Past Performance Questionnaire.pdf
PDF 123 KB Posted
- Attached to
- EEC Campus Improvements Federal contract opportunity
- Solicitation number
- 140P6421R0010
About this file
This document includes a past performance questionnaire template and details of a solicitation for EEC Campus Improvements at Cuyahoga Valley National Park. The solicitation seeks a firm-fixed price contract between $500,000 to $1 million for roof replacement, door and window replacement, siding repairs, painting, and gutter replacement. The National Park Service Midwest Region will evaluate proposals based on technical merit, past performance, and price. The NAICS code is 236115 for new commercial and institutional building construction, with a size standard of $39.5 million. The opportunity is reserved entirely for small businesses. The response deadline is not provided. Interested parties must register in SAM and complete online representations and certifications. The point of contact is Craig D Bryant of the National Park Service Ohio office.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised Specifications - EEC Campus Improvements_0003.pdf | ||
| Questions and Answers_0003.pdf | ||
| Sol_140P6421R0010_Amd_0003.pdf | ||
| Site Visit sign-in sheet_0002.pdf | ||
| Questions and Answers_0002.pdf | ||
| Sol_140P6421R0010_Amd_0002.pdf | ||
| Sol_140P6421R0010_Amd_0001.pdf | ||
| 140P6421R0010_0001.pdf | ||
| Past Performance Questionnaire.docx | DOCX document | |
| Sol_140P6421R0010.pdf | ||
| Technical Questionnaire.pdf | ||
| Technical Questionnaire.docx | DOCX document | |
| Bid Schedule - Campus Improvements.pdf | ||
| Wage Determination.pdf | ||
| Specifications - EEC Campus Improvements.pdf | ||
| COVID-19 Mask Policy.pdf | ||
| Notice to Contractors.pdf | ||
| Bid Schedule - Campus Improvements.xlsx | XLSX spreadsheet |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only/Source Selection Information Revised 26 May 2020 by Ohio MABO
Past Performance Questionnaire Project Name:
EEC Campus Improvements – Cuyahoga Valley National Park
Solicitation Number:
140P6421R0010
Contracting Point of Contact:
Craig D Bryant NPS – Ohio MABO 1113 W. Aurora Road Sagamore Hills, OH 44067 craig_bryant@nps.gov
Instructions:
1) The offeror is to complete only the information in Section A, then send the entire past performance questionnaire to project owner for completion.
2) The project owner (or reference) is to complete Section B, then send the entire past performance questionnaire back to the offeror to be provided with their complete proposal package, which will then be reviewed for evaluation.
3) The past performance questionnaire must be received by the contracting point of contact by the date and time specified in the solicitation (or any amendments). Please note that for electronic submissions, offerors should consider and account for potential delays in transmissions between when an electronic submission is submitted and when an electronic submission is received. Late past performance questionnaires will not be accepted.
4) One past performance questionnaire is to be used for each past performance project submitted. The offeror may submit between 3-5 past performance questionnaires for this solicitation. Past performance projects must have been completed within five years of the completion of performance of the evaluated contract or order.
Section A – To be completed by the offeror
The project information in Section A shall reference the past performance project, not the solicitation project. The description of the work performed must be sufficiently detailed for Government to make a determination of relevance in size, scope, and complexity of each project listed to the work described in this solicitation.
Offeror’s Company Name:
DUNS Number:
Project Name:
(Name of the past performance project)
Project Completion Date:
Project Value:
Description of the work completed by the offeror:
Describe the relevancy of the past performance project to the work required in the solicitation:
Section B – To be completed by the project owner (or reference)
The information provided by the project owner may be verified by contacting references as deemed necessary by the Government.
Project Owner Company Name or Department:
Project Owner Point of Contact:
Name and Title/ Position
Point of Contact Phone Number:
Point of Contact email Address:
Past Performance Rating Scale
Rating
Definition
Excellent
Performance considerably exceeded requirements/expectations.
Good
Performance exceeded requirements/expectations.
Satisfactory
Performance met the requirements/expectations. If any minor problems occurred, corrective actions taken by the contractor were satisfactory.
Marginal
Performance did not meet some contractual requirements and reflects a serious problem in the element being assessed.
Unsatisfactory
Did not meet requirements/expectations. The element being assessed contained a serious problem(s) for which the contractor’s corrective actions were ineffective.
Section B CONTINUED - To be completed by the project owner (or reference)
Past Performance Rating Select applicable rating
Ex ce lle nt
G oo d
Sa tis fa ct or y
M ar gi na l
U ns at is fa ct or y
N ot
A pp lic ab le
Quality of workmanship, including subcontractors work
Conformance with contract requirements
Resolved any issues that occurred
Management of overall project and subcontractors
Adhered to performance period, completed work on time
Responded to owner requests in a timely manner
Conducted business-like cooperation with the project owner and communicated well with all project shareholders – ie: provided documentation timely, ensured minimal errors in documentation, responsive to both owner and contracting office, etc.
Yes No Overall, the Project Owner was satisfied with the services performed for this project
Based on the experience with this contractor for this project, I would recommend them for similar contracts
Comments (may provide additional pages for comments):
Signature of Project Owner Point of Contact:
Once completed and signed, the project owner (or reference) is to submit the entire completed past performance questionnaire back to the offeror to be provided with their complete proposal package, which will then be reviewed for evaluation.
File details come from the government source that posted it. Updated .