PROJECT SCHEDULE (1).pdf
PDF 372 KB Posted
- Attached to
- High School Weight Room Addition
- Solicitation number
- RFP GRPS 270000000030 2
- Issued by
- Macomb County, Michigan
About this file
This is a project schedule document for the High School Weight Room Addition project in Michigan, outlining the construction timeline and phasing for the facility expansion. The project commenced in June 2027 with selective demolition activities running from June 5-26, 2027, followed by sitework and foundation activities occurring from June 22 through July 31, 2027. Concrete work is scheduled for August 2-11, 2027, with masonry construction extending from August 17 through September 17, 2027. Metal installation, roofing systems, aluminum storefronts and glazing, fire protection systems, painting, and flooring work are sequentially scheduled from September 2027 through February 2028. Electrical and mechanical work runs concurrently with other trades from February 14 through February 29, 2028. The project is anticipated to achieve substantial completion on March 6, 2028, with the final day of school occurring on June 4, 2027, indicating the timeline is designed to minimize disruption to the school calendar.
The schedule does not contain information regarding pricing, contract terms, set-asides, funding sources, or other financial details. The document appears to be a Gantt chart format displaying task dependencies and concurrent work phases rather than a comprehensive bid solicitation or contract document. No specific bidder requirements, response dates, site visit information, or award details are included in this schedule document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Gantt
Q2 2027 tones
Last Day of School
28-277 days
Jun 4, '27 Last Day of School
Substantial Completion Mar 6, '28
Q3 2027 Q4 2027 Q12028
Selective Dem Jun 5, 27-Jun 26, '27 Selective Demolition
ECTRICAL Feb 14, '28
MECHANICAL Jun 21, '27- Feb 29, '28
SITEWORK Jun 22, '27-Jul 10, '27
Footings/Foundation Dig Jul 27, 27- Jul 31, '27
SITEWORK
Footings/ Foundation Dig
CONCRETE Aug 2, '27-Aug 11, '27 CONCRETE
MASONRY Aug 17, '27- Sep 17, '27
METALS Sep 20, '27- Sep 30, '27
ROOFING SYSTEMS Oct 4, '27-Oct 14, '27
ALUMINUM STOREFRONTS Nov 1, '27- Nov 11, '27
Nov 8, '27- Nov 27, '27
FIRE PROTECTION Nov 22, '27- Dec 10, '27
PAINTING Dec 13, 27- Jan 6, 28
FLOORING Jan 31, '28-Feb 25, '28
Substantial Co
ELECTRICAL
MECHANICAL
MASONRY
METALS
ROOFING SYSTEMS
|ALUMINUM STOREFRONTS/GLAZING
LPDA
FIRE PROTECTION
PAINTING
FLOORING
• Construction