Sol_140L6422R0002_Amd_0002.pdf
PDF 149 KB Posted
- Attached to
- OAK GROVE BUNKHOUSE RENOVATIONS
- Solicitation number
- 140L6422R0002
About this file
This request for proposal concerns renovations to the Oak Grove Bunkhouse-Administrative Station/Bunkhouse facility. The Bureau of Land Management Arizona State Office requires replacing existing mechanical and electrical systems, plumbing fixtures, interior finishes, and upgrading the well and water storage capacity from 3,000 to 10,000 gallons. The performance period may be extended up to 180 days. Questions are due by January 14, 2022 and proposals are due January 24, 2022. This is a small business set-aside awarded under NAICS code 237990 with a size standard of $39.5 million. The selected contractor will be responsible for construction power and haul-off of debris since no dumping facilities are nearby.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Geotechnical_Engineering_Report_0002.pdf | ||
| Project_Specifications_0001.pdf | ||
| Sol_140L6422R0002_Amd_0001.pdf | ||
| Pricing_Worksheet.xlsx | XLSX spreadsheet | |
| Construction_Plans.pdf | ||
| DOL_Wage_Determination.pdf | ||
| Sol_140L6422R0002.pdf | ||
| Past_Performance_Questionnaire.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L6422R0002 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LZA
PHOENIX AZ 85004
ONE N. CENTRAL AVE, SUITE 800
BLM AZ-STATE OFC ADMN SVCS(AZ951)
01/13/20220002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
12/13/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
A. The purpose of this amendment is to provide the goverment's responses to the questions recieved.
B. A Geotechnical Engineering Report has been made available.
C. The proposal due date has been extended to Monday, January, 24 2022 at 1000 (MST).
D. All other terms and conditions remain unchanged.
Period of Performance: 03/01/2022 to 08/01/2022
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Christopher Jordan
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
SF-30 CONTINUATION PAGE
GOVERNMENT'S RESPONSES TO CONTRACTOR'S QUESTIONS
1. The performance period listed in box 11 of the 1442 states that construction must be completed 100 calendar days after receiving the notice to proceed. There is a substantial amount of work by multiple trades as well as lead time issues that may affect delivery of critical materials. Can the performance period be extended to accommodate the above-mentioned concerns?
The BLM will extend the period of performance up to 180 calendar days to accommodate these concerns.
2. The question due date and the solicitation due date on page 4 of 22 of the solicitation do not appear to match the days of the week. Please clarify.
The Government will accept questions, in writing, no later than January 14, 2021, at 12:00pm (MST). The Government reserves the right to not answer questions submitted after this time.
3. Due to the site being located so far from any town, will the contractor be able to bring trailers for housing staff during construction durations?
This would depend on where the trailers would be housed on site and for how long. There would not be any place or room to hook up multiple trailers for multiple nights. This is something that we will have to review, and adjustments made, as necessary.
4. Is the government anticipating that all under slab plumbing is to remain and be tied into with new above slab plumbing and fixtures?
Yes, new fixtures are to be tied into the under-slab plumbing.
5. The note on sheet C301 states to "refer to sheet P002 for tank details." Sheet P002 could not be found.
Please provide.
The correct sheet number for the details is Sheet CP002 (Sheet 4/42)
6. The drawings to not identify which areas of the building have an existing ceiling that will need to be demolished. Please clarify.
All existing ceilings should be demolished. The intent is to remove and replace existing ceilings and blanket insulation while performing the work to install new electrical and mechanical systems.
7. Please provide information regarding the construction of the existing interior walls that are to remain such as depth, material, finish etc.
Existing interior partition walls are 2x wood frame construction with gypsum sheathing.
8. Are the restroom facilities/ septic system on site currently operational so that it can be utilized during the project by on site contractors?
Facilities are currently operational, but water will be tuned on and off intermittently during water line construction, so contractors may want to bring up portable restrooms as a back-up for periods of time and construction when the water is off.
9. Please clarify what piping shown on sheet C302 is to be reused with the new well pump.
Contractor to is to remove and replace existing well pump. Interior plumbing to remain.
10. Please provide required depth of new 1¿ conduit and HDPE water lines as well as a trench detail showing backfill requirements. Please not that backfilling with non-native material will add substantial costs due to the remote location.
Per Section 331100 - Water Distribution Systems, Part 3,3.1(A)(1) - Provide a minimum of 3 feet of cover over pipe.
Typical trench section is 6-inches of bedding; 12-inches of initial backfill; 24-inches, or more as required of final backfill. Refer to Section 312000 - Earthmoving for material requirements.
11. Will compaction tests be required by third party inspector? Please note that this will add substantial costs due to the remote location.
Yes. Refer to Section 331100 - Water Distribution Systems, Part 3(3.18)(B)
12. Please confirm that the 36" CMP, course aggregate and lid shown on sheet C302 are all existing and will not require any removal and replacement by the contractor.
Existing well structure is to remain in place, with exception of exterior concrete pad, which is to be removed and replaced.
13. Is water available on site that can be utilized for construction purposes?
Water is only available from the well, and the well is being upgraded removed/replaced from its current 3,000 Gallon capacity tank to a 10,000 Gallon capacity tank. So the contractors will need to provide water for construction purposes (concrete, mixing, dust control, etc.).
14. Specification section 011000 paragraph 1.4.A.1 references a radio communication system in the contractor¿s work. A radio communication system could not be found anywhere else in the specifications.
Please advise.
Reference in Part 1 (1.4)(A)(1) regarding radio communication system can be deleted. The original design intent was to have a radio telemetry system between well and tank. The design is now hard-wired.
15. Please provide thickness of existing concrete slab that is to be removed as well as clarify if it can remain on site or will need to hauled off to a landfill.
Actual slab thickness is unknown at this time. Existing concrete slab is assumed to be 4-inches.
Refer to Section 017419 - Construction Waste Management and Disposal Part 3(3.1).
16. Is there any existing furniture or equipment within the building that will need to be removed and reinstalled by the contractor?
There are existing furnishings, a wood burning stove, and various appliances that will need to be removed.
The Arizona Strip District Office (ASDO) should determine how to reuse or dispose of any items under this category. Contractors will be responsible for haul-off of construction waste/rubble/debris as there is no dumping, reclamation, or recycling facility available on or near the site
17. Specification section 01500 calls for a site enclosure fence to be installed to enclose the entire project site. Please confirm that this is not applicable to this project.
Per Section 015000 - Temporary Facilities and Controls Part 3(3.4)(F)(1) the extent of the fence shall be the entire or portion determined sufficient to accommodate construction operations. This shall be based on the Contractor¿s means, methods, sequences, and schedule, as well as his risk.
18. Please confirm that a professional land surveyor will not be required under this contract.
Per State of Arizona regulations, a professional land surveyor is required for construction staking.
19. Due to the distance of the project from a concrete batch plant, the concrete will need to be mixed on site. Please confirm this is acceptable.
On-site mixing of concrete is acceptable, as long as the mix design requirements are maintained. Third-party inspection remains a requirement. This is acceptable as there is no other water available on-site. (See Question 13 response).
20. Will any additional framing be required for the new drywall ceiling? Please advise.
Additional framing is not expected to be required. Replacement of gypsum ceilings does not require additional framing.
21. Please provide height of existing and future ceilings in all rooms.
Height of existing / future ceilings: 8'- 0' AFF. Ceilings are fastened to structure above. (See sheet A421 for confirmation of all interior ceiling heights)
22. Has an in-situ moisture test of the existing concrete slab been performed to determine the moisture content?
Not to our knowledge. Selected contractor shall perform the in-situ test for moisture content prior to and after final construction and share results with ASDO.
23. Please clarify if is any current coating or sealer on the existing concrete that is to receive resinous flooring.
Not to our knowledge.
24. Are there any saw cuts, expansion joints or excessive cracks in the existing slab in excess of the 56 lineal feet included in the cost estimate breakdown?
Not to our knowledge.
25. The contract is being issues as a lump sum however the pricing worksheet represents the project as a unit price contract. Please advise how pricing will be addressed if quantities exceed those shown in the pricing worksheet.
The pricing worksheet will be used to assist in evaluating contractor¿s proposals to see how they plan on doing the work in conjunction with the schedule.
26. Can photos of the interior and exterior of the building be provided showing condition of existing floor, walls, and ceilings?
Images of existing conditions are available. Photos are available to be emailed upon request.
27. Is there any power available on site or will the contractor be responsible for suppling a temporary generator during construction?
Contractor will be responsible for supplying construction power.
28. Please provide size and type of chip media found in section 096723 paragraph 3.1.E.2.
Per manufacturers recommendations.