Amendment___3.pdf

PDF 436 KB Posted

Attached to
EC- FI AIR COOLER REPLACEMENT Federal contract opportunity
Solicitation number
R17PS00256
Issued by
Department of the Interior Bureau of Reclamation

About this file

Amendment No. 0003 - Please note that due to technical issues with FBO, the attachment for Amendment No. 0003 did not post properly, therefore Amendment No. 0004 actually contains the Amendment No. 0003 file.

View the file

Other files for this federal contract opportunity

Other files attached to EC- FI AIR COOLER REPLACEMENT, newest first.
File Type Posted
R17PS00256_Amendment_2.pdf PDF
Amendment__0001_R17PS00256.pdf PDF
R17PS00256_1442_(2)DD.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

R17PS00256

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

Billings MT 59107

R60

PO Box 36900 Regional Office Great Plains Region Bureau of Reclamation

06/19/2017000003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/19/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Generators G1 and G2 Air Coolers Flatiron Powerplant, Colorado-Big Thompson Project, Colorado

See attachment for changes incorporated by this amendment.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Gerri Voto-Braun

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Generators G1 and G2 Air Coolers Flatiron Powerplant Colorado – Big Thompson Project

Solicitation No. 17PS00256 Amendment No. 0003

Description of Changes:

1. In Description of Changes to Amendment No. 2 - Remove Amendment No. 2, Page 2 of 3, in its entirety and substitute therefor with the attached Revised Amendment No. 2, Page 2 of 3, (correcting the contact information of the Contractors in Attendance at the organized site visit), which took place June 29, 2017.

2. In Section B - Price Schedule, Remove the Continuation of Section B - Price Schedule in its entirety and substitute therefor with the attached Revised Continuation of Section B - Price Schedule.

3. In Part I - The Specification, Section C -- Remove Section 01 14 30 - Interruption of Service in its entirety and substitute therefor with the attached Revised Section 01 14 30 - Interruption of Service.

4. In Part I - The Specification, Section C -- Remove Section 01 33 00 - Submittals in its entirety and substitute therefor with the attached Revised Section 01 33 00 - Submittals.

5. In Part I - The Specification, Section C -- Remove Section 22 10 00 - Piping and Valves in its entirety and substitute therefor with the attached Revised Section 22 10 00 - Piping and Valves.

6. In Part I - The Specification, Section C -- Remove Section 22 11 85 - Generator Air Coolers in its entirety and substitute therefor with the attached Revised Section 22 11 85 Generator Air Coolers.

7. In Part I - The Specification, Section C -- Remove (Section) Drawings in its entirety and substitute therefor with the attached Revised (Section) Drawings.

For convenience, essential changes on the revised solicitation pages are indicated by a vertical line within the margin, whereby the lines or paragraphs are changed from the previous version.

However, all portions of the revised solicitation pages shall apply whether changes thereon have or have not been indicated.

Acknowledgement: See Block 11 above regarding acknowledgement by offerors to this amendment. The Government requires acknowledgment by offerors to this amendment at the place designated for receipt of bids. (Please see Block 10 of the Standard Form 1442).

Receipt of Bids and Bid Opening: The hour and date for receipt and opening of bids remains 3:00 PM (Mountain Daylight Time Zone), July 19, 2017.

Third Party: If you have provided a copy of this solicitation to another company or person, please forward this amendment accordingly.

A list of questions from prospective contractors and the respective responses by the Government are attached to this amendment, and are provided for informational purposes only.

Generators G 1 and G2 Air Coolers

Colorado - Big Thompson Project

Description of Changes:

Solicitation No. 17PS00256 Amendment No. 0002

1. In Block 11 of the Standard Form 1442, Remove 180 calendar days and substitute therefor with 300 calendar days.

2. In Section B - Remove pages B - 1 through B - 2 in its entirety and substitute therefor with the attached Revised pages B - 1 through B - 2.

3. In Part I, The Schedule, Section C -- Specifications, Remove Section 01 14 30-1 and 01 14 30-2 and substitute therefor the attached Revised Section 01 14 30-1 and 01 14 30-2.

4. In Part I, The Schedule, Section C -- Specifications, Remove Section 22 10 00-1 and 22 10 00-2 in its entirety and substitute therefor with the attached Revised Section 22 10 00-1 and 22 10 00-2.

5. In Part I, The Schedule, Section C -- Specifications, Remove Section 22 11 85-3 and 22 11 85-4 in its entirety and substitute therefor with the attached Revised Section 22 11 85-3 and 22 11 85-4.

6. In Part I, Section F - Deliveries or Performance--Remove page F-1 in its entirety and substitute therefor with the attached Revised page F-1.

For convenience, essential changes on the revised solicitation pages are indicated by a vertical line within the margin, whereby the lines or paragraphs are changed from the previous version. However, all portions of the revised solicitation pages shall apply whether changes thereon have or have not been indicated.

Acknowled�nent: See Paragraph L.5, 52.214-3, on page L - 3 of the original solicitation, regarding ac owledgment by offerors to this amendment. The Government requires acknowledgment by offerors to this amendment at the place designated for receipt of bids, which is on Block 19 of the Standard Form 1442.

Receipt of Bids and Bid Openin�: The hour and date for receipt and opening of bids remains 3:00 PM (Mountain Daylight Time Zone), July 19, 2017.

Third Party: If you have provided a copy of this solicitation to another company or person, please forward this amendment accordingly.

The following contractors were in attendance at the organized site visit, which took place June 29, 2017:

Albert Rogers Ml Mechanical 719-660-0151 arogers@frontrangeconstructioninc.com

Brandon Cavender PLS Mechanical 719-310-7706 brandonc@plsmech.com

J.W. Nelson Growling Bear 970-353-6964 garysh ironakai@grow I ingbear. com

Adil Khan Accentz, Inc. 303-638-6487 adil@accentzinc.com

Tony Stiglich Modine Mfg. 514-465-0508 Anton.stiglich@modinecis.com

Mark Westphal Modine Mfg. 662-230-3047 Mark.a.westphal@modine.com

Dave Burst HPE 303-950-7296 davidb@hpeinc.com

Todd Johnson Elite Electric 970-214-1763 Toddj930@aol.com

Scott Craner Elite Electric 970-581-6753 Toddj930@aol.com

Pete Coode Tolin Mechanical 970-219-15 I 0 pcoode@hpmservice.com

Brian Carpenter Tolin Mechanical 970-305-7572 bcarpenter@tolin.com

Tyler Walty HD Inc. 719-499-3250 Twalty@hditcam.com

Garret Silva RKMI 720-402-4195 gsil va@rkmi.com

Matt Hanson E-Corp 719-896-6324 None given

Revised - Description of Changes

Generators G1 and G2 Air Coolers, Colorado – Big Thompson Project

THIS PAGE INTENTIONALLY LEFT BLANK

Colorado - Big Thompson Project Amendment #003

Price Schedule Revised B - 1

CONTINUATION OF

SECTION B - SUPPLIES OR SERVICES AND PRICES

GENERATORS G1 AND G2 AIR COOLERS

FLATIRON POWERPLANT

COLORADO-BIG THOMPSON PROJECT, COLORADO

B.1 SCHEDULE

(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.

(b) All offers are subject to the terms and conditions of this solicitation.

(c) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.

(d) Definitions:

(1) CLIN - Contract Line Item Number.

PRICE SCHEDULE

CLIN Section Supplies or Services Quantity and Unit

Unit Price Amount

WBR

1452.232-

Mobilization and Preparatory Work For the lump sum of $

2 22 10 00

Provide Replacement Generator Air Cooler Piping, Valves and Instruments

For the lump sum of $

3 22 11 85 Remove and Dispose of Existing G1 Air Coolers 6 ea $ $

4 22 11 85 Remove and Dispose of Existing G2 Air Coolers 6 ea $ $

Price Schedule Revised B - 2

5 22 11 85 Remove and Store Existing Spare Air Cooler 1 ea $ $

6 22 11 85

Design, Furnish, and Factory Test Generators G1 and G2, and Spare Air Coolers

13 ea $ $

7 22 11 85 Install and Performance Test G1 Air Coolers For the lump sum of $

8 22 11 85 Install and Performance Test G2 Air Coolers

For the lump sum of

TOTAL FOR SCHEDULE $ ____________________

END OF SUPPLIES OR SERVICES AND PRICES

Interruption of Service Revised 01 14 30 - 1

SECTION 01 14 30

INTERRUPTION OF SERVICE

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for items of work for which interruption of services are required.

1.02 SUBMITTALS

A. Submit in accordance with Section 01 33 00 - Submittals.

B. RSN 01 14 30-1, Interruption of Service Request:

1. Area where work will be done (by number or other description).

2. Outline procedures for accomplishing work including:

a. Specific safety precautions to be taken.

b. Type and location of barricades.

c. Warning signs.

d. Protective grounds and devices to be used.

3. Commencement time of work.

4. Duration of work.

5. Number of personnel and their classification.

6. Description of equipment to be used.

7. Information indicating that required materials are on site or data indicating shipping dates of materials not on site.

1.03 PROJECT CONDITIONS

A. Coordinate and schedule interruption of services with COR:

1. Coordinate work with Government operations.

2. No specific interruption of service request will be considered unless:

a. COR has reasonable assurance that materials and equipment required for work will be onsite.

b. Be prepared to perform work on date and during period of time requested for specific interruption of service.

Interruption of Service Revised 01 14 30 - 2

3. Allowable time and available interruption of service periods will govern interruption of service requests, work scheduling, onsite delivery of materials, and required drawings and data submittals.

B. When work cannot be performed during an approved interruption of service period, notify COR that interruption of service is not required.

C. Show construction interruption of services greater than 4 hours in construction schedule.

D. Unit Operational Interruptions of Service:

1. Interruptions of Service will be at the convenience of the Government.

a. Outage times at Flatiron Powerplant will be restricted according to the Government’s requested water and power deliveries, operating conditions and other contractual obligations.

b. The Government anticipates that the interruption of service period for air cooler replacement work will be as follows:

1) Unit G1 – February 26, 2018 to March 23, 2018

2) Unit G2 – April 23, 2018 to May 18, 2018.

c. The units may not be available outside of this period.

2. Schedule, coordinate, and perform the work under this contract requiring an operational interruption of service, with the COR

a. The COR will give the Contractor an advance 30 day notification of the period when Interruptions of Service can be scheduled.

3. The replacement of air coolers identified by these specifications shall be completed, tested, and operational for 1 unit before an interruption of service will be granted on the next unit.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

END OF SECTION

Submittals

Revised 01 33 00 - 1

SECTION 01 33 00

SUBMITTALS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Cost:

1. Include in prices offered in the Price Schedule for other items of work.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME Y14.1-05(2010) Decimal Inch Drawing Sheet Size and Format

B. National Institute of Building Sciences (NIBS)

1. NIBS NCS-14 United States National CAD Standards, Version 6

1.03 DEFINITIONS

A. Days: Calendar days.

B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.

C. Submittals: Considered "shop drawings" within the terms of the clause at FAR 52.236- 21, Specifications and Drawings for Construction.

1.04 SUBMITTAL REQUIREMENTS

A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.

B. General:

1. Prepare in English.

2. Label with contract number and title, and RSN.

3. Measurement units: US Customary Units.

Revised 01 33 00 - 2

C. Drawings:

1. Minimum identification in title block:

a. Contract number and title.

b. Contractor’s or supplier’s title and drawing number.

c. Date.

2. Provide space next to title block for review stamps.

3. Print Size: D size (22 inches by 34 inches).

4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.

a. Lettering shall be neat when drawing preparation with drafting equipment is allowed.

5. Government Format drawings:

a. Prepare drawings designated as "Government Format" in the specifications as follows:

1) Title block and sheet format:

a) As shown on Drawing 40-D-7102.

b) Government will provide specific title block information to be used.

2) Drawing format:

a) AUTOCAD, Version 2015 or later.

b) In accordance with NIBS NCS.

3) Government will provide an electronic AutoCAD template.

6. Final drawings:

a. Drawing format: AUTOCAD, Version 2015 or later.

b. Show as-built changes, including revision dates, made during installation.

Indicate changes by clouding.

c. Electronic files: On CD or DVD discs.

d. Government will provide an electronic AutoCAD template.

D. Product Data:

1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.

a. Identify manufacturer's name, type, model, size, and characteristics.

b. Illustrate that product or equipment meets requirements of specifications.

Revised 01 33 00 - 3

c. Mark items to be furnished in a manner that will photocopy (no highlighter).

d. Strike through items that do not apply.

E. Certifications:

1. Certifications by a registered professional: Signed and sealed by registered professional.

2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.

1.05 SUBMITTALS PROCEDURES

A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.

B. Submit complete sets of required materials for each RSN as specified in "Submittals Required" column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.

C. Submit sets specified in "Sets to be sent:" columns in Table 01 33 00A - List of Submittals.

1. Electronic submittals:

a. In Portable Document Format (PDF).

b. Include RSN transmittal letter.

c. Do not include Personally Identifiable Information (PII) in electronic submittals.

2. Submit electronic submittals via email or CD/DVD based on size:

a. The Government can receive e-mails up to 25 MB. However, e-mails over 10 MB should be considered extra-large. E-mailing of electronic submittals exceeding 10 MB should only occur after transmittal of larger size e-mail has been verified.

b. Address e-mail of electronic submittals less than extra-large size to:

1) sha-GPR-CONSTSVCS@usbr.gov.

c. Include electronic submittals that are too large to e-mail with paper copy of submittal. These electronic submittals shall be on CD or DVD.

D. Include the following information in transmittal letters:

1. Contract number and title.

2. RSN for attached submittal.

3. Responsible code.

Revised 01 33 00 - 4

4. Number of sets for each RSN.

5. Identify submittal as initial or resubmittal.

E. Resubmittal of submittals not approved:

1. Mark changes such that they are readily identifiable and show revision date.

2. Describe reasons for significant changes in transmittal letter.

3. Resubmit returned submittals within 14 days after receiving the comments, unless otherwise directed.

4. Requirements for initial submittals apply to resubmittals.

F. Each submittal shall be submitted under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned to the Contractor for resubmittal.

1.06 REVIEW OF SUBMITTALS

A. Time Required:

1. Submittal review will require 28 days for review of each submittal or resubmittal, unless otherwise specified.

2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.

B. Time in Excess of Specified:

1. The CO may extend the contract completion date to allow additional time for completing work affected by excess review time.

a. The time extension will be to the extent that excess review time caused delay to the contract completion date.

b. The time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.

c. Concurrent days of excess review time resulting from review of two or more separate submittals or resubmittals will be counted only once in extending the contract completion date.

2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.

3. Adjustment for delay will be made only to the extent that:

a. Approval was required under the contract, and

b. Requests for approval were properly and timely submitted and were approved.

Revised 01 33 00 - 5

4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a "suspension order" as the term is used in that clause.

C. Submittal Response:

1. A response letter from the COR for each submittal will be sent to the Contractor indicating if the submittal is either approved, not approved, acceptable, not acceptable, or acknowledged receipt.

a. Revise and resubmit submittals not approved.

b. Do not change designs without approval of the COR after drawings, documentation, and technical data have been approved.

1.07 TRANSMITTAL

A. Addresses for codes listed in Table 01 33 00A - List of Submittals:

1. Where the recipient is the Contracting Officer, address the transmittal letter to Bureau of Reclamation, Attention: GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.

2. Where the recipient is the Contracting Officer’s Representative, address the transmittal letter to Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address is 2021 4th Avenue North, Billings, MT 59101.

a. In addition to the paper copy submissions mailed to the above referenced address, electronic .pdf submittals 10MB or less shall be emailed to the following address: sha-GPR-CONSTSVCS@usbr.gov.

b. Electronic .pdf submittals 10MB or larger shall be submitted to Reclamation via CD or DVD along with the paper copy.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Revised 01 33 00 - 6

Table 01 33 00A. - List of Submittals **CO indicates Contracting Officer and COR indicates Contracting Officer’s Representative

RSN

Clause or

Section Title

Submittals Required Due Date or Delivery Time

Respon-sible Code

No. of sets to be sent: **

CO COR

1 Bonds

FAR 52.228-15

Performance and Payment Bonds

Within 10 calendar days after award

CO 1 paper 0

2 Additional Bond Security 52.228-

Evidence of Increase in Bond Security

Within 10 calendar days after modifications increasing contract value

CO 1 paper 0

3 Insurance-work on a Government Installation 1452.228-70

1) Written certification that the required insurance has been obtained

2) Current certification of insurance for each subcontractor

Before commencing onsite work

CO 1 paper

1 paper

4 Liability Insurance 1452.228-70

Acceptable Certificate of Liability Insurance

Prior to commencement of work under the contract

CO 1 paper 0

5 Equal Opportunity

FAR 52.222-26

Information Required By Executive Order 112246

(SF-100)

Within 30 days following award

CO 1 paper 0

6 Reporting Executive Compensation and First Tier Subcontract Awards

FAR 52.204-10

Certification That Executive Compensation and Subcontract Awards Were Reported

Within 10days of each report being submitted

CO 1 paper 0

7 Release of Claims 1452.204-70

Release of Claims (DI-

137) Against the Government

After completion of the work and prior to final payment

CO 1 paper 0

8 Labor Standards Data 52.222-11

1) List of Subcontractors

2) Statement and Acknowledgement Form (SF-1413) for Each Subcontract

Within 14 days after preconstruction meeting

COR 1 paper

1 paper

1 paper + 1 electronic

1 paper + 1

9 Payrolls and Basic Records 52.222-08

Copies of All Certified Payrolls

Weekly for each week of contract performance

CO 1 paper 2 paper

10 Site Security

WBR 1452.237-

List of All Contractor and Subcontractor Employees

At least 10 days prior to arriving at worksite

COR 0 2 paper

11 Site Security

WBR 1452.237-

List of All Vehicles and Equipment to Be Brought Onsite

At least 10 days prior to arriving at worksite

COR 0 2 paper

Revised 01 33 00 - 7

RSN

Clause or

Section Title

Submittals Required Due Date or Delivery Time

Respon-sible Code

No. of sets to be sent: **

CO COR

12 Schedules for Construction Contracts 52.236-15

Practicable Schedule Within 5 days after work commences on the contract or another period of time as determined by the Contracting Officer

COR 1 paper 1 paper + 1 electronic

13 Schedules for Construction Contracts 52.236-15

Updated Schedule Showing Actual Progress

Monthly or as directed by the Contracting Officer

COR 1 paper 1 paper + 1 electronic

01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan

At least 21 days before use of Government land

COR 0 1 paper + 1 electronic

01 14 30 -1 Interruption of Service

Interruption of Service Requests

At least 28 days before scheduled outage

COR 0 1 paper + 1 electronic

01 35 10-1 Safety Data Sheets

Complete LHM and SDS At least 14 days before jobsite delivery of hazardous material

COR 0 1 paper + 1 electronic

01 35 10-2 Safety Data Sheets

Updated LHM and SDS At least 14 days before jobsite delivery of hazardous material not previously listed

COR 0 1 paper + 1 electronic

01 35 20-1 Safety and Health

Safety Program Submitted and accepted before commencing onsite work. See section 3 of RSHS

COR 0 1 paper + 1 electronic

01 35 20-2 Safety and Health

Monthly Accident Summary Report

First day of each month.

See paragraph 3.8 of

RSHS

COR 0 1 paper + 1 electronic

01 35 20-3 Safety and Health

Respirator User Documentation

At least 28 days before beginning onsite work

COR 0 2 paper

01 35 20-4 Safety and Health

Other Training Certificates

At least 28 days before beginning onsite work

COR 0 2 paper

01 35 30-1 Contractor’s Onsite Safety Personnel

Qualifications At least 28 days before beginning onsite work

COR 0 2 paper

01 35 30-2 Contractor’s Onsite Safety Personnel

CIH Inspection Reports Monthly COR 0 1 paper + 1 electronic

01 35 30-3 Contractor’s Onsite Safety Personnel

Safety Inspection Reports Submit written report to COR monthly

COR 0 1 paper + 1 electronic

01 54 20-1 Use of Government Crane

Crane Use Schedule Weekly COR 0 1 paper + 1 electronic

01 56 10-1 Protection of Existing Installations

Plan for Protecting Existing Installations

At least 28 days before beginning onsite work

COR 0 1 paper + 1

Revised 01 33 00 - 8

RSN

Clause or

Section Title

Submittals Required Due Date or Delivery Time

Respon-sible Code

No. of sets to be sent: **

CO COR

01 57 30-1 Water Pollution Control

Spill Prevention Control and Countermeasure (SPCC) Plan

At least 28 days before delivery or storage of oil.

COR 0 1 paper + 1 electronic

01 74 00-1 Cleaning and Waste Management

Waste Production and Disposal Plan

At least 28 days before beginning onsite work

COR 0 1 paper + 1 electronic

01 74 00-2 Cleaning and Waste Management

Waste Production and Disposal Records

Within 7 days of waste disposal

COR 0 1 paper + 1 electronic

01 74 00-3 Cleaning and Waste Management

Environmental Consultant Resume

At least 28 days before beginning environmental assessment

COR 0 2 paper

01 74 00-4 Cleaning and Waste Management

Environmental Site Assessment

Within 14 days of completion of work

COR 0 1 paper + 1 electronic

02 83 33-1 Removal and Disposal of Equipment Containing Hazardous Materials

Qualifications At least 28 days before beginning onsite work

COR 0 2 paper

02 83 33-2 Removal and Disposal of Equipment Containing Hazardous Materials

Written Compliance Program for Worker Protection

At least 28 days before beginning onsite work

COR 0 1 paper + 1 electronic

02 83 33-3 Removal and Disposal of Equipment Containing Hazardous Materials

Plans At least 28 days before beginning onsite work

COR 0 1 paper + 1 electronic

02 83 33-4 Removal and Disposal of Equipment Containing Hazardous Materials

Certificate of Disposal or Recycling Documentation

Within 14 days aftr disposal

COR 0 1 paper + 1 electronic

22 10 00-1 Piping and Valves

Approval Data At least 28 days prior to air cooler fabrication

COR 0 1 paper + 1 electronic

22 11 85-1 Generator Air Coolers

Approval Drawings and Data

At least 28 days prior to fabrication

COR 0 1 paper + 1 electronic

22 11 85-2 Generator Air Coolers

Final Drawings and Data Within 14 days of installation

COR 0 1 paper + 1 electronic

22 11 85-3 Generator Air Coolers

Test Reports Within 7 days performing test

COR 0 1 paper + 1

Piping and Valves

Revised 22 10 00 - 1

SECTION 22 10 00

PIPING AND VALVES

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

A. Provide Replacement Generator Air Cooler Piping, Valves and Instruments.

1. Payment: Lump sum price offered in the Price Schedule.

1.02 REFERENCE STANDARDS

A. American Society of Mechanical Engineers (ASME)

1. ASME B16.5-13 Pipe Flanges and Flanged Fittings

2. ASME B16.11-11 Forged Fittings, Socket-Welding and Threaded

3. ASME B16.21-11 Nonmetallic Flat Gaskets for Pipe Flanges

B. ASTM International (ASTM)

1. ASTM A53/A53M-12 Pipe, Steel, Black and Hot-Dipped, Zinc- Coated Welded and Seamless

2. ASTM A106/A106M-15 Seamless Carbon Steel Pipe for High- Temperature Service

3. ASTM A307-14 Carbon Steel Bolts, Studs, and Threaded Rod

4. ASTM A563-15 Carbon and Alloy Steel Nuts

C. Manufacturers Standardization Society of the Valve and Fitting Industry (MSS)

1. MSS SP-58-09 Pipe Hangers and Supports

2. MSS SP-80-13 Bronze Gate, Globe, Angle and Check Valves

1.03 SYSTEM DESCRIPTION

A. Verify existing materials and dimensions onsite prior to furnishing new materials.

B. General Requirements:

1. Remove and dispose of existing 2-inch air cooler cooling water supply and discharge piping and valves.

Revised 22 10 00 - 2

2. Provide:

a. Replacement 2 inch diameter piping, fittings and appurtenances for each generator air cooler supply and discharge piping.

b. Replacement cooling water shut-off (gate) valves.

c. Replacement cooling water discharge throttling (globe) valves.

d. New flow measurement instrumentation on each air cooler branch to visually indicate rate of flow in gallons per minute through coolers for the purposes of balancing.

C. Materials shall be newly manufactured and sized to match existing connections to the cooling water header piping and to the new air coolers.

1.04 SUBMITTALS

A. Submit the following in accordance with Section 01 33 00 - Submittals.

B. RSN 22 10 00-1, Approval Data:

1. Manufacturer’s technical data and installation instructions for furnished materials.

PART 2 PRODUCTS

2.01 PIPING, FITTINGS AND APPURTENANCES

A. Piping:

1. Pipe: ASTM A53, Type E or S or ASTM A106, carbon steel.

2. Fittings: Carbon steel, schedule 40.

3. Flanges:

a. Carbon steel, welding neck type, faced and drilled in accordance with

ASME B16.5.

b. Carbon steel, slip-on, faced and drilled in accordance with ASME B16.5.

4. Pipe Hangers and Supports: In accordance with MSS SP-58.

B. Flow Measurement Instrumentation:

1. Variable Area/Direct Reading Flowmeter.

a. Maximum Flow Capacity: 85 gpm of clean water.

b. Direct Reading in GPM.

c. Industrial Grade Construction. Plastic materials not allowed.

d. Self-contained and complete. No external power required.

Revised 22 10 00 - 3

C. Gaskets: non-asbestos, aramid fiber with NBR binder gaskets or equal in accordance with ASME B16.21. Furnish ring gaskets for raised face flanges and full face gaskets for flat face flanges.

D. Insulating gasket set for dissimilar metal flanges: Sets shall include insulating bolt sleeves, washers, and gaskets to prevent galvanic corrosion of mating component.

E. Dielectric pipe unions: Nylon insulator with insulating gasket to prevent galvanic corrosion of mating components.

F. Bolting: Carbon steel machine bolts in accordance with ASTM A307, Grade B and hex nuts in accordance with ASTM A563.

2.02 VALVES

A. Gate Valves: Bronze body, in accordance with MSS SP-80.

B. Globe Valves:

1. Furnish valves that have, in the maximum open position, an effective area of not less than one-half the area of the pipe line.

2. Bronze construction, outside screw and yoke, bolted bonnet, bronze mounted, renewable seat and disc, in accordance with MSS SP-80.

PART 3 EXECUTION

3.01 GENERAL

A. Coordinate delivery of materials with COR.

B. Interior and ends of new piping shall be kept thoroughly cleaned of dirt and foreign matter during shipping and delivery.

C. Provide insulating type union or flanged joints at connections between dissimilar metals, valves and piping accessories.

Revised 22 10 00 - 4

This page intentionally left blank.

Generator Air Coolers Revised 22 11 85 - 1

SECTION 22 11 85

GENERATOR AIR COOLERS

PART 1 GENERAL

1.01 MEASUREMENT AND PAYMENT

Remove and Dispose of Existing G1 Air Coolers:

1. Measurement: Cost of Air Coolers.

2. Payment: Unit price offered in the Price Schedule.

Remove and Dispose of Existing G2 Air Coolers:

1. Measurement: Cost of Air Coolers.

2. Payment: Unit price offered in the Price Schedule.

Remove and Dispose of Existing Spare Air Coolers:

1. Payment: Unit price offered in the Price Schedule.

Design, Furnish, and Factory Test Generators G1 and G2, and Spare Air Coolers:

1. Measurement: Cost of Air Coolers.

2. Payment: Unit price offered in the Price Schedule.

Install and Performance Test G1 Air Coolers:

1. Payment: Unit price offered in the Price Schedule.

Install and Performance Test G2 Air Coolers:

1. Payment: Unit price offered in the Price Schedule.

1.02 REFERENCE STANDARDS

American Society of Mechanical Engineers (ASME)

1. ASME BPVC VIII-15 Boiler and Pressure Vessel Code - Section VIII, Division I - Rules for the Construction of Pressure Vessels

2. ASME BPVC IX-15 Boiler and Pressure Vessel Code - Section IX - Welding and Brazing Qualifications

ASTM International (ASTM)

1. ASTM B111/B111M-11 Copper and Copper-Alloy Seamless Condenser Tubes and Ferrule Stock

Revised 22 11 85 - 2

2. ASTM B171/B171M-12 Copper-Alloy Plate and Sheet for Pressure Vessels, Condensers, and Heat Exchangers

3. ASTM A240/A240M-15b Chromium and Chromium-Nickel Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for General Applications

4. ASTM A653/A653M-15 Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process

5. ASTM A924/A924M-14 General Requirements for Steel Sheet, Metallic-Coated by the Hot-Dip Process

Tubular Exchanger Manufacturer’s Association

1. TEMA-07 Standards for the Tubular Exchanger Manufacturer’s Association, 9th Ed

1.03 SUBMITTALS

Submit the following in accordance with Section 01 33 00 - Submittals.

RSN 22 11 85-1, Approval Drawings and Data:

1. Drawings and data:

a. Field verified dimensions.

b. Thermal design calculations stamped by a Professional Engineer experienced in design of air coolers.

c. Overall, detailed, and sectional air cooler drawings showing the following:

1) Overall cooler dimensions.

2) Water supply and discharge connection details.

3) Cooler vent and drain details.

4) Frame mounting dimensions and connection details.

5) Nameplate data.

6) Direction of air and water flow.

7) Parts and material lists.

8) Fastener tightening torques for headers, cover plates and flanges.

9) Cooler weight empty and filled.

10) Method of fin-tube or plate-fin attachment.

2. Test Plan and Schedule:

a. Detailed description of factory hydrostatic test method and planned dates of testing.

Revised 22 11 85 - 3

RSN 22 11 85-2, Final Drawings and Data:

1. Bound service manual including:

a. Previously approved drawings and data submitted under RSN 22 11 85-1 including half-size (11 inch by 17 inch) prints of air cooler drawings.

b. Manufacturer installation, operation, and maintenance manual.

c. Recommended list of spare parts.

RSN 22 11 85-3, Test Reports:

1. Certified hydrostatic test reports.

2. Certified service test reports.

1.04 SYSTEM DESCRIPTION

General Requirements:

1. Remove and dispose of existing Westinghouse fin-tube air coolers for generators G1 and G2 at Flatiron Powerplant.

a. Existing air coolers are assumed to have lead-based coatings.

2. Design, furnish, factory test, and install new generator air coolers for generators G1 and G2 in accordance with this section.

a. Each air cooler unit shall be identical in design and shall be interchangeable with other coolers.

b. Design each air cooler to fit into the existing space currently occupied by the existing air coolers and shall match vent and water piping connections of the existing air coolers without modification to existing equipment.

c. Each air cooler shall have a rigid frame, be self-contained and designed for handling as a complete assembly. Lifting lugs for handling and installation are required.

d. Air cooler frames shall be used for lifting and mounting, and designed to attach within the generator air housing to the existing outside periphery of the stator frame.

e. Air cooler design shall be heavy-duty, industrial type suitable for continuous or cyclic duty operation.

f. Air coolers shall be free draining.

3. Field verify existing air cooler dimensions, connections, and mounting details from existing equipment at the jobsite prior to design and manufacture of new air coolers.

a. The spare air coolers will be available for inspection at the Eastern Colorado Area Office warehouse facility located at 910 Van Buren

Revised 22 11 85 - 4

Avenue, Loveland, Colorado. Refer to Section 00 00 30 - Foreword for Site visit details.

Performance Requirements:

1. Generator air coolers shall have sufficient cooling capacity to maintain the temperature of the air entering the generator air housing at 40 degrees C or less under the following conditions:

a. Generator delivering 100 percent rated output of 47.8-MVA.

1) The Government estimates maximum heat loads of approximately 2-percent of the generator nameplate rating.

b. Maximum cooling water supply temperature of 25 degrees C.

c. Cooling water flow rate of 300 gpm for each generator.

1) Cooling water flow rates may vary up to a maximum of 500 gpm;

however, design of new air coolers should minimize flow of cooling water to the greatest extent possible.

d. With 6 air coolers in service per generator.

Existing System General Description:

1. Each of the generator units G1 and G2 have 6 finned tube air-to-water air coolers mounted at equal intervals within the generator air housing on the outside periphery of the stator frame. The following are the approximate dimensions measured from the spare cooler:

a. The exterior dimensions of the air coolers are 66-3/4 inches by 44-3/4 inches by 18-1/4 inches deep. Each air housing opening for the air coolers is 46-1/8 inches by 32-3/8 inches.

b. The tubes are 1.0 inch outside diameter.

c. There are 6 fins per inch. The fins are 1.75 inch diameter.

d. There are approximately 3 rows of 16 tubes and 3 rows of 15 tubes, for a total of 93 tubes.

2. Cooling water from the raw water supply is fed to the air coolers. The environmental air of the generator is passed through the air coolers and is then recirculated. Air is circulated through the air coolers by the generator rotor.

3. Air temperature is controlled by the rate of raw water flow through the air coolers, each air cooler of which is fitted with a throttling valve to equalize the flow through coolers within the generator. Exit air temperature is measured by a bulb type thermometer, one at each air cooler. The air entering the generator is cooled to less than 40 degrees C by the 6 air coolers.

4. The elevation of the air coolers at Flatiron Powerplant is 5471.00 feet.

5. The approximate weight of each empty air cooler is 820 lbs.

Revised 22 11 85 - 5

1.05 QUALIFICATIONS

Designer:

1. Professional Engineer experienced in design of this type.

2. This specialist shall be authorized and certified by the manufacturer of the equipment being furnished to determine the requirements of air cooling equipment.

Manufacturer: Company specializing in manufacturing products specified in this Section with minimum 3 years documented experience.

Welding procedures, welders, and welding operators: Conform to Section IX of ASME

BPVC.

1.06 DELIVERY, STORAGE, AND HANDLING

Schedule delivery of new air coolers with the COR.

1. Deliver air coolers on an open flatbed vehicle.

2. Ship to site in accordance with Section 01 14 10 - Use of Site.

Do not ship air coolers to site until an interruption of service has been approved by COR in accordance with Section 01 14 30 - Interruption of Service.

The Government will unload and store the generator air coolers from the delivery vehicle.

Package each air cooler in such a manner as to protect from damage.

Protect piping from entry of foreign materials.

Box each air cooler complete with lifting devices to facilitate handling, and rain shielded or plastic-wrapped for outdoor storage. Clearly mark or attach instructions for handling or lifting to each box.

PART 2 PRODUCTS

2.01 GENERAL REQUIREMENTS

Quantity:

1. 6 air coolers for each generator, total of 12. These air coolers are currently in use and located at Flatiron Powerplant.

2. 2 spare air coolers. The spare coolers are located at the ECAO Warehouse.

Coolers shall comply with TEMA Class "C" for design, fabrication and testing.

Revised 22 11 85 - 6

Coolers shall be designed, built and certified to ASME BPVC VIII and stamped with an ASTM Code "U" stamp.

Design coolers to allow for thermal expansion and contraction.

Coolers shall have lifting eyes for installation and removal.

Generator air coolers shall have a maximum allowable working pressure of 100-pounds per square inch.

Pressure loss through each air cooler shall not exceed 5-pounds per square inch at maximum cooling water flow rate.

2.02 WATER BOXES

Water boxes shall be of brass or stainless steel construction.

Construct with removable covers to permit access to tubes for cleaning and inspection purposes without disturbing water pipe connections.

Boxed-type construction with one to be of a floating head design to accommodate thermal expansion of tubes.

Water inlet and outlet connections shall match existing connection type and diameter.

Vent and drain locations shall match existing air cooler vent and drain locations.

Brass or stainless steel plugs shall be provided for drain and vent taps.

2.03 PLATE-FIN, EXTRUDED FIN-TUBE AND TUBES

Aluminum fin construction.

1. Plate-fin: Minimum thickness 0.010 inches.

2. Extruded fin-tube: Minimum thickness 0.015 inches.

Maximum 11 fins per inch.

Tubes shall be of seamless 90/10 copper-nickel with a minimum 0.049 inch wall thickness in accordance with ASTM B111.

Water velocity in tubes shall not exceed 5 feet per second at full flow.

Tubes shall have straight ends. Belled ends are not allowed.

Support tubes to prevent sagging and vibration at the generator natural frequency or its harmonics. Rotational speed of each generator unit is 163.6 rotations per minute.

Revised 22 11 85 - 7

2.04 TUBE SHEETS

Tube Sheets: 90/10 copper-nickel in accordance with ASTM Bl71.

2.05 FRAMES

Cooler frames shall be manufactured from heavy gauge galvanized steel in accordance with ASTM A924 and ASTM A653 or stainless steel in accordance with ASTM A240 type 304L or 316L.

2.06 GASKETS

Gaskets: Non-asbestos rubber gaskets.

2.07 FELT

Part No. 8762K891, distributed by McMaster-Carr, P.O. Box 5370, Princeton, NJ 08543, 609-259-3575; or equal, having the following essential characteristics:

1. Adhesive backed.

2. Minimum 70 percent wool content.

3. 2 inches wide, 0.25 inches thick, minimum 10 foot roll length.

4. Minimum density of 10 pounds per square yard.

2.08 COATINGS

Coat equipment in accordance with manufacturer’s standard coating system.

PART 3 EXECUTION

3.01 PREPARATION

Field verify existing G1 and G2 air cooler dimensions, frame mounting, piping connections, and other measurements required to design and manufacture new air coolers. Submit field verified data.

Coordinate scheduling the removal, installation, and performance testing of the new air coolers with the COR.

Request generator interruptions of service in accordance with Section 01 14 30 - Interruption of Service.

The Government will operate Government owned crane equipment to remove and install the air coolers from the generator air housing.

Revised 22 11 85 - 8

3.02 REMOVAL AND DISPOSAL

Remove:

1. 6 air coolers for each generator, total of 12 air coolers.

2. 2 spare air coolers.

Remove and store existing air cooler instrumentation for future use as directed by COR.

Disconnect water supply and discharge piping, as well as, vent and drainage piping to each cooler.

Dispose of materials in accordance with 01 74 00 - Cleaning and Waste Management and Section 02 83 33 - Removal and Disposal of Equipment Containing Hazardous Materials.

3.03 INSTALLATION

Do not ship the new air coolers to the site until a confirmed outage has been scheduled in accordance with Section 01 14 30 - Interruption of Service.

Inspect equipment, piping, and support frames before placing into position.

Clean and remove dirt, debris and loose items in the air cooler area before installation.

Install 12 new air coolers as recommended by the equipment manufacturer.

Connect equipment to piping system and install instrumentation and safety devices after installation.

3.04 CONTRACTOR FIELD QUALITY TESTING

Coordinate with the COR to schedule onsite performance testing of the new air coolers for each generator.

Perform onsite tests after air cooler installation is complete and full water flow through the coolers shows no indication of leakage.

Witness and document onsite air cooler performance tests with the following information:

1. Flow rate of water through each cooler.

2. Water temperature at inlet and outlet of each cooler.

3. Average air temperature at inlet and outlet of each cooler.

4. Calculate the heat transfer rate and compare to the design requirements.

Drawings

Revised 52 00 00 - 1

SECTION 52 00 00

DRAWINGS

PART 1 GENERAL

1.01 DISCREPANCIES, ERRORS, OR OMISSIONS

A. Inform the COR of discrepancies discovered on drawings in accordance with clause at FAR 52.236-21, Specifications and Drawings for Construction.

B. In accordance with clause at FAR 52.236-21, Specifications and Drawings for Construction, in case of discrepancies, written specifications take precedence over drawings unless otherwise specified.

1.02 PROJECT CONDITIONS

A. Where there are minor differences as determined by the COR between details and dimensions shown on drawings and details and dimensions of existing features at jobsite, use details and dimensions of existing features at jobsite.

1.03 INFORMATION DRAWINGS

A. Drawings marked "For Information Only" in the drawing list are included to show existing features about which knowledge is required to perform work under this contract.

These drawings do not show work to be performed under this contract.

B. If there are differences as determined by the COR between details and dimensions shown on these drawings and those of existing features at jobsite, use details and dimensions of existing features at jobsite.

1.04 LIST OF DRAWINGS

A. Drawings listed in Table 52 00 00A - List of Drawings, are made a part of Section C - Description/Specifications.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Colorado - Big Thompson Project Amendment #003

Drawings Revised 52 00 00 - 2

Table 52 00 00A - List of Drawings

Sheet No.

Drawing No. Title

General:

1 245-704-4938 Location Map For Information Only

2 245-M-704-200-12 Westinghouse Electric Corporation 840sqft. Air Cooler, Outline, Westinghouse Drawing No. 37-F-261

3 35-A-1987 Westinghouse Electric Corporation Vert. W.W. Gen. FR# 14

- General Assembly

4 35-A-2150 Westinghouse Electric Corporation Vert. W.W. Gen. FR# 14

- Outline

5 245-704-6274 Schematic Piping Diagram Unit Cooling Water System 6 245-D-5948 Flatiron Power and Pumping Plant, General Arrangement, Transverse Section through Centerline of Unit "1" and Pressure Regulator "1"

7 245-D-5952 Flatiron Power and Pumping Plant, General Arrangement, Plan - Generator and Motor Floor El. 5471.00, Drawing No.

8 245-M-704-200-22 Vertical W. W. Generator, Piping Diagram, Westinghouse Drawing No. 35-A-7962

9 40-D-7102 Drawing Boarder, Sample Title Block and Signature Lines

Flatiron Generators G1 and G2 Air Coolers 07/07/17 Solicitation: R17PS00256

Prospective Contractor Questions Flatiron Generators G1 and G2 Air Coolers

Solicitation: R17PS00256

1) What are the model numbers and serial numbers?

The existing coolers were made custom for this location, as such the model numbers and serial numbers would be of little use. Refer to the drawings for the available air cooler manufacturing information.

2) Do you have capacity / specification of the existing coolers?

The contractor should refer to Specification Section 221185, Paragraph 1.04.B.1.a.1, Performance Requirements.

3) Is there a connection diagram?

The contractor should refer to the cooler outline drawing, 245-M-704-200-12; Schematic Piping Diagram, 245-704-6274; and the Piping Diagram, 33-A-7962, as issued in the Solicitation.

4) The Solicitation indicates that there is a spare cooler unit. Where is it located? Can it be inspected, and what arrangements need to be made to look it over?

The spare cooler unit is located at 910 North Van Buren Avenue, Loveland, CO. It is available for inspection. Please contact Mr. Larry Ketcham at (970) 962-4502, or lketcham@usbr.gov to make arrangements.

mailto:lketcham@usbr.gov

Generators G1 and G2 Air Coolers, Colorado – Big Thompson Project

THIS PAGE INTENTIONALLY LEFT BLANK