S02_Attachment 6_IFB Contractor Cost Estimate Worksheet.xlsx

XLSX spreadsheet 14 KB Posted

Attached to
Y1JZ--Baton Rouge, Construct a New Restroom 829CM3018
Solicitation number
36C78622B0020
Issued by

About this file

This document includes a contractor cost estimate worksheet template and information for a related federal contract opportunity to construct a new restroom at the Baton Rouge National Cemetery. The cost estimate worksheet is a template for contractors to provide lump sum pricing for various construction divisions that may be required for the project. Contractors should include pricing for divisions like site work, concrete, masonry, metals, finishes, plumbing, HVAC, electrical, and other related construction work, as well as amounts for bonds, overhead, and profit. The federal contract opportunity is a solicitation from the Department of Veterans Affairs to construct a new restroom at the Baton Rouge National Cemetery, as described in the attached statement of work, with an anticipated award date of Y1JZ. Contractors should use the cost estimate worksheet template to develop their pricing proposals for this contract.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

This Division List is copied from: NCA MASTER CONSTRUCTION SPECIFICATIONS (https://www.cfm.va.gov/til/ncaSpec.asp)
Lump Sums are required for each Division that will be utilized in this project to total the final lump sum number.

If a Division is not being used put N/A in that field.

You can Add additional items you feel are appropriate.

IFB Number
Project Name
DivisionBase BidCLIN1CLIN 2CLIN3Total
Division 0
Special Sections
Division 01
General Requirements
Division 02
Existing Conditions
Division 03
Concrete
Division 04
Masonry
Division 05
Metals
Division 06
Wood, Plastic, and Composites
Division 07
Thermal and Moisture Protection
Division 08
Openings (Doors, Windows, etc...)
Division 09
Finishes
Division 10
Specialties
Division 11
Equipment
Division 12
Furnishings
Division 13
Special Construction
Division 14
Fire Suppression
Division 22
Plumbing
Division 23
Heat, Ventilating, and Air Conditioning
Division 25
Integrated Automation
Division 26
Electrical
Division 27
Communications
Division 28
Electronic Safety and Security
Division 31
Earthwork
Division 32
Exterior Improvements
Division 33
Utilities
Bonds

Overhead

Profit

GRAND TOTALS $ $ $ $ $

File details come from the government source that posted it. Updated .