Pricing_Worksheet.xlsx

XLSX spreadsheet 31 KB Posted

Attached to
OAK GROVE BUNKHOUSE RENOVATIONS
Solicitation number
140L6422R0002
Issued by

About this file

This pricing worksheet and cost estimate are for renovations to the Oak Grove Administration Building and bunkhouse located at the Grand Canyon-Parashant National Monument. The project involves demolishing and replacing portions of the existing structures, including concrete work, installation of doors, windows, and siding, and upgrades to plumbing, HVAC, electrical and utility systems. The cost estimate totals approximately $455,908 and includes general contractor fees, bonds, and insurance.

The related federal contract opportunity is a small business set-aside solicitation from the Department of the Interior Bureau of Land Management Arizona Region to support renovations of the Oak Grove Bunkhouse-Administrative Station. Offerors must be classified as a small business with revenues under $39.5 million to be eligible for award. The solicitation type is a request for proposal.

View the file

Other files

File Type Posted
Sol_140L6422R0002_Amd_0002.pdf PDF
Geotechnical_Engineering_Report_0002.pdf PDF
Project_Specifications_0001.pdf PDF
Sol_140L6422R0002_Amd_0001.pdf PDF
Construction_Plans.pdf PDF
DOL_Wage_Determination.pdf PDF
Sol_140L6422R0002.pdf PDF
Past_Performance_Questionnaire.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Summary

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

OAK GROVE ADMINISTRATION BUILDING RENOVATION
GRAND CANYON-PARASHANT NATIONAL MONUMENT
PRICING WORKSHEET
140L6422R0002
CSIDescriptionTotal
01Mobilization/Demobilization
02Existing Conditions
03Concrete
05Metals
06Wood and Plastic Products
07Thermal and Moisture Protection
08Openings
09Finishes
10Specialties
11Equipment
22Plumbing
23Heating, Ventilation and Air Conditioning
26Electrical and Lighting
31Earthwork
33Utilities
Subtotal$ - 0
General Contractor Fees
General Contractor Overhead8%$ - 0
General Contractor Profit8%$ - 0
Sub Total$ - 0
Bonds and Insurance5%$ - 0
Sub Total$ - 0

Class A Cost Estimate Project Total $ - 0

&"Arial Narrow,Regular"Project Summary &"Arial Narrow,Regular"&P

Item Details

UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

OAK GROVE ADMINISTRATION BUILDING RENOVATION
GRAND CANYON-PARASHANT NATIONAL MONUMENT
CLASS A COST ESTIMATE
Final Construction Plans
September 4, 2020
Task Order: 140L0620F0007
01General ConditionsQuantityUnitCost / UnitTotal
1Mobilization1LS$ 60,000.00$ 60,000.00
Total$ 60,000.00
02Existing ConditionsQuantityUnitCost / UnitTotal
1Demolition1LS$ 20,000.00$ 20,000.00
2Shoring Porch Roof1LS$ 12,500.00$ 12,500.00
Total$ 32,500.00
03ConcreteQuantityUnitCost / UnitTotal
1Concrete Slab on Grade, 4" thick, reinforced235SF$ 23.27$ 5,468.45
2Concrete Slab on Grade, 6" thick, reinforced (Generator Pad)36SF$ 34.90$ 1,256.40
3Concrete Slab on Grade, 6" thick, (Wellhead)36SF$ 34.90$ 1,256.40
4Formed turn-down vertical edge, earthen bottom and inside slope43LF$ 116.22$ 4,997.46
5Concrete Crack Repair56LF$ 225.00$ 12,600.00
64-inch Concrete Bollard8EA$ 175.00$ 1,400.00
Total$ 26,978.71
05MetalsQuantityUnitCost / UnitTotal
1Cut in Lintel Metals Work1LS$ 500.00$ 500.00
Total$ 500.00
06Wood and Plastic ProductsQuantityUnitCost / UnitTotal
1Porch Posts 4x424LF$ 48.09$ 1,154.16
2Wood Roof Beam 4x8 at Porch32LF$ 63.57$ 2,034.24
3Double Door Base Cabinet w/ Drawers - 30" Wide1EA$ 910.97$ 910.97
4Double Door Base Cabinet w/ Drawers - 45" Wide1EA$ 1,108.52$ 1,108.52
5Base Cabinet w/ Drawers - 24" Wide1EA$ 687.24$ 687.24
6Sink Base Cabinet (Kitchen) - 33" Wide1EA$ 890.76$ 890.76
7Sink Base Cabinet (Toilet Room) - 36" Wide1EA$ 740.93$ 740.93
8Wall Cabinet - 48" Wide1EA$ 990.00$ 990.00
9Wall Cabinet - 24" Wide1EA$ 454.82$ 454.82
10Tall Cabinet - 30" Wide x 78" High1EA$ 1,290.00$ 1,290.00RS Means Cost / Unit (Hide)RS Means % Increase (Hide)
11Countertop - Plam15LF$ 344.22$ 5,163.30$ 664.32$ 863.62
Total$ 15,424.94$ 440.97$ 573.26
07Thermal and Moisture ProtectionQuantityUnitCost / UnitTotal
1Gutters70LF$ 20.16$ 1,411.20$ 5.39$ 80.85
2Downspouts40LF$ 22.40$ 896.00$ 2.10$ 31.50
3Standing seam roof - patch8SF$ 18.75$ 150.00$ 2.10$ 31.50
Total$ 2,457.20
08OpeningsQuantityUnitCost / UnitTotal$ 0.25$ 12.50
1Interior Door - Wood, 2'-0" X 6'-8"2EA$ 627.00$ 1,254.00RS Means Cost / Unit (Hide)RS Means % Increase (Hide)
2Interior Door - Wood, 2'-6" X 6'-8"1EA$ 712.50$ 712.50
3Exterior Door - Hollow Metal Door and Frame, 3'-0" X 7'-0"2EA$ 1,375.00$ 2,750.00$ 261.93$ 340.51
4Exterior Door - Screen Door, 3'-0" X 7'-0"1EA$ 725.27$ 725.27
5Door Hardware - Interior3EA$ 366.36$ 1,099.08
6Door Hardware - Exterior2EA$ 795.86$ 1,591.72
7Window Aluminum Slider, 2'-0" X 3'-0"1EA$ 578.94$ 578.94
8Window Aluminum Slider, 4'-0" X 3'-0"3EA$ 728.54$ 2,185.62
9Window Aluminum Slider, 6'-0" X 3'-0"1EA$ 878.48$ 878.48
Total$ 12,378.05
RS Means Cost / Unit (Hide)RS Means % Increase (Hide)
09FinishesQuantityUnitCost / UnitTotal$ 218.80$ 284.44
Ceilings$ 4.00$ 5.20
15/8" Gypsum Board765SF$ 4.44$ 3,396.60
2Batt Insulation (3 1/2")750SF$ 1.75$ 1,312.50
3Paint - Ceilings765SF$ 0.64$ 489.60$ 4.00$ 5.20
Walls & Finishes$ 4.00$ 5.20
4Perimeter Furring 5/8" Gypsum Board on wd studs 2"x4", 24" O.C. w/ batt insulation548SF$ 10.19$ 5,584.12$ 4.00$ 5.20
5Partition Wall Patch and Fill (gypsum board)40SF$ 6.90$ 276.00$ 4.00$ 5.20
6Masonry Wall Patch and Fill2SF$ 41.36$ 82.72
7Painting - Walls (interior gypsum board)533SF$ 1.70$ 906.10
8Painting - Walls (interior CMU walls)492SF$ 5.00$ 2,460.00
9Painting - Exterior Wood Posts70SF$ 1.50$ 105.00$ 8.59$ 11.17
10Painting - Walls (exterior CMU walls)776SF$ 3.75$ 2,910.00
11Painting - Walls (exterior wood siding)206SF$ 2.50$ 515.00
12Resilient Rubber Base (casework base)20SF$ 12.51$ 250.20
Floors$ 4.83$ 6.28
13Resinous/Epoxy Flooring840SF$ 15.00$ 12,600.00
Total$ 30,887.84$ 12.38$ 16.09
10SpecialtiesQuantityUnitCost / UnitTotal$ 4.63$ 6.02
Toilet AccessoriesRS Means Cost / Unit (Hide)RS Means % Increase (Hide)
1Toilet accessories, medicine cabinet1EA$ 600.00$ 600.00$ 88.25$ 114.73
Shower Accessories$ 172.70$ 224.51
2Shower accessories, robe hook1EA$ 37.47$ 37.47$ 421.60$ 548.08
3Allowance for Miscellaneous Metals1LS$ 200.00$ 200.00$ 28.82$ 37.47
Total$ 837.47$ - 0
11EquipmentQuantityUnitCost / UnitTotal
130" Gas Range/Oven1EA$ 937.50$ 937.50$ 440.97$ 573.26
Sbho$ 937.50$ 157.61$ 204.89
22PlumbingQuantityUnitCost / UnitTotal$ 157.61$ 204.89
1ADA Shower, Pan insert and Accessories1EA$ 1,626.50$ 1,626.50
2Tankless Propane Water Heater1EA$ 2,500.00$ 2,500.00
3Water Closets1EA$ 904.14$ 904.14
4Lavatories1EA$ 465.62$ 465.62
5Kitchen Sink1EA$ 815.84$ 815.84
6Shower valve1EA$ 634.90$ 634.90
7Shower enclosure1EA$ 1,500.00$ 1,500.00
8Floor Drains2EA$ 468.11$ 936.22
9Piping175LF$ 71.06$ 12,435.50
10Sanitary piping below grade75LF$ 88.52$ 6,639.00
11Sanitary/vent piping above grade60LF$ 91.64$ 5,498.40
12Gas piping95LF$ 30.42$ 2,889.90
13Heat Trace175LF$ 19.32$ 3,381.00$ 656.04$ 852.85
14Booster Pump1EA$ 1,050.00$ 1,050.00$ 656.04$ 852.85
Total$ 41,277.02$ 656.04$ 852.85
23Heating, Ventilation and Air ConditioningQuantityUnitCost / UnitTotal
1Propane furnace1EA$ 8,100.00$ 8,100.00
2Exhaust fan2EA$ 1,480.00$ 2,960.00
3Ductwork100LF$ 21.00$ 2,100.00
4Return Grilles3EA$ 368.77$ 1,106.31
5Supply Registers9EA$ 157.41$ 1,416.69
6Flue piping/vent40LF$ 80.37$ 3,214.80
7Evaporative Cooler1EA$ 4,850.00$ 4,850.00
9Kitchen hood exhaust and termination1EA$ 940.00$ 940.00
Total$ 24,687.80
26Electrical and LightingQuantityUnitCost / UnitTotal
14kW PV System w/ 6kWH Battery1EA$ 39,540.00$ 39,540.00
2Generator1EA$ 9,150.00$ 9,150.00
3Site work, feeder to Bunkhouse1EA$ 9,912.00$ 9,912.00
4Power distribution panels - bunkhouse bldg1EA$ 14,410.00$ 14,410.00
5Bunkhouse general power and mechanical connections1EA$ 7,470.00$ 7,470.00
6Bunkhouse lighting1EA$ 6,779.00$ 6,779.00
Total$ 87,261.00
31EarthworkQuantityUnitCost / UnitTotal
1Earthwork removal under porch slab and footing21CY$ 50.00$ 1,050.00
2Unclassified Excavation50CY$ 65.00$ 3,250.00
3Structural Backfill64CY$ 200.00$ 12,800.00
4Site Clearing0.5ACRE$ 8,500.00$ 4,250.000
5Trench and Backfill of Exposed Waterline200LF$ 16.00$ 3,200.000
Total$ 24,550.00
33UtilitiesQuantityUnitCost / UnitTotal
11 1/4-inch HDPE Pipe260LF$ 35.48$ 9,224.80
21 1/4-inch Gate Valve and Box6EA$ 195.31$ 1,171.86
31 1/4-inch Check Valve2EA$ 106.25$ 212.50
41 1/4-inch Drain Valve1EA$ 195.31$ 195.31
5Yard Hydrant1EA$ 552.98$ 552.98
6Factory Coated Welded Steel Water Storage Tank1EA$ 45,000.00$ 45,000.00
7Submersible Well Pump, Motor and Power Supply1LS$ 7,800.00$ 7,800.00
8Tank Equipment and Appurtenances1LS$ 500.00$ 500.00
93/4-inch Polyethylene Pipe22LF$ 35.12$ 772.64
10Relocate Propane Tank1LS$ 4,750.00$ 4,750.00
1112"x18"X24" Handhole Box5EA$ 450.00$ 2,250.00
121" Sch80 PVC Conduit1900LF$ 12.00$ 22,800.00
Total$ 95,230.09
Construction Cost Sub-Total$ 455,907.62

&"Arial Narrow,Regular"Item Details &"Arial Narrow,Regular"&P

File details come from the government source that posted it. Updated .