About this file
This is a project description document for the Red Run Street and Moravian Drive Resurfacing Project in Michigan. The project involves resurfacing Red Run Road from 14 Mile Road to Moravian Drive, and Moravian Drive from Red Run Road to Schoenherr Road. The scope of work requires the contractor to furnish all labor, materials, and equipment necessary to complete the resurfacing work as detailed in the proposal specifications. The project is a straightforward road resurfacing initiative with defined geographic boundaries and comprehensive requirements for project completion.
The document does not provide specific details regarding pricing terms, contract duration, renewal options, set-asides, site visit schedules, bidders' meetings, response deadlines, or award dates in the available file content. Additional project specifications, cost estimates, timeline requirements, and bidding procedures would be contained in supplementary project documents or the formal solicitation materials.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
Red Run Street and Moravian Drive
Resurfacing
City Project No. 26-468
July 2026
Project Owner:
City of Sterling Heights
Office of Engineering
40555 Utica Rd
Sterling Heights, MI 48313
(586) 446-2720
Design Engineer:
Spalding DeDecker
905 South Boulevard East
Rochester Hills, MI 48307
(248) 844-5400
PROJECT NO. 26-468 RED RUN/MORAVIAN RESURFACING Page 2
TABLE OF CONTENTS
The Contract Documents consists of three parts as follows:
PART I BIDDING REQUIREMENTS, CONTRACT FORMS, AND CONTRACT CONDITIONS
PART II SPECIFICATIONS
PART III DRAWINGS
This Table of Contents lists the main divisions of Parts I and II and all drawings under this Contract in Part
III.
PART I
BIDDING REQUIREMENTS. CONTRACT FORMS, AND CONTRACT CONDITIONS
Title Page
00 01 00 – Bidding Requirements and Contract Forms
Advertisement for Bids ......................................................................................................................... C-111
Instructions to Bidders .......................................................................................................................... C-200
Sterling Heights Bid Submission Instructions ...................................................................................... C-201
Bid ......................................................................................................................................................... C-410
Hold Harmless ...................................................................................................................................... C-411
Non-Iran Linked Business Certification ............................................................................................... C-412
Non-Collusion Affidavit ....................................................................................................................... C-413
Reference Form ..................................................................................................................................... C-414
Sterling Heights ITB Responsible Qualification Questionnaire ........................................................... C-451
Sterling Heights ITB General Conditions Tariff Adjustments ............................................................. C-452
Sterling Heights Contract Documents................................................................................................... C-600
Contract Conditions
00 02 00 – General Conditions ............................................................................................................. C-700
00 03 00 – Supplementary General Conditions .................................................................................... C-800
PROJECT NO. 26-468 RED RUN/MORAVIAN RESURFACING Page 3
PART II
SPECIFICATIONS
Title Pages
01 01 00 – General Requirements .................................................................................................. 01 01 00-1
01 02 00 – Site and Miscellaneous Work ...................................................................................... 01 02 00-1
01 03 00 – Supplemental Specifications ........................................................................................ 01 03 00-1
01 10 00 – Summary of Work ........................................................................................................ 01 10 00-1
Special Provisions ............................................................................................................................. 23 Pages
Appendix A .................................................................................................................... Geotechnical Report
PART III
DRAWINGS
All drawings under this Contract have the following general caption:
CITY OF STERLING HEIGHTS
RED RUN STREET AND MORAVIAN DRIVE RESURFACING
1. COVER SHEET
2. NOTE SHEET
3. TYPICAL SECTIONS - 1
4. TYPICAL SECTIONS - 2
5. TYPICAL SECTIONS - 3
6. TYPICAL SECTIONS - 4
7. TYPICAL SECTIONS - 5
8. TYPICAL SECTIONS - 6
9. SESC PLAN
10. ALIGNMENT SHEET -1
11. ALIGNMENT SHEET - 2
12. ALIGNMENT SHEET - 3
13. REMOVAL PLAN – P.O.B. STA 10+74 TO STA 29+50
14. REMOVAL PLAN – STA 29+50 TO STA 48+50
15. REMOVAL PLAN – STA 48+50 TO P.O.E. STA 56+28
16. CONSTRUCTION PLAN AND PROFILE – P.O.B. STA 10+74 TO STA 19+50
17. CONSTRUCTION PLAN AND PROFILE –STA 19+50 TO STA 29+50
PROJECT NO. 26-468 RED RUN/MORAVIAN RESURFACING Page 4
18. CONSTRUCTION PLAN AND PROFILE – STA 29+50 TO STA 39+50
19. CONSTRUCTION PLAN AND PROFILE – STA 39+50 TO STA 48+50
20. CONSTRUCTION PLAN AND PROFILE – STA 48+50 TO P.O.E. STA 56+28
21. DETAILED GRADING
22. PAVEMENT MARKING & SIGNING - P.O.B. STA 10+74 TO STA 29+50
23. PAVEMENT MARKING & SIGNING - STA 29+50 TO STA 48+50
24. PAVEMENT MARKING & SIGNING - STA 48+50 TO P.O.E. STA 56+28
25. MAINTENANCE OF TRAFFIC PHASE 1
26. MAINTENANCE OF TRAFFIC PHASE 2
27. MAINTENANCE OF TRAFFIC TYPICALS
28. STERLING HEIGHTS DETAILS – PAVING
29. STERLING HEIGHTS STANDARD DETAILS -1
30. STERLING HEIGHTS STANDARD DETAILS - 2
31. STERLING HEIGHTS STANDARD DETAILS - 3
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ADVERTISEMENT FOR BIDS
CITY OF STERLING HEIGHTS
RED RUN STREET AND MORAVIAN DRIVE RESURFACING
General Notice
The City of Sterling Heights (Owner) is requesting Bids for the construction of the following Project:
RED RUN STREET AND MORAVIAN DRIVE RESURFACING
City Project No. 26-468
Sterling Heights
Bids for the construction of the Project will be received electronically by the City of Sterling Heights until Tuesday July 28, 2026 at 2:30pm local time. At that time the Bids received will be publicly opened and read.
The Project includes the following Work:
Resurfacing of Red Run Street from E 14 Mile Road to Moravian Drive and Moravian Drive from Red Run Street to Schoenherr Road.
The approximate quantities of the major items of Work are:
Sewer, Rem, Less than 24 inch Ft 203
Curb and Gutter, Rem Ft 572
Pavt, Rem Syd 380
Sidewalk, Rem Syd 196
Embankment, CIP Cyd 400
Excavation, Earth Cyd 480
_Ditch Cleanout, Spec Ft 1342
_Fill, HMA Crushed Material, CIP, 6 inch Syd 1500
_Shld, Cl III, 6 inch, Modified Syd 1387
Culv, Cl F, 12 inch Ft 225
Sewer, Cl E, 12 inch, Tr Det B Ft 437
_HMA Surface, Rem, Modified Syd 14866
_HMA, 2C, 4" Leveling Syd 15473
_HMA, 5EML, 2" Wearing Syd 15473
Curb and Gutter, Conc, Det B2 Ft 91
Curb and Gutter, Conc, Det F3 Ft 105
Curb and Gutter, Conc, Det F4 Ft 358
Driveway Opening, Conc, Det M Ft 129
Sidewalk, Conc, 4 Inch Sft 958
Sidewalk, Conc, 8 Inch Sft 769
Curb Ramp, Conc, 6 Inch Sft 915
Slope Restoration, Non-Freeway, Type A Syd 5200
EJCDC® C-111, Advertisement for Bids for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Bids are requested for the following Contract: Red Run and Moravian Resurfacing
Obtaining the Bidding Documents
Information and Bidding Documents for the Project can be found at the following designated website:
MITN website at www.bidnetdirect.com/mitn
The City is providing the Bidding Documents on the MITN website at www.bidnetdirect.com/mitn .
Please see separate files uploaded which consist of the Project Manual and the Drawings.
Bidder’s inquiries shall be directed to Alan Loebach, P.E. (Spalding DeDecker) at aloebach@sda-eng.com.
Instructions to Bidders.
Bid Security in the amount, form, and subject to the conditions provided in the Instructions to Bidders must be submitted with each Bid.
Bids may not be withdrawn for a period of 120 days after the actual date of opening thereof. This time period may be extended by mutual agreement of the OWNER and any Bidder or Bidders.
The City reserves the right to accept any or all alternative Bids and award the contract to other than the lowest bidder, to waive any irregularities or informalities or both; to reject any or all Bids; and in general to make the award of the Contract in any manner deemed by the City, in its sole discretion, to be in the best interest of the City of Sterling Heights
This Advertisement is issued by:
Owner: The City of Sterling Heights By: Office of Engineering Date: July 15, 2026 http://www.bidnetdirect.com/mitn http://www.bidnetdirect.com/mitn mailto:aloebach@sda-eng.com
EJCDC® C-200, Instructions to Bidders for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
TOC Page1 of 1
INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT
TABLE OF CONTENTS
Page
Article 1— Defined Terms
Article 2— Bidding Documents
Article 3— Qualifications of Bidders
Article 4— Pre-Bid Conference
Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;
Other Work at the Site
Article 6— Bidder’s Representations and Certifications
Article 7— Interpretations and Addenda
Article 8— Bid Security
Article 9— Contract Times
Article 10— Substitute and “Or Equal” Items
Article 11— Subcontractors, Suppliers, and Others
Article 12— Preparation of Bid
Article 13— Basis of Bid
Article 14— Submittal of Bid
Article 15— Modification and Withdrawal of Bid
Article 16— Opening of Bids
Article 17— Bids to Remain Subject to Acceptance
Article 18— Evaluation of Bids and Award of Contract
Article 19— Bonds and Insurance
Article 20— Signing of Agreement
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
DEFINED TERMS
1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:
A. Issuing Office—The office from which the Bidding Documents are to be issued, and which registers plan holders.
ARTICLE 2—BIDDING DOCUMENTS
2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.
2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.
2.03 Electronic Documents
A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.
1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf).
It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.
B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described above.
However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
ARTICLE 3—QUALIFICATIONS OF BIDDERS
3.01 Bidder is to submit the following information upon request of the Owner prior to the Award to demonstrate Bidder’s qualifications to perform the Work:
A. Written evidence establishing its qualifications including previous experience with reference contacts, and present commitments.
B. Subcontractor and Supplier qualification information.
3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.
3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.
ARTICLE 4—PRE-BID CONFERENCE
4.01 A pre-bid conference will not be conducted for this Project.
ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S
SAFETY PROGRAM; OTHER WORK AT THE SITE
5.01 Site and Other Areas
A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.
5.02 Existing Site Conditions
A. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.
5.03 Site Visit and Testing by Bidders
A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas.
B. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
C. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Express Representations and Certifications in Bid Form, Agreement
A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.
B. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.
ARTICLE 7—INTERPRETATIONS AND ADDENDA
7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.
7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:
A. Email inquiries to representative identified in the project specific Advertisement
7.03 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda and issued on the bidding document website. Questions received less than seven days prior to the date for opening of Bids may not be answered.
7.04 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.
ARTICLE 8—BID SECURITY
8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of five percent (5%) of Bidder’s maximum Bid price (determined by adding the base bid and all alternates) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions. Such Bid bond will be issued in the form included in the Bidding Documents.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.
8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.
8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.
ARTICLE 9—CONTRACT TIMES
9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.
9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.
ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS
10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.
10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.
ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS
11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
11.02 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.
11.03 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.
ARTICLE 12—PREPARATION OF BID
12.01 The Bid Form is included with the Bidding Documents.
A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink.
Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.
B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”
12.02 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.
12.03 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign.
The official address of the partnership must be shown.
12.04 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.
12.05 A Bid by an individual must show the Bidder’s name and official address.
12.06 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.
12.07 All names must be printed in ink below the signatures.
12.08 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
12.09 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.
12.10 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.
12.11 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.
ARTICLE 13—BASIS OF BID
13.01 Unit Price
A. Bidders must submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.
B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity”, which Owner or its representative has set forth in the Bid Form, for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.
C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.
13.02 Allowances
A. For cash allowances the Bid price must include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.
ARTICLE 14—SUBMITTAL OF BID
14.01 Bidder shall comply with the City of Sterling Heights BID SUBMISSION INSTRUCTIONS included within these specifications.
ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID
15.01 An unopened Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
15.02 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, the Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, the Bidder will be disqualified from further bidding on the Work.
ARTICLE 16—OPENING OF BIDS
16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.
PUBLIC BID OPENING: A public bid opening will be accessible 30 minutes after the posted due date and time via three simultaneous formats:
1. In person at the City of Sterling Heights Council Chambers locate at 40555 Utica Road, Sterling Heights, MI 48313.
2. Microsoft Teams live stream – Join the meeting here
3. Conference call, participants must call 586-446-2663, (enter Conference ID Code 4462740 when prompted)
ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE
17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.
ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT
18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.
18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.
18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.
18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.
18.05 Evaluation of Bids
A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.
https://teams.microsoft.com/l/meetup-join/19%3ameeting_ODVkMDYwZjAtZjIyOS00MDE3LTk3OTYtZWVjOGJkNjU5ZjI1%40thread.v2/0?context=%7b%22Tid%22%3a%22b4d6f201-96e3-4465-b7a5-0a89b7d16abb%22%2c%22Oid%22%3a%22c409637a-761b-428b-b134-24fd1a9caff3%22%7d
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.
18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.
ARTICLE 19—BONDS AND INSURANCE
19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.
19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.
ARTICLE 20—SIGNING OF AGREEMENT
20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.
C201 Page 1 of 2
BID SUBMISSION INSTRUCTIONS
Please read these instructions carefully. Your bid / proposal may be deemed non-responsive if it is not submitted as detailed below. Bids / proposals are considered received when downloaded into the mitn.info system before the submission deadline date and time, late bids / proposals will not be considered.
Bid / Proposal Submission Deadline: Thursday July 28, 2026 before 2:30 PM.
Electronic Bid Submission via the MITN system as described below is the only bid submittal option.
Call the Purchasing Office at 586-446-2740 if you have any questions and we will assist.
Electronic Bid Submission Only The vendor / Contractor will need to complete, scan and upload your entire bid package through the MITN system. All electronic bids / proposals will be submitted directly into a secured MITN “vault” that cannot be opened until the bid / proposal submission deadline date and time.
Vendor / Contractor Submittal Procedure:
Login to the MITN website using your previously registered credentials at http://www.mitn.info.
Locate and enter the Sterling Heights Solicitation you have prepared a bid for.
Click on the “Place Bid” button on the upper right side of the page.
In the “Place a Bid” window, select “Place a new Bid” or “Place a No Bid”
(Depending on your response). Select the “Continue” button .
On the next page, in the “Documents” tab, select “Add File” or “Import
Zip file” (Depending on your file type). Complete all required actions and click the “Next” button.
This will bring you to the “Pricing” tab. There you will see a reminder to “Don’t forget to attach your pricing in the ‘Documents’ section”. Select the “Next” button.
On the following screen, in the “Exceptions” section, select “No” or “Yes”
(depending on your response). In the “Bidder Compliance & Authentication” section, you will enter your full name and password where prompted. Click the
“Submit Bid” button.
In the “Bid Submission Confirmation” window, select “No” or “Yes” (depending on your response).
Finally, the next screen will confirm your bid submission. Here you will receive a confirmation number and will be able to download a PDF version of the confirmation for your records.
Important: The mitn.info system locks at 2:30 pm (Sterling Heights, Michigan Time) on the due date, and no bids / proposals can be downloaded after that time. No exceptions.
Bids / proposals must be downloaded and accepted by the mitn.info downloading portal
C201 Page 2 of 2 before 2:30 pm. Do not wait until the last minute to submit your bid / proposal, internet connections, computer systems failures on the submitter’s part could cause a bid / proposal to be denied from downloading into mitn.info system. The system locks at 2:30
pm. Late bids / proposals will not be considered.
If you have questions with the electronic bid submission procedures, please contact the MITN Vendor Support Department at (800) 835-4603, option #2 or email:
e-procurementsupport@bidnet.com
The City of Sterling Heights officially distributes bid and RFP documents through the Michigan Inter-governmental Trade Network (MITN). Copies of bid and RFP documents obtained from any other source are not considered official copies. Bids or notification of bids issued by members of MITN are to be posted, in whole or in part, ONLY on the MITN system. Any other use is prohibited. Only those vendors who obtain bid documents from the MITN system are guaranteed access to receive addendum information, if such information is issued. The City of Sterling Heights cannot guarantee the accuracy of any information not obtained from the MITN website and is not responsible for any errors contained by information received from alternate sources.
The City reserves the right, at its sole discretion, to allow a bidder to resubmit a copy of a bid that was otherwise submitted via the mitn.info system before the bid due date and time, when the bid document submitted via the mitn.info system is corrupt or otherwise not readable / downloadable by the City, and when in the opinion of the City, the fault was not that of the bidder.
If you received this document from a source other than the sources indicated, please notify us. It is recommended that all vendors register on the MITN website at www.mitn.info to obtain an official copy. All future bids, proposals, quotes and any addenda and tabulations will be posted on the MITN website.
BID BOND SUBMITTAL: Please refer to the specifications and forms for bid bond requirements and additional information. When bid bonds are required, all bidders must submit a photocopy of the Bid Bond (surety, cashier check, certified check) as part of the electronic bid submission. The photocopy must be of sufficient resolution to show a valid stamp, seal, signatures, names, dates, etc. The original Bid Bond must be provided upon request of the City. Failure to submit the original Bid Bond, upon request by the City, may result in the bid being deemed unresponsive and the bid rejected without further evaluation.
PUBLIC BID OPENING: A public bid opening will be accessible 30 minutes after the posted due date and time via three simultaneous formats:
1. Microsoft Teams live stream - Join the meeting here
2. Conference call, participants must call 586-446-2663, (enter Conference ID Code
4462740 when prompted).
A Purchasing Department representative will read the bids / name of firms submitting proposals as they are downloaded and made available.
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BID FORM FOR CONSTRUCTION CONTRACT
The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General
Conditions, and the Supplementary Conditions.
ARTICLE 1—OWNER AND BIDDER
1.01 This Bid is submitted to: City of Sterling Heights, 40555 Utica Rd, Sterling Heights, MI 48313. The undersigned
Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding
Documents.
ARTICLE 2—ATTACHMENTS TO THIS BID
2.01 The following documents are submitted with and made a condition of this Bid:
A. Hold Harmless and Indemnity
B. Non-Iran Linked Business Certification
C. Non-Collusion Affidavit
D. Required Bid security;
E. List of Proposed Subcontractors;
F. Responsible Contractor Qualification Questionnaire with supporting data; and
ARTICLE 3—BASIS OF BID
3.01 Unit Price Bids
A. Bidder will perform the following Work at the indicated unit prices:
Item Code Item Description Unit Quantity Unit Price Total Amount
1047051 _Audio-Visual Filming LSUM 1 $ $
1077060 _Permit Allowance DLR 2000 $ 1.00 $ 2,000.00
1100001 Mobilization, Max_ LSUM 1 $ $
2030001 Culv, Rem, Less than 24 inch Ea 3 $ $
2030011 Dr Structure, Rem Ea 1 $ $
2030015 Sewer, Rem, Less than 24 inch Ft 203 $ $
2040020 Curb and Gutter, Rem Ft 572 $ $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Item Code Item Description Unit Quantity Unit Price Total Amount
2040050 Pavt, Rem Syd 380 $ $
2040055 Sidewalk, Rem Syd 202 $ $
2050010 Embankment, CIP Cyd 400 $ $
2050016 Excavation, Earth Cyd 480 $ $
2050031
Non Haz Contaminated Material Handling and Disposal, LM Cyd 50 $ $
2057001 _Ditch Cleanout, Spec Ft 1342 $ $
2067011 _Fill, HMA Crushed Material, CIP, 6 inch Syd 1500 $ $
2067011 _Fill, 21AA Crushed Concrete, CIP, 6 inch Syd 150 $ $
2080012 Erosion Control, Check Dam, Stone Ft 60 $ $
2080020 Erosion Control, Inlet Protection, Fabric Drop Ea 10 $ $
2080036 Erosion Control, Silt Fence Ft 5000 $ $
3057011 _Shld, Cl III, 6 inch, Modified Syd 1387 $ $
4010012 Culv End Sect, 12 inch Ea 6 $ $
4010607 Culv, Cl F, 12 inch Ft 225 $ $
4020600 Sewer, Cl E, 12 inch, Tr Det B Ft 437 $ $
4030005 Dr Structure Cover, Adj, Case 1 Ea 1 $ $
4030006 Dr Structure Cover, Adj, Case 2 Ea 2 $ $
4030050 Dr Structure Cover, Type K Ea 1 $ $
4030280 Dr Structure, Adj, Add Depth Ft 2 $ $
4037050 Dr Structure Cover, Type B, Modified Ea 2 $ $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Item Code Item Description Unit Quantity Unit Price Total Amount
4037050 Dr Structure Cover, Type G, Modified Ea 1 $ $
4030210 Dr Structure, 48 inch dia Ea 3 $ $
4030390 Dr Structure, Temp Lowering Ea 4 $ $
4040063 Underdrain, Subbase, 6 inch Ft 18 $ $
4040113 Underdrain, Outlet Ending, 6 inch Ea 2 $ $
5017011 _HMA Surface, Rem, Modified Syd 14866 $ $
5010008 Pavt for Butt Joints, Rem Syd 10 $ $
5017011 _HMA, 2C, 4" Leveling Syd 15473 $ $
5017011 _HMA, Approach Syd 93 $ $
5017011 _HMA, 5EML, 2" Wearing Syd 15473 $ $
6020050 Conc Pavt, Misc, Nonreinf, 6 inch Syd 10 $ $
6020056 Conc Pavt, Misc, Nonreinf, 9 inch Syd 265 $ $
8010005 Driveway, Nonreinf Conc, 6 inch Syd 42 $ $
8010007 Driveway, Nonreinf Conc, 8 inch Syd 173 $ $
8020016 Curb and Gutter, Conc, Det B2 Ft 91 $ $
8020037 Curb and Gutter, Conc, Det F3 Ft 105 $ $
8020038 Curb and Gutter, Conc, Det F4 Ft 358 $ $
8020050 Driveway Opening, Conc, Det M Ft 129 $ $
8030010 Detectable Warning Surface Ft 74 $ $
8030030 Curb Ramp Opening, Conc Ft 70 $ $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Item Code Item Description Unit Quantity Unit Price Total Amount
8030044 Sidewalk, Conc, 4 Inch Sft 964 $ $
8030048 Sidewalk, Conc, 8 Inch Sft 769 $ $
8032002 Curb Ramp, Conc, 6 Inch Sft 915 $ $
8070095 Post, Mailbox Ea 8 $ $
8077050 _Mailbox, Temp Ea 8 $ $
8100371 Post, Steel, 3 pound Ft 210 $ $
8100403 Sign, Type III, Rem Ea 8 $ $
8100405 Sign, Type IIIB Sft 78 $ $
8102010 Ground Mtd Sign Support, Rem Ea 8 $ $
8110093 Pavt Mrkg, Polyurea, 6 inch, Crosswalk Ft 212 $ $
8110110 Pavt Mrkg, Polyurea, 12 inch, Crosswalk Ft 510 $ $
8110114 Pavt Mrkg, Polyurea, 24 inch, Stop Bar Ft 66 $ $
8110091 Pavt Mrkg, Polyurea, 4 inch, White Ft 10700 $ $
8110092 Pavt Mrkg, Polyurea, 4 inch, Yellow Ft 3135 $ $
8110103 Pavt Mrkg, Polyurea, Yield Ea 10 $ $
8110321 Rem Curing Compound, for Spec Mrkg Sft 585 $ $
8110405 Pavt Mrkg, Polyurea, Lt Turn Arrow Sym Ea 4 $ $
8120370 Traf Regulator Control LSUM 1 $ $
8127051 _Temporary Traffic Control Devices LSUM 1 $ $
8162001 Slope Restoration, Non- Freeway, Type A Syd 5200 $ $
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Item Code Item Description Unit Quantity Unit Price Total Amount
8210005 Monument Box Adj Ea 1 $ $
8237050 _Rotary Sprinkler Head Ea 10 $ $
8237050 _Spray Sprinkler Head Ea 10 $ $
8237001 _3/4-inch Sprinkler Line Ft 100 $ $
8237001 _1-inch Sprinkler Line Ft 100 $ $
8230431 Gate Box, Adj, Case 1 Ea 5 $ $
TOTAL BID $
B. Bidder acknowledges that:
1. each Bid Unit Price includes an amount considered by Bidder to be adequate to cover Contractor’s overhead and profit for each separately identified item, and
2. estimated quantities are not guaranteed and are solely for the purpose of comparison of Bids, and final payment for all Unit Price Work will be based on actual quantities, determined as provided in the
Contract Documents.
ARTICLE 4—TIME OF COMPLETION
4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.
4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.
ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF ADDENDA
5.01 Bid Acceptance Period
A. This Bid will remain subject to acceptance for 90 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.
5.02 Instructions to Bidders
A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
5.03 Receipt of Addenda
A. Bidder hereby acknowledges receipt of the following Addenda:
Addendum Number Addendum Date
ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS
6.01 Bidder’s Representations
A. In submitting this Bid, Bidder represents the following:
1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.
2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.
3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the
Work.
4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the
Technical Data in such reports and drawings.
5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.
6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on
(a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and (c) Bidder’s
(Contractor’s) safety precautions and programs.
7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.
8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.
9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that
Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the
Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.
10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.
6.02 Bidder’s Certifications
A. The Bidder certifies the following:
1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.
2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.
3. Bidder has not solicited or induced any individual or entity to refrain from bidding.
4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the
Contract. For the purposes of this Paragraph 8.02.A:
a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.
b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.
c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.
d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the
Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
BIDDER hereby submits this Bid as set forth above:
Bidder:
(typed or printed name of organization)
By:
(individual’s signature)
Name:
(typed or printed)
Title:
(typed or printed)
Date:
(typed or printed)
If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.
Attest: