P17PS00752_Solicitation.pdf
PDF 2 MB Posted
- Attached to
- CHOH 150819 Locks 5 to 22 Federal contract opportunity
- Solicitation number
- P17PS00752
About this file
Solicitation
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| SECTION_061300_-_HEAVY_TIMBER_CONSTRUCTION.pdf | ||
| Q&A_for_Amendment_000003.pdf | ||
| P17PS00752_Amendment_000003.pdf | ||
| photos_file_2.pdf | ||
| SECTION_061063_-_EXTERIOR_ROUGH_CARPENTRY.pdf | ||
| photos_file_1.pdf | ||
| P17PS00752_Amendment_000002.pdf | ||
| 080917_revised_specs_combined.pdf | ||
| Q&A_for_Amendment_000002.pdf | ||
| P17PS00752_Amendment_000001.pdf | ||
| P17PS00752_Drawings.pdf | ||
| P17PS00752_Specifications.pdf | ||
| B01_PRESOL_P17PS00752.pdf | ||
| A14_MktRes_Sources_Sought_CHOH_150819_Locks_5_to_22.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
EMAIL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
NPS, DSC Contracting Services Div
12795 W. Alameda Pkwy
P.O. Box 25287 Denver CO 80225-0287
PDS
NPS, DSC Contracting Services Division
12795 W. Alameda Pkwy PO Box 25287 Denver, CO 80225-0287
Heather Vogt
b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS) heather_vogt@nps.gov and pamela_mault@nps.gov
107/12/2017
P17PS00752
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
15 500 calendar days and complete it within ________________ ________________ calendar days after receiving
52.211-10
08/11/2017
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
The Subject Solicitation P17PS00752 requests proposals for a firm fixed price construction contract to rehabilitate locks 5 through 22 of the Chesapeake & Ohio Canal National Historic Park, MD.
NAICS Code 237990 - Size Determination $36.5M
This is a Full and Open Unrestricted Solicitation for a Firm Fixed Priced Construction Contract.
Offerors must comply with the requirements of 52.204-6, 52.204-7 and 52.204-8,52.232-33 through the System for Award Management (SAM) at http://www.sam.gov. SAM is free of charge for both registrants and users.
Estimated Magnitude of Construction: $5M-$10M.
Please see 52.236-27 ALT 1 for Site Visit Information.
x or Pamela Mault
CHOH 150819
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
NPS, DSC Contracting Services Div 12795 W. Alameda Pkwy
P.O. Box 25287 Denver CO 80225-0287
PDS
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
Invoice Processing Platform System US Department of Treasury http://www.ipp.gov
Solicitation Document No.
P17PS00752
Document Title
CHOH 150819 Locks 5 - 22
TABLE OF CONTENTS
PART I – THE SCHEDULE
SECTION A -- SOLICITATION, OFFER, & AWARD
SECTION B – SUPPLIES OR SERVICES AND PRICES
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
SECTION D – PACKAGING AND MARKING
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
SECTION F – DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
52.211-13 TIME EXTENSIONS (SEPT 2000)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.242-14 SUSPENSION OF WORK (APR 1984)
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (JUL 1996)
NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING SYSTEM (DEC 2015)
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM
(APR 2013)
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS .. 23
SPECIAL CLAUSE 2: KEY PERSONNEL
SPECIAL CLAUSE 3: SMALL BUSINESS PARTICIPATION
LIABILITY INSURANCE REQUIREMENTS
PART II – CONTRACT CLAUSES
SECTION I – CONTRACT CLAUSES
52.202-1 DEFINITIONS (NOV 2013)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBONTRACTOR SALES TO THE GOVERNMENT (SEPT 2006)
Document Title
CHOH 150819 Locks 5 - 22
52.203-7 ANTI-KICKBACK PROCEDURES (MAY 2014)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS (OCT
2010)
52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (OCT 2015)
52.203-14 DISPLAY OF HOTLINE POSTER(S) (OCT 2015)
DIAR 1403.1004
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS
OR STATEMENTS (JAN 2017)
1452.203-70 RESTRICTIONS ON ENDORSEMENTS (JUL 1996)
52.204-4 PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER
(MAY 2011)
52.204-9 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL (JAN 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(OCT 2016)
52.204-13 SYSTEM FOR AWARD MANAGEMENT MAINTENANCE (OCT 2016)
52.204-14 SERVICE CONTRACT REPORTING REQUIREMENTS (OCT 2016)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)
52.209-6 PROTECTING THE GOVERNMENT’S INTEREST WHEN SUBCONTRACTING WITH
CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT (OCT 2015)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (JUL 2013)
52.209-10 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS (NOV 2015)
52.210-1 MARKET RESEARCH (APR 2011)
52.215-2 AUDIT AND RECORDS—NEGOTIATION (OCT 2010)
1452.215-70 EXAMINATION OF RECORDS BY THE DEPARTMENT OF THE INTERIOR (APR 1984) .. 54
52.215-8 ORDER OF PRECEDENCE—UNIFORM CONTRACT FORMAT (OCT 1997)
52.215-11 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA—
MODIFICATIONS (AUG 2011)
52.215-13 SUBCONTRACTOR CERTIFIED COST OR PRICING DATA—MODIFICATIONS (OCT 2010)
Document Title
CHOH 150819 Locks 5 - 22
52.215-15 PENSION ADJUSTMENTS AND ASSET REVERSIONS (OCT 2010)
52.215-17 WAIVER OF FACILITIES CAPITAL COST OF MONEY (OCT 1997)
52.215-18 REVERSION OR ADJUSTMENT OF PLANS FOR POSTRETIREMENT BENEFITS (PRB)
OTHER THAN PENSIONS (JUL 2005)
52.215-19 NOTIFICATION OF OWNERSHIP CHANGES (OCT 1997)
52.215-21 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA AND DATA OTHER THAN
CERTIFIED COST OR PRICING DATA—MODIFICATIONS (OCT 2010)
52.219-4 NOTICE OF PRICE EVALUATION PREFERENCE FOR HUBZONE SMALL BUSINESS
CONCERNS (OCT 2014)
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (NOV 2016)
52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (JAN 2017) ALTERNATE II (NOV 2016)
52.219-16 LIQUIDATED DAMAGES—SUBCONTRACTING PLAN (JAN 1999)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013)
52.222-3 CONVICT LABOR (JUN 2003)
52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION
(MAY 2014)
52.222-6 CONSTRUCTION WAGE RATE REQUIREMENTS (MAY 2014)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (MAY 2014)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION—DEBARMENT (MAY 2014)
52.222-13 COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED
REGULATIONS (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APRIL 2015)
52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APRIL
2015)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)
52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014)
Document Title
CHOH 150819 Locks 5 - 22
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
(DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (MARCH 2015)
52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION (OCT 2015)
52-222-55 MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 (DEC 2015)
52.222-60 PAYCHECK TRANSPARENCY (EXECUTIVE ORDER 13673) (OCT 2016)
52.222-61 ARBRITRATION OF CONTRACTOR EMPLYEE CLAIMS (EXECUTIVE ORDER 13673) (DEC
2016)
52.222-62 PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 (JAN 2017)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION (SEP 2013)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-
DESIGNATED PRODUCTS—ALTERNATE I (MAY 2008)
52.223-15 ENERGY EFFICIENCY IN ENERGY-CONSUMING PRODUCTS (DEC 2007)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND
CONSTRUCTION CONTRACTS (MAY 2008)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
(AUG 2011)
52.224-1 PRIVACY ACT NOTIFICATION (APR 1984)
52.224-2 PRIVACY ACT (APR 1984)
52.224-3 PRIVACY TRAINING (JAN 2017)
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT (DEC
2007)
52.227-4 PATENT INDEMNITY—CONSTRUCTION CONTRACTS (DEC 2007)
52.227-17 RIGHTS IN DATA – SPECIAL WORKS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE—WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-11 PLEDGES OF ASSETS (JAN 2012)
52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS (MAY 2014)
Document Title
CHOH 150819 Locks 5 - 22
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.228-15 PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION (OCT 2010)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2014)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT
(JUL 2013)
52.232-39 UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS
(DEC 2013)
52.233-1 DISPUTES (MAY 2014)—ALTERNATE I (DEC 1991)
52.233-3 PROTEST AFTER AWARD (AUG 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-1 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
1452.236-70 PROHIBITION AGAINST USE OF LEAD-BASED PAINT (JUL 1996)
Document Title
CHOH 150819 Locks 5 - 22
52.242-5 PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (JAN 2017)
52.242-13 BANKRUPTCY (JUL 1995)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (JAN 2017)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING—CONSTRUCTION (OCT 2015)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012)—
ALTERNATE I (SEPT 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
PART III – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
SECTION J – LIST OF ATTACHMENTS
PART IV – REPRESENTATIONS AND INSTRUCTIONS
SECTION K – REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS .. 145
52.203-18 PROHIBITION ON CONTRACTING WITH ENTITIES THAT REQUIRE CERTAIN INTERNAL
CONFIDENTIALITY AGREEMENTS OR STATEMENTS—REPRESENTATION (JAN 2017)
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2017)
52.204-17 OWNERSHIP OR CONTROL OF OFFEROR (JUL 2016)
52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC
2014)
52.204-20 PREDECESSOR OF OFFEROR (JUL 2016)
52.209-2 PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS—REPRESENTATION (NOV 2015)
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (JUL 2013)
52.209-11 REPRESENTATION BY CORPORATIONS REGARDING DELINQUENT TAX LIABILITY OR A
FELONY CONVICTION UNDER ANY FEDERAL LAW (FEB 2016)
52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999)
52.223-22 PUBLIC DISCLOSURE OF GREENHOUSE GAS EMISSIONS AND REDUCTION GOALS-
REPRESENTATION (DEC 2016)
SECTION L – INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2016)
52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING (JUL 2016)
52.204-22 ALTERNATE LINE ITEM PROPOSAL (JAN 2017)
52.211-6 BRAND NAME OR EQUAL (AUG 1999)
Document Title
CHOH 150819 Locks 5 - 22
52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION (JAN 2017)
52.215-16 FACILITIES CAPITAL COST OF MONEY (JUN 2003)
1452.215-71 USE AND DISCLOSURE OF PROPOSAL INFORMATION—DEPARTMENT OF THE
INTERIOR (APR 1984)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY
2014)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS (MAY 2014)
52.228-1 BID GUARANTEE (SEP 1996)
1452.233-2 SERVICE OF PROTEST DEPARTMENT OF THE INTERIOR (SEPT 2006) (DEVIATION)
(JUL 1996)
52.236-27 SITE VISIT (CONSTRUCTION) – ALTERNATE I (FEB 1995)
52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION (OCT 1997)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
SECTION M – EVALUATION FACTORS FOR AWARD
SPECIAL PROVISION 1: EVALUATION OF OPTIONS
Document Title
CHOH 150819 Locks 5 - 22
PART I – THE SCHEDULE
SECTION A -- SOLICITATION, OFFER, & AWARD
Solicitation, Offer, and Award (SF-1442) - pages 1- 2 of this package
Document Title
CHOH 150819 Locks 5 - 22
SECTION B – SUPPLIES OR SERVICES AND PRICES
CONTRACT PRICE SCHEDULE
SOLICITATION NUMBER: P17PS00511
PARK - PMIS: CHOH - 150819
DEVELOPED AREA: Locks 5 - 22
PROJECT TITLE: Repair Watered Structures
Offeror: _______________________________
Offerors are required to submit, a minimum, an offer that c onforms to the solicitation documents. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars.
For the OPTION ITEMS, refer to SECTION H, SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE ITEMS and SECTION M, SPECIAL PROVISION 1: EVALUATION OF OPTIONS.
CONTRACT
LINE ITEM
NUMBER
(CLIN)
CONTRACT LINE ITEM (CLI) TITLE QUANTITY UNIT OF
MEASURE UNIT PRICE TOTAL PRICE
1 Repair MP 16.9 Breach (Base) 1 LS
2 Level 20 Bridge/Waste Weir (Base) 1 LS
3 Level 20 Canal Desilting (Base) 500 CY
4 Level 20 Canal Liner (Base) 10300 SF
5 Level 20 Stream Diversion Piping (Base) 1 LS
6 Level 20 Temporary Controls (Base) 1 LS
7 Level 20 New Stones for Walls (Base) 40 CY
Document Title
CHOH 150819 Locks 5 - 22
8 Level 20 Lean Concrete (Base) 20 CY
9 Lock 19 Bridge #1 Replacement (Base) 1 LS
10 Lock 19 Bridge #2 Replacement (Base) 1 LS
11 Lock 19 Gates (Base) 1 LS
12 Lock 19 Bridge New Stones (Base) 16 CY
13 Lock 19 Temporary Controls (Base) 1 LS
14 Lock 19 Repointing (Base) 800 LF
15 Lock 18 New Gates (Base) 1 LS
16 Lock 18 Repointing (Base) 1200 LF
17 Lock 18 Erosion Repair (Base) 1 LS
18 Lock 18 New Stones for Erosion Repair (Base) 30 CY
19 Lock 18 Temporary Controls (Base) 1 LS
20 Lock 17 New Gates (Base) 1 LS
21 Lock 17 Repointing (Base) 1100 LF
22 Lock 17 Temporary Controls (Base) 1 LS
23 Culvert 15 Liner System (Base) 14000 SF
24 Culvert 15 Repointing (Base) 500 LF
25 Culvert 15 Temporary Controls (Base) 1 LS
26 Rock Run Culvert (Base) 1 LS
27 Rock Run New Stones for Wall (Base) 260 CY
28 Rock Run Concrete Patch Repair (Base) 6 CY
29 Rock Run Stone Filler Repair (Base) 20 SF
30 Rock Run Liner System (Base) 9700 SF
31 Rock Run Temporary Controls (Base) 1 LS
Document Title
CHOH 150819 Locks 5 - 22
32 Lock 7 Waste Weir (Base) 1 LS
33 Lock 7 Fuseplug (Base) 1 LS
34 Lock 7 Temporary Controls (Base) 1 LS
TOTAL BASE PRICE (Contract Line Item Numbers 1 through 34)
35 Blockhouse Point Towpath Raising (Option A) 1643 LF
36 Blockhouse Point Reset Cap Stones (Option A) 260 LF
37 Blockhouse Point Reconstruct Dry Laid Stone Wall (Option A) 1 LS
38 Blockhouse Point Temporary Controls (Option A) 1 LS
39 Blockhouse Point New Stones for Wall (Option A) 20 CY
TOTAL Option A (Contract Line Item Numbers 35 through 39) -----------------------------------------
40 Lock 16 New Gates (Option B) 1 LS
41 Lock 16 Repointing (Option B) 1200 LF
42 Lock 16 Cribbing Wall (Option B) 1 LS
43 Lock 16 Temporary Controls (Option
B) 1 LS
TOTAL OPTION B (Contract Line Item Numbers 40 through 43) -------------------------------------
44 Lock 15 New Gates (Option C) 1 LS
45 Lock 15 Repointing (Option C) 1300 LF
46 Lock 15 Cribbing Wall (Option C) 1 LS
47 Lock 15 Temporary Controls (Option
C) 1 LS
TOTAL OPTION C (Contract Line Item Numbers 44 through 47) -------------------------------------
48 Lock 14 Reconstruct Dry Laid Stone Wall (Option D) 1 LS
49 Lock 14 New Stones for Walls (Option
D) 10 CY
TOTAL OPTION D (Contract Line Item Numbers 48 through 49) -------------------------------------
Document Title
CHOH 150819 Locks 5 - 22
50 Lock 13 Reconstruct Dry Laid Stone Wall (Option E) 1 LS
51 Lock 13 New Stones for Wall (Option
E) 20 CY
TOTAL OPTION E (Contract Line Item Numbers 50 through 51) -------------------------------------
TOTAL All Options (A through E, Contract Line Item Numbers 35 through 51)
TOTAL BASE PLUS ALL OPTIONS
Document Title
CHOH 150819 Locks 5 - 22
SECTION C – DESCRIPTIONS/SPECIFICATIONS/STATEMENT OF WORK
This requirement is for the rehabilitation of thirteen sites located along a 10 mile stretch of the C&O Canal outside of Washington D.C. that need repairs. Typical repairs include armoring/raising of the towpath, repairing lock walls, replacing lock gates, canal bridges and waste weirs.
SPECIFICATIONS AND DRAWINGS ARE ATTACHED AND INCORPORATED HEREIN BY REFERENCE, SEE
SECTION J, AND ATTACHMENT(S)
Document Title
CHOH 150819 Locks 5 - 22
SECTION D – PACKAGING AND MARKING
No clauses included.
Document Title
CHOH 150819 Locks 5 - 22
SECTION E – INSPECTION AND ACCEPTANCE
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.
(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.
(c) Government inspections and tests are for the sole benefit of the Government and do not—
(1) Relieve the Contractor of responsibility for providing adequate quality control measures;
(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;
(3) Constitute or imply acceptance; or
(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.
(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.
(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.
(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.
(g) If the Contractor does not promptly replace or correct rejected work, the Government may—
(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or
(2) Terminate for default the Contractor’s right to proceed.
(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.
(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.
(End of clause)
Document Title
CHOH 150819 Locks 5 - 22
SECTION F – DELIVERIES OR PERFORMANCE
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 500 calendar days from the notice to proceed.* The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES—CONSTRUCTION (SEPT 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,000 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.211-13 TIME EXTENSIONS (SEPT 2000)
Time extensions for contract changes will depend upon the extent, if any, by which the changes cause delay in the completion of the various elements of construction. The change order granting the time extension may provide that the contract completion date will be extended only for those specific elements related to the changed work and that the remaining contract completion dates for all other portions of the work will not be altered. The change order also may provide an equitable readjustment of liquidated damages under the new completion schedule.
(End of clause)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
If the quantity of a unit-priced item in this contract is an estimated quantity and the actual quantity of the unit-priced item varies more than 15 percent above or below the estimated quantity, an equitable adjustment in the contract price shall be made upon demand of either party. The equitable adjustment shall be based upon any increase or decrease in costs due solely to the variation above 115 percent or below 85 percent of the estimated quantity. If the quantity variation is such as to cause an increase in the time necessary for completion, the Contractor may request, in writing, an extension of time, to be received by the Contracting Officer within 10 days from the beginning of the delay, or within such further period as may be granted by the Contracting Officer before the date of final settlement of the contract. Upon the receipt of a written request for an extension, the Contracting Officer shall ascertain the facts and make an adjustment for extending the completion date as, in the judgement of the Contracting Officer, is justified.
52.242-14 SUSPENSION OF WORK (APR 1984)
Document Title
CHOH 150819 Locks 5 - 22
(a) The Contracting Officer may order the Contractor, in writing, to suspend, delay, or interrupt all or any part of the work of this contract for the period of time that the Contracting Officer determines appropriate for the convenience of the Government.
(b) If the performance of all or any part of the work is, for an unreasonable period of time, suspended, delayed, or interrupted (1) by an act of the Contracting Officer in the administration of this contract, or (2) by the Contracting Officer’s failure to act within the time specified in this contract (or within a reasonable time if not specified), an adjustment shall be made for any increase in the cost of performance of this contract (excluding profit) necessarily caused by the unreasonable suspension, delay, or interruption, and the contract modified in writing accordingly. However, no adjustment shall be made under this clause for any suspension, delay, or interruption to the extent that performance would have been so suspended, delayed, or interrupted by any other cause, including the fault or negligence of the Contractor, or for which an equitable adjustment is provided for or excluded under any other term or condition of this contract.
(c) A claim under this clause shall not be allowed—
(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and
(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.
Document Title
CHOH 150819 Locks 5 - 22
SECTION G – CONTRACT ADMINISTRATION DATA
1452.201-70 AUTHORITIES AND DELEGATIONS (SEPT 2011)
(a) The Contracting Officer is the only individual authorized to enter into or terminate this contract, modify any term or condition of this contract, waive any requirement of this contract, or accept nonconforming work.
(b) The Contracting Officer will designate a Contracting Officer's Representative (COR) at time of award. The COR will be responsible for technical monitoring of the contractor's performance and deliveries. The COR will be appointed in writing, and a copy of the appointment will be furnished to the Contractor. Changes to this delegation will be made by written changes to the existing appointment or by issuance of a new appointment.
(c) The COR is not authorized to perform, formally or informally, any of the following actions:
(1) Promise, award, agree to award, or execute any contract, contract modification, or notice of intent that changes or may change this contract;
(2) Waive or agree to modification of the delivery schedule;
(3) Make any final decision on any contract matter subject to the Disputes Clause;
(4) Terminate, for any reason, the Contractor's right to proceed;
(5) Obligate in any way, the payment of money by the Government.
(d) The Contractor shall comply with the written or oral direction of the Contracting Officer or authorized representative(s) acting within the scope and authority of the appointment memorandum. The Contractor need not proceed with direction that it considers to have been issued without proper authority. The Contractor shall notify the Contracting Officer in writing, with as much detail as possible, when the COR has taken an action or has issued direction (written or oral) that the Contractor considers to exceed the COR's appointment, within 3 days of the occurrence. Unless otherwise provided in this contract, the Contractor assumes all costs, risks, liabilities, and consequences of performing any work it is directed to perform that falls within any of the categories defined in paragraph (c) prior to receipt of the Contracting Officer's response issued under paragraph (e) of this clause.
(e) The Contracting Officer shall respond in writing within 30 days to any notice made under paragraph (d) of this clause. A failure of the parties to agree upon the nature of a direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the Disputes clause of this contract.
(f) The Contractor shall provide copies of all correspondence to the Contracting Officer and the COR.
(g) Any action(s) taken by the Contractor, in response to any direction given by any person acting on behalf of the
Government or any Government official other than the Contracting Officer or the COR acting within his or her appointment, shall be at the Contractor's risk.
(End of clause)
1452.204-70 RELEASE OF CLAIMS—DEPARTMENT OF THE INTERIOR (JUL 1996)
After completion of work and prior to final payment, the Contractor shall furnish the Contracting Officer with a release of claims against the United States relating to this contract. The Release of Claims form (DI–137) shall be used for this purpose. The form provides for exception of specified claims from operation of the release.
Document Title
CHOH 150819 Locks 5 - 22
NOTICE TO CONTRACTORS - CONTRACTOR PERFORMANCE ASSESSMENT REPORTING
SYSTEM (DEC 2015)
1. FAR 42.1502 directs all Federal agencies to collect past performance information on contracts. The Department of the Interior (DOI) has implemented the Contractor Performance Assessment Reporting System (CPARS) to comply with this regulation. One or more past performance evaluations will be conducted in order to record your contract performance as required by FAR 42.15.
2. The past performance evaluation process is a totally paperless process using CPARS. CPARS is a web-based system that allows for electronic processing of the performance evaluation report. Once the report is processed, it is available in the Past Performance Information Retrieval System (PPIRS) for Government use in evaluating past performance as part of a source selection action.
3. We request that you furnish the Contracting Officer (CO) with the name, position title, phone number, and email address for each person designated to have access to your firm's past performance evaluation(s) for the contract no later than 30 days after award. Each person granted access will have the ability to provide comments in the Contractor portion of the report and state whether or not the Contractor agrees with the evaluation, before returning the report to the Assessing Official (AO). Information in the report must be protected as source selection sensitive information not releasable to the public.
4. When your Contractor Representative(s) are registered in CPARS, they will receive an automatically generated email with detailed login instructions. Further details, systems requirements, and training information for CPARS is available at https://www.cpars.gov/.
5. Within 60 days after the end of a performance period, the AO will complete an interim or final past performance evaluation, and the report will be accessible at https://www.cpars.gov/.
a. Contractor Representatives may then provide comments in response to the evaluation, or return the evaluation without comment.
b. Your comments should focus on objective facts in the AO's narrative and should provide your views on the causes and ramifications of the assessed performance.
c. All information provided should be reviewed for accuracy prior to submission.
d. If you elect not to provide comments, please acknowledge receipt of the evaluation by indicating "No comment" in the space provided, and then selecting “Accept the Ratings and Close the Evaluation”.
e. Your response is due within 60 calendar days after receipt of the CPAR. On day 15, the evaluation will become available in PPIRS-RC marked as “Pending” with or without comments and whether or not it has been closed.
f. If you do not sign and submit the CPAR within 60 days, it will automatically be returned to the Government and will be annotated: "The report was delivered/received by the contractor on (date). The contractor neither signed nor offered comment in response to this assessment."
6. The following guidelines apply concerning your use of the past performance evaluation:
a. Protect the evaluation as source selection information. After review, transmit the evaluation by completing and submitting the form through CPARS. If for some reason you are unable to view and/or submit the form through CPARS, contact the CO for instructions.
b. Strictly control access to the evaluation within your organization. Ensure the evaluation is never released to persons or entities outside of your control.
c. Prohibit the use of or reference to evaluation data for advertising, promotional material, pre-award surveys, responsibility determinations, production readiness reviews, or other similar purposes.
7. If you wish to discuss a past performance evaluation, you should request a meeting in writing to the CO no later than seven days following your receipt of the evaluation. The meeting will be held in person or via telephone or other means during your 60-day review period.
8. A copy of the completed past performance evaluation will be available in CPARS for your viewing and for Government use supporting source selection actions after it has been finalized.
(End of Notice) https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.acquisition.gov/sites/default/files/current/far/html/Subpart%2042_15.html https://www.cpars.gov/ https://www.cpars.csd.disa.mil/ https://www.cpars.csd.disa.mil/
Document Title
CHOH 150819 Locks 5 - 22
ELECTRONIC INVOICING AND PAYMENT REQUIREMENTS – INTERNET PAYMENT PLATFORM
(APR 2013)
Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).
"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.
Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice
1. Payment Application in accordance with contract clause 52.232-5 Payment under Fixed Price Construction Contracts
2. Updated Schedule of Values
3. Updated Progress Schedule
The Contractor must use the IPP website to register access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.
If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.
(End of Local Clause) https://www.ipp.gov/ mailto:ippgroup@bos.frb.org
Document Title
CHOH 150819 Locks 5 - 22
SECTION H – SPECIAL CONTRACT REQUIREMENTS
SPECIAL CLAUSE 1: OPTION FOR ADDITIONAL SERVICES—SEPARATELY PRICED LINE
ITEMS
The Government may require the delivery of the numbered line items identified in the Schedule as option items at the price stated in the Schedule. The Contracting Officer may unilaterally exercise any option by written notice to the Contractor within 120 calendar days of contract award.
(End of clause)
SPECIAL CLAUSE 2: KEY PERSONNEL
(a) The Contractor shall assign to this contract the following key personnel:
Project Manager On-site Superintendent On-site personnel responsible for Quality Control On-site personnel responsible for Safety
(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer.
Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. This clause will be modified to reflect any approved changes of key personnel.
(End of clause)
SPECIAL CLAUSE 3: SMALL BUSINESS PARTICIPATION
(a) Definitions. As used in this clause— “Subcontract” means any agreement (other than one involving an employer-employee relationship) entered into by a Federal Government prime Contractor calling for supplies or services required for performance of the contract.
(b) The contractor shall ensure a minimum 30% of the total contract value is performed by Small Business. This requirement may be met by
i. Self-performance by small business prime contractors and / or
ii. Subcontracting portions of the work to small businesses
(c) Prior to submittal of their initial invoice the contractor shall submit a small business participation plan that demonstrates compliance with the requirements noted in (b) above. The plan shall include:
Document Title
CHOH 150819 Locks 5 - 22
i. A listing of anticipated subcontracts to small businesses including the following information for each subcontract:
Subcontractor name Description of supply or service Subcontract dollar value
ii. If the prime contractor is a small business then also list the dollar value of the work the prime contractor will self-perform.
iii. Total dollar value for all small business subcontracts + dollar value of work to be self-performed by small business prime contractors.
iv. The total prime contract dollar value.
v. Small business participation expressed as a percentage of the total contract value contracted to small businesses and self-performed by small business prime contractors.
(d) Failure of the contractor to meet the minimum required small business participation shall be reflected in the Government’s evaluation of the contractor’s performance upon contract completion.
LIABILITY INSURANCE REQUIREMENTS
(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:
Employer's liability $100,000
General liability $500,000
Construction Per person $100,000 Per occurrence $500,000 Property damage $1,000,000
Architect-Engineer Per person $200,000 Per occurrence $500,000 Property damage $ 20,000
Automobile liability Per person $200,000 Per occurrence for bodily injury $500,000 (other than passenger liability) Per occurrence for property damage $20,000
Aircraft public and passenger liability, when aircraft used in connection with the performing this contract Per person $200,000 Per occurrence for bodily injury $500,000 Per occurrence for property damage $200,000 Passenger liability bodily injury $200,000 multiplied by number of seats or passengers, whichever is greater
If this is a construction contract, the Contractor shall maintain compensation insurance, for employees engaged in the work, complying with the workmen's compensation laws of the State in which the work is to be performed and shall maintain liability insurance protecting the Contractor from claims because of bodily injury (including death) and property damage arising under this Contract.
Document Title
CHOH 150819 Locks 5 - 22
Each policy shall have a certificate evidencing the insurance coverage. The insurance company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of contract services to be performed. The Contractor shall furnish the Contracting Officer with a copy of an acceptable insurance certificate prior to beginning the work.
APPLICABLE CONTRACT WAGE DETERMINATION
General Decision Number: MD170012 01/27/2017 MD12
Superseded General Decision Number: MD20160012
State: Maryland
Construction Type: Heavy Dredging
Counties: Maryland Statewide.
MARYLAND
ALL DREDGING, EXCEPT SELF-PROPELLED HOPPER DREDGES, ON THE
ATLANTIC COAST AND TRIBUTARY WATERS EMPTYING INTO THE ATLANTIC
OCEAN, THE CHESAPEAKE AND DELAWARE CANAL, BALTIMORE CITY AND
BALTIMORE COUNTY, MARYLAND.
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017.
The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/06/2017 1 01/27/2017
* ENGI0025-001 10/01/2016
STATEWIDE
Rates Fringes
Dredging:
CLASS A.....................$ 37.25 15.66+a+b CLASS B1....................$ 32.22 15.26+a+b CLASS B2....................$ 30.33 15.11+a+b CLASS C1....................$ 29.50 14.29+a+b CLASS C2....................$ 28.54 14.21+a+b CLASS D.....................$ 23.71 13.08+a+b
Document Title
CHOH 150819 Locks 5 - 22
CLASSIFICATIONS:
CLASS A: Lead Dredgeman, Operator, Leverman, Licensed Tug Operator over 1000 HP.
CLASS B1: Derrick Operator, Spider/Spill Barge Operator, Engineer, Electrician, Chief Welder, Chief Mate, Fill Placer, Operator II, Maintenance Engineer, Licensed Boat Operator. CLASS B2: Certified Welder.
CLASS C1: Mate, Drag Barge Operator, Steward, Assistant Fill Placer, Welder.
CLASS C2: Boat Operator CLASS D: Shoreman, Deckhand, Rodman, Scowman, Cook, Messman, Porter/Janitor, Oiler.
INCENTIVE PAY: (Add to Hourly Rate) Operator (NCCCO License/Certification) $1.50 Licensed Tug Operator over 1000 HP (Assigned as Master) (USCG licensed Master of Towing Vessels (MOTV) $1.50; Licensed Boat Operator (Assigned as lead boat captain) USCG licensed boat operator $1.00; Engineer (QMED and Tankerman endorsement or licensed engineer (USCG) $1.50 Oiler (QMED and Tankerman endorsement (USCG) $1.50; All classifications (Tankerman endorsement only) USCG $1.25;
Deckhand or Mate (AB with Lifeboatman endorsement (USCG) $1.50; All classifications (lifeboatman endorsement only (USCG) $1.25; Welder (ABS certification) $0.50
FOOTNOTES APPLICABLE TO ABOVE CRAFTS:
a. PAID HOLIDAYS: New Year's Day, Martin Luther King, Jr.'s Birthday, Memorial Day, Good Friday, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day and Christmas Day
b. VACATION: Eight percent (8%) of the straight time rate, multiplied by the total hours worked.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Document Title
CHOH 150819 Locks 5 - 22
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .