This document is a Request for Proposals (RFP) for the Hilfiker Wall Repairs Project at the Land Port of Entry in Sault Ste. Marie, Michigan. The General Services Administration (GSA), Public Buildings Service, Region 5 is soliciting proposals for a single contract award to address distress in the Hilfiker mechanically stabilized earth retaining wall, including bulging wire baskets, vertical and horizontal displacement, and an outward lean. The project will construct a new earth retention soil nail wall and re-slope the concrete parking area above the wall. The estimated range for this project is between $1,000,000 and $5,000,000, and it is set aside for small business concerns under NAICS code 236220. The performance period for on-site work is 120 calendar days from the issuance of the Notice to Proceed. The contractor will be required to provide an Environmental Product Declaration (EPD) for low embodied carbon concrete, cement, and steel materials. The Inflation Reduction Act of 2022 requires the use of these materials, and GSA is seeking expressions of interest from suppliers and manufacturers that can meet these requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Hilfiker Wall Repairs Amendment 0003.pdf | ||
| Pre-Proposal Sign-in Sheet 7-9-24.pdf | ||
| Pre-Proposal Sign in Sheet 10-1-24.pdf | ||
| Hilfiker Wall Repairs Amendment 0002.pdf | ||
| Hilfiker Wall Repairs Amendment 0001.pdf | ||
| Attachment AMD0001 Hilfiker IRA Sustainability Factor Table dated 6.18.24.xlsx | XLSX spreadsheet | |
| Past Performance Questionnaire.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
Request for Proposal (RFP)
U.S. GENERAL SERVICES
ADMINISTRATION
GREAT LAKES REGION
PUBLIC BUILDINGS SERVICE
Wisconsin Service Center 517 E. Wisconsin Ave Milwaukee, WI 53202
PROJECT:
Hilfiker Wall Repair Land Port of Entry 900 International Bridge Plaza Sault Ste. Marie, MI 49783
SOLICITATION NO: 47PF0024R0042
ISSUE DATE: May 23, 2024
CLOSING DATE & TIME: July 8, 2024 4:00 PM (Eastern Time)
CONTRACT NO:
DATE OF AWARD:
ISSUED BY:
U.S. General Services Administration Great Lakes Region Public Buildings Service Milwaukee Service Center 517 E. Wisconsin Ave.
Milwaukee, WI 53202
Note: The Inflation Reduction Act of 2022 (IRA), Pub. L. No. 117-169, enacted in August 2022, provided GSA with significant funding for (a) measures necessary to convert facilities to high-performance green buildings, (b) acquisition and installation of construction materials and products with substantially lower levels of embodied greenhouse gas emissions, and (c) emerging and sustainable technologies. The Contract resulting from this Solicitation will be funded in part by IRA appropriations, and it contains numerous IRA-specific requirements.
Requirements include, but are not limited to, requirements regarding pricing, invoicing, submittals, materials, and construction. In addition, please note that this Solicitation contains an evaluation factor favoring certain construction materials with the lowest possible levels of embodied carbon.
Offerors shall carefully review this Solicitation, the Agreement, the Statement of Work, the Specifications, and the Drawings. Offerors are responsible for accurately pricing and, if successful, fully performing all Contract requirements.
Sol. Reference No. 47PF0024R0042
Document: C101-SB-GC/December 2023 (The Agreement)
Construction Contract for: Hilfiker Wall Repair Project
The Agreement
Table of Contents
I. Project Information A. Project Summary B. The Contract C. Period Of Performance D. Work Conditions/Site Requirements E. Authorized Representatives F. Contract Liquidated Damages Rate G. Buy American Exceptions H. Statement of Work, Specifications, Drawings
II. Prices
A. Basis of Pricing B. Contract Price Form
III. Terms and Conditions
A. Commencement, Prosecutions and Completion of Work B. Contractor Responsibilities C. Submittals D. Finality of Contract Modifications E. Liquidated Damages F. Insurance Requirements G. Order of Precedence H. Administrative Matters I. Non-Compliance with Contract Requirements J. Requirements for GSA Information Systems K. Additional Terms and Conditions
i. Limited Notice to Proceed with Post-award Low Embodied Carbon Materials Research Report
IV. Contract Clauses A. Clauses Incorporated in Full Text
1. FAR 52.204-30, Federal Acquisition Supply Chain Security Act Orders-Prohibition (DEC 2023) Alternate I (DEC 2023)
2. FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (SEP 2013)
3. FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA-Designated Items (MAY 08)
4. GSAR 552.204-9 Personal Identity Verification Requirements
(APR 2023)
5. GSAR 552.252-6 Authorized Deviations in Clauses (NOV 2021)(Deviation FAR 52.252-6)
6. FAR 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (NOV 2021)
7. Buy American Requirements
8. FAR 52.228-11, Pledges of Assets (DEVIATION APR 2020)
9. FAR 52.232-40, Providing Accelerated Payments to Small
Business Subcontractors (MAR 2023)
10. FAR 52.219-14, Limitations on Subcontracting (SEP 2021)
11. Additional Clauses
12. FAR 52.244-5, Competition in Subcontracting (DEC 96)
B. Clauses Incorporated by Reference C. Subcontract Requirements
(The Agreement)
I. Project Information
I.A. Project Summary
Provide needed repairs of Hilfiker retaining wall including but not limited to soil nails, reinforced metal bar, placed concrete, pavement replacement and regrading, and concrete repairs as called for in plans and specifications.
I.B. The Contract
The Contract consists of the SF1442, the Agreement, the Statement of Work, Specifications, Drawings, Exhibits, Amendments, Modifications, and other Attachments identified herein (collectively, the Contract Documents). The Contract contains the entire agreement of the Parties, and no prior written or oral agreement, express or implied, shall be admissible to contradict or modify any part of the Contract.
(2) The Contractor shall provide and pay for all labor, materials, equipment, tools, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution of the work described in and reasonably inferable from the Contract Documents (the Work), whether temporary or permanent. In consideration for, and upon condition of, the Contractor's completion of the Work, GSA shall pay the Contractor the price or prices established in Section II, subject to the terms and conditions set forth in this Contract.
I.C. Period of Performance
(1) Commencement. The Contractor shall commence performance of the Work within 1 day after the Contractor receives the Notice to Proceed (NTP).
(2) Substantial Completion. The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than 120 calendar days from issuance of Notice to Proceed (NTP).
(3) Contract Completion. The Contractor shall achieve Contract Completion, as the term is defined in this Agreement, within 45 calendar days of Substantial Completion.
I.D. Work Conditions/Site Requirements
A. The Contractor will review and document the existing conditions surrounding the project premises. Provide documentation to GSA prior to the commencement of any construction activity.
B. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy and public use.
1. Confine operations at the site to areas indicated in plans. Do not disturb portions of the site beyond the areas in which Work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain port operations in a safe and functional condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the government. Take precautions to protect the facility, its occupants, and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur.
5. Certain roadways adjacent to the work site will need to be closed while on site work occurs. Coordinate public roadway closures with CBP and GSA.
Provide vehicle barriers to divert traffic for roadway closures. Vehicle barriers shall indicate alternate path of vehicular traffic.
6. Keep active roadways and work areas free from accumulation of waste material, rubbish, construction debris and construction materials.
7. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government. Arrange and gain approval for use of this space through the Contracting Officer.
8. Use of the existing site access will be shared with Government activities on a first-come-first-served, wait-your-turn basis. The port is available for the delivery of materials, tools, and supplies between 8 AM and Midnight.
9. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.
10. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into buildings. When not required for powering unloading operations, turn off engines when parked.
11. The contractor shall submit a silica work exposure plan that must be sufficient to minimize the release of visible dust and minimize the accumulation of visible airborne dust before commencing construction activities.
12. Smoking is not permitted in or around buildings, see Facilities Management Regulation
(FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.
13. Limited parking will be available on site during working hours for building occupants. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site as necessary.
14. Cell Phones: Contractor is to provide company cell phones during this contract. Cell phones are only permitted in construction areas and contractor’s office space.
15. No apparatus with an open flame is allowed to be used within the port without the prior receipt of a burn permit. Contact the Field Office to obtain burn permits. Burn permits are required for each separate occurrence.
16. Permits: Refer to FAR 52.236-7
17. The work shall be sequenced to minimize disruption to port operations, visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.
18. Coordinate with the GSA Building Manager and the COR for site access.
(The Agreement)
19. Coordinate with the GSA Building Manager and the COR on correct response procedures for any building system alarms occurring during or resulting from the construction process.
20. All facility systems outside the immediate construction area shall be kept fully operational during normal working hours.
21. Protect port facilities from flying debris.
22. Coordinate with the GSA building manager and CBP Port Operations as to the use of cameras within the Port.
I.E. Authorized Representatives
(1) This Contract is between the United States of America, acting by and through the Administrator of General Services (GSA), and the Contractor (the Parties).
References in this Contract to "the Owner" or "the Government" shall be understood to refer to GSA. The following individual is designated as the only authorized GSA representative under this Contract, unless other warranted contracting officers are designated in writing:
Authorized Representative Information:
Contracting Officer’s Information Name: Thomas Monaweck - 5P1NEC Address: 110 Michigan St. NW, Grand Rapids, MI 49503 Telephone: (616) 222-9151 Email: thomas.monaweck@gsa.gov
(2) For the applicable authorities and limitations see Section IV of this Agreement, GSAR 552.236-70.
I.F. Contract Liquidated Damages Rate In accordance with GSAR 552.211-12, Liquidated Damages – Construction, in Section IV of this Agreement, liquidated damages shall be calculated at the rate of $31.68 per calendar day.
I.G. Buy American Exceptions
(The Agreement)
For the applicable Buy American clause and any exceptions, see Section IV of this Agreement.
I.H. Statement of Work, Specifications, Drawings, Exhibits, and Other Attachments
The following documents are incorporated by reference into this Contract.
(1) Statement of Work for GSA Solicitation No. 47PF0024R0042, Dated
September 2023
(2) Specifications for GSA Solicitation No. 47PF0024R0042, September
(3) Construction Drawings for GSA Solicitation No. 47PF0024R0042, Dated 01/08/2024
(4) Wage Determination MI20240113, Dated April 2, 2024
(5) a list of IRA-Eligible Materials corresponding to the list set forth in the Solicitation’s Sustainability Factor or, for a sole-source award, the proposal submission instructions (See Section II.F)
(6) the successful offeror’s IRA Limit Commitments for each IRA-Eligible
Material
(7) the GWP values from GSA’s concrete (and cement) and steel requirements associated with the IRA Limit for each material.
II. Prices
II.A. Basis of Pricing
(1) Contract Prices. All Contract prices set forth in this Section include all costs necessary to complete the work for which the price is established (e.g., Base Contract, Unit Price, Options) in accordance with the Contract Documents, including, but not limited to, the cost of work performed by subcontractors and consultants, indirect costs, fees, expenses, taxes, and profit.
(2) Knowledge of Conditions Affecting Price. FAR 52.236-3, Site Investigations and Conditions Affecting the Work, is incorporated by reference in this Contract.
The Contractor shall be presumed to have established all prices with knowledge of general and local conditions that may affect the cost of Contract performance at the site where the Work is to be performed, to the extent that such information is reasonably obtainable.
(3) Unit Prices and Allowances. If any portion of the Work is to be performed on a unit price basis, the Unit Price shall include all costs of coordinating and incorporating the unit-priced portion of the Work into the Base Contract Work.
https://www.gsa.gov/system/files/Concrete%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf https://www.gsa.gov/system/files/Steel%20-%20GSA%20IRA%20Low%20Embodied%20Carbon%20Requirements%20%28Dec.%202023%29_508.pdf
The Contractor shall only be obligated to perform unit-priced work to the extent that an Allowance has been established. The Contractor shall be obligated to perform such work in excess of a unit quantity for which an Allowance is established only if directed by the Contracting Officer in writing. The Contractor shall be bound to the unit price or prices set forth herein in all equitable adjustments for changes including unit priced work, and no markups shall be applied to such unit prices.
(4) Options. If any portion of the Work is to be performed upon the timely exercise of an Option, the Option Price shall include all costs of coordinating and incorporating the Option-priced portion of the Work into the Base Contract Work.
An adjustment to the Contract price for such additional work shall be computed solely on the basis of the Option price or prices set forth herein. Unless otherwise specified, all options may be exercised within 90 days of Contract award.
(5) Bid Rates. If this Contract includes Bid Rates to be used in determination of equitable adjustments (e.g., overhead, profit, daily rates for time-related costs), such rates shall be deemed to include all costs recoverable as components of an equitable adjustment consistent with the requirements, definitions, and exclusions applicable to equitable adjustments set forth in this Contract, and consistent with the Contractor's cost accounting practices. Unless otherwise specified, the bid rates shall be deemed to include only the Contractor's costs, and not the costs of any subcontractors.
II.B. Contract Price Form
CLIN & SubCLIN Price
CLIN 0002 IRA Acquisition and installation of low embodied carbon materials
SubCLIN 0002AA Acquisition and installation of low embodied carbon steel and associated expenses
SubCLIN 0002AD Acquisition and installation of low embodied carbon concrete and associated expenses
CLIN 0003 IRA emerging and sustainable Technologies
CLIN 0004 IRA high-performance green building measures
III. Terms and Conditions
III.A. Commencement, Prosecution, and Completion of Work
FAR 52.211-10, Commencement, Prosecution, and Completion of Work and GSAR 552.211-10, Commencement, Prosecution and Completion of Work is supplemented as follows:
The Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of the Work, as defined in GSAR 552.211-70 Substantial Completion (Mar 2019) and the time specified in Section I (Project Information), “Period of Performance” clause. If the Contract specifies different completion dates for different phases or portions of the Work, the Contractor shall diligently prosecute the Work so as to achieve Substantial Completion of such phases or portions of the Work within the times specified.
III.B. Contractor Responsibilities
GSAR 552.236-71, Contractor Responsibilities is located in Section IV.A. of this Agreement and is supplemented as follows:
(1) The Contractor shall secure and pay for all necessary permits and governmental fees, licenses, and inspections that are customarily secured after award of the Contract and that are legally required at the time of award. The Contractor shall provide a copy of the permits required for execution of the work to the Contracting Officer prior to commencement of any related work.
III.C. Submittals
FAR 52.236-21, Specifications and Drawings for Construction, GSAR 552.236- 72, Submittals located in Section IV.A. of the Agreement is supplemented as follows:
(1) The Contractor shall prepare and submit to the Contracting Officer shop drawings, samples, calculations, product information, mockups, and other submittals (collectively, "submittals") demonstrating compliance with Contract requirements for all Work components as specified elsewhere in this Contract.
III.D. Finality of Contract Modifications As set forth elsewhere in this Contract, the Contractor is entitled to additional consideration under certain conditions, including the issuance of change orders.
It is the Contractor's duty to include in proposals for equitable adjustment or other consideration all compensation to which it may be entitled, including cost and time. Unless otherwise explicitly stated in a modification to the Contract providing such consideration, adjustments to the Contract price or time agreed upon therein shall be deemed to provide all compensation to which the Contractor is entitled, and shall constitute final settlement of the Contractor's entitlement to compensation on account of the change or other condition giving rise to the modification.
III.E. Liquidated Damages The Contractor acknowledges that time is of the essence for the performance of the Work, and that determining actual damages from delay would be extremely difficult and impractical. If the Contractor fails to achieve Substantial Completion of the Work in accordance with FAR 52.211-12, Liquidated Damages and GSAR 552.211-12, Liquidated Damages and the time specified in this Contract, the Contractor shall be liable to the Government for liquidated damages at the rate specified in Section I (Project Information), paragraph entitled, “Liquidated Damages Rate,” for each calendar day following the required completion date that the Work is not Substantially Complete.
III.F. Insurance Requirements
(1) The Contractor shall obtain and maintain for the entire life of the Contract, in addition to any insurance required by law, the following minimum kinds and amounts of insurance required pursuant to FAR clause 52.228-5, Insurance – Work on a Government Installation, and GSAR 552.228-5, Government as Additional Insured.
(a) Workers' compensation insurance in the amount required by the jurisdiction in which the Contract is performed. The Contractor shall obtain Employers' liability coverage of at least $2,000,000. If occupational diseases are not covered by workers' compensation insurance, Employers' liability coverage shall include occupational diseases.
(b) Broad form comprehensive commercial general liability insurance in the amount of at least $5,000,000 per occurrence. Such insurance shall include, but not be limited to, contractual liability, bodily injury and property damage.
(c) Comprehensive automobile liability covering the operation of all automobiles used in connection with performing the Contract in the amount of at least $1,000,000 per person and $2,500,000 per occurrence for bodily injury and $1,000,000 per occurrence for property damage.
(2) The Contractor shall promptly provide to the Contracting Officer proof that it has obtained insurance required by the Contract in the form of certificates of insurance. The Contractor shall submit to the Contracting Officer all renewal certificates issued during the life of this Contract immediately upon issuance.
III.G. Order of Precedence Different requirements within this Contract shall be deemed inconsistent only if compliance with both cannot be achieved. In case of inconsistency between Contract Documents, the following order of precedence shall apply:
(1) Section IV of the Agreement
(2) Sections I, II, and III of the Agreement
(3) The Statement of Work
(4) The Specifications
(5) The Drawings
(6) Exhibits and Other Attachments
III.H. Administrative Matters
(1) Project Meetings. The Contractor shall attend a preconstruction conference and shall participate in regularly scheduled Project meetings.
(2) Payments. FAR clause 52.232-5, Payments under Fixed-Price Construction Contracts, is supplemented by GSAR 552.232-5 Payments under Fixed-Price Construction Contracts located in Section IV.A. of this Agreement. In accordance with the relevant FAR and GSAR clauses, GSA requires the following data be included with each invoice:
(a) Invoices shall be submitted electronically to the designated billing office specified in this Contract or in individual delivery/work orders. An electronic copy of the invoice shall be sent to the CO and COR as designated after award.
(b) Invoices must include the Account Document Number (ADN) assigned at award.
(c) The Contractor shall submit the following information or documentation with each invoice:
(i) Updated Schedule of Values upon which the payment request is based;
(ii) GSA Form 2419 - Certification of Progress Payments Under Fixed- Price Construction Contract;
(iii) The payment terms that apply for the particular services rendered
(iv) Additional documentation:
(3) The Contractor shall provide an itemized invoice detailing the amounts requested under each firm-fixed price CLIN and SubCLIN set forth in the
Contract Price Form. Itemized invoices shall reflect progress on each CLIN and SubCLIN and should reflect the latest Schedule of Values. Provide updated IRA D&C Submittal: Contract Reporting Form (Construction Team section) as part of the Monthly Pay Application package. See Specification, Division One, Submittal Procedures, 013300 and Payment Procedures, 012900.
(4) The Contractor shall submit GSA’s IRA Post Award Allocation Form, attached, within 20 days of contract award.
(3) Prompt Payment. In accordance with FAR clause 52.232-27, the period for payments is as follows:
(a) Progress Payments: 14 days
(b) Subsequent Subcontractor Payments: 7 days
(4) Payment Information. The General Services Administration (GSA) makes information on contract payments available electronically at Office of the Chief Financial Officer. The Contractor may register at the site and review its record of payments. This site provides information only on payments made by GSA, not by other agencies.
(5) Security Clearances. Contractor shall comply with the following requirements pertaining to security clearances.
(a) All personnel performing work under the Contract on the Project site must obtain an Enter on Duty (EOD) determination before they will be granted access to the site.
(b) To obtain an EOD determination, Contractor shall submit for all such personnel fingerprints on Form SF87 and a completed Contractor Information Worksheet (CIW). Detailed information is available at GSA Access Card .
USAccess Credentialing Centers can be located at US Access Centers .
(c) In addition, all such personnel who will be on site 6 months or longer must apply for and receive clearance in accordance with Homeland Security Presidential Directive 12 (HSPD-12). See Section IV, Contract Clauses, GSAR 552.204-9.
(6) Safeguarding and Dissemination of Controlled Unclassified Information (CUI) Building Information
This clause applies to all recipients of CUI building information (which falls within the CUI Physical Security category), including offerors, bidders, awardees, contractors, subcontractors, lessors, suppliers and manufacturers.
https://finance.ocfo.gsa.gov/pii/piinotice.aspx?token=PI002 https://finance.ocfo.gsa.gov/pii/piinotice.aspx?token=PI002 http://www.gsa.gov/portal/category/107203 http://www.fedidcard.gov/centerlist.aspx
Marking CUI. Contractors must submit any contractor-generated documents that contain building information to GSA for review and identification of any CUI building information that may be included. In addition, any documents GSA identifies as containing CUI building information must be marked in accordance with the Order and the Marking Controlled Unclassified Information Handbook (the current version may be found at https://www.archives.gov/files/cui/20161206-cui-marking-handbook-v1-1.pdf) before the original or any copies are disseminated to any other parties. If CUI content is identified, the CO may direct the contractor, as specified elsewhere in this contract, to imprint or affix CUI document markings (CUI) to the original documents and all copies, before any dissemination, or authorized GSA employees may mark the documents.
1. Authorized recipients.
a. Building information designated as CUI must be protected with access strictly controlled and limited to those individuals having a Lawful Government Purpose to access such information, as defined in 32 C.F.R. § 2002.4(bb). Those with such a Lawful Government Purpose may include Federal, state and local government entities, and non-governmental entities engaged in the conduct of business on behalf of or with GSA. Non-governmental entities may include architects, engineers, consultants, contractors, subcontractors, suppliers, utilities, and others submitting an offer or bid to GSA, or performing work under a GSA contract or subcontract. Recipient contractors must be registered as “active” in the System for Award Management (SAM) database at www.sam.gov, and have a Lawful Government Purpose to access such information. If a subcontractor is not registered in the SAM database and has a Lawful Government Purpose to possess CUI building information in furtherance of the contract, the subcontractor must provide to the contractor its DUNS number or its tax ID number and a copy of its business license. The contractor must keep this information related to the subcontractor for the duration of the contract and subcontract.
b. All GSA personnel and contractors must be provided CUI building information when needed for the performance of official Federal, state, and local government functions, such as for code compliance reviews and the issuance of building permits. Public safety entities such as fire and utility departments may have a Lawful Government Purpose to access CUI building information on a case-by-https://www.archives.gov/files/cui/20161206-cui-marking-handbook-v1-1.pdf case basis. This clause must not prevent or encumber the necessary dissemination of CUI building information to public safety entities.
2. Dissemination of CUI building information:
a. By electronic transmission. Electronic transmission of CUI information outside of the GSA network must use session encryption (or alternatively, file encryption) consistent with National Institute of Standards and Technology (NIST) SP 800-
171. Encryption must be through an approved NIST algorithm with a valid certification, such as Advanced Encryption Standard or Triple Data Encryption Standard, in accordance with Federal Information Processing Standards Publication 140-2, Security Requirements for Cryptographic Modules, as required by GSA policy.
b. By nonelectronic form or on portable electronic data storage devices. Portable electronic data storage devices include CDs, DVDs, and USB drives.
Nonelectronic forms of CUI building information include paper documents, photographs, and film, among other formats.
i. By mail. Contractors must only use methods of shipping that provide services for monitoring receipt such as track and confirm, proof of delivery, signature confirmation, or return receipt. CUI markings must not appear on the exterior of packages.
ii. In person. Contractors must provide CUI building information only to authorized recipients with a Lawful Government Purpose to access such information. Further information on authorized recipients is found in section 1 of this clause.
3. Record keeping. Contractors must maintain a list of all entities to which CUI is disseminated, in accordance with sections 2 and 3 of this clause. This list must include, at a minimum: (1) the name of the state, Federal, or local government entity, utility, or firm to which CUI has been disseminated; (2) the name of the individual at the entity or firm who is responsible for protecting the CUI building information, with access strictly controlled and limited to those individuals having a Lawful Government Purpose to access such information; (3) contact information for the named individual; and (4) a description of the CUI building information provided. Once “as built” drawings are submitted, the contractor must collect all lists maintained in accordance with this clause, including those maintained by any subcontractors and suppliers, and submit them to the CO. For Federal buildings, final payment may be withheld until the lists are received.
4. Safeguarding CUI documents. CUI building information (both electronic and paper formats) must be stored within controlled environments that prevent unauthorized access. GSA contractors and subcontractors must not take CUI building information outside of GSA or their own facilities or network, except as necessary for the performance of that contract. Access to the information must be limited to those with a Lawful Government Purpose for access.
5. Destroying CUI building information. When no longer needed, CUI building information must either be returned to the CO or destroyed in accordance with guidelines in NIST Special Publication 800-88, Guidelines for Media Sanitization.
6. Notice of disposal. The contractor must notify the CO that all CUI building information has been returned or destroyed by the contractor and its subcontractors or suppliers in accordance with paragraphs 4 and 5 of this clause, with the exception of the contractor's record copy. This notice must be submitted to the CO at the completion of the contract to receive final payment. For leases, this notice must be submitted to the CO at the completion of the lease term.
7. CUI security incidents. All improper disclosures or receipt of CUI building information must be immediately reported to the CO and the GSA Incident Response Team Center at gsa-ir@gsa.gov. If the contract provides for progress payments, the CO may withhold approval of progress payments until the contractor provides a corrective action plan explaining how the contractor will prevent future improper disclosures of CUI building information. Progress payments may also be withheld for failure to comply with any provision in this clause until the contractor provides a corrective action plan explaining how the contractor will rectify any noncompliance and comply with the clause in the future.
8. Subcontracts. The contractor and subcontractors must insert the substance of this clause in all subcontracts.
[End of clause]
III.I. Non-Compliance with Contract Requirements
In the event the Contractor, after receiving written notice from the Contracting Officer of non-compliance with any requirement of this Contract, fails to initiate mailto:gsa-ir@gsa.gov promptly such action as may be appropriate to comply with the specified requirement within a reasonable period of time, the Contracting Officer shall have the right to order the Contractor to stop any or all work under the Contract until the Contractor has complied or has initiated such action as may be appropriate to comply within a reasonable period of time. The Contractor will not be entitled to any extension of Contract time or payment for any costs incurred as a result of being ordered to stop work for such cause.
III.J. Requirements for GSA Information Systems In accordance with GSAR 511.171, Requirements for GSA Information Systems:
(a) CIO Coordination. The contracting officer shall ensure the requirements office has coordinated and identified possible CIO policy inclusions with the GSA IT prior to publication of a Statement of Work, or equivalent as well as the Security Considerations section of the acquisition plan to determine if the CIO policies apply. The CIO policies and GSA IT points of contact are available on the Acquisition Portal at https://insite.gsa.gov/itprocurement.
(b)GSA Requirements. For GSA procurements (contracts, actions, or orders) that may involve GSA Information Systems, excluding GSA’s government-wide contracts e.g. Federal Supply Schedules and Governmentwide Acquisition Contracts, the contracting officer shall incorporate the coordinated Statement of Work or equivalent including the applicable sections of the following policies into solicitations and contracts:
(1)CIO 09-48, IT Security Procedural Guide: Security and Privacy IT Acquisition Requirements; and (2)CIO 12-2018, IT Policy Requirements Guide.
(c)Waivers.
(1)In cases where it is not effective in terms of cost or time or where it is unreasonably burdensome to include CIO 09-48, IT Security Procedural Guide:
Security and Privacy IT Acquisition Requirements or CIO 12-2018, IT Policy Requirements Guide in a contract or order, a waiver may be granted by the Acquisition Approving Official in accordance with the thresholds listed at 507.103(b), the Information System Authorizing Official, and the GSA IT Approving Official.
(2)The waiver request must provide the following information- (A)The description of the procurement and GSA Information Systems;
(B)Identification of requirement requested for waiver;
(C)Sufficient justification for why the requirements should be waived; and https://www.acquisition.gov/gsam/part-511#GSAM_511_171 https://insite.gsa.gov/itprocurement https://www.acquisition.gov/gsam/part-507#GSAM_507_103
(D)Any residual risks that will be encountered by waiving the requirements.
(3)Waivers must be documented in the contract file.
(d)Classified Information. For any procurements that may involve access to classified information or a classified information system, see subpart 504.4 for additional requirements.
III.K. Additional Terms and Conditions
i. Limited Notice to Proceed with Post-award Low Embodied Carbon Materials Research Report.
If any of the Contractor’s IRA Limit Commitments do not correspond to the subject material’s Top 20% Limits, notice to proceed with the project entails only a limited notice to proceed with the Low Embodied Carbon Materials CLIN.
Specifically, Contractor shall only proceed with preparation of a Low Embodied Carbon Materials Research Report explaining why such IRA Limit Commitments did not correspond to the subject material’s Top 20% Limits. Additionally, to the extent applicable, the Contractor shall also explain why any IRA Limit Commitments did not meet the subject material’s Top 40% Limits.
For each IRA-Eligible Material not meeting Top 20% Limits, the report shall detail:
● the Contractor’s process for seeking Top 20% and Top 40% materials;
● sources contacted;
● sources of Top 20% and Top 40% materials identified (if any); and
● the reason why the Contractor did not commit to furnish Top 20% or
Top 40% materials identified (if any) (e.g., insufficient supply, schedule delays, unreasonable cost).
The Low Embodied Carbon Materials Research Report is due within 5 business days of notice to proceed. Following submission of its report, https://www.acquisition.gov/gsam/part-504#GSAM_Subpart_504_4
Contractor shall request that the Contracting Officer issue an unrestricted notice to proceed.
Note: Contractor shall not place orders for any IRA-Eligible Materials until it has received an unrestricted notice to proceed. Contractor consents to unrestricted GSA use of supplier names and the GWP values associated with supplier materials. This information may be disclosed publicly or used to inform other low embodied carbon procurement activities. Technical solutions, supplier pricing and supplier-offeror terms and conditions will not be shared.
Market Reports. Within 10 business days following contract award, the Contractor shall provide the Contracting Officer with a current Market Report on IRA-Eligible Materials referenced in the Solicitation’s Sustainability Factor self-scoring table. The Market Report shall evaluate materials available1 in the quantities and timeframes required by the Contract, prioritizing data on materials compliant with Top 20% and Top 40% Limits. The Market report shall detail:
● the Contractor’s process for seeking IRA-Eligible Materials meeting each material’s respective Top 20% and Top 40% Limits;
● sources contacted;
● sources of Top 20% and Top 40% materials identified (if any); and
● actual or estimated pricing and environmental product declaration
GWP values for each identified material.
The Contractor shall furnish an Updated Market Report 90 calendar days following submission of the initial report.
1 Market research resources for qualifying materials may include, but are not limited to, ASTM International’s EPD Page, Building Transparency’s Embodied Carbon in Construction Calculator (EC3), ICC Evaluation Service’s EPD Directory, EPD International AB’s EPD Library, the National Asphalt Paving Association’s Emerald Eco-Label EPD Tool, the National Ready Mixed Concrete Association’s Concrete EPDs page, NSF's Search for EPDs tool, and UL’s SPOT product catalog.
Note: The information provided herein is for informational purposes only and does not indicate or imply Federal endorsement of any organization, business, material or product. The Government makes no warranties concerning the quality, performance or suitability of any organization, business, material or product.
https://www.astm.org/products-services/certification/environmental-product-declarations/epd-pcr.html https://www.astm.org/products-services/certification/environmental-product-declarations/epd-pcr.html https://carbonleadershipforum.org/ec3-tool/ https://icc-es.org/environmental-program/environmental-product-declarations/epd-directory/ https://icc-es.org/environmental-program/environmental-product-declarations/epd-directory/ https://www.environdec.com/library https://asphaltepd.org/ https://www.nrmca.org/association-resources/sustainability/environmental-product-declarations/ https://info.nsf.org/Certified/Sustain/epd_search.asp https://spot.ul.com/main-app/products/catalog/?keywords=
Note: Contractor consents to unrestricted GSA use of supplier names and the GWP values associated with supplier materials. This information may be disclosed publicly or used to inform other low embodied carbon procurement activities. Technical solutions, supplier pricing and supplier-offeror terms and conditions will not be shared.
IV. Contract Clauses
IV.A. Clauses Incorporated in Full Text
1. FAR 52.204-30, Federal Acquisition Supply Chain Security Act Orders- Prohibition (DEC 2023) Alternate I (DEC 2023)
(a) Definitions. As used in this clause—
Covered article, as defined in 41 U.S.C. 4713(k), means—
(1) Information technology, as defined in 40 U.S.C. 11101, including cloud computing services of all types;
(2) Telecommunications equipment or telecommunications service, as those terms are defined in section 3 of the Communications Act of 1934 (47 U.S.C.
153);
(3) The processing of information on a Federal or non-Federal information system, subject to the requirements of the Controlled Unclassified Information program (see 32 CFR part 2002); or
(4) Hardware, systems, devices, software, or services that include embedded or incidental information technology.
FASCSA order means any of the following orders issued under the Federal Acquisition Supply Chain Security Act (FASCSA) requiring the removal of covered articles from executive agency information systems or the exclusion of one or more named sources or named covered articles from executive agency procurement actions, as described in 41 CFR 201–1.303(d) and (e):
(1) The Secretary of Homeland Security may issue FASCSA orders applicable to civilian agencies, to the extent not covered by paragraph (2) or (3) of this definition. This type of FASCSA order may be referred to as a Department of Homeland Security (DHS) FASCSA order.
https://www.govinfo.gov/link/uscode/41/4713 https://www.govinfo.gov/link/uscode/41/4713 https://www.govinfo.gov/link/uscode/40/11101 https://www.govinfo.gov/link/uscode/40/11101 https://www.govinfo.gov/link/uscode/47/153 https://www.govinfo.gov/link/uscode/47/153 https://www.ecfr.gov/current/title-32/part-2002 https://www.ecfr.gov/current/title-32/part-2002 https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(d) https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(d) https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(e) https://www.ecfr.gov/current/title-41/section-201-1.303#p-201-1.303(e)
(2) The Secretary of Defense may issue FASCSA orders applicable to the Department of Defense (DoD) and national security systems other than sensitive compartmented information systems. This type of FASCSA order may be referred to as a DoD FASCSA order.
(3) The Director of National Intelligence (DNI) may issue FASCSA orders applicable to the intelligence community and sensitive compartmented information systems, to the extent not covered by paragraph (2) of this definition.
This type of FASCSA order may be referred to as a DNI FASCSA order.Intelligence community, as defined by 50 U.S.C. 3003(4), means the following—
(1) The Office of the Director of National Intelligence;
(2) The Central Intelligence Agency;
(3) The National Security Agency;
(4) The Defense Intelligence Agency;
(5) The National Geospatial-Intelligence Agency;
(6) The National Reconnaissance Office;
(7) Other offices within the Department of Defense for the collection of specialized national intelligence through reconnaissance programs;
(8) The intelligence elements of the Army, the Navy, the Air Force, the Marine Corps, the Coast Guard, the Federal Bureau of Investigation, the Drug Enforcement Administration, and the Department of Energy;
(9) The Bureau of Intelligence and Research of the Department of State;
(10) The Office of Intelligence and Analysis of the Department of the Treasury;
(11) The Office of Intelligence and Analysis of the Department of Homeland Security; or
(12) Such other elements of any department or agency as may be designated by the President, or designated jointly by the Director of National Intelligence and https://www.govinfo.gov/link/uscode/50/3003 https://www.govinfo.gov/link/uscode/50/3003 the head of the department or agency concerned, as an element of the intelligence community.
National security system, as defined in 44 U.S.C. 3552, means any information system (including any telecommunications system) used or operated by an agency or by a contractor of an agency, or other organization on behalf of an agency—
(1) The function, operation, or use of which involves intelligence activities;
involves cryptologic activities related to national security; involves command and control of military forces; involves equipment that is an integral part of a weapon or weapons system; or is critical to the direct fulfillment of military or intelligence missions, but does not include a system that is to be used for routine administrative and business applications (including payroll, finance, logistics, and personnel management applications); or
(2) Is protected at all times by procedures established for information that have been specifically authorized under criteria established by an Executive order or an Act of Congress to be kept classified in the interest of national defense or foreign policy.
Reasonable inquiry means an inquiry designed to uncover any information in the entity's possession about the identity of any covered articles, or any products or services produced or provided by a source. This applies when the covered article or the source is subject to an applicable FASCSA order. A reasonable inquiry excludes the need to include an internal or third-party audit.
Sensitive compartmented information means classified information concerning or derived from intelligence sources, methods, or analytical processes, which is required to be handled within formal access control systems established by the Director of National Intelligence.
Sensitive compartmented information system means a national security system authorized to process or store sensitive compartmented information.
Source means a non-Federal supplier, or potential supplier, of products or services, at any tier.
(b) Prohibition. (1) Contractors are prohibited from providing or using as part of the performance of the contract any covered article, or any products or services produced or provided by a source, if the covered article or the source is https://www.govinfo.gov/link/uscode/44/3552 https://www.govinfo.gov/link/uscode/44/3552 prohibited by any applicable FASCSA orders identified by the checkbox(es) in this paragraph (b)(1).
Yes X No ☐ DHS FASCSA Order
(2) The Contractor shall search for the phrase “FASCSA order” in the System for Award Management (SAM) at https://www.sam.gov to locate applicable FASCSA orders identified in paragraph (b)(1).
(3) The Government may identify in the solicitation additional FASCSA orders that are not in SAM, which are effective and apply to the solicitation and resultant contract.
(4) A FASCSA order issued after the date of solicitation applies to this contract only if added by an amendment to the solicitation or modification to the contract (see FAR 4.2304(c)). However, see paragraph (c) of this clause.
(5)(i) If the contractor wishes to ask for a waiver of the requirements of a new FASCSA order being applied through modification, then the Contractor shall disclose the following:
(A) Name of the product or service provided to the Government;
(B) Name of the covered article or source subject to a FASCSA order;
(C) If applicable, name of the vendor, including the Commercial and Government Entity code and unique entity identifier (if known), that supplied or supplies the covered article or the product or service to the Offeror;
(D) Brand;
(E) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);
(F) Item description;
(G) Reason why the applicable covered article or the product or service is being provided or used;
(ii) Executive agency review of disclosures. The contracting officer will review disclosures provided in paragraph (b)(5)(i) to determine if any waiver is warranted. A contracting officer may choose not to pursue a waiver for covered https://www.sam.gov/ https://www.sam.gov/ articles or sources otherwise covered by a FASCSA order and to instead pursue other appropriate action.
(c) Notice and reporting requirement. (1) During contract performance, the Contractor shall review SAM.gov at least once every three months, or as advised by the Contracting Officer, to check for covered articles subject to FASCSA order(s), or for products or services produced by a source subject to FASCSA order(s) not currently identified under paragraph (b) of this clause.
(2) If the Contractor identifies a new FASCSA order(s) that could impact their supply chain, then the Contractor shall conduct a reasonable inquiry to identify whether a covered article or product or service produced or provided by a source subject to the FASCSA order(s) was provided to the Government or used during contract performance.
(3)(i) The Contractor shall submit a report to the contracting office as identified in paragraph (c)(3)(ii) of this clause, if the Contractor identifies, including through any notification by a subcontractor at any tier, that a covered article or product or service produced or provided by a source was provided to the Government or used during contract performance and is subject to a FASCSA order(s) identified in paragraph (b) of this clause, or a new FASCSA order identified in paragraph (c)(2) of this clause. For indefinite delivery contracts, the Contractor shall report to both the contracting office for the indefinite delivery contract and the contracting office for any affected order.
(ii) If a report is required to be submitted to a contracting office under (c)(3)(i) of this clause, the Contractor shall submit the report as follows:
(A) If a Department of Defense contracting office, the Contractor shall report to the website at https://dibnet.dod.mil.
(B) For all other contracting offices, the Contractor shall report to the Contracting Officer.
(4) The Contractor shall report the following information for each covered article or each product or service produced or provided by a source, where the covered https://dibnet.dod.mil/ https://dibnet.dod.mil/ article or source is subject to a FASCSA order, pursuant to paragraph (c)(3)(i) of this clause:
(i) Within 3 business days from the date of such identification or notification:
(A) Contract number;
(B) Order number(s), if applicable;
(C) Name of the product or service provided to the Government or used during performance of the contract;
(D) Name of the covered article or source subject to a FASCSA order;
(E) If applicable, name of the vendor, including the Commercial and Government Entity code and unique entity identifier (if known), that supplied the covered article or the product or service to the Contractor;
(F) Brand;
(G) Model number (original equipment manufacturer number, manufacturer part number, or wholesaler number);
(H) Item description; and
(I) Any readily available information about mitigation actions undertaken or recommended.
(ii) Within 10 business days of submitting the information in paragraph (c)(4)(i) of this clause:
(A) Any further available information about mitigation actions undertaken or recommended.
(B) In addition, the Contractor shall describe the efforts it undertook to prevent submission or use of the covered article or the product or service produced or provided by a source subject to an applicable FASCSA order, and any additional efforts that will be…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .