U.S. Department of the Interior Bureau of Reclamation July 2016
Request For Proposals (RFP) Solicitation No. R16PS01264
Asbestos Abatement Flatiron Power and Pumping Plant Colorado-Big Thompson Project, Colorado
This Page Intentionally Left Blank
ASBESTOS ABATEMENT
FLATIRON POWER AND PUMPING PLANT
FOREWORD
Work is located at Flatiron Power and Pumping Plant, approximately 8 miles southwest of Loveland, CO in Larimer County.
Principal components of work include removing electrical cable tray liners composed of Asbestos Containing Material (ACM), replacing the electrical cable tray liners, removing asbestos contamination from within the hydroelectric cable tunnel, removing asbestos tape wrap/insulation on water cooling pipe within the Unit 1 and Unit 3 air housing for the hydroelectric generators and replacing with new tape/wrap insulation.
EMAIL INQUIRIES REGARDING THIS SOLICITATION SHOULD BE MADE TO:
Contractual Matters: Contracts Specialist Attention: Michael Birkland Billings, Montana Email: mbirkland@usbr.gov
PRE-PROPOSAL SITE VISIT: An organized site visit will be held on Tuesday August 2, 2016 at 8:00 a.m. at the Eastern Colorado Area Office at 11056 W. County Road 18E, Loveland Colorado. If you have questions about the site visit contact John Foreman at 970-962-4527.
Attendees are to provide and wear safety boots, hard hats, and safety vests. Prospective offerors are strongly encouraged to attend the walk-thru and visit the site to gain first-hand knowledge of the work requirements and site conditions. Failure of the prospective offerors to inspect the site will not relieve the offerors from the responsibility to properly estimate the difficulty or cost of the project and successfully perform the work in accordance with the requirements of the contract.
PROPOSAL DUE DATE AND TIME: For date and place proposals are due, see “SOLICITATION, OFFER, AND AWARD,” Standard Form 1442, immediately following the Table of Contents.
ORAL INFORMATION: In accordance to provision 52.214-06 of the Federal Acquisition Regulation, oral explanations, information, or instruction given before the award of the contract will not be binding.
SAFETY AND HEALTH MANUAL: for information regarding bureau of reclamation's publication "reclamation safety and health standards" (RSHS) November 2009 Edition, which is applicable to work under this contract, see clause WBR 1452.223-81 (Safety and Health) of the solicitation. The electronic version of the publication can be found at:
http://www.usbr.gov/safety/RSHS/rshs.html mailto:mbirkland@usbr.gov http://www.usbr.gov/safety/RSHS/rshs.html
SAM: Effective July 29, 2012, any contractor interested in doing business with the federal government must register in the System for Award Management (SAM) database prior to award of a contract or agreement. SAM is a federal government owned and operated free website, which consolidates the central contractor registration (CCR), the online representations and certifications application (ORCA), and the excluded parties list system
(EPLS).
DUNS: The vendor's DUN & Bradstreet number and banking information are required for registration. Contractors may obtain information on registration and annual confirmation requirements via the SAM website accessed through https://www.sam.gov/portal/public/sam/ or by the federal service desk at 1-866-606-8220.
IPP: Payment requests for the anticipated purchase order must be submitted electronically through the U.S. Department of the Treasury’s Internet Payment Platform system (IPP).
The IPP website address is: https://www.ipp.gov. The contractor must use the IPP website to register access and use IPP for submitting requests for payment. Contractor assistance with enrollment can be obtained by contacting the ipp production helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131. If the contractor is unable to comply with the requirement to use ipp for submitting invoices for payment, the contractor must submit a waiver request in writing to the contracting officer with its proposal or quotation.
https://www.sam.gov/PORTAL/PUBLIC/SAM/ https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
Colorado-Big Thompson Project, Colorado Solicitation No. R16PS01264
Table of Contents - 1
TABLE OF CONTENTS
PART 1 – THE SCHEDULE
SECTION A – Solicitation, Offer, and Award Form (SF 1442)
SECTION B – Supplies or Services and Prices
SECTION C – Specification/Drawings/Maps
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions 01 33 00 Submittals 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 51 00 Temporary Utilities 01 55 00 Vehicular Access and Parking 01 56 10 Protection of Existing Installations 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 60 00 Product Requirements 01 74 00 Cleaning and Waste Management
DIVISION 02 - EXISTING CONDITIONS
02 82 20 Removal and Disposal of Asbestos Containing Materials
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
06 52 10 Cable Tray Liner Replacement
DIVISION 22 – PLUMBING
22 07 19 Plumbing Piping Insulation
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 00 10 Flatiron Unit 3 Air Housing Asbestos Report 51 00 20 Asbestos Sampling at Flatiron Powerplant Report
Colorado-Big Thompson Project, Colorado Solicitation No. R16PS01264
Table of Contents - 2
51 00 30 Flatiron Unit 3 Air Housing Second Asbestos Report 51 00 40 Flatiron Unit 3 Air Housing Third Asbestos Report 51 00 50 Flatiron Units 1 and 2 Air Housing Asbestos Report 51 00 60 Flatiron Units 1 and 2 Air Housing Asbestos Sampling Report 51 00 70 Travel Report 51 00 80 Photographs
DIVISION 52 - DRAWINGS
52 00 00 Drawings
SECTION D – Not Used
SECTION E – Inspection and Acceptance E.1 Material and Workmanship E.2 Inspection of Construction E.3 Warranty of Construction
SECTION F – Deliveries or Performance F.1 Commencement, Prosecution, and Completion of Work F.2 Variation in Estimated Quantity F.3 Suspension of Work
SECTION G – Contract Administration Data G.1 Authorities and Delegations G.2 Electronic Invoicing and Payment Requirements
SECTION H – Special Contract Requirements
H.1 Site Security
PART II – CONTRACT CLAUSES
SECTION I – Contract Clauses I.1 Clauses By Reference I.2 Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements
I.3 Commercial and Government Entity Code Maintenance I.4 Order of Precedence – Sealed Bidding I.5 Minimum Wages Under Executive Order 13658
I.6 Buy American Act – Construction Materials I.7 Bid Guarantee I.8 Additional Bonding I.9 Performance and Payment Bonds - Construction I.10 Payments Under Fixed-Price Construction Contracts I.11 Prompt Payment for Construction Contracts
Table of Contents - 3
I.12 Differing Site Conditions I.13 Accident Prevention I.14 Schedules for Construction Contracts I.15 Changes I.16 Restriction on Endorsements I.17 Release of Claims I.18 Examination of Records By the Department of Interior I.19 Liability Insurance I.20 Asbestos – Free Warranty I.21 Safety and Health I.22 Protecting Federal Employees and the Public From Exposure to Tobacco Smoke I.23 Certification of Representations I.24 Equipment Ownership I.25 Payment for Mobilization and Preparatory Work I.26 Other Contracts
I.27 Preservation of Cultural Resources I.28 Security Requirements
I.29 Modification Proposals
PART III – DOCUMENTS, EXHIBITS, AND OTHER
SECTION J – List of Documents, Exhibits, and Other Attachments Wage Determination Standard Form 24 – Bid Guarantee
Past Jobs Reference List Past Performance Questionnaire
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – Representations, Certifications and Other Statements of Offerors
K.1 Prohibition on Contracting with Entities That Require Certain Internal Confidentiality Agreements
K.2 Annual Representations and Certifications
SECTION L – Instructions, Conditions and Notices to Bidders L.1 System for Award Management L.2 Commercial and Government Entity Code Reporting
L.3 Availability of Specifications Listed in the GSA Index of Federal Specifications L.4 Availability of Specifications, Standards, and Data Item Descriptions L.5 Submission of Offers in the English Language L.6 Submission of Offers in U.S. Currency L.7 Instructions to Offerors L.8 Type of Contract L.9 Construction Wage Rate Requirements
Table of Contents - 4
L.10 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction
L.11 Site Visit (Construction) L.12 Preparation of Proposals L.13 Use and Disclosure of Proposal Information L.14 Service of Protest L.15 Notice of Intent to Acquire Metric Products and Services L.16 Source Evaluation and Selection Procedures L.17 General Proposal Instructions L.18 Technical Proposal Instructions L.19 Pricing Proposal Instructions L.20 Instruction for Mobilization and Preparatory Work L.21 Authorized Workers Notice to Potential
SECTION M – Evaluation Factors for Award M.1 Evaluation Factors for Award
M.2 Notice of World Trade Organization Government Procurement Agreement Evaluations
PART I – THE SCHEDULE
THIS PAGE INTENTIONALY LEFT BLANK
SECTION A
SOLICITATION, OFFER, AND AWARD
(STANDARD FORM 1442)
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
0040254874
Bureau of Reclamation
Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Bureau of Reclamation
2021 4th Ave North Billings MT 59101
Michael Birkland 406-247-7646
1x 07/18/2016
R16PS01264
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Asbestos Abatement, Flatiron Power And Pumping Plant, Colorado-Big Thompson Project, Colorado
The range of this project is $100,000 - $250,000
This is 100% set-aside for small business
The North American Industry Classification System (NAICS)code is 238990
The Small Business Size Standard for NAICS 238990 is $15 Million
Taxpayer Identification Number: (TIN) __________________________________
Data Universal Number System (DUNS) ___________________________________
Commercial and Government Entity Code: ____________________________________
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 0 calendar days and complete it within ________________ ________________ calendar days after receiving
See Paragraph F.1
08/18/2016
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
Bureau of Reclamation Great Plains Region
Regional Office PO Box 36900
R60
Billings MT 59107
Gerri Voto-Braun
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
R16PS01264
00010 Asbestos Abatement, Flatiron Power and Pumping
Plant, Colorado-Big Thompson Project, Colorado
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
1 AU
See Continuation of Section B (Clins 1-10)
SECTION B
THE SCHEDULE
Colorado-Big Thompson Project, Colorado Solicitation No. R16PS01264
Price Schedule B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS
ASBESTOS ABATEMENT
FLATIRON POWER AND PUMPING PLANT
COLORADO-BIG THOMPSON PROJECT, COLORADO
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedule.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(d) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(e) Definitions:
(1) CLIN – Contract Line Item Number
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
1 WBR
1452.232 -81
Mobilization and Preparatory Work
For the lump sum of $
2 02 82 20 Removal and Disposal of Existing Cable Tray Transite Liners
810 lin ft $
3 02 82 20 Cleaning Tunnel Surface Areas
5,062 ft2 $
4 02 82 20 Cleaning HV Power Cables/Bushings
1,782 ft2
Colorado-Big Thompson Project, Colorado Solicitation No. R16PS01264
Price Schedule B - 2
PRICE SCHEDULE
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
5 02 82 20 Cleaning Cable Tray Conduits
1,634 ft2 $
6 02 82 20 Cleaning Electrical Conduits 833 ft2 $
7 02 82 20 Cleaning Cable Tray Frames and Brackets
1,056 ft2 $
8 02 82 20 Removal and Disposal of Existing Water Cooling Pipe Insulation Wrappings
30 lin ft $
9 06 52 10 Furnish and Install Replacement Cable Tray Liner
688 lin ft $
10 22 07 19 Furnish and Install Replacement Pipe Insulation
30 lin ft $
TOTAL FOR PRICE SCHEDULE $_________________
END OF SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION C
THE SPECIFICATIONS
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
SECTION 01 11 00
Summary of Work 01 11 00 - 1
SUMMARY OF WORK
PART 1 GENERAL
1.1 LOCATION
A. Work is at Flatiron Power and Pumping Plant located approximately 8 miles southwest of
Loveland, Colorado, in Larimer County.
1.2 PRINCIPAL COMPONENTS OF WORK
A. Removing existing electrical cable tray liners which contain asbestos containing material
(ACM) from within cable trays located in tunnel.
B. Removing Asbestos Dust Contamination From Within Tunnel:
1. On concrete floor, steps, berms, walls, and ceiling.
2. On wire and cable insulation and conduits.
3. On cable trays, lighting fixtures, drains and vents, supporting brackets, and other surfaces within tunnel.
C. Installing new electrical cable tray liners.
D. Removing existing asbestos tape wrapped insulation on water cooling pipes within air housing for Unit 1 and Unit 3.
E. Installing new pipe insulation on water cooling pipes within air housings.
1.3 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 52.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.4 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations
(FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
Summary of Work 01 11 00 - 2
Asbestos Abatement Flatiron Power and Pumping Plant Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
1.5 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 52:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
1.1 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.2 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Areas for processing, storing, and disposing of waste materials from construction operations.
6) Temporary fences.
b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Use of Site 01 14 10 - 2
1.3 PROJECT CONDITIONS
A. Government land may be used for required construction facilities.
B. Contractor tunnel access and staging areas are limited to the hatched areas shown on photographs included in Section 51 00 80 – Photographs. Access to the work area is based on the following conditions:
1. Preferred Route: To reduce asbestos contamination occurring within the plant area, the preferred route to access the tunnel area is through the switchyard area (will be deenergized).
2. Alternate Route: An alternate route is available to access the tunnel area subject to approval of the COR if site conditions of the preferred route are inadequate.
C. No private land shall be used for required construction facilities.
D. Location, construction, operation, maintenance, and removal of construction facilities on
Government land will be subject to approval of COR.
E. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
F. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.
PART 2 PRODUCTS
PART 3 EXECUTION
3.01 RESTORATION
A. Restore Contractor use areas to pre-construction condition.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Work Restrictions 01 14 12 - 1
SECTION 01 14 12
WORK RESTRICTIONS
1.2 WORK RESTRICTIONS
A. Bureau of Reclamation operates and maintains the Flatiron Power and Pumping Plant.
B. Maintain Bureau of Reclamation access to the Flatiron Power and Pumping Plant and other facilities at all times.
C. Allowable Work Hours:
1. Monday through Sunday: 6:30 am to 6:00 pm.
2. Work outside of allowable work hours shall be coordinated with COR.
D. Access to work area will be through the switchyard area.
E. Contractor will not be allowed unescorted access to the power plant tunnel. Government will provide Contractor escorted access through to the power plant tunnel work site area during allowable work hours.
F. Photographs of the power and pumping plant and within the power plant tunnel are not allowed.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Work Restrictions 01 14 12 - 2
This page intentionally left blank.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Submittals 01 33 00 - 1
SECTION 01 33 00
SUBMITTALS
1.2 REFERENCE STANDARDS
A. American Society of Mechanical Engineers (ASME)
1. ASME Y14.1-12 Decimal Inch Drawing Sheet Size and Format
B. National Institute of Building Sciences (NIBS)
1. NIBS NCS-14 United States National CAD Standards, Version 6
1.3 DEFINITIONS
A. Days: Calendar days.
B. Required Submittal Number (RSN): Identifies items to be submitted together as a complete submittal.
1.4 SUBMITTAL REQUIREMENTS
A. In case of conflict between requirements of this section and requirements included elsewhere in these specifications, requirements included elsewhere take precedence.
B. General:
1. Prepare in English.
2. Label with contract number and title, and RSN.
3. Measurement units: US Customary Units.
C. Drawings:
1. Minimum Identification in Title Block:
a. Contract number and title.
b. Contractor’s or supplier’s title and drawing number.
c. Date.
2. Reserve 3- by 3-inch space next to title block for review stamps.
01 33 00 - 2
Asbestos Abatement
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
3. Print Size: D size (22 inches by 34 inches).
4. Draw to scale using computer drafting or drafting equipment, unless otherwise specified.
a. Computer drafted drawings:
1) In accordance with NIBS NCS.
2) Electronic file format: Compatible with AUTOCAD, Version 2007 or later.
3) Compile using “eTransmit” utility in AUTOCAD.
b. Drawing prepared with drafting equipment, when allowed: Lettering shall be neat.
5. Drawings Designated as “Government Format” in Specifications:
a. Computer drafted.
b. Government will provide electronic AutoCAD format template.
c. Title block and sheet format:
1) As shown on standard drawing 40-D-7102.
2) Government will supply template.
3) Government will supply specific title block information to be used.
6. Final Drawings:
a. Computer drafted.
b. Government will supply electronic AutoCAD format template.
c. Show as-built changes, including revision dates, made during installation.
Indicate changes by clouding.
d. Electronic files: On CD or DVD discs.
D. Product Data:
1. Mark manufacturer's data for commercial products or equipment, such as catalog cut sheets.
a. Identify manufacturer's name, type, model, size, and characteristics.
b. Illustrate that product or equipment meets requirements of specifications.
c. Mark items to be furnished in a manner that will photocopy (no highlighter).
d. Strike through items that do not apply.
E. Certifications:
1. Certifications by a registered professional: Signed and sealed by registered professional.
01 33 00 - 3
Asbestos Abatement
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
2. Manufacturer’s certifications: Signed by authorized representative of manufacturer.
F. Sample Submittals:
1. Label with complete manufacturer's product and color identification.
2. Include type and quantity of materials specified in the referenced section in each “set” of samples.
3. Samples: Representative of product to be installed.
4. Label each sample or sample kit with contract number and title.
1.5 SUBMITTALS PROCEDURES
A. Submit only checked submittals. Submittals without evidence of Contractor's approval will be returned for resubmission.
B. Submit complete sets of required materials for each RSN as specified in “Submittals
Required” column in Table 01 33 00A - List of Submittals. A complete set includes all listed items for RSNs with multiple parts.
C. Submit number of sets specified in “No. of sets to be sent to:” columns in
Table 01 33 00A – List of Submittals.
D. Electronic Submittals:
1. In Portable Document Format (PDF).
2. Include RSN transmittal letter.
3. Do not include Personally Identifiable Information (PII) in electronic submittals.
4. Submittal Method (sized based):
a. The Government can receive e-mails up to 10MB. Receipt of e-mails exceeding 10 MB (extra-large) may be possible. E-mailing of extra-large electronic submittals may occur only after size limit for transmittal of extra-large e-mail has been verified.
b. Electronic media for submittals too large to e-mail: CD or DVD.
E. Include the following information in transmittal letters:
1. Contract number and title.
2. RSN for each attached submittal.
3. Responsible code.
4. Number of sets for each RSN.
5. Identify submittal as initial or resubmittal.
01 33 00 - 4
Asbestos Abatement Flatiron Power and Pumping Plant Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
F. Resubmittal of submittals not approved:
1. Mark changes such that they are readily identifiable and show revision date.
2. Describe reasons for significant changes in transmittal letter.
3. Resubmit rejected submittals within 14 days after receiving the comments, unless otherwise directed.
4. Requirements for initial submittals apply to resubmittals.
G. Submit each RSN under a separate transmittal letter. Multiple RSNs submitted under a single letter will be returned for resubmittal.
1.6 REVIEW OF SUBMITTALS
A. Time Required:
1. Submittal review will require 21 days for review of each submittal or resubmittal, unless otherwise specified.
2. Time required for review of each submittal or resubmittal begins when complete sets of materials required for a particular RSN are received and extends through return mailing postmark date.
B. Time in Excess of Specified:
1. CO may extend the contract completion date to allow additional time for completing work affected by excess review time.
a. Time extension will be to the extent that excess review time caused delay to the contract completion date.
b. Time extension will not exceed the time used in excess of the specified number of days for review of submittals or resubmittals.
c. Concurrent days of excess review time resulting from review of 2 or more separate submittals or resubmittals will be counted only once in extending contract completion date.
2. No time extension will be allowed if the Contractor fails to make complete action submittals in sequence and within time periods specified.
3. Adjustment for delay will be made only to the extent that:
a. Approval was required under the contract, and
b. Requests for approval were properly and timely submitted and were approved.
4. Adjustment will be subject to terms of paragraphs (b) and (c) of the clause at FAR 52.242-14, Suspension of Work, however, no such delay shall be deemed to be a “suspension order” as the term is used in that clause.
C. Submittal Response:
01 33 00 - 5
Asbestos Abatement
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
1. Response letter will indicate whether submittal is approved, approved subject to identified changes, or not approved.
a. Revise and resubmit submittals not approved.
b. Do not change designs without approval of the CO after drawings, documentation, and technical data have been approved.
1.7 TRANSMITTAL
A. Addresses for codes listed in Table 01 33 00A - List of Submittals:
1. CO: Bureau of Reclamation, Attention GP-5000, P.O. Box 36900, Billings, MT 59107-6900. Physical address: 2021 4th Avenue North, Billings, MT 59101.
2. COR: Bureau of Reclamation, Attention: GP-2600, P.O. Box 36900, Billings, MT 59107-6900. Physical address: 2021 4th Avenue North, Billings, MT 59101.
B. E-mail address for electronic submittals listed in Table 01 33 00A – List of Submittals: sha-GPR-CONSTSVCS@usbr.gov.
1. Submit electronic submittals that are too large for e-mail along with paper copy.
C. Submittals required by the specifications, but not listed in Table 01 33 00A – List of Submittals:
1. Submit in accordance with this section.
2. Submit to COR, unless otherwise specified.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
mailto:sha-GPR-CONSTSVCS@usbr.gov
Colorado-Big Thompson Project, Colorado
Submittals 01 33 00 - 6
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
Sets to be sent: *
CO COR
1 Reporting Executive Compensation and First Tier Subcontract Awards 52.204-10
Certification that executive compensation and subcontract awards were reported
Within 10 days of each report being submitted
CO 1
paper
2 Additional Bond Security 52.228-02
Evidence of increase in Bond Security
Within 10 Calendar days after modifications increasing contract value
CO 1
paper
3 Equal Opportunity 52.222-26
Information required by Executive Order
112246 (SF-100)
Within 30 days following award CO 1 paper
4 Performance and Payment Bonds – Construction 52.228-15
Performance and Payment Bonds
Within 10 calendar days after award
CO 1
paper
5 Release of Claims 1452.204-70
Release of Claims (DI-137) against the Government
After completion of the work and prior to final payment
CO 1
paper
6 Insurance-work on a Government Installation 1452.228-70
1) Written certification that the required insurance has been obtained
2) Current certification of insurance for each subcontractor
Before commencing onsite work CO 1 paper paper
7 Liability Insurance 1452.228-70
Acceptable Certificate of Liability Insurance
Prior to commencement of work under the contract
CO 1
paper
8 Payrolls and Basic Records 52.222-08
Copies of all payrolls
Weekly for each week of contract performance
COR 1
paper
2 paper
9 Labor Standards Data 52.222-11
1) List of subcontractors
2) Statement and acknowledgement Form (SF-1413) for each subcontract
Within 14 days after award of contract
COR 1
paper paper
1 paper + 1 electronic
1 paper + 1 electronic
01 33 00 - 7
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
Sets to be sent: *
CO COR
10 Security Requirements
(WBR
1452.237-80) and GP-7
List of conractor and subcontractor employees
Initially at least 21 days before beginning onsite work; at least 21 days before additional employees arrive onsite
COR 0 2 paper
11 Security Requirements
(WBR
1452.237-80) and GP-7
Vehicle Information At least 21 days before beginning onsite work
COR 0 1 paper + 1 electronic
12 Schedules for Construction Contracts (52.236-15)
Practicable Schedule:
Blackline Prints
Within 7 days after work commences on the contract or another period of time a determined by the CO
COR 1
paper
1 paper + 1 electronic
13 Schedules for Construction Contracts (52.236-15)
Annotated Schedule Showing Actual Progress:
Blackline Prints
As directed by the CO COR 1 paper
1 paper + 1 electronic
01 14 10-1 Use of Site Land Use and Landscape Rehabilitation Plan
At least 21 days before use of Government land
COR 0 1 paper + 1 electronic
01 35 10-1 Safety Data Sheets
Complete LHM and
SDS
At least 21 days before jobsite delivery of hazardous material
COR 0 1 paper + 1 electronic
01 35 10-2 Safety Data Sheets
Updated LHM and
SDS
At least 21 days before jobsite delivery of hazardous material not previously listed
COR 0 1 paper + 1 electronic
01 35 20-1 Safety and Health
Safety Program Submitted and accepted before commencing on-site work. See section 3 of RSHS
COR 0 1 paper + 1 electronic
01 35 20-2 Safety and Health
Monthly Accident Summary Report
Within 5 days after the first of the month
COR 0 1 paper + 1 electronic
01 35 20-3 Safety and Health
Respirator User Documentation
At least 21 days before beginning on-site work
COR 0 2 paper
01 35 20-4 Safety and Health
Crane Training Certificates
At least 21 days before beginning on-site work
COR 0 2 paper
01 35 20-5 Safety and Health
Other Training Certificates
At least 21 days before beginning on-site work
COR 0 2 paper
01 35 30-1 Contractor’s Onsite Safety Personnel
Qualifications At least 21 days before beginning on-site work
COR 0 2 paper
01 35 30-2 Contractor’s Onsite Safety Personnel
CIH Inspection Reports
Within 7 days after inspection COR 0 1 paper +
01 33 00 - 8
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
Sets to be sent: *
CO COR
01 35 30-3 Contractor’s Onsite Safety Personnel
Safety Inspection Reports
Monthly COR 0 1 paper + 1 electronic
01 57 30-1 Water Pollution Control
Water Management Plan
At least 28 days before start of on-site construction work
COR 0 1 paper + 1 electronic
01 57 30-2 Water Pollution Control
Spill Prevention, Control, and Countermeasure (SPCC) Plan
At least 28 days before delivery or storage of oil or oil products
COR 0 1 paper + 1 electronic
01 74 00-1 Cleaning and Waste Management
Waste Production and Disposal Plan
Within 7 days of mobilization
COR 0 1 paper +
01 74 00-2 Cleaning and Waste Management
Waste Production and Disposal Records
Within 7 days of waste disposal
01 74 00-3 Cleaning and Waste Management
Environmental Consultant Resume
At least 21 days before beginning environmental assessment
COR 0 2 paper
01 74 00-4 Cleaning and Waste Management
Environmental Site Assessment
Within 14 days of completion of work
02 82 20-1 Removal and
Disposal of Asbestos Containing Materials
Safety Plan At least 28 days before beginning removal and disposal of asbestos containing materials
COR 0 1 paper + 1 electronic
02 82 20-2 Removal and Disposal of Asbestos Containing Materials
Current State of Colorado/Asbestos Hazard Emergency Response Act
(AHERA)
Certificates
At least 28 days before beginning removal and disposal of asbestos containing materials
COR 0 1 paper + 1 electronic
02 82 20-3 Removal and Disposal of Asbestos Containing Materials
Resumes of Key Individuals Providing Service
At least 28 days before beginning removal and disposal of asbestos containing materials
COR 0 2 paper
02 82 20-4 Removal and Disposal of Asbestos Containing Materials
Independent Testing Laboratory
At least 28 days before beginning removal and disposal of asbestos containing materials
01 33 00 - 9
Table 01 33 00A. - List of Submittals
* CO indicates Contracting Officer, and COR indicates Contracting Officer’s Representative.
RSN
Clause or
Section Title
Submittals required
Due date or delivery time
Respon-sible code
Sets to be sent: *
CO COR
02 82 20-5 Removal and Disposal of Asbestos Containing Materials
Project Design Plan At least 28 days before beginning removal and disposal of asbestos containing materials
COR 0 1 paper + 1 electronic
02 82 20-6 Removal and Disposal of Asbestos Containing Materials
Asbestos Hazard Abatement Plan
At least 28 days before beginning removal and disposal of asbestos containing materials
COR 0 1 paper + 1 electronic
02 82 20-7 Removal and Disposal of Asbestos Containing Materials
Working Level and Clearance Test Results
Within 2 days after working level and clearance test results completed
COR 0 1 paper + 1 electronic
02 82 20-8 Removal and Disposal of Asbestos Containing Materials
Clearance Sampling Results
Within 2 days after sampling completed
COR 0 1 paper + 1 electronic
02 82 20-9 Removal and Disposal of Asbestos Containing Materials
Baseline Sampling and Testing Results
Within 2 days after sampling completed
COR 0 1 paper + 1 electronic
02 82 20-
Removal and Disposal of Asbestos Containing Materials
Analyses, Permits, Manifests, Certificates, and Documentation
Within 15 days after disposal COR 0 1 paper + 1 electronic
02 82 20-
Removal and Disposal of Asbestos Containing Materials
Post Abatement Sampling and Testing Results
Within 2 days after post abatement sampling and testing results completed
COR 0 1 paper + 1 electronic
06 52 10-1 Cable Tray Liner Replacement
Approval Data At least 28 days before beginning cable tray liner replacement
COR 0 1 paper + 1 electronic
22 07 19-1 Plumbing Piping Insulation
Approval Data At least 28 days before beginning piping insulation replacement
COR 0 1 paper +
Colorado-Big Thompson Project, Colorado
Submittals 01 33 00 - 10
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Safety Data Sheets 01 35 10 - 1
SECTION 01 35 10
SAFETY DATA SHEETS
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedule for other items of work.
1.2 DEFINITIONS
A. LHM: List of Hazardous Materials.
B. SDS: Safety Data Sheet.
1. Referred to as Material Safety Data Sheets in the clause at 52.223-3, Hazardous Material Identifications and Material Safety Data - Alternate 1.
1.3 APPLICATION
A. For the purposes of this contract, “delivered under this contract” in paragraph (b) of the clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1, includes:
1. Materials delivered to Government.
2. Materials incorporated into work.
3. Materials used by the Contractor during contract performance at the jobsite.
1.4 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 35 10-1, Complete LHM and SDS.
C. RSN 01 35 10-2, Updated LHM and SDS:
1. Comply with paragraph (e) of clause at FAR 52.223-3, Hazardous Material Identification and Material Safety Data - Alternate 1.
1.5 DELIVERY
A. Do not deliver hazardous materials to jobsite which are not included on original or previously updated LHM and SDS before receipt of updated LHM and SDS by COR.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Safety Data Sheets 01 35 10 - 2
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
Safety and Health 01 35 20 - 1
SECTION 01 35 20
SAFETY AND HEALTH
1. Include in the prices offered in the Price Schedule for other items of work.
A. Bureau of Reclamation (USBR)
1. RSHS Reclamation Safety and Health Standards.
Available on the Internet at:
http://www.usbr.gov/ssle/safety/RSHS/rshs.
html
2. FIST 1-1-12 Hazardous Energy Control Program.
Available on the Internet at:
www.usbr.gov/power/data/fist_pub.html
B. Occupational Safety and Health Administration (OSHA)
1. 29 CFR Part 1910 Occupational Safety and Health Standards
2. 29 CFR Part 1926 Safety and Health Regulations for Construction. Available on the Internet at www.osha.gov
C. American Conference of Governmental Industrial Hygienists (ACGIH)
1. Threshold Limit Values (TLVs). Available at www.acgih.org
1.3 SUBMITTALS
B. RSN 01 35 20-1, Safety Program:
1. Comprehensive, job-specific safety and health program in accordance with Section 01 33 00 - Submittals and in accordance with the requirements of Section
3.3 of RSHS and these specifications.
2. The Safety Program will not be accepted for review by the COR unless it addresses, in order, lettered and numbered per Appendix B of the RSHS, a http://www.usbr.gov/ssle/safety/RSHS/rshs http://www.usbr.gov/ssle/safety/RSHS/rshs http://www.usbr.gov/power/data/fist_pub.html http://www.usbr.gov/power/data/fist_pub.html http://www.osha.gov/ http://www.acgih.org/ http://www.acgih.org/
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
01 35 20 - 2 comprehensive narrative for each applicable item in the outline and program elements contained in these specifications.
3. Generic company safety programs are not acceptable. The Safety Program must be site specific for this contract.
4. The Contractor’s Safety Program must be submitted and accepted by Reclamation prior to commencing onsite work, including mobilization.
5. The Safety Program Statement of Responsibility must state that “the contractor is responsible for ensuring that all work will be in compliance with Reclamation Safety and Health Standards and these specifications.”
6. The Safety and Health Program shall include but not be limited to the following program elements:
a. Emergency Action Plan.
1) Detail coordination plan for outside emergency services including response time and a site visit where a rescue requires special capabilities or equipment.
2) This plan shall address detailed emergency contacts and procedures to be used during an onsite emergency.
b. Hazardous Energy Control (lockout/tagout)
1) Include the Contractor’s written Hazardous Energy Control Program (HECP).
c. Electrical Safety.
1) Include safe work procedures at the site, electrically qualified persons, grounding techniques, use of mobile generators, construction lighting, power tool safety, and use of personal protective equipment.
d. Hot Work and Fire Prevention.
1) Include a plan to address hazards associated with hot work.
2) Include list of workplace fire hazards, potential ignition sources, safe work procedures, engineering controls and equipment to be used to prevent fires during the hot work process.
e. Job Hazard Analysis.
1) Provide a list of proposed JHA’s in the Safety Program for each anticipated work task.
2) A detailed JHA shall be completed onsite prior to starting each work task. Work will not begin on the phase of the work until a JHA is acceptable to the Onsite Government Representative.
3) Activities involving hazardous materials shall have the appropriate Material Safety Data Sheet(s) attached to the JHA.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
01 35 20 - 3
f. Respiratory Protection.
1) Identify respirator users, tasks and operations with recognized respiratory hazards.
2) The plan shall address exposure to respirable silica associated with concrete work as follows.
a) Use of tight fitting half face air purifying respirators with P100 cartridges in the absence of an on-site exposure assessment.
3) The level of respiratory protection may only be diminished on the basis of an exposure assessment conducted by a certified industrial hygienist (CIH) specific to each dust-generating operation that is acceptable to Reclamation.
g. Hearing Conservation.
1) Include a task- and site-specific hearing conservation plan.
2) Identify the type of hearing protection and verify that workers are in a Hearing Conservation Program.
h. Crane, Hoisting and Rigging Safety.
1) Include operator and rigging safety, materials handling, signaling and communication procedures.
2) All Operators, Riggers and Signalpersons shall be qualified in accordance with OSHA 1926 Subpart CC. Crane Operators shall be certified by an accredited crane operator testing organization such as NCCCO or equivalent.
3) Reclamation requires an onsite verified load test in accordance with RSHS Appendix F prior to use of cranes.
i. Personal Protective Equipment (PPE):
1) Include a detailed plan for each task that specifies which personal protective equipment shall be used for all construction activities.
2) The employer must ensure that the PPE is verified by the manufacturer for the intended use and protection.
3) Provide appropriate PPE at no cost to the employees.
j. Hazard Communication.
1) Include a written Hazard Communication plan. .
2) The safety and health practices, procedures, and protective equipment used for new and existing products shall be based upon the health hazards identified in the SDS.
k. Fall Protection and Prevention.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
01 35 20 - 4
1) Detail safe work procedures, training and engineering controls for work in elevated areas where employees are exposed to a fall.
2) The Contractor shall use engineered fall protection systems, fall restraint, and/or fall arrest systems for work in elevated areas.
Warning line and safety monitoring systems are not permitted.
l. Protection Against Drowning.
1) The safety program shall include a plan to minimize the hazards associated with working adjacent to water.
C. RSN 01 35 20-2, Monthly Accident Summary Report:
1. Form 7-2218 or other acceptable form in accordance with paragraph 3.8 of RSHS.
2. Submit on the first day of every month.
D. RSN 01 35 20-3, Respirator User Documentation.
1. Submit documentation of medical qualifications less than 12 months old for all respirator users at the site.
2. Submit results of fit tests less than 12 months old for all users of tight fitting negative pressure respirators at the site.
E. RSN 01 35 20-4, Crane Training Certificates.
1. Qualifications for all riggers and signalpersons.
2. Crane Operator Qualifications:
a. Certifications for all crane and hoist operators.
b. Medical Qualifications to operate a crane in accordance with RSHS Section 19.5.
F. RSN 01 35 20-5, Other Training Certificates.
1. First Aid/CPR certifications for onsite foreman and/or safety personnel. Training shall be in accordance with the American Red Cross or the American Heart Association.
2. Proof of fall protection and prevention training for employees who work in elevated areas.
3. Proof of Lockout/tagout training for all employees who will work in any area protected by lockout/tagout and hazardous energy control procedures.
1.04 SAFETY AND HEALTH
A. Comply with RSHS, local safety programs, and any other referenced safety and health standards. Perform work in accordance with the specific safety program elements and referenced standards.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
01 35 20 - 5
B. Provide and maintain a work environment and procedures that will:
1. Safeguard the public, Government personnel, and Contractor employees from Contractor operations and activities that are unsanitary, hazardous, or dangerous to health and safety.
2. Avoid interruptions of site operations and delays in project completion dates.
3. Control costs in contract performance.
C. Provide appropriate safety barricades, signs, and warnings.
D. Erect or label all limited approach and arc flash hazard boundaries for exposed energized equipment.
E. Comply specifically with all requirements contained in RSHS Section 3 - Contractor
Requirements.
F. Investigate and report all accidents, incidents and near misses in accordance with RSHS
Section 3.7.
G. When the Contractor fails or refuses to promptly correct a compliance directive, the CO may issue an order to stop all or any part of the work.
1. When satisfactory corrective action is taken, an order to resume work will be issued.
2. The Contractor shall not be entitled to extension of time or to claim for damage or to additional compensation by reason of ether the directive or the stop order.
3. Failure of the CO to order discontinuance of any or all of the Contractor’s operations shall not relieve the Contractor of the responsibility for the safety of personnel and property.
H. Disputes regarding safety and health issues will be settled in accordance with RSHS
Section 3.
I. The Contractor shall be responsible for providing medical and emergency assistance in a timely manner that is consistent with recognized emergency protocols.
1. In instances where local emergency responders are not readily available, the responsibility to provide emergency services shall default back to the Contractor.
J. The Contractor shall be responsible for insuring that Subcontractors comply with the requirements set forth in this specification, written programs, the regulatory standards and the industry standards incorporated by reference in the RSHS and OSHA standards.
K. Where there is conflict between the standards, the more stringent or restrictive shall be utilized.
Colorado-Big Thompson Project, Colorado Solicitation R16PS01264
01 35 20 - 6
L. The Contractor shall fully participate in the Contractor Safety Program Review meeting, according to RSHS Section 3.4.1. The Contractor Safety Program Review meeting will take place before the start of construction.
1. Include subcontractor management representatives.
2. The Safety Personnel shall be present, in order to discuss in detail the Safety Program and Plans.
M. The Contractor shall participate in the Joint Safety Policy Meeting. The COR, the
Contractor's principal onsite representative, and designated members of respective staffs shall…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .