Preliminary Schedule.pdf

PDF 160 KB Posted

Attached to
Request for Subcontractor Qualifications for Iowa DOT Donnellson MBW & Salt Structure
Solicitation number
645-RFQW-2598-2026
Issued by
Jasper County, Iowa

About this file

This is a Preliminary Schedule document for the Iowa Department of Transportation (Iowa DOT) Donnellson project, prepared as a master schedule for construction activities spanning from January 2026 through June 2027. The project encompasses multiple construction phases including procurement, constructability review, trade package preparation, bid package issuance, GMP preparation, submittal activities, and full construction execution. Key project milestones include Notice to Proceed scheduled for May 15, 2026, with construction activities commencing June 15, 2026, and Substantial Completion targeted for May 17, 2027. The schedule details 79 distinct activities with identified predecessor and successor relationships, resource dependencies, and critical path sequencing. Major construction components include the Salt Structure, Brine Tank Structure, and MBW Building, with activities spanning site mobilization, earthwork, utilities, structural installation, mechanical-electrical-plumbing systems, interior finishes, and final completion by June 7, 2027. The schedule indicates current progress as of March 10, 2026, with procurement activities at 20.69% completion and Trade Packages Front End & Estimation at 100% completion.

The schedule establishes a comprehensive 276-day construction period beginning May 15, 2026, with sequential phasing of major work packages including foundations, structural elements, roofing, and finishing trades. Punchlist activities are scheduled for a 15-day period following Substantial Completion, with Final Completion marking project conclusion on June 7, 2027. The document does not disclose pricing information, funding sources, set-asides, or incumbent vendor details. No specific contract values, budget allocations, or financial terms are contained within the preliminary schedule document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2025 2026 2027

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

DOT Donnellson Master Schedule

Procurement

Constructability Review

Trade Packages, Front End & Estimation

Bid Package Invites/RFP

GMP Preparation & Execution

Submittal Activity

Construction

Notice to Proceed

Mobilize

Salt Structure

Earthwork & Utilities

Install Granular Fill

Precast Barrier Install

Foundations, Posts & Bollards

Joint and Paint Barriers

Install Woodframe

Install Siding

Install Concrete

OH Door

Punch

Brine Tank Structure

Earthwork & Utilities

Footings and Foundations

SOG

MEP

MBW Building

Earthwork and Utilities

Footings & Foundations

Precast Walls

Steel Roof Structure

Roofing

Underground MEP

Interior SOG

Today: 10 Mar

# Activity Start Duration End Progress Predecessors Successors

0 01/13/26 365 days 06/07/27 3.57%DOT Donnellson Master Schedule

1 01/13/26 76 days 04/28/26 20.69%Procurement

2 03/03/26 20 days 03/30/26 0.00%Constructability Review

7 01/13/26 33 days 02/27/26 100.00% 18fs+23dTrade Packages, Front End & Esti…

13 03/11/26 35 days 04/28/26 0.00%Bid Package Invites/RFP

21 04/29/26 11 days 05/13/26 0.00%GMP Preparation & Execution

26 05/14/26 130 days 11/11/26 0.00%Submittal Activity

38 05/15/26 276 days 06/07/27 0.00%Construction

39 05/15/26 0 days 05/15/26 0.00% 25fs+2d 40fs+20dNotice to Proceed

40 06/15/26 2 days 06/16/26 0.00% 39fs+20d 42fs+0d;53fMobilize

41 06/17/26 68 days 09/18/26 0.00% 77fs+0dSalt Structure

42 06/17/26 5 days 06/23/26 0.00% 40fs+0d 43fs+0dEarthwork & Utilities

43 06/24/26 5 days 06/30/26 0.00% 42fs+0d 44fs+0dInstall Granular Fill

44 07/09/26 3 days 07/13/26 0.00% 43fs+0d;33fs+10d 45fs+0dPrecast Barrier Install

45 07/23/26 7 days 07/31/26 0.00% 34fs+0d;44fs+0d 47fs+0dFoundations, Posts & Bollards

46 09/07/26 5 days 09/11/26 0.00% 49fs+0d 51fs+0dJoint and Paint Barriers

47 08/03/26 10 days 08/14/26 0.00% 45fs+0d 48fs+0dInstall Woodframe

48 08/17/26 10 days 08/28/26 0.00% 47fs+0d 49fs+0dInstall Siding

49 08/31/26 5 days 09/04/26 0.00% 48fs+0d 46fs+0d;50fInstall Concrete

50 09/07/26 2 days 09/08/26 0.00% 49fs+0d 51fs+0dOH Door

51 09/14/26 5 days 09/18/26 0.00% 46fs+0d;50fs+0dPunch

52 08/26/26 50 days 11/03/26 0.00% 77fs+0dBrine Tank Structure

53 08/26/26 5 days 09/01/26 0.00% 58sf+0d;40fs+3d 54fs+0dEarthwork & Utilities

54 09/02/26 25 days 10/06/26 0.00% 53fs+0d 55fs+0dFootings and Foundations

55 10/07/26 5 days 10/13/26 0.00% 54fs+0d 56fs+0dSOG

56 10/14/26 15 days 11/03/26 0.00% 55fs+0dMEP

57 09/02/26 184 days 05/17/27 0.00% 77fs+0dMBW Building

58 09/02/26 15 days 09/22/26 0.00% 27fs+0d;40fs+55d 53sf+0d;59fEarthwork and Utilities

59 09/23/26 25 days 10/27/26 0.00% 58fs+0d 60fs+0dFootings & Foundations

60 11/12/26 10 days 11/25/26 0.00% 59fs+0d;37fs+0d 61fs+0dPrecast Walls

61 11/26/26 15 days 12/16/26 0.00% 60fs+0d 63fs+0d;62fSteel Roof Structure

62 12/17/26 10 days 12/30/26 0.00% 61fs+0dRoofing

63 12/17/26 15 days 01/06/27 0.00% 61fs+0d 64fs+0dUnderground MEP

64 01/07/27 8 days 01/18/27 0.00% 63fs+0d 68fs+0d;67fInterior SOG

25-140 IDOT Donnellson

Main Schedule

2025 2026 2027

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

# Activity Start Duration End Progress Predecessors Successors

General

Parent Activity

Child Activity

Baseline

(+# days) Delay

Milestone

Printed on: 03/10/26

Page: 1/2

Masonry Walls

OH Doors

Misc Metals

Bridge Crane

Exterior Concrete Approaches

Mezzanine Construction

MEP Rough Ins

Doors

Painting

Finish MEP

Misc Finishes

Bathroom Specialties

Substantial Completion

Punchlist

Final Completion

65 01/19/27 10 days 02/01/27 0.00% 64fs+0d 72ff+0d;70fMasonry Walls

66 01/19/27 8 days 01/28/27 0.00% 64fs+0d 69fs+53dOH Doors

67 02/23/27 10 days 03/08/27 0.00% 70fs+0d;64fs+0dMisc Metals

68 04/06/27 10 days 04/19/27 0.00% 71fs+0d;64fs+0dBridge Crane

69 04/14/27 5 days 04/20/27 0.00% 66fs+53dExterior Concrete Approaches

70 02/02/27 15 days 02/22/27 0.00% 65fs+0d 67fs+0d;71fMezzanine Construction

71 02/23/27 30 days 04/05/27 0.00% 70fs+0d 68fs+0d;73fMEP Rough Ins

72 01/26/27 5 days 02/01/27 0.00% 65ff+0d 73fs+0dDoors

73 04/06/27 5 days 04/12/27 0.00% 72fs+0d;71fs+0d 76fs+0d;74fPainting

74 04/13/27 20 days 05/10/27 0.00% 73fs+0d 75ff+0d;76fFinish MEP

75 04/20/27 15 days 05/10/27 0.00% 74ff+0dMisc Finishes

76 05/11/27 5 days 05/17/27 0.00% 74fs+0d;73fs+0dBathroom Specialties

77 05/17/27 0 days 05/17/27 0.00% 52fs+0d;57fs+0d;41fs 78fs+0dSubstantial Completion

78 05/18/27 15 days 06/07/27 0.00% 77fs+0d 79fs+0dPunchlist

79 06/07/27 0 days 06/07/27 0.00% 78fs+0dFinal Completion

25-140 IDOT Donnellson

Main Schedule

2025 2026 2027

Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

# Activity Start Duration End Progress Predecessors Successors

General

Parent Activity

Child Activity

Baseline

(+# days) Delay

Milestone

Printed on: 03/10/26

Page: 2/2