Contract Summary: RR-26-2037

This is Addendum No. 1 to the contract requirements for the Illinois State Toll Highway Authority (ITHA), issued April 7, 2026. The addendum modifies Contract RR-26-2037 for pavement and structural rehabilitation work on the Veterans Memorial Tollway (I-355) between Mile Post 12.3 and Mile Post 29.9, spanning DuPage County and Will County in Illinois. The contract involves coordination with multiple agencies including the Illinois Department of Transportation, Will County Division of Transportation, and DuPage Division of Transportation.

The scope of work includes pavement patching, bridge deck and approach slab repairs, joint cleaning and replacement, cleaning and painting of exposed rebar, structural PPC beam repairs, slope wall repairs, pavement crack sealing and routing, shoulder microsurfacing, shoulder sealer application, pavement markings, and maintenance of traffic operations. Compliance goals include a 23% Disadvantaged Business Enterprise (DBE) participation rate and 2.0% Veteran-Owned Small Business (VOSB) participation, with workforce targets of 19.6% minority and 6.9% female employment. The anticipated notice-to-proceed is July 20, 2026, with substantial completion required by October 31, 2026, and final contract completion by December 31, 2026. Bidding opened April 17, 2026 at 10:30 a.m. central time. The addendum includes revised schedule of prices (pages P-10R through P-11R), revised special provisions (pages J-201R through J-203R), and multiple revised and new contract drawings for various maintenance stages and construction details.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

71/inois ollway

MEETING PURPOSE:

MEETING DATE:

MEETING TIME:

CHAIRPERSON:

LOCATION:

TO:

Names

Capital Program

PRE-BID MEETING MINUTES

Optional Pre-Bid Meeting - Contract RR-26-2037

March 18, 2026

11:00 a.m.

Vanessa Ramos -Senior Contract Negotiator

Illinois Tollway Microsoft Teams

Organization / Title Eric Occomy Maria Campuzano Vanessa Ramos Ann Seagrave Sue Garcia Alexander Karahalios AJ Pebler

Initials

EO

MC

KH

RH

SG

AK

AP

LJ

Procurement I Chief of Contract Services Procurement/Deputy Chief of Procurement

Procurement/Senior Contract Negotiator Procurement I Contract Analyst

Procurement I Compliance Analyst Diversity/Business Analyst of Diversity & Strategic Dev

Engineering / Project Manager Lukas Janulis DSE / Orion Engineers

TOPICS DISCUSSED:

1.0 Open: Welcome; Self-introduction by Procurement Representative

2.0 Introduction of Presenters

2.1 Tollway Procurement-Contract Services -Kathi Hacking

2.2 Tollway Procurement-Contract Compliance -Yolanda Ramirez

2.3 Tollway Diversity-Timothy Coleman

2.4 Tollway Engineering Project Manager-AJ Pebler

2.5 Design Section Engineers -Lukas Janulis

3.0 Brief Project Description

3.1 The location of the services to be performed for this contract is on the Veterans Memorial

Tollway (1-355) between Mile Post 12.3 and Mile Post 29.9 in DuPage County and Will County, Illinois

The work under this contract includes pavement patching, bridge deck and approach slab repairs, joint cleaning, joint replacement, cleaning and painting exposed rebar, structural PPC beam repairs, slope wall repairs, pavement crack sealing and routing, shoulder

Illinois State Toll Highway Authority Contract No. RR-26-2037 Addendum 1 Page 1 of 3 4/7/2026

Capital Program

PRE-BID MEETING MINUTES

microsurfacing, application of shoulder sealer, pavement markings, maintenance of traffic, and other miscellaneous work.

4.0 Advertisement Schedules

4.1 Plan Holder questions should be provided 9241 D.2037 _ Questions@docs.e-builder.net as identified on Page A-1

4.2 Final Date for Plan Holder Questions -March 27, at 2:00 pm

4.3 Bid Opening Date -April 17, 10:30 a.m. local time.

4.4 System will not accept late bid submittals.

4.5 Please note that in accordance with the R pages of the Illinois Tollway Bid Requirements and section 45-105 of the Illinois Procurement Code (30 ILCS 500/45-105), the bidder or contractor must submit at the time of bid the Illinois Business Bid Preference Affidavit and any other supporting documents demonstrating that the bidder or contractor is an Illinois business at the time of bid in order to be eligible for a 4% bid preference.

5.0 Compliance Goals

5.1 Disadvantaged Business Enterprise Program (DBE) -23%

5.2 Veteran-Owned Small Business Program (VOSB) -2.0%

5.3 Workforce

5.3.1 Equal Employment Opportunity (EEO)

• Minority (19.6%)

• Female (6.9%)

6.0 Diversity Programs - Overview of Available Programs

6.1 Earned Credit Program (ECP) Bid Credit Cap

6.2 Technical Assistance Program

6.3 Partnering for Growth (P4G)

6.4 Construction Works

7.0 Project Schedule

7.1 S.P. 104 Anticipated Notice-to-Proceed -July 20,2026

7 .2 S. P. 103.2 Substantial Completion Date -October 31, 2026

7.3 S.P. 103.1 Contract Completion Date -December 31, 2026

8.0 Special Items to Note

8.1 Cooperation with other agencies is required. Please review the S. P. 106.

8.1.1 Illinois Department of Transportation

8.1.2 Will County Division of Transportation

8.1.3 DuPage Division of Transportation

Illinois State Toll Highway Authority

Addendum 1 Page 2 of 3 4/7/2026

Capital Program

PRE-BID MEETING MINUTES

9.0 Responses to Plan Holder Questions

9.1 No Questions received to date

9.2 Anticipated Addendum 1 targeted for week of April 10, 2026

10.0 Questions

Illinois State Toll Highway Authority

Addendum 1 Page 3 of3 4/7/2026

Optional Pre-Bid Meeting Contract RR-26-2037 Veterans Memorial Tollway (1-355) Pavement and Structural Rehabilitation 1-55 to Army Trail Road Mile Post 12.3 to Mile Post 29.9

Name Email

Ramos, Vanessa VRamos@getipass.com

Seagrave, Ann ASeagrave@getipass.com

Jim Kowalewski (External) jkowalewski@fhpaschen.com

Coleman, Timothy TJColeman@getipass.com

Garcia, Susan L SLGarcia@getipass.com

'+17089277333

'+ 16307433704

Kelly, Sherita skelly@getipass.com

Prohammer, Valerie VProhammer@getipass.com

Lukas Janulis (External) ijanulis@orionengineersllc.com

Spencer, Takesha TSpencer@getipass.com

Myers, Lindia LMyers@getipass.com

Drozd, Laura LDrozd@getipass.com

Pebler, Alfred apebler@getipass.com

Andy Moore (External) a.moore@dconstruction.com

Benjamin Cuthbert (External) bcuthbert@gsJl-consultants.com

Mark Oliphant (External) mark.oliphant@dvwidag.com

Eliwbeth Covalt Elizabeth.Covall@ohla-usa.com

Illinois State Toll Highway Authority Contract No. RR-26-2037 Addendum 1

Role Job title Organization Phone Number

Organizer

Organizer

Attendee Senior Estimator FH Paschen 13122885926

Presenter

Presenter

Attendee

Attendee

Attendee Senior Contract Negotiator Illinois Tollway 16302416800

Attendee Contract SpeciaUst ISHTA 331.399.3498

External Presenter

Attendee Contract Specialist Tollway 6308950878

Attendee Senior Contract Negotiator Illinois Tollway 6302416800

Attendee Contract Analyst Tollway 630-796-8658

Presenter

Attendee Chief Estimator & Protect Manal!er "D" Construction Inc. 8154823939

Attendee Civil Engineer 1 llllnols Tollway GEC 2242504270

Attendee Head of Estimatinll Dvwidal!-Systems International, USA, Inc. 8172399435

Attendee Estimating Assistant OHLA Central, Inc. 6307797577

Contract Analyst TollWay 3313993495

Contracts Analyst Illinois Tollway 630-743-8214

Director Illinois Hispanic Chamber of Commerce 5642252609

Senior Contract Negotiator Illinois Tollway CA 3316310562

Page 1 of 1 4/7/2026