Hilfiker Wall Repairs Amendment 0002.pdf

PDF 536 KB Posted

Attached to
Hilfiker Wall Repairs Project, Sault Ste. Marie, MI Federal contract opportunity
Solicitation number
Kahua3134
Issued by
General Services Administration Public Buildings Service Region 5

About this file

This document is an amendment to a Request for Proposals (RFP) for the Hilfiker Wall Repairs Project at the Land Port of Entry in Sault Ste. Marie, MI. The purpose of the amendment is to modify the Environmental Product Declaration (EPD) submission requirements and establish a second site visit date.

The key details are:

  • The solicitation number is 47PF0024R0042.
  • The project is funded in part by the Inflation Reduction Act of 2022, which requires the use of construction materials with lower embodied greenhouse gas emissions.
  • Offerors must commit to furnishing IRA-Eligible Materials (concrete, cement, asphalt, steel, and glass) that meet specific global warming potential (GWP) limits.
  • Offerors must submit EPDs for the proposed IRA-Eligible Materials, and those without compliant EPDs by the proposal due date will be deemed unacceptable.
  • The proposal due date remains November 8, 2024 at 4:00 PM Eastern.
  • A second site visit is scheduled for September 12, 2024 at 1:30 PM Eastern.
  • The procurement is set aside for small business concerns under NAICS code 236220 (Commercial and Institutional Building Construction).

View the file

Other files for this federal contract opportunity

Other files attached to Hilfiker Wall Repairs Project, Sault Ste. Marie, MI, newest first.
File Type Posted
Hilfiker Wall Repairs Amendment 0003.pdf PDF
Pre-Proposal Sign-in Sheet 7-9-24.pdf PDF
Pre-Proposal Sign in Sheet 10-1-24.pdf PDF
Hilfiker Wall Repairs Amendment 0001.pdf PDF
Attachment AMD0001 Hilfiker IRA Sustainability Factor Table dated 6.18.24.xlsx XLSX spreadsheet
RFP Pkt 47PF0024R0042.pdf PDF
Past Performance Questionnaire.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

5P2QCCMIL

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Oana Sandru, Contracting Officer

Amendment 0002, RFP 47PF0024R0042 - Hilfiker Wall Repair Project, Land Port of Entry, Sault Ste. Marie, MI

The purpose of this amendment is to modify the existing Environmental Product Declaration submission requirements and establish a second site visit date of September 12, 2024...

[See Description of Modification Continuation Page]

5P2QCC

R5 AMD Repair & Alterations Contracting Branch Northern

Team

517 E Wisconsin Ave

Milwaukee, WI 53202 USA

R5 AMD Repair & Alterations Contracting Branch Northern

Team

230 S Dearborn St

Chicago, IL 60604 USA

EQ5P1NEC-24-0009

47PF0024R0042

1 7

9/3/2024

5/23/2024

1X

Description of Modification Continuation Page

... at 1:30 PM Eastern. The proposal due date remains unchanged at November 8, 2024 at 4:00 PM Eastern. Please see the attached description of amendment.

Please acknowledge receipt of this and all amendments as indicated in Block 11. Failure to do so may result in rejection of your offer. If a proposal was submitted prior to this amendment, you shall acknowledge the amendments and shall submit a final proposal revision even if price has not changed from the original proposal.

47PF0024R0042/0002

Description of Amendment

47PF0024R0042, Amendment 0002, Hilfiker Wall Repair, Land Port of Entry, Sault Sainte Marie, MI

The purpose of Amendment 0002 is to incorporate the following changes:

THE SOLICITATION:

I.D. Pre-Proposal Conference (Virtual and In-Person)

Date: Thursday, September 12, 2024 Time: 1:30 PM Eastern Location: Land Port of Entry, Sault Ste. Marie, MI*; also available virtually.

I.G. FAR 52.236-27 Site Visit – Construction (Feb 95)

(2) Site visits will be held at the following date and time:

Site Visit and/or Pre-proposal Conference registration is mandatory. To register and for further information about the site visit, virtual meeting link and access requirements, please contact:

Name: Thomas Monaweck - 5P1NEC Address: 110 Michigan St. NW, Grand Rapids, MI 49503 Telephone: (616) 222-9151 Email: thomas.monaweck@gsa.gov

II.D. Technical Proposal

Changes are provided in RED text:

Evaluation Factors:

1) Sustainability

Time: 1:30 PM Eastern (following the Pre-Proposal Conference) Date: Thursday, September 12, 2024

* Please meet at the parking lot elevator vestibule.

mailto:thomas.monaweck@gsa.gov

Background and Overview This project is funded in part by Section 60503 of the Inflation Reduction Act of 2022 (IRA), which provides funding for purchase of construction materials with substantially lower levels of embodied greenhouse gas emissions.

GSA’s IRA Low Embodied Carbon asphalt, concrete (and cement), glass and steel requirements establish numeric global warming potential (GWP) limits for certain EPA-approved construction materials: concrete (and cement), asphalt, steel, and glass (IRA-Eligible Materials). For each material, GWP limits have been established for the best performing 20% of materials in terms of embodied carbon (Top 20% Limits), the best performing 40% of materials in terms of embodied carbon (Top 40% Limits), and better than industry average (Better Than Average Limit).

This Evaluation Factor calls for Offeror commitments to furnishing IRA-Eligible Materials with the lowest possible GWP values. IRA Limit commitments proposed under this evaluation factor will be incorporated into the successful offeror’s resultant contract.

Individual materials’ GWP values may be found on individual manufacturers’ environmental product declarations (EPDs). EPDs must meet the standards reflected in GSA’s IRA Low Embodied Carbon asphalt, concrete (and cement), glass and steel requirements (see Compliance Documentation criteria listed for each IRA-Eligible Material).

Technical Acceptability and Scoring

Offerors will only meet the standard for technical acceptability under this Factor if they commit to furnish all required IRA-Eligible Materials with a GWP better (lower) than each IRA-Eligible Material’s Better Than Average Limit.

Offerors meeting the standard for technical acceptability will receive a number of Raw Scores, one for each IRA-Eligible Material required by the Contract:

● Offerors will receive a Raw Score of 100 for each IRA-Eligible Material commitment that is better (lower) than GSA’s Top 20% Limits.

● Offerors will receive a Raw Score of 40 for each IRA-Eligible Material commitment that is only better (lower) than GSA’s Top 40% Limits.

● Offerors will receive a Raw Score of 20 for each IRA-Eligible Material commitment that is only better (lower) than GSA’s Better

Than Average Limit.

Offerors shall complete the “IRA Sustainability Factor Table” attached to this solicitation by filling out the applicable IRA Limit they commit to meet for each IRA-Eligible Material. Based upon the offeror’s selection in the “IRA Limit Commitment” column, the associated Raw Score, the Weighted Score, and the Total Weighted Score will be automatically calculated.

In addition, for each IRA-Eligible Material identified in the IRA Sustainability Factor Table, offerors shall submit EPDs listing that material’s GWP. Such EPDs must meet the standards reflected in GSA’s IRA Low Embodied Carbon asphalt, concrete (and cement), glass and steel requirements (see Compliance Documentation criteria listed for each IRA-Eligible Material).

Note 1: By submitting an offer, Offeror consents to unrestricted GSA use of supplier names and the GWP values associated with supplier materials.

Such information may be disclosed publicly or used to inform other low embodied carbon procurement activities. Technical solutions, supplier pricing and supplier-offeror terms and conditions will not be shared. Any objection shall be transmitted to the Contracting Officer by the due date for offers and shall adhere to 41 C.F.R. § 105-60.601.

Note 2: For each offeror that is unable to submit any of the compliant EPDs by the proposal due date, the offeror will submit a statement for each such missing compliant EPD certifying that it is unable to submit the compliant EPD by the proposal due date. Failure by an offeror to submit any compliant EPD or its certification (as described in the immediately preceding sentence) by the proposal due date will result in the offeror’s proposal being unacceptable and the offeror being ineligible for award.

The contract resulting from this solicitation will have the following provision:

“Within 180 days after contract award, the Contractor will submit a compliant EPD for any IRA- eligible Material for which the Contractor was unable to submit a compliant EPD by the proposal due date. GSA will not issue a Notice to Proceed with construction services to the Contractor until the Contractor has submitted a compliant EPD for each IRA-eligible Material for which the Contractor was unable to submit a compliant EPD by the proposal due date. In addition to other remedies available to the Government, if the Contractor fails to comply with the 180-day requirement in this paragraph for submission of compliant EPDs, GSA will have the option to cancel the contract for the construction services at no cost to either the Contractor or GSA.

VI.F. Non-Price Factors

Changes are provided in RED text:

(1) Sustainability

Weight 15%

(1) The Sustainability Factor will be self-scored as outlined in Section II.D, above.

(2) GSA will verify Offeror’s scoring and that IRA Limits are supported by environmental product declarations (EPDs) from proposed suppliers.

(3) GSA will verify that Offeror’s EPDs adhere to EPD standards reflected in GSA’s Interim IRA Low Embodied Carbon Material Requirements (see Compliance Documentation criteria listed for each IRA-Eligible Material). If an EPD is not available, GSA will review the offeror’s statement confirming unavailability.

(4) GSA will make any scoring adjustments necessary to correct patent errors. Once GSA has verified the Offeror’s scoring and, if necessary, made any corrections, the overall weighted score will be assigned an adjectival rating, as follows:

Weighted Score

Adjectival Rating

100 points Exceptional

90-99 points Very Good

20-89 points Acceptable

Unacceptable Unacceptable

Note 1: Any proposal that does not furnish all required IRA-Eligible Materials with a GWP better (lower) than each IRA-Eligible Material’s Better Than Average Limit will be rated as “Unacceptable” under this factor and will be ineligible for award.

Note 2: Any proposal that furnishes all required IRA-Eligible Material with a GWP better (lower) than GSA’s Top 20% Limits will receive a weighted score of 100 points (Exceptional).

All other terms and conditions not addressed herein remain unchanged and in full force and effect.