RFQ_260120_Technical_Attachments.pdf
PDF 35 MB Posted
- Attached to
- ADVANCED WATER PURIFICATION PROGRAM - TRES RIOS State and local contract opportunity
- Solicitation number
- 260120
- Issued by
- Pima County, Tucson City, Arizona
About this file
This document is a Technical Memorandum prepared by HDR for Tucson Water's Advanced Water Purification (AWP) Program, involving Tucson Water, Pima County, and the U.S. Bureau of Reclamation. The project involves designing and constructing a 2.5 million gallon per day (MGD) Advanced Water Purification Facility (AWPF) located on Pima County property near the Tres Rios Water Reclamation Facility. The primary objective is to receive Class A+ secondary treated effluent from Tres Rios WRF and implement advanced treatment for potable distribution, with a secondary water source from Tucson Water's reclaimed system. The project will utilize a Progressive Design-Build (PDB) approach, with an anticipated project completion by Q3 2031, and key milestones including releasing the RFQ for a Progressive Design Builder in Q3/Q4 2025 and selecting the builder in Q1/Q2 2026.
The project is substantially funded by the Bureau of Reclamation at $86.7M and is part of Tucson's broader One Water 2100 Plan, which aims to diversify water resources and reduce system dependency. The AWPF will address water supply challenges, including PFAS-related well shutdowns, and contribute to long-term water conservation for both the local community and the Colorado River system. Technical considerations include complex treatment train selections (carbon-based and reverse osmosis options), rigorous water quality testing, pathogen and chemical control requirements per Arizona Administrative Code, and site-specific evaluations addressing conveyance piping, power supply, floodplain impacts, and geotechnical conditions. The project emphasizes portfolio diversification, reduced system loss, and economic development through innovative water purification technology.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| ADVANCED_WATER_PURIFICATION_PROGRAM_-_TRES_RIOS_(Addendum_#2_Revision).pdf | ||
| ADVANCED_WATER_PURIFICATION_PROGRAM_-_TRES_RIOS.pdf | ||
| RFQ_260120_DBRA_Provisions.pdf | ||
| RFQ_260120_DBRA_Provisions.pdf | ||
| RFQ_260120_Detailed_Evaluation_Criteria.pdf | ||
| RFQ_260120_Detailed_Evaluation_Criteria.pdf | ||
| RFQ_260120_Design-Build_Scope_of_Work.pdf | ||
| BOR_Terms_and_Conditions.pdf | ||
| RFQ_260120_Technical_Attachments.pdf | ||
| BOR_Terms_and_Conditions.pdf | ||
| RFQ_260120_Design-Build_Scope_of_Work.pdf | ||
| SBE_Provisions_Revised_May_2024_Includes_Subcontractor_Modification_Form.docx | DOCX document | |
| Offer_and_Acceptance.pdf | ||
| Offer_and_Acceptance.pdf | ||
| SBE_Provisions_Revised_May_2024_Includes_Subcontractor_Modification_Form.docx | DOCX document |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TUCSON WATER
ADVANCED WATER
PURIFICATION PROGRAM
ATTACHMENT D -
TECHNICAL
ATTACHMENTS
For informational purposes only
PURIFICATION PROGRAM
SITE EVALUATION TECHNICAL
MEMORADUM
Advanced Water Purification Facility Site Evaluation Technical Memorandum
Tucson Water Planning On-Call | Contract No.
226004-02
Owner’s Advisory Services for Tucson Water’s
Advanced Water Purification Program
Revised DRAFT with Portions Redacted
August 11, 2025
Advanced Water Purification Facility Site Evaluation Technical Memorandum
Owner’s Advisory Services for Tucson Water’s Advanced Water Purification Program
August 11, 2025 | i
Contents
Foreword
1 Background
2 Technical Evaluation Criteria
2.1 Conveyance Piping
2.1.1 Effluent and Reclaimed Supply to the AWPF
2.1.2 Connecting AWPF Treated Water to the Potable Water Distribution
System
2.1.3 Wastewater Discharge to Existing Collection System
2.2 Power Supply
2.3 Impact of Floodplain
2.4 Geotechnical
3 Non-Technical Evaluation Criteria
3.1 Site Access
3.2 Boundary Survey Requirements
3.3 Phase I Environmental Site Assessment (ESA)
3.4 Cultural Resources and Historical Clearance
3.5 Native Plant Preservation Requirement
4 Summary and Recommendations
Figures
Figure 1-1. AWPF Site Location
Figure 2-2. Proposed Conveyance Pipeline to AWPF (Option 2)
Figure 2-3. Treated Water Connections to Potable Distribution Lines (Option 2)
Figure 2-4. Wastewater Discharge from AWPF to Gravity Sewer System (Options 2)
Figure 2-5. Potential Overhead Power Supply Source for AWPF at Site Option 2
Figure 2-6. Flood Mapping at Option 2 Location
Figure 3-1. Access to AWPF for Site Option 2
Figure 3-2. Site Option 2 in Pima County
August 11, 2025 | 1
Foreword
This Draft Technical Memorandum (TM) was originally submitted to Tucson in March 2025 and included a comparison of two site options for the AWPF. Since the development of the
TM, Tucson Water chose to eliminate a site option from consideration. Thus, this TM has been updated with information on Site Option 1 redacted. The purpose of this TM is to relay consideration of the Site Option 2 (the selected site) to interested proposers and provided as supplemental information for RFQ 260120. The information contained herein is provided for informational purposes only and is based on conditions, data, and assumptions available at the time of preparation. No representation or warranty, express or implied, is made as to the accuracy, completeness, or applicability of the information for any purpose other than the stated intent.
1 Background
As part of its Advanced Water Purification (AWP) Program, Tucson Water (TW) intends to receive Class A+ secondary treated effluent from Pima County’s Tres Rios Water
Reclamation Facility (WRF) and implement further advanced treatment for potable distribution. The proposed 2.5 MGD Advanced Water Purification Facility (AWPF) will primarily receive effluent from the Tres Rios WRF, however, Agua Nueva WRF and Tucson
Water’s reclaimed distribution system may be used as alternate sources.
The location (selected Site Option 2) identified for constructing the AWPF (see Figure 1-1) is at the Radio-Controlled Flying Field, located on six adjacent County-owned parcels (Pima
County Parcel Nos. 214-01-0270, 214-01-0260, and 214-01-025A, -025B, -025C, and -
025G), located southeast of Tres Rios WRF. It is conveniently located near a 42-inch potable pipeline (PN# 052-1998) which the AWPF would discharge into TW’s distribution system.
Figure 1-1. AWPF Site Location
The purpose of this technical memorandum (TM) is to present a considerations for the new
AWPF and make recommendations for next steps to support the acquisition of land. The following criteria were evaluated:
260120.
August 11, 2025 | 2
• Technical criteria o Conveyance piping (supply- and discharge-side) o Power supply o Floodplain o Geotechnical
• Non-technical criteria o Site access o Boundary survey o Environmental site assessment o Cultural resources and historical clearances o Native plant preservation requirements
2 Technical Evaluation Criteria
2.1 Conveyance Piping
2.1.1 Effluent and Reclaimed Supply to the AWPF
Tucson Water is actively designing a reclaimed booster pump station at the Tres Rios
WRF effluent chlorine contact basin (referred to as ‘Facility 52’) and a new 24-inch force main which will convey reclaimed water from Facility 52 to an existing 24-inch reclaimed pipeline (PN#031-2014) located along Ina Road. The purpose of that project is to increase reclaimed water supply to Tucson Water’s north and northwest reclaimed customers. Facility 52 is also the proposed primary water source for the AWPF.
HDR recommends the reclaimed booster pump station and force main be used for the water supply to the AWPF. To accomplish that, we propose the addition of a 12-inch tee on the proposed 24-inch reclaimed force main (see Figure 2-1), which could then be used to divert Tres Rios WRF effluent to supply the AWPF as its primary supply. In the event the Tres Rios WRF effluent source were disrupted, reclaimed water from the 24-inch reclaimed pipeline along Ina Road would then be used as the alternate supply. This controlled flow split would include motor operated valves (MOVs), flow meter, pressure reducing valve, check valves located inside a vault.
Figure 2-1 show the proposed pipeline configurations to achieve this diversion. Given the high concentration of cultural/archaeological resources in this general area, pipeline installation for both options has the potential for delays and clearing both alignments may be prudent. The pipeline alignment to the Selected Site Option 2 will parallel an existing buried service water line within a previously disturbed area and may have less potential for encountering cultural/archaeological obstructions.
August 11, 2025 | 3
Figure 2-1. Proposed Conveyance Pipeline to AWPF (Option 2)
August 11, 2025 | 4
2.1.2 Connecting AWPF Treated Water to the Potable Water Distribution System
For the Selected Site Option 2, the AWPF is conveniently located nearby an existing 42-inch Zone A1 potable water line (PN# 052-1998), as shown in Figure 2-2.
Overall, considering constructability and future maintenance access, the convenience of
Option 2 tying into the 42-inch line may be considered more favorable. Hydraulic modeling for the tie-in is recommended to understand impacts to the potable distribution system.
Based on information received from Tucson Water, Option 2 has been confirmed to work hydraulically for the connection. The exact location of the tie into the 42-inch line is currently being determined.
Figure 2-2. Treated Water Connections to Potable Distribution Lines
(Option 2)
2.1.3 Wastewater Discharge to Existing Collection System
For site Option 2, emergency overflows and off-spec water from the full-scale plant could be discharged into the existing 42-inch sewer line as shown in Figure 2-3, which is considered generally large enough to accommodate emergency overflows. However, this would need to be confirmed with Pima County.
August 11, 2025 | 5
Figure 2-3. Wastewater Discharge from AWPF to Gravity Sewer System
(Option 2)
2.2 Power Supply
The proposed AWPF will receive power from Tucson Electric Power (TEP). Based on preliminary analysis, conservatively assuming the new AWPF will involve energy intensive
Reverse Osmosis (RO) treatment, the estimated power consumption is approximately one megawatt. At that magnitude, the power draw will not require a new substation. Instead, the power supply would come from an existing distribution line or dedicated feeder from a substation. The nearest TEP substation is the West Ina Substation, located east of I-10 and south of Ina Road. This substation is not conveniently located for connecting a dedicated feeder to the AWPF at either location and a connection to an overhead power line would be preferred.
TEP has three high voltage lines that parallel I-10 through this general area1, with secondary overhead lines located along the south side of Ina Road, including dedicated overhead lines to the entrance of the Radio Controlled Flying Field parcels (Figure 2-4).
The secondary overhead lines would have to be further evaluated to supply the AWPF, which may entail expanding overhead service to the nearest high voltage line. Further coordination with TEP will be required to determine more specifically how to provide power from their existing system.
1 TEP-Ten-Year-Plan-Transmission-Projects-2023-2032-Maps.pdf
August 11, 2025 | 6
Figure 2-4. Potential Overhead Power Supply Source for AWPF at Site Option 2
2.3 Impact of Floodplain
Site Option 2 is mainly located in FEMA’s Zone X which is not within any floodplain and is outside the 500-year limits. However, the southwest corner of the site is within FEMA designate Zone AE (see Figure 2-5), which refers to an area located within the 100-year floodplain and subjected to a 1% annual chance of flooding. Additionally, this particular
Zone AE area is integral to the floodway as shown in Figure 2-5.
Based on the information obtained from FEMA’s website, these designated zones were established based on a flood mapping model that was last updated in 2011. Without performing additional floodplain analysis, it is uncertain how accurate these zones are depicted. One potential concern with the Zone AE area is that it is based on an older topography and could possibly be inaccurate. Considering the limitations with the available maps, the facility should be constructed away from Zone AE and the finished elevation should be at least one foot above the 500-year flood elevation. Additional information on the 500-year floodplain has been requested but was not yet received during the update of this TM.
AWPF Site Option
Overhead power
August 11, 2025 | 7
Figure 2-5. Flood Mapping at Option 2 Location
2.4 Geotechnical
Geotechnical evaluations have previously been performed for the Tres Rios WRF and were summarized in Tres Rios Biosolids Solar Dryer Report, 2024 and Interim Biosolids
Facilities, Ina Road WRF report, 2008. These reports stated a potential for hydro-collapse
(settlement upon wetting) of the native site soils. Boring investigations identified potentially collapsible soils occurring in depths from 5- to 10-ft. Depending on the bearing depth of foundation of the new AWPF structures, ground improvement by over-excavation and re-compaction or other method may be needed to reduce potential settlement for structures in particularly with shallow foundation, bearing within the upper 10-ft from existing grade. The reports recommended over-excavation of a minimum depth of 2.0-ft of existing native soils and replacement with compacted engineered fill beneath new facilities. The fact that site
Option 2 is within the vicinity of Zone AE/100-year floodplain and a floodway, potential for hydro-collapse of shallow bearing soils is likely to be more of an issue. Shallow or perched groundwater could be encountered in structure excavations, depending on the time of year. It is recommended to perform a comprehensive geotechnical investigation and consider the following:
• Preliminary investigation for site selection/ “fatal flaw” geotechnical evaluation o Perform one 50-foot deep geotechnical boring at Option 2 site.
o Perform program of soil laboratory tests, including typical classification and soil moisture tests, and consolidation/collapse tests on near-surface samples
(from approximately the upper 10 feet from existing grade) to evaluate hydro-collapse potential.
• Final Design investigation to support design of the new AWPF:
o Sufficient number and depth of borings to cover and support design of the proposed new facility locations.
August 11, 2025 | 8 o For larger size and below-grade structures, depth of the borings should extend to reach an elevation equivalent to approximately 20% of the estimated applied bearing stress.
o Final design investigation should include investigation of foundation conditions and suitability of site soils (from project excavations) for modification of or reconstruction of erosion protection (hardbank or other) along the existing floodway.
o Perform program of soil laboratory tests, including classification and soil moisture tests, and consolidation/collapse tests on near-surface samples
(from the upper 10 feet from existing grade) to confirm the hydro-collapse potential.
The current AWP program master schedule is based on a one-year design phase period. The geotechnical investigation and report is anticipated to take 6 – 8 weeks, which may not be achievable within the expedited design schedule. Tucson Water may want to consider performing the geotechnical investigation prior to selecting the collaborative delivery contractor.
3 Non-Technical Evaluation Criteria
3.1 Site Access
Site Option 2 can be accessed via Walker Road, which is an access road off the I-10 off ramp and is located on Pima County property (Figure 3-1). Tucson Water will need to acquire a right-of-way easement from Pima County to have access to the new AWPF at this location. The requested easement will need to be surveyed to develop a legal description that will need to be incorporated in the easement acquisition documents.
Figure 3-1. Access to AWPF for Site Option 2
3.2 Boundary Survey Requirements
Site Option 2 is entirely located within six different parcels all owned by Pima County (Figure
3-2). Although prior record survey information is available, this survey was conducted in 1987
August 11, 2025 | 9 and would likely need to be updated to facilitate a land sale. Usually, boundary surveys are required only for the area that is partially located with a County owned parcel, in this case
Parcel #214-010-260, since a boundary survey is always required when splitting a parcel.
TW is currently underway completing surveying efforts for this Site.
Figure 3-2. Site Option 2 in Pima County
3.3 Phase I Environmental Site Assessment (ESA)
Site Option 2 will require a Phase I Environmental Site Assessment (ESA) to determine any environmental hazardous materials risks before these parcels are acquired. The ESA would include a record search and site visits to assess the property’s current condition, to determine if there were any previous hazardous materials or environmental incidents on the property or within the surrounding area, or if there is potential contamination to the site from neighboring properties or environmental events. Even if the funding for the purchase was not from a federal agency, it is recommended that an ESA is completed for both sites before acquisition to evaluate the potential environmental risks.
During design and/or construction, projects receiving federal funds may have additional hazardous material requirements in addition to the ESA requirements. Both sites may contain environmental concerns. Option 2 is located near a wastewater facility and may have past environmental concerns associated with it.
August 11, 2025 | 10
3.4 Cultural Resources and Historical Clearance
Numerous cultural resources investigations, both surface and subsurface, have been performed in the vicinity of both site options, which are encompassed by a large prehistoric village.
Site Option 2, which is not fully paved, was previously surveyed for cultural resources in the 1980s, resulting in the identification of prehistoric surface remains. Because previous surveys were conducted more than 10 years ago, a new pedestrian survey would likely be required; the survey, and archival research that would be required for reporting purposes, would be performed not only to determine whether cultural remains are extant on the site surface but would also allow archaeologists to assess whether subsurface investigations
(archaeological data recovery) are warranted.
Site Option 2 is currently owned by Pima County and was previously developed by them to create the Catalina Radio Control Modelers RC Flying Field. There is evidence that the site was previously subjected to archaeological testing in the 1980s; however, the resulting letter report has yet to be located but, given that the Pima County developed the Flying
Field in 2002 (based on archival aerial photography), it is suspected (not confirmed) that the results of prior archaeological testing were negative. It is possible that Site Option 2 would not require any additional archaeological investigations prior to construction. Since the site is developed, there is also a high likelihood that the area has been disturbed, decreasing the likelihood that intact cultural resources are extant.
The project constitutes a federal undertaking. The U.S. Bureau of Reclamation, as the lead federal agency for Section 106 of the National Historic Preservation Act, will need to consider the effects of the undertaking on cultural resources. Section 106 review is likely to involve consultation with numerous entities including, minimally, Pima County, the Arizona
State Historic Preservation Office, and interested tribes.
3.5 Native Plant Preservation Requirement
Pima County’s Native Plant Preservation Ordinance (NPPO, 18.72) requires a native plant inventory prior to any destruction or removal of native plants “on sites for which a grading plan is required or the total area covered by all grading permits is fourteen thousand
(14,000) square feet or more.”2
Site Option 2 will likely require a NPPO survey as there is vegetation on the western and southern border of the site. As majority of site Option 2 does not have heavy vegetation, it is estimated that the NPPO survey will require minimal effort. The NPPO survey would be conducted prior to vegetation removal and ground-disturbing activities but would not be needed prior to acquisition of the site.
4 Summary and Recommendations
This site evaluation study has identified several tasks that to select the preferred site for the new AWPF. These tasks are described below according to their priority:
1. https://codelibrary.amlegal.com/codes/pimacounty/latest/pimacounty_az/0-0-0-21996
August 11, 2025 | 11
1. Obtaining Right of Entry (ROE): Tucson Water will need to establish an agreement with Pima County and Radio Control Flying Field (for Option 2) to obtain ROE before performing field investigations including geotech borings, boundary surveys, site and cultural assessments, archaeological and native plant surveys.
2. Fatal Flaw Geotechnical Evaluation: A fatal flaw geotechnical study, comprising borings and soil laboratory tests will need to be completed. Specific items relevant to this evaluation is described in Section 2.4.
3. Coordination with TEP: A preliminary meeting agreement with TEP is recommended to investigate power supply options.
4. Coordination with Pima County Regional Flood Control District: The 100-and 500-year flood elevations will need to be obtained from Pima County
Regional Flood Control District and verified for site Option 2.
SUPPLEMENTAL INFORMATION FOR THE SITE
EVALUATION TECHNICAL MEMORADUM
RECORD DRAWINGS FOR THE CAP
NORTHWEST PHASE 1B TRANSMISSION MAIN
REGULATORY AND PERMITTING MATRIX
Draft Communications
Plan
Submission of AWP
Permit Application
Distribution of AWT
Final
Communications
Plan Submitted at least 30 days prior
Pre-Application
Meeting with
ADEQ
Pilot Plan
Pilot Plan and Report
Initial Source Water
Characterization
Plan
ISWC Plan and Report
Conduct Initial
Source Water
Monitoring
Draft ESCP
Draft TMF
Proposed Pilot Train
NPPs Applicant
Draft
Communications
Plan
Optional to Submit to ADEQ
Initial Source Water
Characterization
Report
Conduct Piloting
APP
Permit
Joint Plan
Plans and Specs
Design Report
Full Scale Verification Plan
Draft Operations Plan
TMF
Initial ESCP Plan
Proposed Action Levels
Final Design & As-builts
Operations Plan
Full-Scale Verification
Report
Vulnerability Assessment
Final Communications
Plan
Final ESC Plan
Engineer’s COC
Department approves all compliance schedule items
Prove Control of Projected Chemical
Treatment List (Tier 1, Tier 2, Pass
Through)
Informs ESC Plan
Not Required to Submit to ADEQ before Permit Application
Not Required to Submit to ADEQ
Prior to Initial Source Water
Monitoring but Recommended
Construction of
AWP Facility
Advanced Water Purification Program
Regulatory and Permitting Matrix for 18 AAC 9, Art 8 as interpreted by HDR as of August 2025
Optional
O p tio n a l
O p tio n a l
TREATMENT FEASIBILITY
WORKSHOP SLIDE DECK
Originally presented to Tucson Water in May
2025 by HDR
© HDR 2024, all rights reserved.© HDR 2024, all rights reserved.
Tucson Water Advanced Water Purification (AWP) Treatment Feasibility Study
May 23, 2025
AGENDA
Treatment Train Selection
Source Water Quality
Finished Water Quality/Goals
Preliminary Site Layouts
Next Steps
Project & Task Background
Team Introduction
01 Team Introduction
01 Project & Task Background
• Key driver - loss of water supply capacity in the NW portion of TW’s service area
• Comparative analysis of AWP trains meeting ADEQ Final AWP Rule requirements
• Carbon (non-RO) based treatment
• RO based treatment
2.5-MGD Advanced Water Purification Facility (AWPF)
AWP Location: Pima
County Property
Tres Rios Water
Reclamation
Facility
Supply Option 1:
TRWRF Effluent
(Class A+)
Supply Option 2:
Reclaimed System
(Class A+)
02 Source Water Quality
Source Water Quality Data Summary
• Tres Rios Final Effluent (2019-2024)
• Reclaimed Water
• Agua Nueva Final Effluent (2019-2024)
• Recovery Well 522 (2019-2024)
• Recovery Well EW-007A (2024)
• Recovery Well TA-030A (2024)
Supply Option 1 – Tres Rios Water Reclamation Facility Effluent
AWP
Location
Tres Rios Water
Reclamation
Facility
EFFLUENT
Supply Option 2
– Reclaimed System Supply
Source Water Quality Recovery Wells
Average
Agua Nueva Final
Effluent Average
Tres Rios Final
Effluent Average LimitUnitContaminant
390.860.6510ng/L Perfluorohexanesulfonic acid
(PFHxS)
135.84.74ng/LPerfluorooctanoic acid (PFOA)
322.02.74ng/L Perfluorooctanesulfonic acid
(PFOS)
758766721
450 (Average Native
Groundwater)
500 (SMCL)
mg/LTotal dissolved solids (TDS)
3.2No dataNo data2 (AWP)mg/LTotal organic carbon (TOC)
0.720.610.580 (TW goal)µg/L1,4-Dioxane
0.010.370.390.2µg/LBenzo(a)pyrene (PAHs)
0.300.070.070.2µg/L 1,2-Dibromo-3-chloropropane
(DBCP)
0.26No dataNo data0.05µg/LEthylene dibromide
0.0381.11.11µg/LPentachlorophenol
No data34350.03ng/LDioxin (2,3,7,8-TCDD)
03 Finished Water Quality/Goals
Existing Water Quality at Proposed Point of Connection
Pressure Zone ZA
• SP-030
• SP-035
5.5 years of data – 2020 to 2025 (inclusive)
Water Quality at Proposed Point of Connection Source
Waters* SP-035SP-030LimitUnit
Water Quality
Parameter
1092729749Noneumhos/cmConductivity
7.27.87.86.5-8.5s.u.pH
184108108Nonemg/L CaCO3Alkalinity
1.080.340.41TTNTUTurbidity
4.70.760.7110mg/L NNitrate
0.140.050.051mg/L NNitrite
3.20.420.452mg/LTOC
282228235Nonemg/L CaCO3Hardness
1376465Nonemg/LSodium
1517276250mg/LChloride
170154162250mg/LSulfate
748570 (other wells)**250mg/LTDS
* Average of Tres Rios effluent, Agua Nueva effluent, and reclaimed water concentrations, if available
** Further evaluation needed.
04 Treatment Train Selection
ADEQ Final AWP Rule - Key Requirements
18 AAC 9, Article 8, F832
• Pathogen Control:
• Standard Approach:
• 13/10/10 log reductions for Virus/Crypto/Giardia
• Site Specific Approach:
• 8/6/5.5 log reductions for Virus/Crypto/Giardia (even if non-detects are demonstrated by the sampling program)
• Site-specific pathogen monitoring for at least 24 months
• Disinfection:
• At least one validated disinfection treatment process targeting each of the three reference pathogens
• UV disinfection with a dose of at least 300 mJ per cm2
ADEQ Final AWP Rule - Key Requirements
18 AAC 9, Article 8, F832
• Chemical Control:
• At least one validated filtration process targeting each of the three reference pathogens
• At least three diverse and separate treatment processes, including, but not limited to Advanced Oxidation Process (AOP) and physical separation process
• AOP to achieve ≥ 0.5 log reduction of 1,4-dioxane and Tucson Water’s operational goal of 0.35 µg/L
• Ozone/BAC processes designed to provide no less than 1.0 log reduction of formaldehyde, acetone, carbamazepine, and sulfamethoxazole
Pathogen Log Reduction Values (LRVs)
• ADEQ AWP TAG Recommendations provided values for illustration and discussion purposes only
• Needs to be validated per established literature and pilot testing.
• Final AWP Rule
• Max 6 credit per each treatment/physical barrier
• Treatment train, cumulatively, shall meet or exceed either the standard (13/10/10) or site-specific (8/6/5.5) log reduction targets
NotesGiardia Crypto Virus Unit Process
*For Crypto- ADEQ TAG mentioned
>2, using 2 here conservatively2.52*2
Coag-Floc-
Sed- Filtration
*For Crypto- ADEQ TAG mentioned up to 1; British Columbia’s
Guidelines for Pathogen Log
Reduction Credit Assignment provides CT needed to reach 2 LRV of crypto.62*6Ozone
000BAC
000GAC
440MF/UF
*Range is 1.5 to 3 (ADEQ TAG);
usually the LRV is 0.5 to 21.5*1.5*1.5*RO
666UV/AOP
*For Virus- ADEQ TAG mentioned up to 6, EPA technical Guidance Manual provides CT requirements up to 4 credit
**For Giardia- ADEQ TAG mentioned up to 6, EPA technical Guidance
Manual provides CT requirements up to 3 credit3**04*Chlorine
Carbon-Based Treatment Train
• Process and chemical dosing pumps are not shown.
• Process and chemical dosing pumps are not shown.
Minimum LRV
Requirement Total LRVChlorineIX GACUV/AOPOzone-BACMF/UFFloc-SedUnit Process
1318.04006602Virus
1014.00006242Crypto
1021.53006642.5Giardia
PFAS (esp.
short-chain)
PFAS, VOCs, SVOCs, TOC/DOC
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, 1,4 –dioxane
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, TOC/DOC
Turbidity
Turbidity
IOCs
TOC/DOC
Chemical Barrier
GAC after UV/AOP serves as quenching agent in addition to adsorber
Minimum LRV
Requirement Total LRVChlorineIX GACUV/AOPOzone-BACMF/UFFloc-SedUnit Process
1318.04006602Virus
1014.00006242Crypto
1021.53006642.5Giardia
PFAS (esp.
short-chain)
PFAS, VOCs, SVOCs, TOC/DOC
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, 1,4 –dioxane
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, TOC/DOC
Turbidity
Turbidity
IOCs
TOC/DOC
Chemical
IX provide chemical barrier for short-chain PFAS
Minimum LRV
Requirement Total LRVChlorineIX GACUV/AOPOzone-BACMF/UFFloc-SedUnit Process
1318.04006602Virus
1014.00006242Crypto
1021.53006642.5Giardia
PFAS (esp.
short-chain)
PFAS, VOCs, SVOCs, TOC/DOC
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, 1,4 –dioxane
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole
Pharmaceuticals, VOCs, SVOCs, TOC/DOC
Turbidity
Turbidity
IOCs
TOC/DOC
Chemical
RO-Based Treatment Train
Minimum LRV
Requirement Total LRVChlorineUV/AOPROMF/UFOzone-BACUnit Process
1317.5461.506Virus
1013.5061.542Crypto
1020.5361.546Giardia
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole, Pharmaceuticals, VOCs, SVOCs, 1,4 – dioxane
Formaldehyde, Acetone, Carbamazepine, Sulfamethoxazole, Pharmaceuticals, Turbidity
1,4-dioxane, VOCs, SVOCs, TOC/DOC, PFAS
TDS
Turbidity
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole, Pharmaceuticals, VOCs, SVOCs, TOC/DOC
Chemical Barrier
Ozone/BAC provides additional chemical barrier and other advantages.
Minimum LRV
Requirement Total LRVChlorineUV/AOPROMF/UFOzone-BACUnit Process
1317.5461.506Virus
1013.5061.542Crypto
1020.5361.546Giardia
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole, Pharmaceuticals, VOCs, SVOCs, 1,4 – dioxane
Formaldehyde, Acetone, Carbamazepine, Sulfamethoxazole, Pharmaceuticals, Turbidity
1,4-dioxane, VOCs, SVOCs, TOC/DOC, PFAS
TDS
Turbidity
Formaldehyde, Acetone
Carbamazepine, Sulfamethoxazole, Pharmaceuticals, VOCs, SVOCs, TOC/DOC
Chemical Barrier
Why Ozone/BAC?
• Additional treatment barrier → process resiliency
• Reduces downstream membrane fouling → operational savings + improved uptime
• Improves RO concentrate quality → easier disposal
• AWPs using/testing ozone/BAC with RO
• Los Angeles
• San Diego
Source:
Trussell and
Pisarenko (2024)
05 Preliminary Site Layouts
Site Layout- Carbon Based
Site Layout- RO Based (With Ozone-BAC)
Site Layout- RO Based (Without Ozone-BAC)
OPEN HOUSE SLIDE
DECK
TUCSON WATER DEPARTMENT
VIRTUAL OPEN HOUSE
ADVANCED WATER PURIFICATION PROJECT
Scott Schladweiler, P.E.
Deputy Director Tucson Water
June 2nd, 2025
Agenda
Project Need & Background
Project Scope
Schedule
Questions
Project Need & Background
Water Production & Rainwater Offset for Tucson Water Service Area (1940-2024)
Colorado River WaterGroundwater Remediated Groundwater Recycled Rainwater Harvesting (Not to Scale)
System Conservation “Bucket 1” System Conservation
- 2023 through 2025
- Total of 110,000 acre-feet left in Lake Mead
- $44M used to enhance long term water supply resiliency projects
- Water quality projects
“Bucket 2” System Conservation
- Proposed a 2.5 MGD Advanced Water
Purification Facility (AWPF)
- Located near the Tres Rios Water
Reclamation Facility
- Total BOR Funding: $86.7M
Tres Rios WRF
Tucson Water Reclaimed Plant
Agua Nueva WRF
One Water 2100 Plan
• Approved by Tucson Mayor and Council in
October 2023
• Comprehensive, long range water resource management plan
• Right water for the right purpose
• Identified key strategies with community and stakeholder input
TucsonOneWater.com
Project Benefits
PORTFOLIO
DIVERSIFICATION
REDUCED
SYSTEM LOSS
REDUCED
DEPENDENCY
ECONOMIC
DEVELOPMEMT
Project Scope RFQ for Progressive Design Builder
• Advanced Water Purification Facility (AWPF) designed for 2.5 MGD capacity
• Primary Source: Tres Rios WRF Effluent
• Secondary Source: TW’s Reclaimed System
• Progressive Design Builder
• Final Treatment Selection
• 1-Year Pilot
• Design & Construction
• GMP Development
• Permitting (AWP & APP)
• Close Coordination with Operations
Manager at Risk
Proposed Scope
AWPF Location:
Pima County Property
Tres Rios Water Reclamation
Facility
Supply Option 1:
TRWRF Effluent (Class A+)
Supply Option 2:
• Operations of the AWPF (future RFQ)
• Public Communications
• Owner’s Advisory Services
• Initial Source Water Characterization
• Enhanced Source Control Plan / Program
• Initial Coordination with Pima County
Scope by Others
AWPF Location:
Pima County Property
Tres Rios Water Reclamation
Facility
Supply Option 1:
TRWRF Effluent (Class A+)
Supply Option 2:
Schedule
Project Completion by Q3 - 2031
Q3/Q4
RFQ for Progressive
Design Builder
Released
Q1/Q2
Progressive Design Builder
Selected and NTP
Q2/Q3
RFQ for Operations
Team Released
Q3/Q4
Operations Team
Selected and NTP
Today
Open House & Market
Sounding
Q3
One-on-One Meetings w/
Potential Proposers
Tentative Schedule (subject to change)
1x1’s
Agenda’s provided by PDB / Operations Firms
Questions submitted ahead of 1x1
Interested in topics that reduce risk, streamline delivery, improve delivery success, foster collaboration and engagement
Subject to additional requirements by TW
Procurement
Questions?
| ATTACHMENT I - TECHNICAL ATTACHMENTS |
| Site Evaluation Technical Memoradum |
| Supplemental Information for the Site Evaluation Technical Memorandum |
| Regulatory and Permitting Matrix |
| Treatment Feasibility Workshop Slide Deck |
| Open House Slide Deck |