This is an addendum response document from the City of Seattle related to the Seattle City Hall Plaza Waterproofing Replacement project, addressing a contractor inquiry regarding damaged ceiling and wall finishes in the Red Room. The project involves a comprehensive restoration of the plaza at Seattle City Hall, located at 600 4th Ave, Seattle, WA 98104, including waterproofing, concrete decking, sub-grade interior repairs, landscaping, and the addition of one flagpole. In response to Question 19, which sought clarification on repair quantities and methods for damaged sheetrock noted on plan A106, the City provided specific scope guidance: removal and replacement of sheetrock at the south end of the Red Room with refinishing and painting as outlined in the accompanying photo, plus an additional 10 square feet of ceiling sheetrock replacement with refinishing and painting at the north end of the Red Room.
The project carries an Engineer's Estimate of $6,864,865.00 and is classified as a Covered Project subject to the City of Seattle's Community Workforce Agreement and Priority Hire requirements under SMC 20.37. These requirements mandate that contractors provide economic and employment opportunities to individuals from distressed communities, women, and people of color on the construction project. The project is supported by the mayor and City Council as part of the City's broader commitment to racial and economic equity through contracting initiatives. This rebid document, identified as PW#2026-029, serves to clarify bid specifications for prospective contractors preparing proposals for this significant civic infrastructure project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| REBID_PW#2025-029_Bid_Form.pdf | ||
| REBID_PW#2025-029_Drawings.pdf | ||
| REBID_PW#2025-029_Project_Manual.pdf | ||
| SCH_Tree_1_Transplant_TPP_Specifications.PDF |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question 1 9:
"Per the plan note on A106 Note in Red Room, contractor is required to replace damaged ceiling and wall finishes and paint to match, however no quantities or repair methods are given. Please provide an allowance amount for the quantity and type of repairs that are required here for bidding purposes."
Response:
Assume removal and replacement of sheetrock replacement at the south end of Red Room including refinishing and painting, outlined in yellow indicated in the photo above.
Assume replacement of 10 ft² of sheetrock at the ceiling including refinishing and painting at the north end of the Red Room (not shown).
PW#2026-029 SCH PLAZA WATERPROOFING REPLACEMENT ADDENDUM 3