This document outlines requirements for a federal design-build contract opportunity to replace motor control centers at a Department of Veterans Affairs medical facility in Puerto Rico. The solicitation will require offerors to provide all labor, materials, equipment, and design services necessary to replace six aging motor control centers at the OPA Basement and Main Building Sub-basement Area of the VA Caribbean Healthcare System in San Juan. Offerors must have an active System for Award Management registration and be verified in the Vendor Information Pages database as a service-disabled veteran-owned small business to be eligible for this set-aside contract. The anticipated award is a firm-fixed-price contract valued between $2-5 million. The solicitation is expected to be issued on June 16, 2021, with proposals due July 19, 2021. The replacement project involves installing new motor control centers with a minimum 800-amp capacity, along with associated electrical components, feeders, and conduits. Offerors must also provide for the safe removal and disposal of existing equipment, design and construction of an equipment lift, and replacement of lighting fixtures.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Offer
Base Offer Cost Breakdown
Project Number:
Edward L Roy: VA assigned project #
| Date: | |
| Project Title |
Edward L Roy: VA assigned Project Title
| Project Location | ||
| Offeror Name | ||
| Offeror Street | ||
| Offeror City | State | Zip |
Item Description Labor Cost Edward L Roy: Enter all Labor Costs by Division
| Material Cost | |
| Edward L Roy: Enter all Material Costs by Division | Total Cost |
Edward L Roy: This Column is the sum of the Division's Labor and Material Costs
| Division 1 | General Requirements | $ - 0 | $ - 0 | $ - 0 |
| Division 2 | Existing Conditions | - 0 | - 0 | - 0 |
| Division 3 | Concrete | - 0 | - 0 | - 0 |
| Division 4 | Masonry | - 0 | - 0 | - 0 |
| Division 5 | Metals | - 0 | - 0 | - 0 |
| Division 6 | Wood and Plastic | - 0 | - 0 | - 0 |
| Division 7 | Thermal & Moisture Protect | - 0 | - 0 | - 0 |
| Division 8 | Doors and Windows | - 0 | - 0 | - 0 |
| Division 9 | Finishes | - 0 | - 0 | - 0 |
| Division 10 | Specialties | - 0 | - 0 | - 0 |
| Division 11 | Equipment | - 0 | - 0 | - 0 |
| Division 12 | Furnishings | - 0 | - 0 | - 0 |
| Division 13 | Special Construction | - 0 | - 0 | - 0 |
| Division 14 | Conveying Equipment | - 0 | - 0 | - 0 |
| Division 21 | Fire Suppression | - 0 | - 0 | - 0 |
| Division 22 | Plumbing | - 0 | - 0 | - 0 |
| Division 23 | HVAC | - 0 | - 0 | - 0 |
| Division 26 | Electrical | - 0 | - 0 | - 0 |
| Division 27 | Communications | - 0 | - 0 | - 0 |
| Division 28 | Electronic Safety & Security | - 0 | - 0 | - 0 |
| Division 31 | Earthwork | - 0 | - 0 | - 0 |
| Division 32 | Exterior Improvements | - 0 | - 0 | - 0 |
| Division 33 | Utilities | - 0 | - 0 | - 0 |
| Division 34 | Transportation Subtotal | - 0 | - 0 | - 0 |
| Division Subtotals : | $ - 0 | $ - 0 | $ - 0 |
Overhead % 0.00% Edward L Roy: Enter Overhead % here. This % will be multiplied by the Division Total Cost Subtotal (cell F36).
Edward L Roy: Date Offer Prepared/Submitted
| - 0 | |||
| Profit % | 0.00% | ||
| Edward L Roy: Enter Profit % here.This % will be multiplied by the sum of the Division Total Cost subtotal (cell F36) plus the calculated Overhead (cell F38). | - 0 | ||
| Bond % | 0.00% |
Edward L Roy: Enter Bond % here. This % will be multiplied by the sum of the Division Total Cost Subtotal (cell F36), the amount of calculated Overhead (cell F38) and the amount of calculated Profit (cell F39).
Edward L Roy: Enter all Labor Costs by Division
| - 0 | ||
| Overhead/Profit Subtotals : | $ - 0 |
Edward L Roy: Sum of Overhead, Profit and Bond %.