Project Summary
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
| OAK GROVE ADMINISTRATION BUILDING RENOVATION |
| GRAND CANYON-PARASHANT NATIONAL MONUMENT |
| PRICING WORKSHEET |
| 140L6422R0002 |
| CSI | Description | | Total |
| 01 | Mobilization/Demobilization | | |
| 02 | Existing Conditions | | |
| 03 | Concrete | | |
| 05 | Metals | | |
| 06 | Wood and Plastic Products | | |
| 07 | Thermal and Moisture Protection | | |
| 08 | Openings | | |
| 09 | Finishes | | |
| 10 | Specialties | | |
| 11 | Equipment | | |
| 22 | Plumbing | | |
| 23 | Heating, Ventilation and Air Conditioning | | |
| 26 | Electrical and Lighting | | |
| 31 | Earthwork | | |
| 33 | Utilities | | |
| | Subtotal | $ - 0 |
| General Contractor Fees | | | |
| General Contractor Overhead | 8% | | $ - 0 |
| General Contractor Profit | 8% | | $ - 0 |
| | Sub Total | $ - 0 |
| Bonds and Insurance | 5% | | $ - 0 |
| | Sub Total | $ - 0 |
Class A Cost Estimate Project Total $ - 0
&"Arial Narrow,Regular"Project Summary &"Arial Narrow,Regular"&P
Item Details
UNITED STATES DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
| OAK GROVE ADMINISTRATION BUILDING RENOVATION |
| GRAND CANYON-PARASHANT NATIONAL MONUMENT |
| CLASS A COST ESTIMATE |
| Final Construction Plans |
| September 4, 2020 |
| Task Order: 140L0620F0007 |
| 01 | General Conditions | | Quantity | Unit | Cost / Unit | Total |
| 1 | Mobilization | 1 | LS | $ 60,000.00 | $ 60,000.00 |
| Total | | | | | $ 60,000.00 |
| 02 | Existing Conditions | | Quantity | Unit | Cost / Unit | Total |
| 1 | Demolition | 1 | LS | $ 20,000.00 | $ 20,000.00 |
| 2 | Shoring Porch Roof | 1 | LS | $ 12,500.00 | $ 12,500.00 |
| Total | | | | | $ 32,500.00 |
| 03 | Concrete | | Quantity | Unit | Cost / Unit | Total |
| 1 | Concrete Slab on Grade, 4" thick, reinforced | 235 | SF | $ 23.27 | $ 5,468.45 |
| 2 | Concrete Slab on Grade, 6" thick, reinforced (Generator Pad) | 36 | SF | $ 34.90 | $ 1,256.40 |
| 3 | Concrete Slab on Grade, 6" thick, (Wellhead) | 36 | SF | $ 34.90 | $ 1,256.40 |
| 4 | Formed turn-down vertical edge, earthen bottom and inside slope | 43 | LF | $ 116.22 | $ 4,997.46 |
| 5 | Concrete Crack Repair | 56 | LF | $ 225.00 | $ 12,600.00 |
| 6 | 4-inch Concrete Bollard | 8 | EA | $ 175.00 | $ 1,400.00 |
| Total | | | | | $ 26,978.71 |
| 05 | Metals | | Quantity | Unit | Cost / Unit | Total |
| 1 | Cut in Lintel Metals Work | 1 | LS | $ 500.00 | $ 500.00 |
| Total | | | | | $ 500.00 |
| 06 | Wood and Plastic Products | | Quantity | Unit | Cost / Unit | Total | | |
| 1 | Porch Posts 4x4 | 24 | LF | $ 48.09 | $ 1,154.16 | | |
| 2 | Wood Roof Beam 4x8 at Porch | 32 | LF | $ 63.57 | $ 2,034.24 | | |
| 3 | Double Door Base Cabinet w/ Drawers - 30" Wide | 1 | EA | $ 910.97 | $ 910.97 | | |
| 4 | Double Door Base Cabinet w/ Drawers - 45" Wide | 1 | EA | $ 1,108.52 | $ 1,108.52 | | |
| 5 | Base Cabinet w/ Drawers - 24" Wide | 1 | EA | $ 687.24 | $ 687.24 | | |
| 6 | Sink Base Cabinet (Kitchen) - 33" Wide | 1 | EA | $ 890.76 | $ 890.76 | | |
| 7 | Sink Base Cabinet (Toilet Room) - 36" Wide | 1 | EA | $ 740.93 | $ 740.93 | | |
| 8 | Wall Cabinet - 48" Wide | 1 | EA | $ 990.00 | $ 990.00 | | |
| 9 | Wall Cabinet - 24" Wide | 1 | EA | $ 454.82 | $ 454.82 | | |
| 10 | Tall Cabinet - 30" Wide x 78" High | 1 | EA | $ 1,290.00 | $ 1,290.00 | RS Means Cost / Unit (Hide) | RS Means % Increase (Hide) |
| 11 | Countertop - Plam | 15 | LF | $ 344.22 | $ 5,163.30 | $ 664.32 | $ 863.62 |
| Total | | | | | $ 15,424.94 | $ 440.97 | $ 573.26 |
| 07 | Thermal and Moisture Protection | | Quantity | Unit | Cost / Unit | Total | | |
| 1 | Gutters | 70 | LF | $ 20.16 | $ 1,411.20 | $ 5.39 | $ 80.85 |
| 2 | Downspouts | 40 | LF | $ 22.40 | $ 896.00 | $ 2.10 | $ 31.50 |
| 3 | Standing seam roof - patch | 8 | SF | $ 18.75 | $ 150.00 | $ 2.10 | $ 31.50 |
| Total | | | | | $ 2,457.20 | | |
| 08 | Openings | | Quantity | Unit | Cost / Unit | Total | $ 0.25 | $ 12.50 |
| 1 | Interior Door - Wood, 2'-0" X 6'-8" | 2 | EA | $ 627.00 | $ 1,254.00 | RS Means Cost / Unit (Hide) | RS Means % Increase (Hide) |
| 2 | Interior Door - Wood, 2'-6" X 6'-8" | 1 | EA | $ 712.50 | $ 712.50 | | |
| 3 | Exterior Door - Hollow Metal Door and Frame, 3'-0" X 7'-0" | 2 | EA | $ 1,375.00 | $ 2,750.00 | $ 261.93 | $ 340.51 |
| 4 | Exterior Door - Screen Door, 3'-0" X 7'-0" | 1 | EA | $ 725.27 | $ 725.27 | | |
| 5 | Door Hardware - Interior | 3 | EA | $ 366.36 | $ 1,099.08 | | |
| 6 | Door Hardware - Exterior | 2 | EA | $ 795.86 | $ 1,591.72 | | |
| 7 | Window Aluminum Slider, 2'-0" X 3'-0" | 1 | EA | $ 578.94 | $ 578.94 | | |
| 8 | Window Aluminum Slider, 4'-0" X 3'-0" | 3 | EA | $ 728.54 | $ 2,185.62 | | |
| 9 | Window Aluminum Slider, 6'-0" X 3'-0" | 1 | EA | $ 878.48 | $ 878.48 | | |
| Total | | | | | $ 12,378.05 | | |
| | | | | | | RS Means Cost / Unit (Hide) | RS Means % Increase (Hide) |
| 09 | Finishes | | Quantity | Unit | Cost / Unit | Total | $ 218.80 | $ 284.44 |
| Ceilings | | | | | | $ 4.00 | $ 5.20 |
| 1 | 5/8" Gypsum Board | 765 | SF | $ 4.44 | $ 3,396.60 | | |
| 2 | Batt Insulation (3 1/2") | 750 | SF | $ 1.75 | $ 1,312.50 | | |
| 3 | Paint - Ceilings | 765 | SF | $ 0.64 | $ 489.60 | $ 4.00 | $ 5.20 |
| Walls & Finishes | | | | | | $ 4.00 | $ 5.20 |
| 4 | Perimeter Furring 5/8" Gypsum Board on wd studs 2"x4", 24" O.C. w/ batt insulation | 548 | SF | $ 10.19 | $ 5,584.12 | $ 4.00 | $ 5.20 |
| 5 | Partition Wall Patch and Fill (gypsum board) | 40 | SF | $ 6.90 | $ 276.00 | $ 4.00 | $ 5.20 |
| 6 | Masonry Wall Patch and Fill | 2 | SF | $ 41.36 | $ 82.72 | | |
| 7 | Painting - Walls (interior gypsum board) | 533 | SF | $ 1.70 | $ 906.10 | | |
| 8 | Painting - Walls (interior CMU walls) | 492 | SF | $ 5.00 | $ 2,460.00 | | |
| 9 | Painting - Exterior Wood Posts | 70 | SF | $ 1.50 | $ 105.00 | $ 8.59 | $ 11.17 |
| 10 | Painting - Walls (exterior CMU walls) | 776 | SF | $ 3.75 | $ 2,910.00 | | |
| 11 | Painting - Walls (exterior wood siding) | 206 | SF | $ 2.50 | $ 515.00 | | |
| 12 | Resilient Rubber Base (casework base) | 20 | SF | $ 12.51 | $ 250.20 | | |
| Floors | | | | | | $ 4.83 | $ 6.28 |
| 13 | Resinous/Epoxy Flooring | 840 | SF | $ 15.00 | $ 12,600.00 | | |
| Total | | | | | $ 30,887.84 | $ 12.38 | $ 16.09 |
| 10 | Specialties | | Quantity | Unit | Cost / Unit | Total | $ 4.63 | $ 6.02 |
| Toilet Accessories | | | | | | RS Means Cost / Unit (Hide) | RS Means % Increase (Hide) |
| 1 | Toilet accessories, medicine cabinet | 1 | EA | $ 600.00 | $ 600.00 | $ 88.25 | $ 114.73 |
| Shower Accessories | | | | | | $ 172.70 | $ 224.51 |
| 2 | Shower accessories, robe hook | 1 | EA | $ 37.47 | $ 37.47 | $ 421.60 | $ 548.08 |
| 3 | Allowance for Miscellaneous Metals | 1 | LS | $ 200.00 | $ 200.00 | $ 28.82 | $ 37.47 |
| Total | | | | | $ 837.47 | | $ - 0 |
| 11 | Equipment | | Quantity | Unit | Cost / Unit | Total | | |
| 1 | 30" Gas Range/Oven | 1 | EA | $ 937.50 | $ 937.50 | $ 440.97 | $ 573.26 |
| Sbho | | | | | $ 937.50 | $ 157.61 | $ 204.89 |
| 22 | Plumbing | | Quantity | Unit | Cost / Unit | Total | $ 157.61 | $ 204.89 |
| 1 | ADA Shower, Pan insert and Accessories | 1 | EA | $ 1,626.50 | $ 1,626.50 | | |
| 2 | Tankless Propane Water Heater | 1 | EA | $ 2,500.00 | $ 2,500.00 | | |
| 3 | Water Closets | 1 | EA | $ 904.14 | $ 904.14 | | |
| 4 | Lavatories | 1 | EA | $ 465.62 | $ 465.62 | | |
| 5 | Kitchen Sink | 1 | EA | $ 815.84 | $ 815.84 | | |
| 6 | Shower valve | 1 | EA | $ 634.90 | $ 634.90 | | |
| 7 | Shower enclosure | 1 | EA | $ 1,500.00 | $ 1,500.00 | | |
| 8 | Floor Drains | 2 | EA | $ 468.11 | $ 936.22 | | |
| 9 | Piping | 175 | LF | $ 71.06 | $ 12,435.50 | | |
| 10 | Sanitary piping below grade | 75 | LF | $ 88.52 | $ 6,639.00 | | |
| 11 | Sanitary/vent piping above grade | 60 | LF | $ 91.64 | $ 5,498.40 | | |
| 12 | Gas piping | 95 | LF | $ 30.42 | $ 2,889.90 | | |
| 13 | Heat Trace | 175 | LF | $ 19.32 | $ 3,381.00 | $ 656.04 | $ 852.85 |
| 14 | Booster Pump | 1 | EA | $ 1,050.00 | $ 1,050.00 | $ 656.04 | $ 852.85 |
| Total | | | | | $ 41,277.02 | $ 656.04 | $ 852.85 |
| 23 | Heating, Ventilation and Air Conditioning | | Quantity | Unit | Cost / Unit | Total |
| 1 | Propane furnace | 1 | EA | $ 8,100.00 | $ 8,100.00 |
| 2 | Exhaust fan | 2 | EA | $ 1,480.00 | $ 2,960.00 |
| 3 | Ductwork | 100 | LF | $ 21.00 | $ 2,100.00 |
| 4 | Return Grilles | 3 | EA | $ 368.77 | $ 1,106.31 |
| 5 | Supply Registers | 9 | EA | $ 157.41 | $ 1,416.69 |
| 6 | Flue piping/vent | 40 | LF | $ 80.37 | $ 3,214.80 |
| 7 | Evaporative Cooler | 1 | EA | $ 4,850.00 | $ 4,850.00 |
| 9 | Kitchen hood exhaust and termination | 1 | EA | $ 940.00 | $ 940.00 |
| Total | | | | | $ 24,687.80 |
| 26 | Electrical and Lighting | | Quantity | Unit | Cost / Unit | Total |
| 1 | 4kW PV System w/ 6kWH Battery | 1 | EA | $ 39,540.00 | $ 39,540.00 |
| 2 | Generator | 1 | EA | $ 9,150.00 | $ 9,150.00 |
| 3 | Site work, feeder to Bunkhouse | 1 | EA | $ 9,912.00 | $ 9,912.00 |
| 4 | Power distribution panels - bunkhouse bldg | 1 | EA | $ 14,410.00 | $ 14,410.00 |
| 5 | Bunkhouse general power and mechanical connections | 1 | EA | $ 7,470.00 | $ 7,470.00 |
| 6 | Bunkhouse lighting | 1 | EA | $ 6,779.00 | $ 6,779.00 |
| Total | | | | | $ 87,261.00 |
| 31 | Earthwork | | Quantity | Unit | Cost / Unit | Total | |
| 1 | Earthwork removal under porch slab and footing | 21 | CY | $ 50.00 | $ 1,050.00 | |
| 2 | Unclassified Excavation | 50 | CY | $ 65.00 | $ 3,250.00 | |
| 3 | Structural Backfill | 64 | CY | $ 200.00 | $ 12,800.00 | |
| 4 | Site Clearing | 0.5 | ACRE | $ 8,500.00 | $ 4,250.00 | 0 |
| 5 | Trench and Backfill of Exposed Waterline | 200 | LF | $ 16.00 | $ 3,200.00 | 0 |
| Total | | | | | $ 24,550.00 | |
| 33 | Utilities | | Quantity | Unit | Cost / Unit | Total |
| 1 | 1 1/4-inch HDPE Pipe | 260 | LF | $ 35.48 | $ 9,224.80 |
| 2 | 1 1/4-inch Gate Valve and Box | 6 | EA | $ 195.31 | $ 1,171.86 |
| 3 | 1 1/4-inch Check Valve | 2 | EA | $ 106.25 | $ 212.50 |
| 4 | 1 1/4-inch Drain Valve | 1 | EA | $ 195.31 | $ 195.31 |
| 5 | Yard Hydrant | 1 | EA | $ 552.98 | $ 552.98 |
| 6 | Factory Coated Welded Steel Water Storage Tank | 1 | EA | $ 45,000.00 | $ 45,000.00 |
| 7 | Submersible Well Pump, Motor and Power Supply | 1 | LS | $ 7,800.00 | $ 7,800.00 |
| 8 | Tank Equipment and Appurtenances | 1 | LS | $ 500.00 | $ 500.00 |
| 9 | 3/4-inch Polyethylene Pipe | 22 | LF | $ 35.12 | $ 772.64 |
| 10 | Relocate Propane Tank | 1 | LS | $ 4,750.00 | $ 4,750.00 |
| 11 | 12"x18"X24" Handhole Box | 5 | EA | $ 450.00 | $ 2,250.00 |
| 12 | 1" Sch80 PVC Conduit | 1900 | LF | $ 12.00 | $ 22,800.00 |
| Total | | | | | $ 95,230.09 |
| Construction Cost Sub-Total | | | | | $ 455,907.62 |