This Project Manual establishes the procurement and contractual requirements for CSP #27-01, an electrical upgrades project for San Jacinto Community College District's Central Campus located at 8060 Spencer Highway, Pasadena, Texas. The project involves replacement and reconfiguration of the existing 12.47kV medium voltage electrical distribution system serving Buildings C30, C31, and C32, including removal of existing medium-voltage conductors, installation of a new 12.47kV 1-in, 2-out PME-7 sectionalizer and equipment pad, installation of underground Quazite pull boxes, conduits, and medium-voltage conductors, and reuse of existing empty conduit pathways. The work will be executed in phased construction to allow concurrent work on multiple buildings while coordinating a final system cutover to minimize campus power outages and operational impacts. The project is being procured through competitive sealed proposals under Texas Government Code Section 2269.151 et seq. The District has engaged ACR Engineering, Inc. as the design consultant, with Charles Smith serving as the Associate Vice Chancellor for Fiscal Initiatives and Capital Projects and John Haugen as the Director of Capital Projects overseeing project management.
The contractor is responsible for securing all required permits from the City of Pasadena and City of La Porte jurisdictions and must include permit costs within the project bid. Performance and Payment Bonds are required, with the Performance Bond executed pursuant to Texas Government Code Title 10, Chapter 2253. Prevailing wage rates apply to all workers employed on the public work, as established under Texas Government Code Chapter 2258, with contractors subject to penalties of $60 per worker per day for non-compliance. The District requires comprehensive submittal procedures with 10-day review periods for initial submittals and resubmittals, coordination with a Commissioning Authority, and photographic documentation of at least 20 images monthly. Contractors must comply with extensive safety requirements including designated competent persons, site-specific safety plans, substance abuse programs, incident reporting within 24 hours, and restrictions on personnel mobile electronic devices in designated work areas. Additional mandatory requirements include hazardous materials assessments, environmental and indoor air quality procedures, traffic control and logistics plans, and protection of all installed construction with equipment warranties maintained for their full expected duration at no additional cost to the District.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
ELECTRICAL UPDATES, BUILDINGS C30, C31, & C32
CSP #27-01
Issue Date: September 15, 2026
CENTRAL CAMPUS
8060 SPENCER HIGHWAY
PASADENA, TEXAS 77505
09/16/26
PERMIT APPLICATION 00 31 43
DOCUMENT 00 01 01 PROJECT TITLE PAGE
PROJECT: CSP #27-01 Electrical Upgrades, Buildings C30, C31, & C32
LOCATION: San Jacinto Community College District
Central Campus 8060 Spencer Highway Pasadena, Texas 77505
MEMBERS OF THE BOARD OF TRUSTEES
Dan Mims, Chair Dr. Michelle Cantu’-Wilson, Vice Chair Keith Sinor, Secretary Erica Davis Rouse, Assistant Secretary Judy Harrison, Member Larry Wilson, Member Chad Burke, Member Ben Meador, Emeritus Trustee
CHANCELLOR
Dr. Brenda Hellyer
CAPITAL PROJECTS AND FACILITIES SERVICES
Charles Smith - Associate Vice Chancellor, Fiscal Initiatives and Capital Projects Bryan D. Jones - Associate Vice Chancellor, Facilities and Construction
CONSULTANT FIRMS
Ricardo Troncoso, President ACR Engineering, Inc. 3001 S. Lamar Blvd. Suite 101, Austin, TX 78704
Project Manager Charles Smith Associate Vice Chancellor, Fiscal Initiatives and Capital Projects
DOCUMENT 00 01 10 TABLE OF CONTENTS
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION
00 01 01 Project Title Page 00 01 10 Table of Contents 00 31 43 Permit Applications 00 52 13 Reference: Agreement for Construction Services 00 61 13.13 Performance Bond 00 61 13.16 Payment Bond Form
00 62 76 Payment Application Form 00 62 76.1 Release of Partial Payment 00 62 76.13 Sales Tax Form 00 65 19.1 Subcontractor’s Hazardous Materials Certificate 00 65 19.16 Affidavit of Release of Liens Form 00 72 13 Reference: General Conditions for Construction Contract Between San Jacinto
Community College District and Contractor 00 73 00 Supplementary Conditions 00 73 43.1 Prevailing Wage Rates
DIVISON 01 – GENERAL REQUIREMENTS
SECTION
01 00 00 General Requirements 01 10 00 Summary 01 11 00 Summary of Project 01 11 13 Work Covered by Contract Documents 01 11 16 Work by Owner or under Separate Contracts 01 14 00 Work Restrictions 01 14 13 Access to Site and Use of Premises 01 18 00 Project Utility Sources 01 18 13 Utility Service Connections 01 21 00 Allowances 01 22 00 Unit Prices 01 23 00 Alternates 01 25 00 Substitution Procedures 01 26 13 Requests for Interpretation 01 26 53 Proposal Requests 01 31 00 Project Management and Coordination 01 32 33 Photographic Documentation 01 33 00 Submittals Procedures 01 35 23 Contractor Safety Requirements Exhibit A – Personnel Mobile Electronic Devices for SJCCD Construction Projects 01 35 43 Environmental Procedures 01 35 46 Indoor Air Quality Procedures 01 35 53 Security Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Control 01 55 19 Temporary Parking Areas 01 64 00 Owner-Furnished Products 01 70 00 Execution and Closeout Requirements 01 74 19 Construction Waste Management and Disposal 01 76 00 Protecting Installed Construction 01 77 00 Project Closeout Procedures
01 89 13 Site Preparation Performance Requirements
FORMS
01 21 00.1 Allowance Expenditure Authorization (EA) Form 01 25 00.1 Request for Substitution Form 01 26 53.1 Change Proposal Request Form 01 35 23.1 Personnel Mobile Electronic Device Permit Request
TECHNICAL SPECIFICATIONS
033000 Cast-in-Place Concrete 260010 Summary of Electrical Work 260513 MV Cables 260528 Grounding 260532 Raceways 260553 Identification 261300 MV Sectionalizers 312000 Earthwork
LIST OF DRAWING SHEETS
Sheet Number and Title
C0.1 Cover Sheet E0.1 Electrical Site Plan – Demolition E0.2 Electrical Site Plan – New Construction E1.1 Electrical Riser Diagram – Demolition and New Construction E1.2 Electrical One-Line Diagram – Demolition and New Construction E1.3 Electrical Details E1.4 Electrical Details
DOCUMENT 00 31 43 PERMIT APPLICATION
REQUIREMENTS
For all construction projects, the local jurisdiction where a campus of the San Jacinto Community College District is located will be final authority on all permits. The Central Campus is located within the jurisdictions of the Cities of Pasadena and La Porte, Texas. The North Campus is located in unincorporated Harris County. The South Campus is located in the jurisdictions of the City of Houston, Texas and Harris County. The Maritime Center is located within the jurisdictions of the City of Pasadena ETJ and Harris County.
Generally, permitting will be required for all new construction and renovation projects, regardless of size or scope.
In minor Physical Plant directed projects, permitting will be required when a new circuit is installed or a new plumbing line is installed.
The Contractor is responsible for securing all required permits.
The Contractor will include the cost of a Construction permit in the cost of the project.
Contractor is responsible for the posting of all Permits.
Applicable permits will be obtained before the start of construction.
SAMPLE AGREEMENT FOR CONSTRUCTION SERVICES 6
DOCUMENT 00 52 13 REFERENCE: AGREEMENT FOR CONSTRUCTION SERVICES
Sample of complete agreement is available as a separate attachment in IonWave, Attachment tab.
PERFORMANCE BOND 00 61 13.13
DOCUMENT 00 61 13.13 PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS, that we _______________________ (Contractor) hereinafter called “Principal”, and ___________________________ (Surety) hereinafter called “Surety”, are held and firmly bound unto the San Jacinto Community College District, hereinafter called “Owner”, in the amount of: _____________________________________ Dollars ($______________) for payment whereof the said principal and surety bind themselves and their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH that whereas the Principal has entered into a certain contract with the Owner, dated the _______ day of ___________, ______ for the complete construction on the property of the Owner, located in Harris County, Texas, of the work described as:
CSP 27-01 Electrical Upgrades, Buildings C30, C31, & C32
Which said Contract and Documents referred to therein is herein now referred to and made part hereof as fully and completely as if copied in detail herein.
NOW, THEREFORE, the condition of this obligation is such that if said Principal shall well and truly and faithfully perform all the undertakings, covenants, terms, conditions, and agreements of said Contract, including, but not limited to, the faithful performance of the work required in accordance with the Contract Documents, during the original term thereof and extension thereof which may be granted by the Owner with or without notice to the Surety, and if said Principal shall satisfy all claims and demands incurred under such contract and shall fully indemnify, defend, and save harmless the Owner from all costs, including attorney’s fees, which the Owner may incur in the prosecution or defense of any suit or proceeding arising out of the breach or default of the Principal, then this obligation shall be void; otherwise, to remain in full force and effect.
The said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alterations or additions to the terms of the Contract or to the work to be performed thereunder, or of the specifications accompanying the same, shall in anywise affect its obligation on this bond, and it does hereby waive notice of such change, extension of time, alterations or additions to the terms of the Contract or to the work or to the specifications thereunder.
It is expressly provided that if any legal action shall be filed upon this bond, venue shall lie in Harris County, Texas.
Simultaneously with the execution of this Performance Bond, the parties hereto have executed a Payment Bond, reference to which is made for all purposes. Nothing in this Performance Bond shall any way nullify the obligations of the parties as set forth in said Payment Bond.
PERFORMANCE BOND 00 61 13.13
Provided, however, that this bond is executed pursuant to the provisions of the Texas Government Code Title 10, Chapter 2253 or successor statues, and liabilities on this bond shall be determined in accordance with the provisions of said Article to the same extent as if it were copies at length herein.
Provided, however, that nothing in the bond shall be construed to limit the rights of the beneficiaries of this Bond which they might have under general, special or common law of the State of Texas not inconsistent with the terms hereof and not inconsistent with the provisions of Texas Government Code Title 10, Chapter 2253, as amended.
IN TESTIMONY WHEREOF, the parties hereto have executed this instrument on this __________ day of _______________, ________.
SURETY PRINCIPAL
By _______________________________ By _______________________________ Name ____________________________ Name ____________________________ Title _____________________________ Title _____________________________ License Number ___________________ Business Address ___________________ Business Address ___________________ _________________________________ _________________________________ Telephone ________________________ Telephone ________________________ Witness __________________________ Witness __________________________ Name ____________________________ Name ____________________________ Title _____________________________ Title _____________________________
APPROVED AS TO FORM:
SAN JACINTO COMMUNITY COLLEGE DISTRICT
By _______________________________ By _______________________________ Name ____________________________ Name ____________________________ Title _____________________________ Title _____________________________
PAYMENT BOND FORM 00 61 13.16
DOCUMENT 00 61 13.16 PAYMENT BOND FORM
San Jacinto Community College District CSP 27-01 Electrical Upgrades, Buildings C30, C31, & C32 COUNTY______________________
BOND NO._____________________
KNOW ALL PERSONS BY THESE PRESENTS: That we ________________________________ (Contractor) hereinafter called “Principal”, and _______________________________(Surety) hereinafter called “Surety”, are held and firmly bound unto the San Jacinto Community College District, hereinafter called “Owner”, in the amount of: _____________________________________ Dollars ($_______________), lawful money of the United States, well and truly to be paid to the State of Texas, and we bind ourselves, our heirs, successors, executors, and administrators jointly and severally, firmly by these presents.
Whereas, the above bounden principal has entered into the foregoing contract with the State of Texas attached hereto, and whereas, under the law said Principal is required before commencing the work provided for in said contract to execute a bond in the amount of said contract solely for the protection of all claimants, as defined by the Texas Government Code Title 10, Chapter 2253, or successor statutes, in the prosecution of the work provided for in said contract supplying labor and materials as defined by law, in the prosecution of the work provided for in said contract, for the use of each such claimant.
The condition of this obligation is such that if the above bounden principal, his or its heirs, successors, executors, and administrators shall well and faithfully make payment to each and every claimant as defined by law, supplying labor and materials as defined by law, in the prosecution of the work provided for in said contract and any and all duly authorized changes to said contract that may hereafter be made, notice of such changes to the Surety(s) being hereby waived, then this obligation shall be null and void, otherwise it shall remain in full force and effect.
WITNESS our hand this ______________day of ______________, _______.
SURETY CONTRACTOR
(Print Firm Name and Seal) (Company Name)
* By: _______________________________ By: _________________________________
(Print Name) (Print Name)
(Title & License Number) (Title)
* Note: A Power of Attorney, showing that the surety officer or Attorney-in-Fact has authority to sign such obligation, must be impressed with the corporate seal and attached behind the Payment Bond.
The ATTORNEY GENERAL OF TEXAS & TEXAS DEPARTMENT OF INSURANCE has approved this form.
PAYMENT APPLICATION FORM 00 62 76
DOCUMENT 00 62 76 PAYMENT APPLICATION FORM
1.1 REQUIREMENTS
Applications for payment will be accompanied by completed Release of Partial Payment form.
Release of Partial Payment form will be provided to the Contractor in Microsoft Excel format.
Form is to be signed by the Contractor, Architect/Engineer before being sent to the District for payment.
All applications for pay will be sent to the Director of Construction for processing.
2.1 REFERENCES
SECTION 01 29 00, this manual
SECTION 00 62 76.1 Release Partial Payment form
RELEASE OF PARTIAL PAYMENT 00 62 76.1
DOCUMENT 00 62 76.1 RELEASE OF PARTIAL PAYMENT
SALES TAX EXEMPTION FORM 00 62 76.13
DOCUMENT 00 62 76.13 SALES TAX EXEMPTION FORM
SUBCONTRACTOR HAZARDOUS MATERIAL CERTIFICATE 00 65 19.1
DOCUMENT 00 65 19.1 SUBCONTRACTOR HAZARDOUS MATERIAL CERTIFICATE
OWNER: San Jacinto Community College District
SPECIFICATION SECTION(S): _____________________________________________________
KNOW ALL MEN BY THESE PRESENTS:
______________________________________, being first duly sworn, deposes and says that I am the ______________________________ of _______________________, the subcontractor/supplier who constructed or provided the section(s) of work referenced above, and that I am duly authorized to certify to the best of my information, knowledge, and belief no asbestos containing, or radon emitting materials have been used in our portion of the project.
Additionally, to the best of my knowledge no PCB, lead, or lead bearing materials have been incorporated into the potable water system materials that have been incorporated into this project.
ATTEST (If Corporation)
Name of Subcontractor/Supplier
Secretary Signature Title
THE STATE OF ____________________________________
COUNTY OF ______________________________________
Sworn to and subscribed before me on this ________ day of ____________________, _______.
(Seal) _____________________________ (Notary Public Signature)
AFFIDAVIT OF RELEASE OF LIEN 00 65 19.16
DOCUMENT 00 65 19.16 AFFIDAVIT OF RELEASE OF LIENS FORM
TO WHOM IT MAY CONCERN:
WHEREAS, ________________________________ has been partially paid for labor and materials furnished for use in connection with the repair and renovation of the premises located at San Jacinto College, and we have no claims against any person, firm or corporation for labor performed or materials furnished in connection with the furnishing of materials and/or installation of our work on said contract.
In consideration of _______________________________________ Dollars ($_____________), which is sum due for said work, and other goods and valuable consideration, upon the receipt and of which, the undersigned does hereby waive and release any mechanics lien or materialmen’s lien or claims of lien, including any constitutional lien or claim thereto, that the undersigned has on the above mentioned real property and/or improvements thereon on account of any work furnished or to be furnished by the undersigned where pursuant to the above mentioned contract or otherwise.
The undersigned further certifies and warrants that there are no known mechanics’ or materialmen’s liens outstanding as of the date hereof, that all bills incurred by it with respect to the work have been paid in full, and that there is known basis for the filing of any mechanics’ or materialmen’s liens on the property and/or improvements above described by any person or entity performing the work on behalf of the undersigned; and to the extent permitted by applicable law, the undersigned does hereby waive and release any mechanics’ or materialmen’s lien or claims of lien of any other such person or entity, and further agrees to indemnify and hold the Owner harmless from said lien or claim.
Signed: ___________________________ Name: ___________________________ Title: ____________________________
STATE OF TEXAS
COUNTY OF HARRIS
Before me, the undersigned authority, on this day personally appeared __________________________ of ____________________________________, a Corporation, known to me to be the person whose name is subscribed to the foregoing instrument and acknowledged which was executed the same for the purposes and consideration therein express, in the capacity therein stated and as the act and deed of said Corporation, and upon being duly sworn, stated the foregoing instrument and that it is true and correct.
GIVEN UNDER MY HAND AND SEAL OF OFFICE THIS ____ DAY OF _____________, ______.
NOTARY PUBLIC in and for the STATE of TEXAS
Supplementary Conditions 00 73 00
DOCUMENT 00 72 13 Reference: General Conditions for Construction Contract Between San Jacinto Community College District and Contractor
Sample of complete General Conditions is available as a separate attachment in IonWave, Attachment tab.
DOCUMENT 00 73 00 SUPPLEMENTARY CONDITIONS
Reserved
PREVAILING WAGE RATE SCHEDULE 00 73 43.1
DOCUMENT 00 73 43.1 Prevailing Wage Rate Determination Information
The following information is from Chapter 2258 Texas Government Code:
Sec. 2258.021. Right to be Paid Prevailing Wage Rates.
(a) A worker employed on a public work by or on behalf of the state or a political subdivision of the state shall be paid:
(1) not less than the general prevailing rate of per diem wages for work of a similar character in the locality in which the work is performed; and
(2) not less than the general prevailing rate of per diem wages for legal holiday and overtime work.
(b) Subsection (a) does not apply to maintenance work.
(c) A worker is employed on a public work for the purposes of this section if the worker is employed by a contractor or subcontractor in the execution of a contract for the public work with the state, a political subdivision of the state, or any officer or public body of the state or a political subdivision of the state.
Sec. 2258.023. Prevailing Wage Rates to be paid by Contractor and Subcontractor; Penalty.
(a) The contractor who is awarded a contract by a public body or a subcontractor of the contractor shall pay not less than the rates determined under Section 2258.022 to a worker employed by it in the execution of the contract.
(b) A contractor or subcontractor who violates this section shall pay to the state or a political subdivision of the state on whose behalf the contract is made, $60 for each worker employed for each calendar day or part of the day that the worker is paid less than the wage rates stipulated in the contract. A public body awarding a contract shall specify this penalty in the contract.
(c) A contractor or subcontractor does not violate this section if a public body awarding a contract does not determine the prevailing wage rates and specify the rates in the contract as provided by Section 2258.022.
(d) The public body shall use any money collected under this section to offset the costs incurred in the administration of this chapter.
(e) A municipality is entitled to collect a penalty under this section only if the municipality has a population of more than 10,000.
Sec. 2258.051. Duty of Public Body to Hear Complaints and Withhold Payment.
A public body awarding a contract, and an agent or officer of the public body, shall:
(1) take cognizance of complaints of all violations of this chapter committed in the execution of the contract; and
(2) withhold money forfeited or required to be withheld under this chapter from the payments to the contractor under the contract, except that the public body may not withhold money from other than the final payment without a determination by the public body that there is good cause to believe that the contractor has violated this chapter.
Prevailing Wage Rates – School Construction Trades
June 2, 2025
Prevailing Wage Rates
SAN JACINTO COMMUNITY COLLEGE DISTRICT
DESIGN STANDARDS AND GUIDELINES
Division 01 – General Requirements
01 00 00 General Requirements
A. The following are provided as Division 01, General Requirements for all San Jacinto Community College District (“SJCCD”) projects. Additional information or modifications required shall be included in the “Special Conditions” document for each project.
01 10 00 Summary
A. This Division 01 expands upon specific administrative and procedural provisions in the Contract and applies broadly to execution of the work of under all other Sections of the specifications.
B. Information presented in this Division 01 applies to all specification sections not covered by specific exceptions, thereby eliminating the need for repetition and reducing the possibility of conflicts and omissions. Only administrative or procedural requirements that are unique to a specific Section of Divisions 02 through 49 should be covered in those Sections.
C. Topics not addressed in this Division 01 shall be managed per the Agreement between the Contractor and the Owner for the Work.
D. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
01 11 00 Summary of Project
A. SJCCD Project Identification: 776611J Electrical Upgrades, Buildings C30, C31, & C32 B. Project Location: Central Campus, Building C30, C31, & C32, 8060 Spencer Highway, Pasadena, TX 77505 C. Owner: San Jacinto College D. Owner's Representative: Charles D. Smith, AVC Fiscal Initiatives and Capital Projects E. Owner's Project Manager: John Haugen, Director, Capital Projects F. Other Owner Consultants.
1. The Owner has retained the following design professionals to assist the Designer with designated portions of the Contract Documents:
a. N/A
2. The Owner has retained the following professional service providers to assist in the completion of the Work to the Owner’s Satisfaction:
G. Designer: ACR Engineering, Inc. 3001 S. Lamar, Suite 210, Austin, TX 78704 H. Phases: It is anticipated that the work will require completion by phases. Any phased work required shall be as specifically described in the Contract Documents or as generally described in the Special Conditions for this project.
01 11 13 Work Covered by Contract Documents
A. The Work of Project is defined by the Contract Documents and consists of all materials and activities required to deliver the facilities described in those contract documents issued under or in response to San Jacinto Community College District procurement action CSP 27-01
B. Project will be delivered under a Competitive Sealed Proposal as described under TGC 2269.151 et.seq.
01 11 16 Work by Owner or under Separate Contracts A. Satisfactory attainment of the Owner's purpose may require preceding, concurrent, or subsequent work by the Owner or Others under separate contract.
B. Cooperate fully with Owner and/or separate contractors so work may be carried out smoothly, without interfering with or delaying work under this Contract or work by Owner and/or separate contractors. Coordinate the Work of this Contract with work performed by Owner and/or separate contractors.
1. No separate work is anticipated on this project..
01 14 00 Work Restrictions A. Work Restrictions for this project are as described in the Special Conditions for this Project.
01 14 13 Access to Site and Use of Premises A. Limitations to Site Access and the Use of Premises by the Contractor are as described in the Special Conditions for this
Project.
B. All visitation to the project site by non-project personnel will be on an escorted basis only.
1. Anyone who is not assigned to work at the site on a regular basis shall be considered a visitor.
2. All visits to the site will begin at the Contractor’s site office.
3. The College does not have the right to lower any Contractor’s safety standards. Non- Contractor personnel involved in the project only acquire unescorted visitation rights after completing the Contractor’s safety protocols.
4. Prior permission is required for all construction site visits due to safety, security, liability, and legal reasons. Visits will be coordinated through the San Jacinto Community College District Project Manager, who will escort (or arrange for an escort) for all visitors to the site.
5. All visitors shall sign a release prior to touring a site.
6. The Project Manager or his designee will be allowed to escort a maximum of three visitors to the site at one time.
i. Additional visitors will require additional qualified escorts.
ii. Any group of visitors larger than six individuals will be considered a “tour”. Tour requests will be granted on a case-by-case basis at the discretion of the Director of Capital Projects.
1. Requests for tours shall be screened and limited in both frequency and numbers of people.
2. Tours will most often be conducted during non-working hours, along a designated route that has been cleared of hazards and properly protected to avoid potential personal injury.
3. A designated member of the Project staff shall guide all approved tours.
4. All tours will begin with a mandatory site safety brief by a Contractor representative.
5. Requests must be made at least one week in advance of the tour. Two weeks’ notice will be required for groups larger than ten individuals.
i. Groups of more than five visitors will receive a mandatory site safety in brief by a Contractor representative.
ii. Groups of more than fifteen visitors will only tour the site after it has been made safe and construction activities suspended for the duration of the tour. PPE will not be required for tours when construction is suspended.
6. Except for those tours conducted along sanitized routes during non-working hours, all visitors must wear OSHA/ANSI approved hard hats, safety glasses, shirts with sleeves over the shoulder, trousers, safety vests, and hard-soled shoes when on site. Ear protection, safety gloves, and steel or composite toed shoes may be required for certain situations. No inappropriate clothing or footwear shall be permitted.
01 18 00 Project Utility Sources
A. The San Jacinto Community College District owns all utility systems on each of its constituent campuses. (Electric power is transmitted to each campus location over Center Point Energy transmission lines.)
B. Project Utility Sources approved by the Owner for Contractor’s use without charge to the Contractor are as described in the Special Conditions for this Project. Any required Project Utilities not provided by the Owner shall be provided by Contractor as described under Section 01 50 00 “Temporary Facilities and Controls”.
C. For all projects, the Contractor will be responsible for providing fully functional utility connections (electrical, water, sewer, telecommunication, data, natural gas, hydronics, and fire water) only to the extent indicated on the plans.
01 18 13 Utility Service Connections A. The Contractor shall prearrange a meeting with the Designated Service Provider and Owner whenever it becomes necessary to introduce or energize new services or interrupt any service to make connections, alterations or relocations and shall fully cooperate with the Owner in doing Work so as to cause the least annoyance and interference with the continuous operation of the Owner's business. Following this meeting the Contractor shall submit a work authorization request that will include a detailed description and procedure for each task, schedule for each task, any safety controls being implemented and signoff locations for tasks completed. The work authorization request will be similar to the document identified in 29 CFR 1910.147 App A and must be approved by the San Jacinto Community College District Facilities Services craft supervisor for the intended utility. The work authorization document is considered a submittal subject to the review periods indicated in the contract and must be approved prior to scheduling work.
B. Any existing utility distribution or internal plumbing, heating, ventilating, air conditioning or electrical disconnections which may affect portions of existing buildings or other construction projects must be coordinated with the Designated Service Provider and Owner to avoid any disruption of operation.
C. While bidding, the Contractor shall assume that all shutdowns shall occur during afterhours and/or weekends unless specifically stated otherwise in the contract documents. In no case, unless previously approved in writing by Owner, shall utilities be left disconnected at the end of a work day or over a weekend.
D. Any interruption of utilities shall be reported immediately to the Owner’s Project Manager. Such interruptions, whether negligently, intentionally, or accidentally, shall not relieve the Contractor's responsibility for the interruption or from liability for loss or damage caused by such interruption even though such loss or damage was not foreseeable by Contractor or subcontractor, or from responsibility for repairing and restoring the utility to normal service. Repairs and restoration shall be made before the Contractor leaves the project site.
01 21 00 Allowances
A. Certain items are specified in the Contract Documents by allowances. These allowances have been established in lieu of defining additional requirements or to defer the selection of actual materials and equipment to a later date when additional information is available for consideration. If necessary, additional requirements will be issued by Change Order.
B. Allowances are to be considered a Cost of Work item and do not include Bonds, Insurance, Contractor Overhead, General Conditions, or Fee; each of which shall be handled as indicated in the Contract.
1. All other related costs for the provisioning and installation of allowance items shall be included within the allowance amount.
2. Costs of services not required by the Contract Documents are changes in the Scope of Work and are not included in allowances.
C. At the earliest practical date after award of the Contract, advise Architect of the date when final selection and purchase of each product or system described by an allowance must be completed to avoid delaying the Work.
1. At Architect's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.
2. Purchase products and systems selected by Architect and approved by Owner from the designated supplier.
D. Approvals:
1. Use allowances only as approved by Owner and only by written authorization that indicates the specific amounts to be charged to the allowance line item.
2. Use only District approved Allowance Expenditure Authorization (AEA) form. (See forms following Section 01 76
00, including Document 01 21 00 – Allowance Expenditure Authorization Form.)
3. At Project closeout or upon direction by Owner, credit unused amounts remaining in each allowance item to Owner by Change Order, plus any corresponding overhead, profit or fee calculated on such amounts and include in the Contract Sum or GMP.
01 22 00 Unit Prices
A. Definition: Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.
B. Procedures.
1. Unit prices include all necessary material, plus cost for delivery, installation, indirect contractor expense, and profit.
2. Methods of measurement and payment for unit prices are as specified in individual Specification Sections that require the establishment of unit prices.
3. Contractor shall provide a Schedule of Unit Prices on the proposal form for incorporation into the Agreement.
4. Where Unit Prices are required, Contractor shall include on the Proposal the following statement: “The Proposer understands and acknowledges that the unit priced allowances and quantities specified in the plans have been included in the figure submitted as the Base Proposal Figure. The Proposer understands that such unit prices are additive and deductive and shall apply where such quantities are over or under the quantities estimated.”
01 23 00 Alternates A. Definition: An Alternate is an amount proposed by bidders and stated on the Bid Form work defined in the bidding requirements that may be added to or deducted from the base bid amount at the Owner’s discretion.
1. Alternates become part of the Work only after notice to Contractor, at which point they become part of the
Agreement. Execute accepted alternates under the same conditions as other work of the Contract.
2. The work required by an Alternate, if accepted, shall conform to the specifications for similar work in every particular and to specified items of work which apply to the Alternates.
3. Each alternate includes any coordination, revision, or adjustment to adjacent work and miscellaneous devices, accessory objects, or similar items required for a complete and proper installation whether or not indicated as part of alternate.
4. The cost or credit for each alternate is the net addition to (“ADD”) or deduction from (“DEDUCT”) the Contract Amount to incorporate alternate into the Work. No other adjustments are made to the Contract Sum.
B. NOTIFICATION: Immediately following award of the Contract, Owner shall notify Contractor in writing of the status of each alternate, whether accepted, rejected, or deferred for later consideration. Such notification shall include a complete description of any negotiated revisions to alternates.
C. SCHEDULE: The following Schedule of Alternates is provided. Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.
1. Alternate No.: None
01 25 00 Substitution Procedures
A. DEFINITION: Substitutions are changes in products, materials, equipment, and methods of construction which differ from those required by the Contract Documents.
B. PROCEDURE:
1. Requests for Substitution may be made at any time. Justification for substitutions are generally due to changed
Project conditions, unavailability of product, or a recognition of clear benefit to the project which was not evident at the time the Contract Documents were prepared.
2. Requests for Substitution should generally be informally proposed in three-way discussion between the Owner, Architect, and Contractor. If the Owner determines that the proposed Substitution offers a clear benefit to the project, approval to submit a formal Substitution Request will be given.
3. Requests for Substitution that have been previously discussed with Owner will be submitted to the Designer by Contractor in writing. (See forms following Section 01 76 00, including Document 01 23 00 - Request for Substitution Form)
a. Such requests shall include the name of the material or equipment to be substituted and a complete description of the proposed substitutions including such drawings, performance, cost and other data that may be necessary for evaluation by the Designer.
b. A statement setting forth all changes in adjacent or related materials, equipment, or other portions of the Work (including changes in the work of other contracts that may be affected) shall be included.
c. The burden of proof of the merit of the proposed substitution and its benefit to Owner is on the Contractor.
d. If, upon detailed review, the Designer deems the substitution request has merit, he will approve it in writing and forward the approval document to the Owner for approval.
e. Substitutions will be approved only when of benefit to the Owner. The Owner’s approval or disapproval of a proposed substitution shall be final.
f. Upon approval of a substitution request, formal Submittals as outline in Section 0133 00 will be required.
01 26 13 Requests for Interpretation A. Construction Drawings, Technical Specifications, Addenda, and general provisions of the Contract, including Contract General
Conditions and Supplementary General Conditions and other Division 1 Specification Sections, apply to this Section.
B. A Request for Interpretation is a document submitted by the Contractor requesting clarification of a portion of the Contract
Documents, hereinafter referred to as an RFI.
1. Should Contractor be unable to determine from the Contract Documents the exact material, process, or system to be installed; or when the elements of construction are required to occupy the same space (interference); or when an item of Work is described differently at more than one place in the Contract Documents; the Contractor shall request that the Architect make an interpretation of the requirements of the Contract Documents to resolve such matters.
2. Contractor shall comply with procedures specified herein to make Requests for Interpretation (RFIs) on behalf of the Contractor, Subcontractors and Suppliers.
a. RFIs shall be prepared and submitted on a form provided by the Architect.
b. Each RFI shall be given a discrete, consecutive number.
c. Contractor shall sign all RFIs attesting to good faith effort to determine from the Contract Documents the information requested for interpretation.
i. Frivolous RFIs shall be subject to reimbursement from Contractor to University for fees charged by Architect, Architect's consultants and other design professionals engaged by the University.
ii. RFIs submitted to request clarification of issues related to means, methods, techniques and sequences of construction or for establishing trade jurisdictions and scopes of subcontracts will be returned without interpretation. Such issues are solely the Contractor's responsibility.
iii. RFIs submitted by entities other than the Contractor will be returned without interpretation.
iv. RFIs that request interpretation of requirements clearly indicated in the Contract Documents will be returned without interpretation.
v. Contractor shall be responsible for delays resulting from the necessity to resubmit an RFI due to insufficient or incorrect information presented in the RFI.
d. Contractor shall prepare and maintain a log of RFIs and make copies of the log available to the Owner and Designer not less than weekly after the first RFI is issued.
3. Designer will return RFIs to Contractor and Owner within seven calendar days of receipt.
C. RFIs shall not be used:
1. as a means of delaying the work;
2. for the approval of submittals or substitutions; or
3. to circumvent the change order process.
01 26 53 Proposal Requests
A. Requests to the Contractor for proposals for changes in the Contract Sum and Contract Time for suggested modifications to the work described in the Contract Documents shall only be made following discussion and approval of the anticipated modifications by the Owner.
B. Requests for Change Proposals should generally originate informally in three-way discussion between the Owner, Architect, and Contractor. If the Owner determines that the proposed modification offers a clear benefit to the goals of the project, approval to submit a formal Change Proposal Request. (See forms following Section 01 76 00, including Document 01 26 53 – Change Proposal Request Form)
1. A statement setting forth all changes in adjacent or related materials, equipment, or other portions of the Work
(including changes in the work of other contracts that may be affected) shall be included.
2. The effect of all such changes will be included in the Contractor’s response to the Change Proposal Request.
C. Change Proposal Requests must be approved in writing by the Owner and only when of benefit to the Owner. The Owner’s approval or disapproval of a proposal requests shall be final.
01 31 00 Project Management and Coordination
A. Contractor's attention is specifically directed, but not limited, to the following documents for additional requirements:
1. Uniform General Conditions for Construction Contracts Uniform General Conditions for Construction Contracts
2. Supplemental General Conditions for Construction Central Campus and FOB Delivery Method
3. Special Conditions for Construction of CSP #27-01 Electrical Upgrades, Buildings C30, C31, & C32. Contractors are required to follow the SJCCD Coronavirus (COVID-19) procedures while on College property; details are at the following links:
• https://www.sanjac.edu/coronavirus
• https://www.sanjac.edu/about-san-jac/safety/communicable-diseases/coronavirus-covid-19/visitor-resources
B. PROJECT MEETINGS
1. Prior to notice to proceed with Construction, project meetings shall be held at a location indicated by Owner.
2. Following issuance of the Notice to Proceed with Construction, schedule and conduct meetings and conferences at Project site unless otherwise indicated. The entity responsible for conducting meeting will record significant https://www.sanjac.edu/coronavirus https://www.sanjac.edu/about-san-jac/safety/communicable-diseases/coronavirus-covid-19/visitor-resources discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within three days of the meeting.
3. A Preconstruction Conference shall be conducted prior to starting construction. Such meeting will review the responsibilities and personnel assignments of the authorized representatives of Owner, Owner's Commissioning Authority, Architect, Architect’s consultants; Contractor and its superintendent; major subcontractors; suppliers;
and other concerned parties.
a. At this meeting and all subsequent meetings participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work for their employer. (i.e.; Participants will be empowered to make binding decisions on project matters for the firm they represent. Repeated attempts to substitute lackeys for decision makers shall result in letters of non-compliance to the offending entities.)
b. All project meetings shall have an Agenda prepared and published in advance of the meeting.
4. Activity Transition Meetings shall be conducted at the Project site before each significant change in construction activity, before each construction activity that requires coordination with other construction, and before each activity that could change the nature of the hazards at the site. Invite Owner will be invited to such meetings, and advise Architect and Owner's Commissioning Authority of meetings as appropriate.
5. Pre-Installation Meetings shall be conducted at the Project site prior to each construction activity that requires coordination with other construction. (Activity Transition and Pre- Installation Meetings may sometimes be one and the same.)
a. Do not proceed with installation if any entity present has unresolved concerns at the conclusion of the conference.
b. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.
6. Construction Progress Meetings shall be conducted at regular intervals, but not less than bi- weekly after issuance of the Notice to Proceed.
a. In addition to representatives of Owner, Owner's Commissioning Authority and Architect, each contractor, subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of activities to be discussed shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
b. Prepare and publish and agenda in advance of the Progress Meeting. Include topics for discussion as appropriate to status of Project, which may include:
i. Safety.
ii. Contractor's Construction Schedule; status against plan and anticipated for three weeks into the future by day and six weeks into the future by week.
iii. Present and future needs of each entity present.
iv. Status of correction of deficient items.
v. Status of RFIs.
vi. Status of Submittals.
vii. Status of proposal requests.
viii. Status of Change Orders.
ix. Pending claims and disputes.
x. Status of payment requests.
01 32 33 Photographic Documentation A. Take digital construction photographs at regular intervals and of all significant issues.
B. Take not less than 20 photographs monthly.
C. For new construction, arrange for aerial photographs of entire job site on not less than a monthly basis.
D. Archive all photographs in a location accessible by Designer and Owner. Each Photograph will be identified with the date taken, and text describing the subject of the photograph. Generic descriptions such as “Photo 1” will not be used.
E. Archive digital images exactly as originally recorded in the digital camera, without alteration, manipulation, editing, or modifications using image-editing software.
F. Circumstances that could require additional photographs include, but are not limited to immediate follow-up when on-site events result in construction damage or losses and photographs to be taken at fabrication locations away from Project site.
01 33 00 Submittal Procedures A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.
1. Written and graphic information and physical samples that require Architect's responsive action are indicated in individual Specification Sections as "action submittals."
2. Written and graphic information and physical samples that do not require Architect's responsive action are indicated in individual Specification Sections as "informational submittals."
3. Submittals may be rejected for not complying with requirements.
B. Submittal Schedule: Submit a schedule of submittals, arranged in chronological order by dates required by construction schedule. Include time required for review, ordering, manufacturing, fabrication, and delivery when establishing dates.
Include additional time required for making corrections or revisions to submittals noted by Architect and additional time for handling and reviewing submittals required by those corrections.
C. Submittal Procedures:
1. The Construction Manager will maintain a submittal log that is updated not less than weekly. Said log shall have a column to record Architect/Engineer (A/E), Commissioning Agent (CxA) and Project Manager (PM) submittal review status. Standard Statuses and abbreviations shall be:
a. Reviewed: AAS (Approved as submitted). The reviewing authority has reviewed and approved the submittal exactly as submitted, without comment.
b. Reviewed: CAN (Approved as Noted, or Approved, Coordinate as Noted). The reviewing authority has reviewed and approved the submittal, but wishes the submitter and A/E to be cognizant of some minor coordination, adjustment, or installation concern which is detailed on the returned submittal or coversheet. The Construction Manager will take responsibility for hand-annotating the Issued for Construction Drawing set to ensure that the annotation is incorporated into the final project.
c. Reviewed: DNC (Does Not Comply). The reviewing authority has reviewed or attempted to review the submittal, but cannot approve it because the submittal violates the basis of design, is outside the specification, or is otherwise unacceptable. A DNC evaluation from the Reviewer should be interpreted as a requiring A/E interaction with the submitter before the A/E’s issuance of an “R&R” or “Rejection” notice to the submitter.
d. Reviewed: NAR (No Action Required). The reviewing authority has reviewed the submittal, has no objections to it, but lacks the moral fortitude to expressly approve it.
e. Reviewed: R&R (Discrepancies as Noted, Revise and Resubmit). The reviewing authority has reviewed or attempted to review the submittal, but cannot approve it for the specific reasons noted, which the submitter must correct before additional consideration.
f. Not Reviewed: ANC (Existence Acknowledged, but No Comment). For whatever reason, the reviewing authority chooses not to review or to take definitive action on a submittal. This status is particularly applicable to the CxA, which may choose to focus its efforts on critical review packages and not touch every package.
g. The Owner’s expectation is that every instance of CAN, R&R, and DNC, will be discussed by the project team, and that issues requiring a potential compromise in some aspect of the project expectations will be escalated to the Owner’s Representative in a timely manner.
2. All comments from Owner’s Representative or stakeholders will be sent to the Owner’s PM for inclusion in the PM’s formal response. Comments from the CxA will be sent to the A/E with a copy to the PM.
a. Submittal Comments by Owner & Tenant Reps => Owner’s PM for consideration, coordination, & inclusion as appropriate.
b. Submittal Comments by Owner’s PM => A/E
c. Submittal Comments by CxA => A/E, Copy PM
d. Submittal Comments by A/E => CM
3. NO SUBMITTAL MAY BE ACCEPTED BY THE A/E UNLESS IT HAS BEEN REVIEWED BY THEPM OR CxA.
4. Electronic digital data files of the Contract Drawings will be provided by Architect for Contractor's use in preparing
Submittals, Shop Drawings and Project Record Drawings. Limitations on the use of such files by the Contractor, if any, will be include in the Project’s Special Conditions.
5. Coordinate preparation and processing of submittals with the performance of sequential construction activities.
a. Submit all submittal items required for each Specification Section concurrently unless partial submittals are allowed by the approved submittal schedule.
i. Submit action and informational submittals required by the same Specification Section as separate packages under separate transmittals.
ii. Submittals that require concurrent review should be so indicated in those Sections and transmittal coordinated so that processing will not be delayed.
iii. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
iv. Unless additional copies are required for final submittal, and…