R17PS00256_Amendment_2.pdf
PDF 622 KB Posted
- Attached to
- EC- FI AIR COOLER REPLACEMENT Federal contract opportunity
- Solicitation number
- R17PS00256
About this file
Amendment No. 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment___3.pdf | ||
| Amendment__0001_R17PS00256.pdf | ||
| R17PS00256_1442_(2)DD.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
R17PS00256
x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
Billings MT 59107
R60
PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation
06/19/2017
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION
NO. 000002
5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
06/19/2017
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Generators G1 and G2 Air Coolers, Flatiron Powerplant, Colorado-Big Thompson Project, Colorado
See attachment for changes incorporated by this amendment.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Gerri Voto-Braun
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Generators G1 and G2 Air Coolers Flatiron Powerplant Colorado – Big Thompson Project
Solicitation No. 17PS00256 Amendment No. 0002
Description of Changes:
1. In Block 11 of the Standard Form 1442, Remove 180 calendar days and substitute therefor with 300 calendar days.
2. In Section B - Remove pages B - 1 through B - 2 in its entirety and substitute therefor with the attached Revised pages B - 1 through B - 2.
3. In Part I, The Schedule, Section C -- Specifications, Remove Section 01 14 30-1 and 01 14 30-2 and substitute therefor the attached Revised Section 01 14 30-1 and 01 14 30-2.
4. In Part I, The Schedule, Section C -- Specifications, Remove Section 22 10 00-1 and 22 10 00-2 in its entirety and substitute therefor with the attached Revised Section 22 10 00-1 and 22 10 00-2.
5. In Part I, The Schedule, Section C -- Specifications, Remove Section 22 11 85-3 and 22 11 85-4 in its entirety and substitute therefor with the attached Revised Section 22 11 85-3 and 22 11 85-4.
6. In Part I, Section F - Deliveries or Performance--Remove page F-1 in its entirety and substitute therefor with the attached Revised page F-1.
For convenience, essential changes on the revised solicitation pages are indicated by a vertical line within the margin, whereby the lines or paragraphs are changed from the previous version. However, all portions of the revised solicitation pages shall apply whether changes thereon have or have not been indicated.
Acknowledgement: See Paragraph L.5, 52.214-3, on page L - 3 of the original solicitation, regarding acknowledgment by offerors to this amendment. The Government requires acknowledgment by offerors to this amendment at the place designated for receipt of bids, which is on Block 19 of the Standard Form 1442.
Receipt of Bids and Bid Opening: The hour and date for receipt and opening of bids remains 3:00 PM (Mountain Daylight Time Zone), July 19, 2017.
Third Party: If you have provided a copy of this solicitation to another company or person, please forward this amendment accordingly.
The following contractors were in attendance at the organized site visit, which took place June 29, 2017:
Albert Rogers Brandon Cavender J.W. Nelson Adil Khan Tony Stiglich Mark Westphal Dave Burst Todd Johnson Scott Craner Pete Coode Brian Carpenter Tyler Walty Garret Silva Matt Hanson
M1 Mechanical PLS Mechanical Growling Bear Accentz, Inc.
Modine Mfg.
Modine Mfg.
HPE
Elite Electric Elite Electric Tolin Mechanical Tolin Mechanical HD Inc.
RKMI
E-Corp
The final date and time for acceptance of questions by the Government is July 7, 2017, at 5:00 PM (MDT), which is the close of business. The Government will not respond to questions received after 5:00 PM (MDT), July 7, 2017. All questions are to be sent via e-mail to ddillon@usbr.gov. Failure of the Government's receipt of electronic commerce (emails), remains the responsibility of the company inquiring. It is suggested persons submitting questions via email ensure to request a received/read receipt.
Generators G1 and G2 Air Coolers Flatiron Powerplant Colorado – Big Thompson Project
Solicitation No. 17PS00256 Amendment No. 0002
Generators G1 and G2 Air Coolers, Colorado – Big Thompson Project
THIS PAGE INTENTIONALLY LEFT BLANK
Colorado - Big Thompson Project Amendment #002
Price Schedule Revised B - 1
CONTINUATION OF
SECTION B - SUPPLIES OR SERVICES AND PRICES
GENERATORS G1 AND G2 AIR COOLERS
FLATIRON POWERPLANT
COLORADO-BIG THOMPSON PROJECT, COLORADO
B.1 SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) All offers are subject to the terms and conditions of this solicitation.
(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(d) Definitions:
(1) CLIN - Contract Line Item Number.
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
WBR
1452.232-
Mobilization and Preparatory Work For the lump sum of $
2 22 10 00
Provide Replacement Generator Air Cooler Piping, Valves and Instruments
For the lump sum of $
3 22 11 85 Remove and Dispose of Existing G1 Air Coolers 6 ea $ $
4 22 11 85 Remove and Dispose of Existing G2 Air Coolers 6 ea $ $
Colorado - Big Thompson Project Amendment #002
Price Schedule Revised B - 2
5 22 11 85 Remove and Store Existing Spare Air Cooler 1 ea $ $
6 22 11 85
Design, Furnish, and Factory Test Generators G1 and G2, and Spare Air Coolers
13 ea $ $
7 22 11 85 Install and Performance Test G1 Air Coolers For the lump sum of $
8 22 11 85 Install and Performance Test G2 Air Coolers
For the lump sum of $
TOTAL FOR SCHEDULE $ ____________________
END OF SUPPLIES OR SERVICES AND PRICES
Colorado - Big Thompson Project Amendment #002
Interruption of Service Revised 01 14 30 - 1
SECTION 01 14 30
INTERRUPTION OF SERVICE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for items of work for which interruption of services are required.
1.02 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 30-1, Interruption of Service Request:
1. Area where work will be done (by number or other description).
2. Outline procedures for accomplishing work including:
a. Specific safety precautions to be taken.
b. Type and location of barricades.
c. Warning signs.
d. Protective grounds and devices to be used.
3. Commencement time of work.
4. Duration of work.
5. Number of personnel and their classification.
6. Description of equipment to be used.
7. Information indicating that required materials are on site or data indicating shipping dates of materials not on site.
1.03 PROJECT CONDITIONS
A. Coordinate and schedule interruption of services with COR:
1. Coordinate work with Government operations.
2. No specific interruption of service request will be considered unless:
a. COR has reasonable assurance that materials and equipment required for work will be onsite.
b. Be prepared to perform work on date and during period of time requested for specific interruption of service.
Colorado - Big Thompson Project Amendment #002
Interruption of Service Revised 01 14 30 - 2
3. Allowable time and available interruption of service periods will govern interruption of service requests, work scheduling, onsite delivery of materials, and required drawings and data submittals.
B. When work cannot be performed during an approved interruption of service period, notify COR that interruption of service is not required.
C. Show construction interruption of services greater than 4 hours in construction schedule.
D. Unit Operational Interruptions of Service:
1. Interruptions of Service will be at the convenience of the Government.
a. Outage times at Flatiron Powerplant will be restricted according to the Government’s requested water and power deliveries, operating conditions and other contractual obligations.
b. The Government anticipates that the interruption of service period for air cooler replacement work will be as follows:
1) Unit G1 – February 26, 2018 to March 23, 2018
2) Unit G2 – April 23, 2018 to May 18, 2018.
c. The units may not be available outside of this period.
2. Schedule, coordinate, and perform the work under this contract requiring an operational interruption of service, with the COR
a. The COR will give the Contractor an advance 30 day notification of the period when Interruptions of Service can be scheduled.
3. The replacement of air coolers identified by these specifications shall be completed, tested, and operational for 1 unit before an interruption of service will be granted on the next unit.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Piping and Valves
Revised 22 10 00 - 1
SECTION 22 10 00
PIPING AND VALVES
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Provide Replacement Generator Air Cooler Piping, Valves and Instruments.
1. Payment: Lump sum price offered in the Price Schedule.
1.02 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME B16.5-13 Pipe Flanges and Flanged Fittings
2. ASME B16.11-11 Forged Fittings, Socket-Welding and Threaded
3. ASME B16.21-11 Nonmetallic Flat Gaskets for Pipe Flanges
B. ASTM International (ASTM)
1. ASTM A53/A53M-12 Pipe, Steel, Black and Hot-Dipped, Zinc- Coated Welded and Seamless
2. ASTM A106/A106M-15 Seamless Carbon Steel Pipe for High- Temperature Service
3. ASTM A307-14 Carbon Steel Bolts, Studs, and Threaded Rod
4. ASTM A563-15 Carbon and Alloy Steel Nuts
C. Manufacturers Standardization Society of the Valve and Fitting Industry (MSS)
1. MSS SP-58-09 Pipe Hangers and Supports
2. MSS SP-80-13 Bronze Gate, Globe, Angle and Check Valves
1.03 SYSTEM DESCRIPTION
A. Verify existing materials and dimensions onsite prior to furnishing new materials.
B. General Requirements:
1. Remove and dispose of existing 2-inch air cooler cooling water supply and discharge piping and valves.
Piping and Valves
Revised 22 10 00 - 2
2. Provide:
a. Replacement 2 inch diameter piping, fittings and appurtenances for each generator air cooler supply and discharge piping.
b. Replacement cooling water shut-off (gate) valves.
c. Replacement cooling water discharge throttling (globe) valves.
d. New flow measurement instrumentation on each air cooler branch to visually indicate rate of flow in gallons per minute through coolers for the purposes of balancing.
C. Materials shall be newly manufactured and sized to match existing connections to the cooling water header piping and to the new air coolers.
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 22 10 00-1, Approval Data:
1. Manufacturer’s technical data and installation instructions for furnished materials.
PART 2 PRODUCTS
2.01 PIPING, FITTINGS AND APPURTENANCES
A. Piping:
1. Pipe: ASTM A53, Type E or S or ASTM A106, carbon steel.
2. Fittings: Carbon steel, schedule 40.
3. Flanges:
a. Carbon steel, welding neck type, faced and drilled in accordance with
ASME B16.5.
b. Carbon steel, slip-on, faced and drilled in accordance with ASME B16.5.
4. Pipe Hangers and Supports: In accordance with MSS SP-58.
B. Flow Measurement Instrumentation:
1. Variable Area/Direct Reading Flowmeter.
a. Maximum Flow Capacity: 85 gpm of clean water.
b. Direct Reading in GPM.
c. Industrial Grade Construction. Plastic materials not allowed.
d. Self-contained and complete. No external power required.
Generator Air Coolers Revised 22 11 85 - 3
RSN 22 11 85-2, Final Drawings and Data:
1. Bound service manual including:
a. Previously approved drawings and data submitted under RSN 22 11 85-1 including half-size (11 inch by 17 inch) prints of air cooler drawings.
b. Manufacturer installation, operation, and maintenance manual.
c. Recommended list of spare parts.
RSN 22 11 85-3, Test Reports:
1. Certified hydrostatic test reports.
2. Certified service test reports.
1.04 SYSTEM DESCRIPTION
General Requirements:
1. Remove and dispose of existing Westinghouse fin-tube air coolers for generators G1 and G2 at Flatiron Powerplant.
a. Existing air coolers are assumed to have lead-based coatings.
2. Design, furnish, factory test, and install new generator air coolers for generators G1 and G2 in accordance with this section.
a. Each air cooler unit shall be identical in design and shall be interchangeable with other coolers.
b. Design each air cooler to fit into the existing space currently occupied by the existing air coolers and shall match vent and water piping connections of the existing air coolers without modification to existing equipment.
c. Each air cooler shall have a rigid frame, be self-contained and designed for handling as a complete assembly. Lifting lugs for handling and installation are required.
d. Air cooler frames shall be used for lifting and mounting, and designed to attach within the generator air housing to the existing outside periphery of the stator frame.
e. Air cooler design shall be heavy-duty, industrial type suitable for continuous or cyclic duty operation.
f. Air coolers shall be free draining.
3. Field verify existing air cooler dimensions, connections, and mounting details from existing equipment at the jobsite prior to design and manufacture of new air coolers.
a. The spare air coolers will be available for inspection at the Eastern Colorado Area Office warehouse facility located at 910 Van Buren
Colorado - Big Thompson Project Amendment #002
Generator Air Coolers Revised 22 11 85 - 4
Avenue, Loveland, Colorado. Refer to Section 00 00 30 - Foreword for Site visit details.
Performance Requirements:
1. Generator air coolers shall have sufficient cooling capacity to maintain the temperature of the air entering the generator air housing at 40 degrees C or less under the following conditions:
a. Generator delivering 100 percent rated output of 47.8-MVA.
1) The Government estimates maximum heat loads of approximately 2-percent of the generator nameplate rating.
b. Maximum cooling water supply temperature of 25 degrees C.
c. Cooling water flow rate of 300 gpm for each generator.
1) Cooling water flow rates may vary up to a maximum of 500 gpm;
however, design of new air coolers should minimize flow of cooling water to the greatest extent possible.
d. With 6 air coolers in service per generator.
Existing System General Description:
1. Each of the generator units G1 and G2 have 6 finned tube air-to-water air coolers mounted at equal intervals within the generator air housing on the outside periphery of the stator frame. The following are the approximate dimensions measured from the spare cooler:
a. The exterior dimensions of the air coolers are 66-3/4 inches by 44-3/4 inches by 18-1/4 inches deep. Each air housing opening for the air coolers is 46-1/8 inches by 32-3/8 inches.
b. The tubes are 1.0 inch outside diameter.
c. There are 6 fins per inch. The fins are 1.75 inch diameter.
d. There are approximately 3 rows of 16 tubes and 3 rows of 15 tubes, for a total of 93 tubes.
2. Cooling water from the raw water supply is fed to the air coolers. The environmental air of the generator is passed through the air coolers and is then recirculated. Air is circulated through the air coolers by the generator rotor.
3. Air temperature is controlled by the rate of raw water flow through the air coolers, each air cooler of which is fitted with a throttling valve to equalize the flow through coolers within the generator. Exit air temperature is measured by a bulb type thermometer, one at each air cooler. The air entering the generator is cooled to less than 40 degrees C by the 6 air coolers.
4. The elevation of the air coolers at Flatiron Powerplant is 5471.00 feet.
5. The approximate weight of each empty air cooler is 820 lbs.