IFB_R17PS00593_Tule_Lake_Road_Improvement_Phase_2.pdf
PDF 5 MB Posted
- Attached to
- Tule Lake Road Improvement Phase 2 Federal contract opportunity
- Solicitation number
- R17PS00593
About this file
Solicitation R17PS00593 Tule Lake Road Improvement Phase 2
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| R17PS00201_Abstract_of_Offers.pdf | ||
| R17PS00593-Amendment_0003.pdf | ||
| SF-30_and_Attachments_-_Amendment_0002.pdf | ||
| R17PS00593_Amendment_0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior Bureau of Reclamation Mid-Pacific Region
Solicitation No. R17PS00593 Tule Lake Road Improvement Phase 2 Klamath Basin Area Office
Klamath Project, Oregon- California
This page intentionally left blank
Tule Lake Road Improvement, Phase 2
TOC - 1
TABLE OF CONTENTS
SECTION A - Solicitation, Offer and Award Form (SF 1442)
SECTION B - Pricing Schedule
SECTION C - Specifications/Appendices
SECTION D - Packaging and Marking
SECTION E - Inspection and Acceptance
SECTION F - Deliveries or Performance
SECTION G - Contract Administration Data
SECTION H - Special Contract Requirements
SECTION I - Contract Clauses
SECTION J - List of Documents, Exhibits, and Other Attachments
SECTION K - Representations, Certifications and Other Statements of Offerors
SECTION L - Instructions, Conditions and Notices to Offerors
SECTION M - Evaluation Factors for Award
TOC - 2
TOC - 3
!!!!!!ATTENTION TO BIDDERS!!!!!!
In preparing your bid -----
1. Have you signed the bid? Are all blocks under Offer section of the SF1442 properly filled?
2. Have you included price information in Schedule B to include both page 3 (Columns E and F of Line item 0010) of SF1442 and Schedule B continuation pages? Have you checked your bid for possible mathematical errors?
3. Have you acknowledged receipt of all amendments by one of the methods identified in Block 11 of SF30?
4. Are you submitting your bid on time? If mailed, will it reach the place of bid opening prior to the designated date and hour?
5. Have you submitted the required bid guarantee in accordance with FAR 52.228-1?
6. In addition to above, have you furnished all documents/information requested by the invitation for bids?
a. Section K - Representations, Certifications And Other Statements Of Offerors
b. Section J Attachment 3 - Offeror Responsibility Information
7. Have you identified on the face of the envelope containing your bid, the invitation number to which it pertains, and the date and hour of opening?
***ABOVE INFORMATION SHOULD NOT BE CONSIDERED A COMPLETE CHECKLIST
FOR REQUIRED BID PACKAGE CONTENTS. BIDDERS SHOULD REVIEW THE IFB IN
ITS ENTIRETY AND ENSURE THAT THEIR BID PACKAGE MEETS ALL OF THE
REQUIREMENTS MENTIONED IN THIS SOLICITATION. PLEASE DO NOT SUBMIT
ANSWERS TO ABOVE QUESTIONS***
TOC - 4
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
Bureau of Reclamation
Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Bureau of Reclamation - MP Regional Office
Attention: Erim Celik, Contracting Officer 2800 Cottage Way, Room E-1815 Sacramento CA 95825-1898
Erim Celik 916-978-5549 x
6/5/2017
1. SOLICITATION NO.
R17PS00593
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
A. Title: Tule Lake Road Improvement Project, Phase 2 B. Work Site Location: The roads to be improved are located approximately 5 miles south of Tulelake, California in Siskiyou County.
C. Site Visit Information: See Section L, FAR 52.236-27, Site Visit (Construction)
Alt 1
D. Estimated Price Range: The estimated cost of construction is between
$500,000.00 and $1,000,000.00 E. Set-Aside Information: This requirement is restricted to Service-Disabled
Veteran-Owned Small Business concerns under NAICS 237130 with the applicable size standard of $36.50 million. FAR Clause 52.219-27, "Notice of Service-Disabled
Veteran-Owned Small Business Set-Aside" applies to this requirement.
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
7 240 calendar days and complete it within ________________ ________________ calendar days after receiving
0 / /2017 05 7
NSN 7540-01-155-3212
x x x x
_____0________ copies to perform the work required are due at the place specified in Item 8 by ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17-542
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Mid-Pacific Region
Regional Office Division of Acquisition Services
R20
2800 Cottage Way, Room E-1815
Sacramento CA 95825-1898
Erim Celik
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R16PS00243
00010 1 AU
FOB: Destination
Tule Lake Road Improvement Project, Phase 2
Price Schedule - CLINS 1 through 5
See following continuation pages
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Price Schedule – Consist of both lump sum and estimated quantities. Estimated quantity line items (2, 3, 4 and 5) will be used for measurement and payment for those items. See the appropriate measurement and payment sections of the specification. The estimated quantity line items shall be paid in accordance with FAR Clause 52.211-18 Variation in Estimated Quantities.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number.
(2) AU- Activity Unit: AU – Activity Unit is used solely for the purposes of allowing progress payments under the Department of Interior’s Financial & Business Management System (FBMS). This line represents the total value for the pricing proposal.
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 WBR
1452.232-
Mobilization and Preparatory Work
Lump Sum $________
2 31 02 30 Dust Palliative Application 2,347 yd2 $_______ $________
3 31 02 30 Dust Palliative Material 6.4 tons $_______ $________
4 32 15 10 Gravel Surfacing - ¾”-0” Aggregate
17,887 tons $_______ $________
5 32 15 10 Gravel Surfacing - 4”-0” Aggregate
18,585 tons $_______ $________
PROPOSED PRICE FOR PHASE 2 $___________________
END OF SECTION
Schedule
B - 2
SECTION C - STATEMENT OF WORK
SECTION 00 01 10
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 14 10 Use of Site
01 31 22 Coordination Meetings
01 32 20 Construction Program
01 33 00 Submittals
01 35 10 Material Safety Data Sheets
01 35 20 Safety and Health
01 35 30 Contractor Onsite Safety Personnel
01 55 00 Vehicle Access and Parking
01 55 20 Traffic Control
01 56 10 Protection of Existing Installations
01 56 15 Protection of Existing Utilities
01 64 40 Government Furnished Products
DIVISIONS 02 - 30 Not Used
DIVISION 31 - EARTHWORK
31 02 30 Dust Palliative
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 15 10 Gravel Road Surfacing
DIVISIONS 33 - 51 Not Used
DIVISION 52 - DRAWINGS
52 00 00 Drawings
END OF CONTENTS
This page intentionally left blank.
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. The roads to be improved are located in the Tule Lake Lease Lands, approximately 5 miles south of the town of Tulelake, California in Siskiyou and Modoc Counties.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Apply “Dust Off” or equivalent dust palliative to specific haul roads to minimize dust. Using a water trucks at all times, apply water for dust control on roads used that did not receive dust palliative.
B. Prepare and grade existing roads prior to placing base and aggregate.
C. Haul government supplied base and aggregate rock to the Tule Lake Lease Land roads.
D. Place and compact base and aggregate per the locations and thicknesses specified.
E. Perform final grading of roads.
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through
53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
1.04 DEFINITIONS
A. When the specifications use a word or term defined in the Federal Acquisition
Regulations (FAR), the definition of the word or term shall be in accordance with FAR sections in effect at the time this solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer
2. COR: Contracting Officer’s Representative
3. OGR: Onsite Government Representative
4. CE: Construction Engineer
5. ASTM: ASTM International
6. FAR: Federal Acquisition Regulations
7. JHA: Job Hazard Analysis
8. OSHA: Occupational Safety and Health Administration
9. RSHS: Reclamation Safety and Health Standard
10. SLE: Safety and Law Enforcement
11. SOP: Standard Operating Procedure
12. TSC: Technical Service Center
13. USBR: United States Bureau of Reclamation
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. USBR Cleaning Manual - - Inspection and Cleaning Manual for Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at: http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land use and landscape rehabilitation plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, haul routes, and stockpile locations.
3) Utilities including air, power, and waterlines; fire hydrants;
and compressor station.
4) Areas for processing, storing, and disposing of waste materials from construction operations.
5) Temporary fences.
b. Describe methods to preserve, protect, and repair if damaged, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to the jobsite, which are not to be removed and which do not interfere with the work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
http://www.usbr.gov/mussels/prevention
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near the jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages, or after use of Government, land is in operation.
1.02 PROJECT CONDITIONS
A. Where shown on drawings, government land may be used for required construction facilities.
B. When private land is used for construction facilities or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of the COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. During the months of September and October, trucks use the Tule Lake Lease Land roads to haul harvested produce. Access to roads for hauling and repair under this contract will be limited during these months. The contractor must receive Government approval regarding roads available for work under this contract in September and October.
F. The contractor shall observe the following speed limits when operating vehicles in the Tule Lake Lease Lands:
1. 35 mph for gravel roads,
2. 25 mph for dirt roads.
2.01 PORTABLE TOILET FACILITIES
A. The contractor shall provide a minimum of one (1) portable toilet at the job site and near road sections being constructed.
B. Self-Contained Toilet Units:
1. Single-occupant units.
2. Chemical, aerated recirculation, or combustion type.
3. Vented.
4. Fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material].
3.01 CLEANING
A. Clean and service portable toilets weekly.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
B. Restore temporary construction roads to original contours and make impassable to vehicular traffic when no longer required.
C. After completion of work, regrade and scarify Government land used for construction purposes and outside of the roadway. Grade so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
D. For disturbed areas of Government land used for construction purposes that were vegetated prior to road construction: Seed with species of native plants, or other approved perennial species.
E. The contractor shall remove the portable toilets from the job site.
SECTION 01 31 22
COORDINATION MEETINGS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 SUBMITTALS
Not Used.
1.03 SPECIFICATION DRAWINGS
Not Used.
1.04 COORDINATION MEETING[S]
A. Preconstruction Meeting
1. Date: Approximately 14 days after receipt of Notice to Proceed.
a. Notify Government of meeting date at least 7 days before meeting.
2 Location: To be determined.
3. Purpose: Review with Government personnel the road plan and technical requirements of specifications.
4. Attendees: Responsible contractor employees who understand the specifications with respect to technical requirements and equipment to be furnished.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
SECTION 01 32 20
CONSTRUCTION PROGRAM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Developing Baseline Schedule: Include in lump sum price offered in the schedule for mobilization and preparatory work.
2. Updating and Using Construction Program: Include as an element of Contractor’s overhead.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 32 20-1, Baseline Schedule:
1. Bar chart for project.
C. RSN 01 32 20-2, Updated Schedule:
1. Bar chart for project.
1.03 SCHEDULE
A. Develop, maintain, and use approved Construction Schedule to plan, monitor, and evaluate accomplishment of work.
B. Failure to include any element of the work will not release Contractor from completing all required work under the contract.
C. Construction Schedule:
1. Progress chart of suitable scale to indicate percentage of work scheduled for completion by any date.
2. Prepare schedule based on required sequence and interdependence of activities.
3. Include work of subcontractors, Government interfaces, and contract milestones.
4. Include contract title, contract number, and Contractor's name on each sheet.
D. Baseline Schedule:
1. Represents Contractor’s as-planned approach to accomplishing the work.
2. Include planned start and completion dates for features of work.
E. Updated Schedule: Enter actual progress.
F. If in the opinion of the CO, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the CO.
1. The CO may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contacting Officer deems necessary to demonstrate how the approved rate of progress will resume.
2. Costs for actions required to improve progress will the responsibility of the Contractor.
1.04 FAILURE TO COMPLY
A. Failure to comply with the requirements of this section shall be grounds for a determination by the CO that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the specified time. The CO may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.
1.05 PRODUCTS
1.06 EXECUTION
SECTION 01 33 00
SUBMITTALS
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-2005(2010) Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-2011 United States National CAD Standards, Version 5
1.03 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
1.04 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units
C. Drawings:
1. Minimum identification in title block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
3. Print Size: 11 inches by 17 inches.
4. Final drawings:
a. Drawing format: Adobe Acrobat pdf file
b. Show as-built changes, including revision dates, made during installation. Indicate changes by clouding.
c. Electronic files: On CD or DVD discs.
d. Original plots: 11 inches by 17 inches.
e. Government will provide an electronic pdf drawing template.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
1.05 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “No. of sets to be sent to:” columns in Table 01 33 00A - List of Submittals.
D. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
E. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
F. More than one RSN may be submitted under a transmittal letter, provided the responsible code is the same.
1.06 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 14 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. The time extension will be to the extent that excess review time caused delay to the contract completion date.
b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Return of Submittals:
1. Action Submittals: One set of submittals required for action will be returned either approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.
2. Informational Submittals: The Government will acknowledge Informational submittals.
a. Informational submittals will not be returned when they comply with the specifications.
b. Informational submittals that do not comply with the specifications may be returned for resubmittal or additional information may be requested.
1.07 TRANSMITTAL
A. Send submittals listed in Table 01 33 00A - List of Submittals to the following addresses:
1. Construction Engineer (CE), Bureau of Reclamation, MP Construction Office, P.O. Box 988, Willows CA 95988-0988. (For express mail service, use 1140 West Wood Street, Willows CA 95988-2615).
2. Onsite Government Representative (OGR), Bureau of Reclamation, Klamath Basin Area Office, 6600 Washburn Way, Klamath Falls, OR 97603.
B. Send original transmittal letter with appropriate number of sets to office listed in Responsible Code” column in Table 01 33 00A - List of Submittals.
1. Responsible codes starting with “86-6” are located in the Technical Service Center. Send these submittals to the TSC address shown above.
C. Send copy of transmittal letter with appropriate number of sets to offices that are not the responsible code, but show “No. of sets to be sent to” in Table 01 33 00A - List of Submittals.
D. When “No. of sets to be sent to” is 0, send a copy of transmittal letter to that office.
Table 01 33 00A - List of Submittals
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Responsible code
No. of sets to be sent to: **
CE OGR KBAO
01 32 10-1 Construction Program
Baseline Schedule:
Within 21 days after receipt of Notice to Proceed CE 3 1 1
01 32 10-2 Construction Program
Updated Schedule:
With monthly requests for progress payments. CE 3 1 1
01 35 10-1 Material Safety Data Sheets
Complete LHM and MSDS
At least 14 days before jobsite delivery of hazardous material CE 3 1 1
01 35 10-2 Material Safety Data Sheets
Updated LHM and MSDS
At least 14 days before jobsite delivery of hazardous material not previously listed
CE 3 1 1
01 35 20-1 Safety and Health Safety Program
Submitted and accepted before commencing onsite work. See section 3 of RSHS.
CE 3 1 1
01 35 20-2 Safety and Health
Monthly accident summary report
First day of each. See section 3 of RSHS month. CE 3 1 1
01 35 30-1 Contractor‘s Onsite Safety Personnel
Qualifications for Contractor’s Onsite Safety Rep
At least 14 days before start of onsite construction work CE 3 1 1
01 35 30-2 Contractor’s Onsite Safety Personnel
Safety inspection report At least once each week CE 3 1 1
01 55 20-1 Traffic Control Traffic control plan
At least 14 days before affecting public traffic. CE 3 1 1
31 02 30-1 Dust Palliative Application equipment
Within 14 days of dust palliative application CE 3 1 1
* Submittal types: A - Approval, I - Information
** CE indicates Construction Engineer, OGR indicates Onsite Government Representative, KBAO indicates Klamath Basin Area Office.
SECTION 01 35 10
MATERIAL SAFETY DATA SHEETS
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 DEFINITIONS
A. LHM: List of Hazardous Materials
B. MSDS: Material Safety Data Sheet.
1.03 APPLICATION
A. For the purposes of this contract, the definition of “materials delivered under this contract” in the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes materials delivered to the Government, materials incorporated into the work, and materials used by the Contractor during contract performance at the jobsite.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and MSDS.
C. RSN 01 35 10-2, Updated LHM and MSDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.05 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on the original or previously updated LHM and MSDS before receipt of updated LHM and MSDS by the CE.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
SECTION 01 35 20
SAFETY AND HEALTH
PART 1 GENERAL
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2001, Reclamation Safety and Health Standards
a. Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
1.03 SUBMITTALS
B. RSN 01 35 20-1, Safety program:
1. Written safety program in accordance with Section 3 of RSHS.
2. In the form and time intervals prescribed in Section 3 of RSHS.
3. Cover all aspects of onsite and applicable offsite operations and activities associated with this contract.
4. Follow the outline in Appendix B of RSHS (included at end of this Section).
5. Will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B, a narrative for each applicable item in the outline.
6. Provide a list of Job Hazard Analyses (JHA) that will be submitted throughout the project. Forms for the plans may be obtained at http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
7. A generic Company Safety Plan is not acceptable. The Safety Program shall be site specific for this contract.
C. RSN 01 35 20-2, Monthly accident summary report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of
RSHS.
1.04 PROJECT CONDITIONS
A. Comply with RSHS and any Federal, State, and Local regulations that apply.
B. Do not require anyone employed in performance of the contract (including subcontractor) to work under conditions which are unsanitary, hazardous, or dangerous to the employee’s health or safety.
C. Under no circumstances will onsite work, including mobilization, be permitted until the Safety Program has been considered acceptable by the COR.
D. Fully participate in a Contractor Safety Program Review meeting, according to RSHS Section 3.4.1, prior to mobilization. Include subcontractor management representatives.
E. Develop Job Hazard Analyses for each distinct phase of work under the contract.
1. Work will not begin on the phase of work until a JHA is acceptable to
COR.
2. Activities involving hazardous materials shall have the appropriate Material Safety Data Sheet(s) attached to the JHA.
F. In addition to requirements in the clause entitled “Accident Prevention”, fully comply with RSHS.
1. RSHS may be downloaded at http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
2. Errata for the RSHS are available at:
http://www.usbr.gov/ssle/safety/RSHS/RSHS01-errata.pdf
The errata apply to work under this contract.
G. Be cognizant of and ensure compliance with requirements set forth in paragraphs above.
1. Contractor’s responsibility applies to all operations, including those of the Contractor’s Subcontractors.
2. When violations of safety and health requirements contained in these specifications or referenced standards are called to the Contractor’s attention by the CO or COR immediately correct the condition to which attention has been directed.
3. Either oral or written notice shall be deemed sufficient.
H. When the Contractor fails or refuses to promptly correct a compliance directive, the CO or COR may issue an order to stop all or any part of the work.
1. When satisfactory corrective action is taken, an order to resume work will be issued.
2. The Contractor shall not be entitled to extension of time, or to claim for damage or to additional compensation by reason of either the directive or the stop order.
3. Failure of the CO or COR to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
I. Maintain an accurate record of, and report to the COR in the manner prescribed by the CO, all cases of death, occupational diseases, or traumatic injury to employees or the public involved, and property damage in excess of $2,500 occurring during the performance of work under this contract.
J. The rights and remedies of the Government provided in this section are in addition to any other rights and remedies provided by law or under this contract.
1. In the event there is a conflict between requirements contained in RSHS, specification paragraphs, Contractor’s approved Safety Program, referenced safety and health codes, and standards, or the U.S. Department of Labor Construction Safety and Health Standards, promulgated under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.), as amended, the more stringent requirement shall prevail.
K. Provide and maintain a work environment and procedures that will:
1. Safeguard the public and Government's personnel exposed to Contractor operations and activities.
2. Avoid interruptions of site operations and delays in project completion dates.
3. Control costs in contract performance.
L. Provide appropriate safety barricades, signs, and signal lights.
PART 3 EXECUTION
A. The contractor shall prepare and submit for review by the COR, detailed Job
Hazard Analyses (JHA), and an Accident Prevention Plan (Health and Safety Plan) in accordance with Reclamation Safety and Health Standards (RSHS).
1. JHA:
a. Required for each phase of the project.
b. Contractor shall submit to COR list of proposed JHA construction phases of the job.
B. Forms for the plan may be obtained at http://www.usbr.gov/ssle/safety/RSHS/rshs.html.
1. The plan shall be submitted and accepted by Reclamation prior to any construction activities at the site.
RSHS - APPENDIX B
CONTRACTOR SAFETY PROGRAM
Unless waived by Contracting Officer’s Representative (COR), prime and supplementary Safety Program submittals must, as a minimum, address all appropriate contractual requirements shown under the program outline. Program items will be so detailed that reviewers can ascertain adequacy. The original program submittal can cover all work phases or only address the initial work phases with timely supplementary submittals as a major work phases occur. Contractors desiring to follow this latter course of action will, in the initial submission, clearly define the original work covered and the work phases to be covered by supplements.
In no case will any phases of work commence until a program for that portion of the work has been accepted by the COR. Original and supplemental submissions covering hazardous operations and/or activities will include a standing operating procedure (SOP) and hazard analysis. The SOP will break down the operation or activity into specific basic steps. The hazard analysis will define the hazards associated with each basic step and proposed method(s) for eliminating or neutralizing the hazard. Such methods will outline, as a minimum, employee training requirements, personal protective equipment requirements, procedural changes, methods for evaluating program effectiveness, etc.
All activities involving use of hazardous and/or toxic materials, work in confined spaces, work at heights over 6 feet, or underwater work require an SOP and hazard analysis. Material Safety Data Sheets will be attached to all SOPs governing work that involves use of hazardous or toxic materials.
Program Outline I. General Requirements
A. Statement of Policy
B. Statement of Safety and Health Responsibilities
C. Statement of Compliance with Regulations, Standards, and Codes
D. Statement of Subcontractor Compliance
E. Safety Inspection Procedures
F. Accident Investigation and Reporting Procedures
G. Applicable Emergency Plans
H. Confined Space Procedures
I. Lockout/Tagout Procedures
J. Fire Protection Plans
1. Type and location of suppression equipment or systems
2. Offsite assistance agreement
3. Temporary heating devices
II. Medical A. Facilities
B. Training
C. Certifications
D. Physician, Ambulance (Name, location, and telephone number)
F. Physical Qualification of Employees
G. Records
III. Communications A. Employee Training
B. Safety Meetings
C. Onsite Training
D. Supervisor Training
IV. Occupational Health A. Procedures and Equipment to Minimize Hazards
B. Testing program for employees and work environments
C. Qualified personnel
D. Personal protective equipment
E. Ventilation plans
V. Machinery and Mechanical Equipment A. Procedures and Equipment to Minimize Hazards
1. Testing program for employees and work environments
2. Mobile and stationary equipment
B. Inspection Procedures
C. Maintenance Procedures
D. Operating Personnel
E. Protective Safety Devices
F. Elevators and Aerial Lifts
VI. Excavation and Demolition A. Tunnels and Shafts
1. Internal combustion engines
2. Ventilation plans
3. Transportation systems and equipment
4. Work environment testing
5. Ground support
B. Blasting
1. Blaster certification
2. Written procedures
3. Storage
4. Transportation
C. Excavations Other Than Tunnels and Shafts
1. Slide protections
2. Support systems
3. Inspections
4. Access
D. High Scaling
1. Definition
2. Personal protective equipment
3. Specific operating procedure
E. Haulage
1. Haul roads
2. Equipment and Procedures
VII. Working Surfaces A. Access
1. Ladders
2. Platforms, stairways, and ramps
B. Personal Protective Equipment
C. Scaffolding
D. Safety Nets
VIII. Protection of the Public A. Signs and Barricades
B. Flagging Procedures
C. Jurisdictional Approvals
IX. Marine and Diving Operations A. Detailed Plan and Written Procedures
X. Electrical Facilities A. Substations
XI. Required Safety Program Coordination
1. Confined Space Program
2. Electrical and Lockout/Tagout Program
This outline is provided as guidance in preparing a safety program and does not cover all material that may be necessary. The Contractor must review specifications and all safety and health regulations to ensure a comprehensive plan.
SECTION 01 35 30
CONTRACTOR’S ONSITE SAFETY PERSONNEL
Cost: Include in prices offered in the schedule for other items of work.
1.02 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 30-1, Qualifications:
1. Contractor’s Onsite Safety Representative
C. RSN 01 35 30-2, Safety Inspection Reports:
1. List noted deficiencies, their abatement dates, and follow-up action for jobsite activities.
2. Base inspection report on findings of jobsite walk-through with Government personnel.
1.03 QUALIFICATIONS
A. Contractor’s Onsite Safety Representative:
1. Competent supervisory employee with appropriate level of safety related training and experience.
1.04 APPLICATION
A. Designate an employee as the Contractor’s Onsite Safety Representative prior to start of construction.
B. Contractor’s Onsite Safety Representative authorities, duties, and responsibilities:
1. Review and approve the Contractor’s Safety Program prior to submittal.
2. Responsible for effectively implementing the Contractor’s Safety Program
3. Full authorization to correct unsafe acts on the spot.
4. Prepare safety inspection reports.
5. Onsite during construction activities.
1.05 QUALITY ASSURANCE
A. Contractor’s Onsite Safety Representative:
1. The effectiveness of the Contractor’s Onsite Safety Representative in prosecuting the safety program will be subject to continued review and approval by the CO.
2. Should the Contractor’s safety effort be considered inadequate, the CO has the option to require the Contractor to employ a qualified Safety Professional.
B. Safety Program:
1. The effectiveness of the Contractor’s Safety Program will be subject to continued review and approval by the CO.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
SECTION 01 55 00
VEHICULAR ACCESS AND PARKING
A. Cost:
1. Include in prices offered in the schedule for other items of work, except as specified.
2. Haul Road Maintenance and Repair: Include in lump sum price offered in the schedule for haul road maintenance.
1.02 REGULATORY REQUIREMENTS
A. Meet requirements established by jurisdictional authority for use of existing roadways and haul routes; including seasonal or other limitations or restrictions, payment of excess size and weight fees, and posting of bonds conditioned upon repair of damage.
B. Comply with applicable regulations for haul routes over public highways, roads, or bridges.
1.03 SITE CONDITIONS
A. Rights-of-way for access to work from existing roads will be established by the
Government.
1. In accordance with the clause at FAR 52.236-10, Operations and Storage Areas, use only established roadways, parking areas, and haul routes; or temporary roadways, parking areas, or haul routes constructed by the Contractor when and as authorized by the CO.
2. Subject to the clause at FAR 52.249-10, Default (Fixed-Price Construction), unavailability of transportation facilities or limitations thereon shall not become a basis for claims for damages or extension of time for completion of work.
Not used
3.01 EXAMINATION
A. Investigate condition of available public or private roads for clearances, restrictions, bridge-load limits, bond requirements, and other limitations that affect or may affect access and transportation operations to and from the jobsite.
3.02 HAUL ROUTES
A. Use existing available public highways, roads, or bridges as haul routes subject to applicable local regulations, existing restrictions, and approval of the COR.
Roadways available for the Contractor’s use are shown on the contract drawings.
B. Minimize interference with or congestion of local traffic.
3.03 MAINTENANCE
A. Maintain roadways, parking areas, and haul routes in a sound, smooth condition.
B. Maintain surfacing of gravel-surfaced roads and parking areas in a smooth condition until completion and acceptance of all work under this contract.
C. Snow removal for convenience of the Contractor or to facilitate work operations of the Contractor is considered to be normal required maintenance.
3.04 REPAIR
A. Promptly repair ruts, broken pavement, potholes, low areas with standing water, and other deficiencies to maintain road surfacing and drainage in original or specified condition. Contractor is responsible for damage caused by construction operations.
B. Restore haul roads to preconstruction conditions.
3.05 REMOVAL
A. Remove materials used to construct temporary roadways, parking areas, and haul routes prior to contract completion. Recycle salvageable materials as approved by the COR.
SECTION 01 55 20
TRAFFIC CONTROL
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Federal Highway Administration, Department of Transportation
1. MUTCD, Part 6 - - Part 6, Temporary Traffic Control, Manual on Uniform Traffic Control Devices, 2009 Edition with Revisions 1 and 2, (http://mutcd.fhwa.dot.gov/kno_2009r1r2.htm)
1.03 SUBMITTALS
B. RSN 01 55 20-1, Traffic control plan.
PART3 EXECUTION
3.01 TRAFFIC CONTROL
A. Meet requirements of MUTCD, Part 6.
B. Provide cones, delineators, concrete safety barriers, barricades, flasher lights, danger signals, signs, and other temporary traffic control devices as required to protect work and public safety.
C. Provide flaggers and guards as required to prevent accidents and damage or injury to passing traffic.
D. Do not begin work along public or private roads until proper traffic control devices for warning, channeling, and protecting motorists are in place in accordance with approved traffic control plan.
E. Maintain traffic flow and conduct construction operations to minimize obstruction and inconvenience to public traffic.
F. Protect roads closed to traffic with effective barricades and warning signs.
Illuminate barricades and obstructions from sunset to sunrise.
G. Remove traffic control devices when no longer needed.
SECTION 01 56 10
PROTECTION OF EXISTING INSTALLATIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the schedule for other items of work, except as specified.
2. Costs for repair of installations damaged by the Contractor's operations are the Contractor's responsibility.
1.02 PROJECT CONDITIONS
A. Drawings included in these specifications show items of existing materials and equipment but may not show all equipment and materials existing at the jobsite.
B. Obtain the location of embedded conduit, pipe, cable, ground mat, and other buried items before performing any excavations.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 PROTECTION
A. Provide protection for personnel and existing facilities from harm due to the Contractor's operations. Protection shall be subject to approval of the Government.
B. Arrange protective installations to permit operation of existing equipment and facilities by the Government while work is in progress.
3.02 REMOVAL OF PROTECTIVE INSTALLATIONS
A. Remove protective installations after purpose has been served. Materials furnished by the Contractor to provide protection remain property of the Contractor.
3.03 REPAIR
A. Repair, at Contractor's expense, damage to existing installations due to
Contractor's operations or Contractor's failure to provide proper protection. At the Government's option, damage may be repaired by the Government, and the Contractor will be back-charged repair costs.
SECTION 01 56 15
PROTECTION OF EXISTING UTILITIES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost: Include in prices offered in the schedule for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. RSHS-2009 Reclamation Safety and Health Standards
B. Institute of Electrical and Electronics Engineers (IEEE)
1. IEEE C2-2012 National Electrical Safety Code (NESC)
1.03 PROJECT CONDITIONS
A. Obtain location of buried conduit, pipe, cable, ground mat, and other buried items before excavating.
3.01 INTERFERENCE WITH OPERATION OR MAINTENANCE
A. Do not interfere with operation or maintenance service on utilities, existing on date offers are received.
1. Provide for access to utilities in a manner satisfactory to owners and operators, and the Government.
B. Provide required temporary structures; make necessary repairs, replacements, or similar operations; and furnish indemnity or other bonds.
3.02 CLEARANCES
A. Clearances in accordance with IEEE C2 provided by Government:
1. Where existing overhead powerline or communication line crosses a feature of work to be constructed, the Government will provide clearance at the crossing site between the line and the higher of (1) original ground;
or (2) final elevation of constructed work.
2. Where existing buried powerline or communication line crosses a feature of work to be constructed, the Government will provide clearance at the crossing site between the line and the lower of (1) original ground; or (2) final elevation of constructed work.
SECTION 01 64 40
GOVERNMENT-FURNISHED PRODUCTS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Except as specified below for backcharges and expenses to the Contractor, include cost of unloading, hauling, inspecting, storing, protecting, handling, and caring for products furnished by the Government in prices offered in the Price Schedule for work in which products are to be used.
2. Include cost of handling and installing minor miscellaneous items of metal, timber, and other products for which specific prices are not provided in the Price Schedule, in prices offered in the Price Schedule for work to which they are appurtenant.
3. Pay demurrage charges incurred due to failure to promptly unload railroad cars or trucks.
B. Backcharges and Expenses to the Contractor:
1. The Contractor will be charged for, or required to replace, any product lost or damaged after delivery and inspection.
2. The Contractor will be backcharged for products lost or damaged beyond repair after delivery and inspection or for products not incorporated in the work and not returned to the Government. The backcharge amount will be the initial Government product cost at point of delivery or the Government replacement cost at point of delivery, whichever is higher. This amount will include reasonable charges for Government warehousing and handling.
3. When directed by the CO to replace products lost or damaged by the Contractor, such replacement shall be at the Contractor's expense.
4. Repair of products damaged by the Contractor shall be at the Contractor's expense.
C. Estimated Costs:
1. Estimated costs listed in Table 01 64 40A - Government-Furnished Products are provided so that offerors may include in their offers applicable Federal, State, and local taxes and duties on Government-furnished products. These costs are not guaranteed, however, and the Government obligates itself only in that the costs are the Government's best estimates at time offers are received.
1.02 SUBMITTALS
B. RSN 01 64 40-1, Shortage report.
1. Written report of shortage in or damage to Government-furnished products.
1.03 DELIVERY, STORAGE, AND HANDLING
A. Products furnished by the Government include ¾”-0” and 4”-0” aggregate available in stockpiles at: O’Conner Pit and Flowers Pit, operated by Rocky Mountain Construction (RMC), Klamath Falls, OR. The entire supply of ¾”-0 aggregate and approximately 16,192 tons of 4”-0” aggregate is available at O’Conner Pit. The balance of 4”-0” aggregate is available at Flowers Pit. RMC is responsible for loading and weighing material (live ticketing), thus Contractor is required to coordinate with RMC for material pickup.
B. Estimated aggregate availability dates listed in Table 01 64 40A - Government- Furnished Products are provided so that offerors may develop a tentative construction program. These delivery dates are not guaranteed, however, and the Government obligates itself only to make reasonable efforts to secure delivery of items at times and in sequence to permit completion of work within time allowed under a reasonable and orderly construction program.
C. After availability date, load and haul…
This is the start of the file's text. The full file is on GovTribe.