S02 - HS Scope of Work - Final Revised 5-16-22.pdf

PDF 148 KB Posted

Attached to
Y1DA--568A4-21-702 EHRM Infrastructure Construction - Hot Springs, SD Federal contract opportunity
Solicitation number
36C77622B0032
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This scope of work document outlines the requirements for an infrastructure upgrade project at the Hot Springs VA Medical Center. The selected contractor will be responsible for renovating and upgrading data cable infrastructure across multiple campus buildings, which involves demolishing abandoned phone lines, upgrading electrical panels and emergency generators, renovating mechanical systems, upgrading the data center and telecommunications rooms, installing new data outlets and fiber optic cabling, conducting asbestos abatement and lead paint removal, and implementing physical security and fire system integrations. The contractor must coordinate their work to minimize downtime to hospital operations and security and fire systems. The performance period is 365 calendar days from notice to proceed. The solicitation number for this opportunity is 36C77622B0032.

View the file

Other files for this federal contract opportunity

Other files attached to Y1DA--568A4-21-702 EHRM Infrastructure Construction - Hot Springs, SD, newest first.
File Type Posted
36C77622B0032 0009.pdf PDF
S05 - Technical Questions - Hot Springs - 8.8.22.pdf PDF
36C77622B0032 0008.pdf PDF
36C77622B0032 0007.pdf PDF
36C77622B0032 0006.pdf PDF
36C77622B0032 0005.pdf PDF
Hot Springs VA EHRM Upgrade Amendment 2 of 2.pdf PDF
Hot Springs VA EHRM Upgrade Amendment 1 of 2.pdf PDF
36C77622B0032 0004.pdf PDF
36C77622B0032 0003.pdf PDF
36C77622B0032 0002.docx DOCX document
Hot Springs EHRM Site Visit Sign In Sheet.pdf PDF
S02 - EHRM Final Drawings Volume 1B - 2022-05-12.pdf PDF
S02 - EHRM Final Drawings Volume 1A - 2022-05-12.pdf PDF
S02 - EHRM Final Drawings Volume 2 - 2022-05-12.pdf PDF
S02 - EHRM Final Drawings Volume 4 - 2022-05-12.pdf PDF
S02 - PCRA ICRA Risk Assessment v2.pdf PDF
36C77622B0032_1.docx DOCX document
S02 - Specifications Volume 3 - Rev100 - 4-25-22.pdf PDF
S02 - EHRM Final Drawings Volume 3 - 2022-05-12.pdf PDF
S02 - Specifications Volume 1 - Rev100 - 4-25-22.pdf PDF
S02 - Cutsheets Small Diameter CAT6A - Final.zip ZIP file
S02 - Wage Rates - Fall River - 2.25.22.pdf PDF
S02 - Old-New TR Telecommunication Rooms.pdf PDF
S02 - HS Campus Ground Infrastructure 2.pdf PDF
S02 - Background Report Investigation Form.pdf PDF
S02 - Brand Name Justification - Hot Springs.pdf PDF
S02 - Campus Map - Hot Springs.pdf PDF
S02 - Contractor Safety - Environmental Form.docx DOCX document
S02 - HS Campus Ground Infrastructure.pdf PDF
S02 - Specifications Volume 2 - Rev100 - 4-25-22.pdf PDF
S02 - COVID-19 Safety Protocols 12-14-21.pdf PDF
Show all 32

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5‐16‐22

P a g e 1 | 4

Scope of Work (SOW)

EHRM Infrastructure Upgrades Construction – Hot Springs, SD

*The purpose of this SOW is to provide additional information to what is in the Drawings and Specifications. The Specs and Drawings Supersede this SOW.

The Hot Springs VAMC is seeking a general contractor to furnish all labor, tools, material, equipment, and supervision for a near‐complete refresh of the data cable infrastructure. The scope of this project includes but not limited to the following infrastructure improvements:

Demolition Applicable to each category below

Phone lines 14k‐33k phone line pairs in buildings (backbone from building to building to remain in support of existing mass communications system and ancillary fax/building access phones) Demo and remove all abandoned hardware and cables

Electrical Panel upgrades (normal and emergency/bonding) Emergency generator upgrade building 10 Integrate into the fire alarm system

Mechanical Upgrades/replacement/relocate of existing HVAC

DDC HVAC

Condensate drain piping Provide cooling loops Renovation (piping, exterior wall, interior wall for water proofing) Commissioning (spec 23 05 93)

Fire System Data Center (DC) room upgrade (building 65)

Sprinkler head migration Renovation

Expansion and renovation of existing space Walls, doors, ESD flooring, painting, Rack alignment, fire stopping

New building expansion (buildings 1, 11, and 66) IT specialty, cable/data outlet

Migrating from 50 IT closets/cabinets to 29 TRs/cabinets Data Center (DC) upgrades (building 66) Upgrades to TR/DC rooms

Racks, sensor, UPS, zone and vertical (amp monitored) PDU’s, patch panels Separate IT equipment ground bonding per building Cable trays/management

New data outlets Upgrade to CAT6A cable in buildings Upgrade campus backbone and building fiber, dual pathing Commission of communications system (spec 27 08 00)

Physical security upgrades

TR/DC

P a g e 2 | 4

Hazardous material abatement Asbestos Abatement Lead Paint

Campus ground vault system New route from building 65 to 66

Data line demolition of abandoned infrastructure and upgrades Phasing

Minimize down times for hospital operations Minimize security and fire system down times Maintaining a clean area per ICRA/PCRA (HEPA cart(s) usage, living cleaning document) Multiple shifts proposed, “first pass draft” (spec 01 35 26) Contractor shall move VA furniture and similar items obstruction work in office (w/COR approval)

Other Material Lead Time recurring status Progress meetings Meeting minutes Weekly meeting with VA facilities for phasing and drawing review (up to 1 hour, drawings in hand for active areas) Cleaning check list (living document) May require remote storage for staging material Background investigation in support non‐escort to TRs Registered RCDD support during construction Maintain/submit As‐built drawings as work progresses

Project building locations include buildings 1,2,3,4,5,6,7,8,11,12, 13,14,17,18,20,23,29,43,65, and 66 (likely some runs to other buildings). Technical complexity is high for this project due to migrating 90% of the telecommunication rooms (TRs) while leaving facilities infrastructure (building management equipment etc.) in the old closets, demoing out 14k‐33k abandoned phone line pairs in buildings while not impacting the mass communications system that sits on the existing phone network system, re‐ integration with the air gapped security campus system, reintegration with the fire safety campus system. Completion of all these tasks will be difficult due to phasing needs for all areas and departments. A "first pass construction hours matrix" has been developed in the specifications 01 35 26 to assist with phasing/ICRA risks.

Long Lead Items: High risk lead times shall be elevated to contracting/COR as early as possible (preferably prior to NTP) with recurring communications.

IT Support: Support from local IT will be "extremely limited," hence the requirement for a registered RCDD on site during construction to minimize hospital operational down time risks. Since local OIT will not have any individuals to watch the TR rooms during construction, the contractor must have several applicants complete a contractor background investigation in support of no VA OIT Escort when visiting TR’s. If the old or new TR door is open with active switches the room/closet must be monitored by an approved individual, hence phasing of this project is critical with the majority of the TRs being relocated.

Coordination will be needed to allow the VA time to program and complete connections to patch panels.

P a g e 3 | 4

Government Furnished Equipment: The VA will provide a minimal count of switches to assist with the phasing.

Winter Conditions: Contractor shall include labor, tools, material, heat, power, equipment, supervision in the scenario concrete work needs to be completed in winter conditions.

The contractor shall be responsible to move/relocate any furniture, equipment, boxes, files, user belongings, etc. That would be in an area of work and obstruction/interfere with the performance of the contractor’s work, and with COR approval. The VA does not have staff to support this effort.

The contractor shall be responsible for moving heavier equipment on campus to complete construction.

It is highly suggested the contractor procure/allocate the below items or similar to complete these types of moves. Additional equipment will likely be needed for removal of the existing generator, etc:

Two (2) Johnson Bars capable of 5,000 lbs each with poly‐on‐steel wheels (to protect flooring) o https://www.amazon.com/Vestil‐PLB‐S‐5‐Prylever‐

Capacity/dp/B0027YIPAO/ref=sr_1_4?keywords=johnson+bar&qid=1647023075&sr=8‐4

Four (4) men

Eight (8) heavy duty machine dolly skates, 3,300 lbs each poly‐on‐steel o https://www.amazon.com/dp/B08VRPW48J/ref=sspa_dk_detail_2?psc=1&pd_rd_i=B08

VRPW48J&pd_rd_w=TLVzQ&pf_rd_p=0c758152‐61cd‐452f‐97a6‐ 17f070f654b8&pd_rd_wg=X9Ajt&pf_rd_r=X9HNXYMHNBWARJD0ZR6P&pd_rd_r=78274 62b‐b1ff‐4f05‐a264‐ e4f58fee8cc4&s=industrial&spLa=ZW5jcnlwdGVkUXVhbGlmaWVyPUEyU1BUUk82M1Qz QU1WJmVuY3J5cHRlZElkPUEwNjQxNDUyM1RSM1RFRUpIRFVGViZlbmNyeXB0ZWRBZElk PUEwMDczOTg5M0NKWUFSTExENU9JNSZ3aWRnZXROYW1lPXNwX2RldGFpbCZhY3Rpb 249Y2xpY2tSZWRpcmVjdCZkb05vdExvZ0NsaWNrPXRydWU=

The sensitivity of information relating to this project is emphasized. All the information and documentation divulged in the course of this construction effort shall be treated as For Official Use Only.

This information is not to be distributed without a confirmed need to know as confirmed by the VA.

Contractor trades include general construction, concrete, plumbing, HVAC, communications, electrical, earthwork, fire suppression, exterior improvements, and a registered RCDD.

Period of performance: The period of performance is 365 calendar days from issuance of the Notices to Proceed. If a due date on the timeline below falls on a Holiday or weekend, the task shall be due the following business day. The remaining timeline will not be shifted to accommodate Holidays or Weekends.

Period of Performance: The period of performance for this project is 365 calendar days from issuance of the Notice to Proceed. Below are some recommended approaches:

1. After award, work with the COR and site to initiate background checks for required employees and bring on board the RCDD registered individual.

2. Identify the long lead items and a mitigation strategy.

3. Provide in a submittal the RCDD qualifications.

4. Establish a plan for concrete work and share with the COR after mobilization.

P a g e 4 | 4

Attachments:

1 ‐ EHRM Final Drawings Volume 1A ‐ 2022‐05‐12

2 ‐ EHRM Final Drawings Volume 1B ‐ 2022‐05‐12

3 ‐ EHRM Final Drawings Volume 2 ‐ 2022‐05‐12

4 ‐ EHRM Final Drawings Volume 3 ‐ 2022‐05‐12

5 ‐ EHRM Final Drawings Volume 4 ‐ 2022‐05‐12

6 ‐ Specifications Volume 1 ‐ Rev100% ‐ 4‐25‐22

7 ‐ Specifications Volume 2 ‐ Rev100% ‐ 4‐25‐22

8 ‐ Specifications Volume 3 ‐ Rev100% ‐ 4‐25‐22

9 ‐ PCRA ICRA Risk Assessment v2

10 ‐ Old‐New TR Telecommunication Rooms (Treat as a 10,000‐foot overview, a guidance document.

See Basis of Design (BOD) TR table and the networking drawing volume for details.)

11 ‐ HS Campus Ground Infrastructure (Use in support of IT equipment bonding per building, foundations, ground vault)

12 ‐ HS Campus Ground Infrastructure 2 (Use in support of IT equipment bonding per building, foundations, ground vault)

13 ‐ Cutsheets Small Diameter CAT6A – Final (Use as a guide for some of the brand name or equal items)

File details come from the government source that posted it. Updated .