01-19-2017_RFI__2.pdf
PDF 85 KB Posted
- Attached to
- Replace Vehicle Gate
- Solicitation number
- RFQP06031700002
About this file
Responses to RFI #2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 01-19-2017_Pre-Quotation_Meeting_Minutes.pdf | ||
| 01-19-2017_Site_Visit_Photos.pdf | ||
| RFI__1.pdf | ||
| 6_-_NCIC_Form.pdf | ||
| 5_-_Wage_Rate.pdf | ||
| 3_-_Statement_of_Work.pdf | ||
| 4_-_Drawing.pdf | ||
| 1_-_Cover_Letter.pdf | ||
| 2_-_Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FDC HONOLULU – REPLACE VEHICLE GATE
SOLICITATION RFQP06031700002 ‐ PROJECT 6B5C
REQUEST FOR INFORMATION (RFI) #2
1. Please provide the name and contact information for the contractor that installed the Siemens Control System at the facility.
Response:
Travis Gregg, Project Manager Solid State Automation and Controls travis.gregg@solidstateautomation.com
713.467.1005 x101 5200 Mitchelldale Ste E‐17 Houston, TX 77092
2. Please provide the code and security requirements that must be met for the temporary Gate.
Response: Per SOW, page 1 Part 2, Scope of Work, sub part E: “The Contractor must secure the vehicle gate upon completion of work throughout the duration of the contract.”
Page 2 also states “The contractor shall ensure security gate for this Vehicle Gate is secured and locked in cases where the work is unfinished for the day. At no time will the Vehicle gate be unsecured before, during and after working hours. The Contractor will coordinate the security of this Vehicle Gate with the Rear Gate Officer. FDC Honolulu Control Center shall be informed and in control on the security status of the gate at all times.”
3. Please confirm that the temporary gate can be manually operated.
Response: Yes, but needs to be approved by the Facilities Manager.
4. Please confirm that a double swing temporary gate can be attached to existing posts and swing into the facility.
Response: Similar to answer in #2, for as long as this gate meets the criteria that is set herein and meets all local, state and federal code.
5. Please confirm that the location of the control room is less than 300’ from the location of the gate.
Response: Straight line measurement via CAD on plan shows 200 ft.
6. Please provide the suggested location for a gate controller, and any additional security requirements that must be met if the gate controller is located outside of the existing secure perimeter.
Response: Please submit proposed plans and specifications for review and approval prior installation of gate controller and we will be able to tell you where to install the lock box controller.
7. Can the existing gate panel frame be re‐configured for use with the new Gate?
Response: No.
8. Can the existing gate mesh be re‐used for the new gate?
Response: No.
File details come from the government source that posted it. Updated .