufacturer's Certificates Pre-construction
DIV 10 - SPECIALTIES
43 10 26 00 Shop Drawings Pre-construction
44 10 26 00 Manufacturer's Literature and Data Pre-construction
45 10 26 00 Samples Pre-construction
46 10 26 00 Manufacturer's Certificates Pre-construction
47 10 26 00 Warranty Pre-construction
DIV 12 - FURNISHES
48 12 24 00 Manufacturer's Literature and Data Pre-construction
49 12 24 00 Samples Pre-construction
50 21 13 13 WET-PIPE SPRINKLER SYSTEMS: Calculations Pre-construction
51 21 13 13 Product Data - Submittals Pre-construction
52 21 13 13 As-Built Drawings Post-construction
53 21 13 13 Training Post-construction
54 21 13 13 Inspector's sign off on testing and construction
Post-construction
55 22 05 11 COMMON WORK RESULTS FOR PLUMBING: Product
Data - Submittals
Pre-construction
56 22 05 11 Product Data O&Ms - Submittals Post-construction
57 22 05 23 GENERAL-DUTY VALVES FOR PLUMBING PIPING:
Product Data - Submittals
Pre-construction
58 22 07 11 PLUMBING INSULATION: Product Data -
Submittals
Pre-construction
59 22 11 00 FACILITY WATER DISTRIBUTION: Product Data -
Submittals
Pre-construction
60 22 13 00 FACILITY SANITARY AND VENT PIPING Pre-construction
61 22 13 00 As-Built Drawings Post-construction
62 22 13 00 Training Post-construction
63 22 13 00 Inspector's sign off on testing and construction
Post-construction
64 23 05 11 COMMON WORK RESULTS FOR HVAC: Product Data
O&Ms - Submittals
Post-construction
65 23 05 12 GENERAL MOTOR REQUIREMENTS FOR HVAC AND STEAM
GENERATION EQUIPMENT: Product Data -
Submittals
Pre-construction
66 23 05 41 NOISE AND VIBRATION CONTROL FOR HVAC PIPING
AND EQUIPMENT: Product Data - Submittals
Pre-construction
67 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC:
TAB Submittals (phased)
Pre-construction
68 23 05 93 TAB Submittal Post-construction
69 23 07 11 HVAC AND BOILER PLANT INSULATION: Product
Data - Submittals
Pre-construction
70 23 08 00 COMMISSIONING OF HVAC SYSTEMS: Construction
Verification Checklist sheets
Pre-construction
DIV 21 - FIRE
DIV 22 - PLUMBING
DIV 23 - HEATING, VENTILATION AND AIR CONDITIONING
00 01 16 -2
# Section # Title Due
71 23 08 00 Functional performance test sheets Post-construction
72 23 08 00 Final Commissioning Report Post-construction
73 23 08 11 DEMONSTRATIONS AND TESTS FOR BOILER PLANT:
Product Data - Submittals
Pre-construction
74 23 09 23 DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC:
Product Data - Submittals
Pre-construction
75 23 11 23 FACILITY NATURAL-GAS PIPING: Product Data -
Submittals
Pre-construction
76 23 21 13 HYDRONIC PIPING: Product Data - Submittals Pre-construction
77 23 21 23 HYDRONIC PUMPS: Product Data - Submittals Pre-construction
78 23 21 23 Start up paperwork Post-construction
79 23 22 13 STEAM AND CONDENSATE HEATING PIPING: Product
Data - Submittals
Pre-construction
80 23 25 00 HVAC WATER TREATMENT: Product Data -
Submittals
Pre-construction
81 23 25 00 Start up paperwork Post-construction
82 23 31 00 HVAC DUCTS AND CASINGS: Product Data -
Submittals
Pre-construction
83 23 51 00 BREECHINGS, CHIMNEYS AND STACKS: Product Data
- Submittals
Pre-construction
84 23 52 25 LOW-PRESSURE WATER HEATING BOILERS: Product
Data - Submittals
Pre-construction
85 23 52 25 Start up paperwork Post-construction
86 23 82 00 CONVECTION HEATING AND COOLING UNITS: Product
Data - Submittals
Pre-construction
87 23 82 00 Start up paperwork Post-construction
88 23 82 16 AIR COILS: Product Data - Submittals Pre-construction
89 25 13 00 BUILDING AUTOMATION SYSTEM (BAS) INTEGRATION:
Product Data - Submittals
Pre-construction
90 25 13 00 As-Built Drawings Post-construction
91 25 13 00 Training Post-construction
92 25 13 00 Inspector's sign off on testing and construction
Post-construction
93 26 05 19 Elec conductor and cable information Pre-construction
94 26 05 19 Installation certification Pre-construction
95 26 05 26 Shop Drawings Pre-construction
96 26 05 26 Test Reports Pre-construction
97 26 05 26 Installation certification Post-construction
98 26 05 33 Raceway & Boxes shop drawings Pre-construction
99 26 05 33 Raceway & Boxes certification Post-construction
100 26 24 16 Panelboard: Shop drawings Pre-construction
101 26 24 16 Manuals Pre and Post-construction
102 26 24 16 Certification Post-construction
103 26 29 11 Motor Controllers: Shop drawings Pre-construction
104 26 29 11 Motor Controllers: Certification Post-construction
105 26 29 11 Manuals Pre and Post-construction
106 26 29 21 Disconnects: Shop drawings Pre-construction
107 26 29 21 Certification Post-construction
108 26 29 21 Manuals Pre and Post-construction
109 26 51 00 Lighting : Shop drawings Pre-construction
110 26 51 00 Manuals Pre and Post-construction
DIV 26 - ELECTRICAL
00 01 16 -3
# Section # Title Due
111 26 51 00 Lighting: Certification Post-construction
00 01 16 -4
12-01-18 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.10 RESTORATION
1.11 PHYSICAL DATA
1.13 LAYOUT OF WORK
1.14 AS-BUILT DRAWINGS
1.16 USE OF ROADWAYS
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.19 TEMPORARY USE OF EXISTING ELEVATORS
1.21 TEMPORARY TOILETS
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
1.24 TESTS
1.25 INSTRUCTIONS
1.27 RELOCATED EQUIPMENT ITEMS
1.31 PHOTOGRAPHIC DOCUMENTATION
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. See Solicitation Bid Schedule
1.3 STATEMENT OF BID ITEM(S)
A.SEE BID SCHEDULE.
01 00 00 -2
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense,.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security can be provided
01 00 00 -3 for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
01 00 00 -4
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be within the jobsite’s space being renovated..
01 00 00 -5
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
F*. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; . All such actions shall be coordinated with the COR or Utility Company involved:
G. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
01 00 00 -6
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:
H. Cwing Part of Bldg. 1_will be vacated by Government in accordance with above phasing beginning immediately after date of receipt of Notice to
Proceed and turned over to Contractor.
K. Utilities Services: Maintain existing utility services for Cemetery at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR [Chief Engineer][Chief of
Facilities Management]. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the
Medical Center Director’s prior knowledge and written approval.
Refer to specification Sections 26 05 11, REQUIREMENTS FOR
ELECTRICAL INSTALLATIONS, for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 21 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
01 00 00 -7
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
01 00 00 -8
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative //, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls
01 00 00 -9 and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain
01 00 00 -10 the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
01 00 00 -11
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.13 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR
01 00 00 -12
1.14 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR review, as often as requested.
C. Contractor shall deliver two approved completed sets ofas-built drawings in the electronic version (scanned PDF) to the COR [Chief
Engineer][Chief of Facilities Management] within 15 calendar days after beneficial accupancy nd before the acceptance of the project by the
COR
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.16 USE OF ROADWAYS
A. For hauling, use only established public roads and roads on Medical
Center property and, when authorized by the COR such temporary roads which are necessary in the performance of contract work. Temporary roads shall be constructed and restoration performed by the Contractor at Contractor's expense. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.18 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:
1. Permission to use each unit or system must be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the
COR will withdraw permission for use of the equipment.
2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted.
01 00 00 -13
Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical Code, (2014
Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.
3. Units shall be properly lubricated, balanced, and aligned.
Vibrations must be eliminated.
4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.
5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.
6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use; maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the GovernmentB.
Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.
C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.
D. Any damage to the equipment or excessive wear due to prolonged use will be repaired replaced by the contractor at the contractor’s expense.
1.19 TEMPORARY USE OF EXISTING ELEVATORS
A. Contractor will not be allowed the use of existing elevators. Outside type hoist shall be used by Contractor for transporting materials and equipment.
01 00 00 -14
A*. Use of existing freight elevator #5s for handling building materials and Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The CORwill ascertain that elevators are in proper condition.
Contractor may use elevators Nos. __5_____ in Building Nos. __1____ for exclusive use for daily use between the hours of __8am-5 pm______. and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.
2. PLACE ELEVATOR IN CONDITION EQUAL, LESS NORMAL WEAR, TO THAT EXISTING AT
TIME IT WAS PLACED IN SERVICE OF CONTRACTOR AS APPROVED BY CONTRACTING
OFFICER. 1.21 TEMPORARY TOILETS
A. Provide where directed, (for use of all Contractor's workers) ample temporary sanitary toilet accommodations with suitable sewer and water connections; or, when approved by COR , provide suitable dry closets where directed. Keep such places clean and free from flies, and all connections and appliances connected therewith are to be removed prior to completion of contract, and premises left perfectly clean.
B. Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center.
Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.
1.22 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the Government. The Contractor shall carefully conserve any utilities furnished without charge.
B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, 01 00 00 -15 shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.
C. Contractor shall install meters at Contractor's expense and furnish the
Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.
D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:
1. Obtain heat by connecting to Medical Center heating distribution system.
E. Electricity (for Construction and Testing): Furnish all temporary electric services.
1. Obtain electricity by connecting to the Medical Center electrical distribution system. The Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.
F. Water (for Construction and Testing): Furnish temporary water service.
1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the
Contractor.
2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted. Failure to stop leakage or other wastes
01 00 00 -16 will be cause for revocation (at COR discretion) of use of water from Medical Center's system.
1.24 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental
01 00 00 -17 conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.25 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of equipment that are component parts of a complete system, shall be given
01 00 00 -18 in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in the operation of inter-related systems. All instruction periods shall be at such times as scheduled by the COR and shall be considered concluded only when the COR is satisfied in regard to complete and thorough coverage. The contractor shall submit a course outline with associated material to the COR for review and approval prior to scheduling training to ensure the subject matter covers the expectations of the VA and the contractual requirements. The Department of Veterans Affairs reserves the right to request the removal of, and substitution for, any instructor who, in the opinion of the COR , does not demonstrate sufficient qualifications in accordance with requirements for instructors above.
1.27 RELOCATED EQUIPMENT ITEMS
A. Contractor shall disconnect, dismantle as necessary, remove and reinstall in new location, all existing equipment and items indicated by symbol "R" or otherwise shown to be relocated by the Contractor.
B. Perform relocation of such equipment or items at such times and in such a manner as directed by the COR .
C. Suitably cap existing service lines, such as steam, condensate return, water, drain, gas, air, vacuum and/or electrical, at the main whenever such lines are disconnected from equipment to be relocated. Remove abandoned lines in finished areas and cap as specified herein before under paragraph "Abandoned Lines".
D. Provide all mechanical and electrical service connections, fittings, fastenings and any other materials necessary for assembly and installation of relocated equipment; and leave such equipment in proper operating condition.
F. All service lines such as noted above for relocated equipment shall be in place at point of relocation ready for use before any existing equipment is disconnected. Make relocated existing equipment ready for operation or use immediately after reinstallation.
01 00 00 -19
1.31 PHOTOGRAPHIC DOCUMENTATION
A. During the construction period through completion, furnish the VA's COR an average of 25 views of digital color images per month. These digital views shall be taken of the exterior and/or interior depending on the location of the progress made during the construction. The subject matter of these pictures shall be representative of the work being done during the construction period through to the end of the construction. Provide the photos taken for the month to the COR electronically, or on a CD. A CD that contains all of the photos taken for the project is also required at the end of the project. Note: Ensure that no patients, license plates, VA employees or personal identifiable information are in the pictures.
B. Photographic documentation elements:
1. Before construction, the building pad, adjacent streets, roadways, parkways, driveways, curbs, sidewalks, landscaping, adjacent utilities and adjacent structures surrounding the building pad and site shall be documented. - - - E N D - - -
02-01-15
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS – DESIGN/BID/BUILD)
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COTR).
B. The Contractor's…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .