RFB930600-01 - CCF Metal Roof Replacement - Addendum 1.pdf
PDF 519 KB Posted
- Attached to
- DOC CCF Metal Roof Replacement
- Solicitation number
- RFB930600-01
- Issued by
- Page County, Iowa
About this file
This is Addendum #1 to the Request for Bids (RFB930600-01) issued by the Iowa Department of Administrative Services for the DOC CCF Metal Roof Replacement project at the Clarinda Correctional Facility. The addendum, dated September 13, 2023, modifies and supplements the original bidding documents dated August 18, 2023, and must be acknowledged by bidders on the bid form to avoid disqualification. Key clarifications address site logistics including dumpster responsibilities, material storage requirements, equipment protocols, and the provision of facility resources such as restroom facilities, a gator and wagon for equipment hauling, and coordination procedures for material craning. The addendum specifies that demolition dumpsters shall be contractor-provided while metal scrap dumpsters shall be owner-provided, with metal roofing and trim to be cut into approximately 22-foot lengths. Contractors must remove boom lifts, scissor lifts, gang boxes, and small tools from the fenced area daily unless equipment has lockable dead man switches or removed batteries, and any scaffolding must be erected, dismantled, and removed daily.
The addendum introduces significant specification modifications to Section 07 6100 regarding manufacturer oversight and warranty requirements. These additions mandate that the roofing manufacturer provide a qualified technical representative to observe installation periodically to ensure compliance with warrantable details and that the same representative conduct warranty inspection reports in years 2, 5, 10, and 15 following substantial completion at no additional cost to the owner. For warranty issues identified during these inspections, the manufacturer must furnish all materials and labor to restore the roof to watertight condition. The addendum also approves Petersen Pac-Clad Pac T-250 as a substitution option and clarifies that material storage within the fenced area is limited to same-day use, with a designated lay-down area provided in the southwest corner of the parking lot outside the fence. All addendum content must be acknowledged by bidders and forms part of the binding contract documents.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DOC CCF Metal Roof Replacement Clarinda, Iowa
DAS#9306.00
RFB930600-01
Addendum #1
ADDENDUM #1
Project Name:
DAS# 9306.00
RFB 930600-01
Dated: September 13, 2023
This Addendum forms a part of the bidding and contract documents. This Addendum supersedes and supplements all portions of the original bidding and contract documents dated Aug. 18, 2023 with which it conflicts.
ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE
BID FORM. FAILURE TO DO SO MAY SUBJECT THE BIDDER TO
DISQUALIFICATION.
1) CLARIFICATIONS
A. Metal Scrap Dumpster: The owner/construction manager shall provide the metal scrap dumpster. The contractor shall demo and salvage all existing metal roofing and trim and place it in the dumpster provided by the owner. The contractor shall cut down metal roofing/trim into lengths that will fit in the scrap dumpster (approximately 22’ +/- lengths).
B. Demolition and garbage dumpsters are provided by the contractor.
C. All dumpsters can remain inside the fence area until filled.
D. Temporary toilets shall not be required. The use of the facility toilets shall be acceptable.
E. Craning materials over the perimeter fence shall be allowed. Coordinate with facility 72 hours in advance.
F. Boom lifts and scissor lifts shall be removed from the facility at the end of the workday unless the boom lift and/or scissor lift has a lockable dead man switch, or the battery is removed.
G. Gang boxes and small tools shall be removed from the fenced in area (yard) at the end of the day. The facility shall provide a gator and wagon for this purpose.
H. Scaffolding: If the contractor intends to use scaffolding for any of the project areas, the scaffolding will need to be erected, dismantled, and removed each day.
2) SPECIFICATIONS
A. Section 01 1200: Work Performed by Owner, Add Item 3. “The facility shall provide a gator and wagon for hauling gang boxes and small materials.”
B. Section 07 6100 Paragraph 1.3. Quality Assurance. Add the following paragraphs as 1.3.E and 1.3.F:
Clarinda, Iowa
DAS#9306.00
RFB930600-01
1.3.E Manufacturer’s Installation Inspection Requirement: Manufacturer shall provide a qualified technical representative to observe the roof installation periodically, as needed, to ensure adherence to warrantable details. The Contractor installing the roof shall be responsible to coordinate their roofing schedule with the Manufacturer’s representative in advance to ensure roof access and timely inspections during roof installation.
1.3.F. Manufacturer’s Technical Representative Qualifications: An authorized full-time employee representative of the manufacturer and experienced in the installation and maintenance of the specified roof panel system, and qualified to determine the Installer’s compliance with the warranty requirements of this Project.
C. Section 07 6100 Paragraph 1.5.B. Manufacturer’s Warranty. Add the following paragraph as 1.5.B.4:
1.5.B.4 Manufacturer Warranty Inspection Requirement: Manufacturer shall provide a qualified technical representative, to report maintenance responsibilities to Owner necessary for preservation of Owner's warranty rights. Inspections to occur in years 2, 5, 10, and 15 at no additional cost, following Substantial Completion. For any warranty issues found during these inspections, the manufacturer shall, at their expense, furnish and supply all materials and labor required to return the roof to a watertight condition in order to maintain the warranty.
3) DRAWINGS
A. No items.
4) QUESTIONS AND CLARIFICATIONS
A. Can materials be stored inside the fenced in area of the correctional facility? A> Stacked materials (Example: Insulation) that are brought into the fenced area (yard) shall be used and placed the same day they are brought in. There is a lay down area for stored materials outside of the fence area in the southwest corner of the parking lot. The contractor shall be responsible for hauling or hoisting large pallets of materials (Example: Insulation) into and out of the facility.
B. Would you be interested in exploring Coatings options for this roof replacement? A> No, a coating is not a viable option for the roof.
5) SUBSTITUTION REQUESTS
A. Petersen Pac-Clad – Pac T-250 – Approved substitution
6) ATTACHMENTS
A. Petersen Pac-Clad – Pac T-250 substitution request. (2 pages).
END OF ADDENDUM