PART 7.1_Performance Requirements.docx

DOCX document 18 KB Posted

Attached to
CERFP Baton Rouge, LA 1-7 April
Solicitation number
W912NR22R0014
Issued by

View the file

Other files

File Type Posted
Questions and Answers.docx DOCX document
PART 7.2_Deliverables Schedule.docx DOCX document
PWS FINAL.docx DOCX document
PART 7.3_Estimated Workload Data.docx DOCX document
PART 7.4_Role Players Information.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL EXHIBIT 7.1

PERFORMANCE REQUIREMENTS SUMMARY

The Contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

Standard
Performance Threshold

Method of Surveillance

PRS # 1

5.3.1 5.4

50 civilian casualty role players prepared to support LA CERFP SYCTE on 5-7 April in accordance with the PWS and Exhibit 7.4
NLT 0830 on each day of exercise
COR will inspect

PRS # 2

5.3.6

Criminal background check resulting in no felony offenses for any role player
Provided NLT one (1) day prior to first day of exercise
Delivered to COR

PRS # 3

5.6

Qualified IMT role players in accordance with the PWS and Exhibit 7.4
Certifications provided NLT one (1) day prior to first day of exercise
Delivered to COR

PRS # 4

5.8

SCVS is reset and ready for CERFP operations in accordance with the PWS
NLT one (1) hour prior to the start of each day’s exercise
COR will inspect

PRS # 5

5.8.2.6

Ten (10) new concrete breaching slabs, no less than 5ft X 5ft X 6in, with no less than 1/4" reinforced rebar
NLT the last day of the exercise, 7 April 2022
COR will inspect