Q&A.pdf
PDF 239 KB Posted
- Attached to
- Building 41 Boiler 1 and 2 Replacement
- Solicitation number
- 2137314
- Issued by
- Oneida County, New York
About this file
This is a Questions and Answers document for a boiler replacement solicitation issued by the New York State Office of Mental Health for the Central New York Psychiatric Center located in Marcy, NY. The project involves the replacement of Building 41 Boiler 1 and 2. A mandatory site visit is scheduled for Thursday, July 30th, 2026 at 10:00 AM ET, with site visit registration forms due by Wednesday, July 29th, 2026 at 3:00 PM ET. Interested bidders must submit questions by 3:00 PM ET on Thursday, August 6th, 2026, with accumulated questions and responses to be distributed on Thursday, August 13th, 2026 and posted to the contract reporter. Bids are due no later than 3:00 PM ET on Thursday, August 20th, 2026 and must be submitted via email to Bids@omh.ny.gov.
The solicitation includes contracting goals requiring a 6.00% Service-Disabled Veteran-Owned Business (SDVOB) participation goal and a combined 30.00% Minority/Women Business Enterprise (MWBE) goal, with a 0.00% Disadvantaged Business Enterprise (DBE) goal. Stephen S. Starr Mechanical Corp, the incumbent contractor from IFB 25-070, was previously awarded an identical boiler replacement service contract within the past five years and may be considered for this opportunity.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| IFB 26-031 Building 41 Boiler 1 and 2 Replacement.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
KATHY HOCHUL
Governor
ANN MARIE T. SULLIVAN, M.D.
Commissioner
IFB 26-031
Building 41 Boiler Replacement
Questions and Answers
# Question Answer
Given the time frame for state approval, and current equipment lead times, this project would not start until after the heating season has begun. What construction schedule should be assumed for bidding purposes?
The construction schedule was briefly discussed during the site visit. Since the site visit, the facility has modified the set up of the boilers so boilers can be shut down for the install.