A1_Specifications.pdf

PDF 2 MB Posted

Attached to
Accessible Facilities at Mori Point - Golden Gate NRA Federal contract opportunity
Solicitation number
P15PS01964
Issued by
Department of the Interior National Park Service

About this file

Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Accessible Facilities at Mori Point - Golden Gate NRA, newest first.
File Type Posted
A8_Relevant_Prior_Experience_.pdf PDF
A5_PAST_PERFORMANCE_QUESTIONNAIRE.pdf PDF
A3_Price_Schedule_RM.pdf PDF
A6_SUBCONTRACTOR_REF_FORM.pdf PDF
A7_Key_Personnel_Qualifications.pdf PDF
A4_General_References_Form.pdf PDF
A2_Drawings_with_Map.pdf PDF
A9_DB_Wages_CA150029_07172015_CA29.pdf PDF
P15PS01964_Standard_Form_1442.pdf PDF
Clauses_ _Provisions.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT MANUAL

INCLUDING SPECIFICATIONS

FOR

CONSTRUCTION

FOR THE

ACCESSIBLE FACILITIES

AT MORI POINT

100% Final Construction Documents

GOLDEN GATE

NATIONAL RECREATION AREA

May 29, 2015

RLLA Accessible Facilities at Mori Pt., GGNRA 100% final Construction Documents

SECTION 00 01 10

TABLE OF CONTENTS

PROJECT MANUAL

INTRODUCTORY INFORMATION

Section 00 01 10 Table of Contents 00 41 00 Bid Form

CONTRACTING REQUIREMENTS

By GGNRA

SPECIFICATIONS GROUP

DIVISION 1 – GENERAL REQUIREMENTS

Section 01 11 00 Summary of Work 01 23 00 Alternates 01 25 00 Substitution Procedures 01 30 00 Administrative Requirements 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 51 00 Tree Protection and Pruning 01 57 23 Temporary Storm Water Pollution Prevention 01 60 00 Product Requirements 01 73 00 Cutting and Patching 01 73 40 Execution and Utility Marking 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 00 Warranties

DIVISION 2 – EXISTING CONDITIONS

Section 02 41 20 Selective Demolition

DIVISION 9 – FINISHES

Section 09 90 90 Traffic Line Painting

DIVISION 10 – SPECIALTIES

Section 10 14 00 Signage

DIVISION 12 – FURNISHINGS

Section 12 93 00 Site Furnishings

DIVISION 31 – EARTHWORK

Section 31 00 00 Earthwork 31 10 00 Site Clearing

May 29, 2015 00 01 10 - 1 Table of Contents

100% final Construction Documents

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 12 00 Asphalt Paving 32 15 50 Compacted Aggregate Paving 32 16 00 Concrete Paving 32 17 00 Parking Bumpers

APPENDIX

I. Sampling Language memorandum

II. Submittal Checklists.

III. Vault Toilet manufacturer’s specifications

END OF SECTION

May 29, 2015 00 01 10 - 2 Table of Contents

SECTION 00 41 00

BID FORM

1.1 SUBMIT COPY OF BID FORM TO:

Gary Kramer, Contracting Officer 401 West Hillcrest Drive Thousand Oaks CA 91360-4217

1.2 PROJECT

A. In compliance with proposed Contract Documents for construction of:

ACCESSIBLE FACILITIES AT MORI POINT

GOLDEN GATE NATIONAL RECREATION AREA

B. Including Addenda Numbers ____ ____ ____ ____ ____ ____ ____ ____

C. The undersigned has become thoroughly familiar with the terms and conditions of proposed Contract Documents and with local codes and conditions affecting performance and costs of Work at place where Work is to be completed.

D. The undersigned has fully inspected the site in all particulars.

E. The undersigned hereby proposes and agrees to fully perform Work as follows.

1. The undersigned agrees to perform Work within time agreed upon.

2. The undersigned agrees to perform Work in strict accordance with proposed Contract Documents, including furnishing any and all labor and materials.

3. The undersigned agrees to do all work required to construct and complete said Work in accordance with Contract Documents.

1.3 BID SCHEDULE

A. Base Bid: In case of error in summation, the total of the corrected bid amount shall govern.

B. Submittals and Approvals (Division 01):

_____________________________________Dollars ($______________________)

C. Soils Testing for Hazardous Materials:

D. Mobilization (Division 01):

_____________________________________Dollars ($______________________)

E. Demolition (Section 02 41 20):

May 29, 2015 00 41 00 - 1 Bid Form

F. Layout, Clear and Grub

G. Earthwork, Cut&Fill, Vault excavation, Paths, Parking (Section 31 00 00):

H. Survey, Compaction Testing

I. Base Rock (Section 32 15 50, 32 12 00, 32 16 00)

J. Concrete Paving, Parking (Section 32 16 00)

K. Compacted Aggregate Paving (Section 32 15 50)

L. Bollards, Trash Receptacle (Section 12 93 00)

M. Vault Toilet (Section 12 93 30)

N. Pavement Markings(Section 09 90 90)

O. Signage (Section 10 14 00):

P. Tree Pruning and removals(Section 01 51 00)

Q. Parking Bumpers (Section 32 17 00):

_____________________________________Dollars ($______________________)

R. Demobilization (Division 01):

_____________________________________Dollars ($______________________)

S. All labor, materials, services, and equipment necessary for completion of the Work not otherwise listed, except for items described as "Alternates".

T. Bid Summary: Total Bid

May 29, 2015 00 41 00 - 2 Bid Form

1.4 Bid Options

A. Refer to Section 01 23 00 - Alternates for a complete description of work to be included in each alternate.

1. Bid Option Number 1: Remove Easternmost tree and install two standard parking spaces and associated striping and bumpers.

_____________________________________Dollars ($______________________)

1.5 AWARD OF CONTRACT

A. It is understood that Owner reserves right to reject this bid but that it shall remain open and not be withdrawn for a period of sixty calendar days from date prescribed for its opening.

B. Undersigned agrees to execute and deliver Contract to Owner in accordance with this bid if written acceptance is mailed or delivered before bid is withdrawn by written notification to Owner.

1.6 TIME OF COMPLETION

A. The undersigned agrees to commence work under this Contract on or before a date to be specified in a written notice from Owner and to complete project within the following limits:

1. _____ consecutive calendar days after specified date (Contractor to fill in).

1.7 IDENTIFICATION

A. Notice of acceptance, or request for additional information, may be addressed to the undersigned at address set forth below.

B. The names of all persons interested in the foregoing bid as principals are:

1. Important Notice: If a corporation, give legal name of corporation, state where incorporated, and names of president and secretary; if a partnership, give name of firm and names of all individual co-partners composing the firm; if an individual, give first and last names in full.

C. License: Contractor is licensed in accordance with an act for registration of contractors with license number:

May 29, 2015 00 41 00 - 3 Bid Form

D. Business Address:

E. Telephone Number: ______________________________________________

F. Date of Bid: ____________________________________________________

G. Signature of person(s) with legal authority to sign contracts:

1.8 INSURANCE ATTACHMENT

A. Attach copy of Contractor insurance coverage to be provided for Project.

May 29, 2015 00 41 00 - 4 Bid Form

SECTION 01 11 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Project consists of construction of accessible parking, restroom and trailhead facilities at Mori Point, Golden Gate National Recreation Area, as indicated in Contract Documents.

1. Items noted "NIC" (Not In Contract) will be furnished and installed by National Park Service or under separate contract.

a. Hazardous Materials Removal: Known hazardous materials will be removed under separate contract (NIC); inform National Park Service immediately where materials suspected of being hazardous are encountered.

b. Hazmat Testing: Refer to Section 31 00 00 - Earthwork.

2. National Park Service reserves right to remove and retain possession of existing items prior to start of Contract.

1.2 REQUIREMENTS INCLUDED

A. This section includes administrative provisions:

1. Work sequence.

2. Contractor use of premises.

3. Regulatory requirements and reference standards.

4. National Park Service furnished, Contractor installed products.

1.3 WORK SEQUENCE

A. Coordinate construction schedule and operations with Contracting Officer.

1.4 CONTRACTOR USE OF PREMISES

A. Limit use of premises for Work and construction operations and to allow for work by other contractors.

B. Coordinate use of premises and access to site under direction of Contracting Officer.

C. Accessible Facilities at Mori Point and Golden Gate National Recreation Area outside of construction area will be occupied during construction for conduct of normal operations.

1. Cooperate and coordinate with Contracting Officer to minimize conflict and to facilitate operations.

May 29, 2015 01 11 00 - 1 Summary of Work

1.5 REGULATORY REQUIREMENTS AND REFERENCE STANDARDS

A. Regulatory Requirements:

1. Contractor shall be responsible for contacting applicable authorities directly for necessary information and decisions bearing upon performance of Work.

B. Reference Standards:

1. For Products specified by association or trade standards, comply with requirements of referenced standard, except when more rigid requirements are specified or are required by applicable codes.

2. Applicable date of each standard is in effect as of date on proposal or date on Contract where no proposal is available, except when a specific date is specified.

1.6 NATIONAL PARK SERVICE FURNISHED, CONTRACTOR INSTALLED PRODUCTS

A. Select products are to be furnished and paid for by National Park Service and installed by Contractor:

1. Refer to Drawings and Specifications.

May 29, 2015 01 11 00 - 2 Summary of Work

SECTION 01 23 00

ALTERNATES

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes a description of alternate work.

B. Related Requirements:

1. Pricing Documents: Quotation of cost of each alternate.

2. National Park Service-Contractor Agreement: Alternates accepted by National Park Service for incorporation into the Work.

3. Sections of Specifications identified in each Alternate.

1.2 PROCEDURES

A. Alternates will be exercised at National Park Service's option.

B. Coordinate Related Work: and modify surrounding work as required to complete Work, including changes under each alternate, when acceptance is designated in National Park Service-Contractor Agreement.

1.3 Bid Option

A. Bid Option 01: Add two asphalt paved parking spaces and remove adjacent cypress tree(s) as indicated on drawings.

1. Work Included in Alternate: Add to contract price the cost of earthwork, asphalt conform, concrete paving, striping and wheel stops for two non accessible spaces

2. Work Included in Contract Price: Tree(s) is/are to remain in base contract. Include necessary safety pruning and re-grading of edge of accessible parking space to provide positive drainage away from paving and in to planting area.

3. Refer to Sheets D1.0, L1.0 and L2.0

May 29, 2015 01 23 00 - 1 Alternates

SECTION 01 25 00

SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. General: Procedures are described for requesting substitution of unlisted materials in lieu of materials named in Specifications or approved for use in addenda.

1. Provide products listed in Contract Documents, products by manufacturers listed in Contract Documents, and products meeting specified requirements.

a. Contract Amount: Base on materials and products included in Contract Documents.

b. Where materials and products are listed in Contract Documents, materials and products by manufacturers not listed shall not be used without Contracting Officer's approval of Contractor's written request for substitution.

2. Purpose: After bidding, substitutions will only be considered where National Park Service will receive benefit or because specified materials are no longer available due to no fault of Contractor.

a. National Park Service benefits either from a Contractor proposed reduction of the Contract amount or from a reduction in Contract time based on acceptance of proposed substitution.

b. List proposed cost or time reductions on request for substitution.

c. Requests not including a proposed cost or time reduction will not be considered unless Contractor submits supporting information indicating specified materials are not available.

B. Related Sections:

1. Section 01 60 00: Product requirements.

1.2 SUBSTITUTIONS

A. Within a period of 35 days after award of Contract, Contracting Officer will consider formal requests for substitutions only from Contractor as specified in 1.1 Summary.

1. Contracting Officer will consider only one request for substitution for each material; where requests are denied Contractor shall be required to provide specified materials.

2. After initial 35 day period, requests will be considered only when a product becomes unavailable through no fault of Contractor; more than one request for substitution will be considered if necessary.

May 29, 2015 01 25 00 - 1 Substitution Procedures

B. Submit each request with sequentially numbered “Substitution Request Transmittal” acceptable to Contracting Officer; submit separate request for each product and support each request with:

1. Product identification with manufacturer's literature and samples where applicable.

2. Name and address of similar projects on which product has been used, and date of installation.

C. Submit itemized comparison of proposed substitution with product specified and list significant variations.

D. Submit data relating to changes in construction schedule.

E. Note effect of substitution on other work, products, or separate contracts.

1. Note if acceptance of substitution could require revision of Contract Documents, Drawings, details or Specifications.

F. Include accurate cost data comparing proposed substitution with product and amount of net change in Contract price.

1. Include costs to other contractors and costs for revisions to Drawings, details or Specifications.

G. Substitutions will not be considered for acceptance when:

1. They are indicated or implied on submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of Contract Documents.

H. Substitute products shall not be ordered without written acceptance of Contracting Officer.

I. Contracting Officer will determine acceptability of proposed substitutions and reserves right to reject proposals due to insufficient information.

1.3 CONTRACTOR'S REPRESENTATION

A. Requests constitute a representation that Contractor:

1. Has investigated proposed product and determined it meets or exceeds, in all respects, specified product.

2. Will provide same warranty or longer warranty for substitution as for specified product.

3. Will coordinate installation and make other changes that may be required for Work to be complete in all respects.

4. Waives claims for additional costs that subsequently become apparent.

May 29, 2015 01 25 00 - 2 Substitution Procedures

1.4 CONTRACTING OFFICER'S DUTIES

A. Review Contractor's requests for substitutions with reasonable promptness.

B. Notify Contractor in writing of decision to accept or reject requested substitution.

May 29, 2015 01 25 00 - 3 Substitution Procedures

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This section describes general procedural requirements for ongoing submittals.

1. Construction progress schedules.

2. Schedule of values.

3. Product data and manufacturer’s literature.

4. Shop drawings.

5. Samples.

6. Manufacturers' certificates.

7. Design/build procedures.

B. Related Requirements:

1. Section 01 40 00: Test reports, manufacturer's field reports, and mock-ups.

2. Section 01 77 00: Closeout requirements including Project Record Documents.

3. Section 01 78 00: Warranties.

1.2 GENERAL SUBMITTAL PROCEDURES

A. Submittals: Transmit each item using DSC CM-16 and CM-17 forms as provided by Contracting Officer.

1. Contractor: Review and stamp submittals from subcontractors prior to submitting to Contracting Officer.

a. Review submittals and indicate where conflicts occur with Contract Documents and with work of other subcontractors.

b. Return submittals that vary significantly from Contract Documents for correction and resubmittal prior to submitting to Contracting Officer.

c. Submittals that vary significantly from Contract Documents and that fail to indicate thorough Contractor review prior to submission to Contracting Officer will be returned without review.

d. Cursory review and stamping of subcontractor submittal by Contractor shall not be acceptable.

B. Contractor to provide sequenced bar chart schedule of major activities and subcontractors with initial pricing proposal including a written description of contractors proposed approach to executing the project.

May 29, 2015 01 30 00 - 1 Administrative Requirements

C. Initial Schedules: Submit initial progress schedule and schedule of value in duplicate at least 7 calendar days prior to pre-construction conference.

1. After review by Contracting Officer revise and resubmit where required.

D. Comply with progress schedule for submittals related to Work progress. Coordinate submittal of related items.

E. After Contracting Officer review of submittal, revise and resubmit as required, identify changes made since previous submittal.

F. Distribute copies of reviewed submittals to concerned persons.

Instruct recipients to promptly report any inability to comply.

1.3 TYPES OF SUBMITTALS

A. General: Project requires various types of submittals to maintain communications, minimize misunderstandings, avoid unnecessary conflicts, and to ensure complete documentation for Project Record Documents.

1. Maintain complete set of submittals including required revisions.

B. Construction Schedules: Submit construction progress schedules for Design Team and Owner review and to maintain entire team up-to-date on construction activities.

C. Schedule of Values: Submit Schedule of Values indicating division of Work, subcontractors to perform work, products being used, and values attributed to each to inform Contracting Officer.

D. Action Submittals: Submittals relating to product data and manufacturer’s literature, shop drawings, and samples for Contracting Officer review and comment; do not begin fabrication, delivery, or installation until Contracting Officer review is complete.

E. Information Submittals: Submittals relating to certifications, qualifications, reports, including test reports, and instructions are for information; Contracting Officer may choose to comment but action is not generally anticipated.

1. Manufacturer installation instructions and recommendations shall be considered information submittals.

F. Maintenance Materials Submittals: Compile maintenance information and materials during Work to ensure complete set of documents, maintenance manuals, and operation instructions.

1. Excess materials shall be considered property of National Park Service; inform Contracting Officer of extent of excess materials and methods required for handling and storage.

2. Remove from site excess materials not required by Contracting officer to be retained for maintenance stock.

May 29, 2015 01 30 00 - 2 Administrative Requirements

G. Closeout Submittals: Compile closeout submittals, organize, and submit to Contracting Officer prior to or at time of Substantial Completion.

1. Project will not be considered Substantially Complete until closeout submittals have been received by Contracting Officer.

1.4 CONSTRUCTION PROGRESS SCHEDULES (See Section 01.32.16)

A. Submit construction progress schedule with separate item for each major trade and operation, identifying first day of each week.

1. Show complete sequence of construction by activity, identifying work of separate stages and logically grouped activities.

2. Show projected percentage of completion for each item of Work as of time of each progress Application for Payment.

3. “Submittal Schedule”: Show Contractor submittal dates required for shop drawings, product data, and samples, and product delivery dates; deliver to Contracting Officer per approved “Submittal Schedule.”

a. “Submittal Schedule” may be incorporated into construction progress schedule or may be separate, Contractor option.

b. Contracting Officer’s Review Period: Contracting Officer will be expedient in review, however, Contractor shall schedule submittals to allow for thirty (30) days submittal review time by Contracting Officer for each submittal or resubmittal, who may reject and may require resubmittal.

c. Contract extension shall not be allowed for Contractor’s failure to properly schedule submittals to allow for Contracting Officer requiring resubmittal.

B. Progress Schedule Format: Submit both horizontal bar chart and network analysis system using critical path method as approved by Contracting Officer.

1. Submit revised progress schedules with each Application for Payment reflecting changes since previous submittal, not less than monthly.

1.5 SCHEDULE OF VALUES

A. Submit typed schedule on Contracting Officer pre-approved 8-1/2" by 11" format; Contractor's standard media-driven printout will be considered on request. Submit within 7 calendar days prior to pre-construction conference.

B. Format: Table of Contents of this Project Manual, with modifications as pre-approved by Contracting Officer; identify each line item with number and title of major Specification sections.

C. Revise schedule to list change orders for each Application for Payment.

May 29, 2015 01 30 00 - 3 Administrative Requirements

1.6 PRODUCT DATA/MANUFACTURERS' LITERATURE

A. Action Submittals: Mark each copy to identify applicable Products, models, options, and other data; supplement manufacturers' standard data to provide information unique to the Work.

B. Information Submittals: Include manufacturers' installation instructions only when required by Specifications or specifically requested by Contracting Officer.

1. Maintain copy of manufacturer installation instructions and recommendations in Contractor's field office for review.

C. Product data shall be submitted in electronic PDF format unless otherwise noted or approved by Contracting Officer in Advance.

1. Where paper submittals are approved submit number of copies Contractor requires, plus one copy to be retained by Contracting Officer.

1.7 SHOP DRAWINGS

A. Shop drawings shall be submitted in reproducible format acceptable to Contracting Officer; computerized PDF files will be acceptable unless otherwise directed.

B. Shop drawings shall be submitted as electronic PDF files unless otherwise noted or approved by Contracting Officer in advance.

1. Where paper submittals are approved submit one reproducible print.

C. Distribution: After review, reproduce and distribute.

1.8 SAMPLES

A. Submit full range of manufacturers' standard colors, textures, and patterns for Contracting Officer's selection.

B. Submit samples to illustrate functional characteristics of Product, with integral parts and attachment devices.

C. Coordinate submittal of different categories for interfacing work.

D. Include identification on each sample, giving full information.

D. Submit number of samples required by Contractor plus one to be retained by Contracting Officer.

E. Sizes: Provide following sizes unless otherwise specified.

1. Flat or Sheet Products: Minimum 6" square, maximum 12" by 12".

2. Linear Products: Minimum 6", maximum 12" long.

3. Bulk Products: Minimum one pint, maximum one gallon.

F. Full size samples may be used in the Work upon approval.

May 29, 2015 01 30 00 - 4 Administrative Requirements

1.9 MANUFACTURERS' CERTIFICATES

A. Submit certificates, in duplicate in accordance with requirements of each Specification section.

May 29, 2015 01 30 00 - 5 Administrative Requirements

SECTION 01 31 00

PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Requests for Information (RFIs).

3. Project meetings.

4. Environmental Coordination.

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule”.

2. Section 01 73 40 “Execution and Utility Marking”.

3. Section 01 77 00 “Closeout Procedures”.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of seven calendar days prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

May 29, 2015 01 31 00 - 1 Project Management & Coordination

8. Waste Management Plan.

9. Quality Control Plan.

10. Storm Water Pollution Prevention Plan.

11. All other Div. I items on Submittal List

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received seven calendar days prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Contracting Officer will return RFIs submitted by other entities controlled by Contractor with no response.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially

2. Project name.

3. Contract number.

4. Date.

5. Name of Contractor.

6. RFI subject.

7. Specification Section number and title and related paragraphs, as appropriate.

8. Drawing number and detail references, as appropriate.

9. Field dimensions and conditions, as appropriate.

10. Contractor's suggested resolution. If Contractor's suggested resolution impacts the Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

11. Contractor's signature.

12. Requested date for response.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

May 29, 2015 01 31 00 - 2 Project Management & Coordination

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Utilize the RFI form that can be downloaded from the Workflows website at http://www.nps.gov/dscw/con_rfi217.htm.

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the

Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Resolution of comments on required Division 01 documents.

4. Coordination of Subcontractors.

5. Labor law application.

6. Modifications.

7. Payments to Contractor.

8. Payroll reports.

9. Contract time.

May 29, 2015 01 31 00 - 3 Project Management & Coordination http://www.nps.gov/dscw/con_rfi217.htm

10. Liquidated damages.

11. Display of Hotline posters.

12. Notice to proceed.

13. Correspondence procedures.

14. Acceptance/rejection of work.

15. Progress meetings.

16. Submittal procedures.

17. NPS Final Accessibility Inspection.

18. Environmental requirements.

19. As-constructed drawings/operation and maintenance

(O&M) manuals.

20. Saturday, Sunday, holiday and night work.

21. Reference materials.

22. Value engineering.

B. Progress Meetings: The Project Manager will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each

Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.).

g. Inspections of work in progress and projected.

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

May 29, 2015 01 31 00 - 4 Project Management & Coordination

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Sustainable design requirements.

i. Review of mockups.

j. Possible conflicts.

k. Compatibility requirements.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written instructions.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations of authorities having jurisdiction.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.6 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO

May 29, 2015 01 31 00 - 5 Project Management & Coordination

14001; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan(WMP).

c. Implementation of the Storm Water Pollution Prevention

Plan(SWPPP).

d. Present an overview of environmental issues and summarize site-specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Noise & Acoustics Management.

3. Temporary Storm Water Pollution Prevention

4. Environmental Management.

5. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Noise & Acoustics Management.

c. Temporary Storm Water Pollution Prevention.

4. Pollution Prevention (P2) practices: Submit evidence of participation in P2 programs.

5. Compliance with environmental regulations: As specified in Regulatory Requirements. Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for approval of environmental procedures in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan prior to preconstruction meeting.

May 29, 2015 01 31 00 - 6 Project Management & Coordination

SECTION 01 32 16

CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values.

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

May 29, 2015 01 32 16 - 1 Construction Schedule

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity. Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

1. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

2. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Schedule of Values: After contract award and before the Pre- Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

B. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two (2) paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

C. CPM Reports: Concurrent with CPM schedule, submit three (3) paper copies of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

D. Construction Schedule Updates: On or before the seventh (7) day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two (2) paper copies.

May 29, 2015 01 32 16 - 2 Construction Schedule

E. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two (2) paper copies of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing, work stages, area separations, interim milestones, and partial Government occupancy.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of separate Government contracts.

6. Review time required for review of submittals and re-submittals.

7. Review requirements for tests and inspections by independent testing and inspecting agencies.

8. Review time required for completion and startup procedures.

9. Review and finalize list of construction activities to be included in schedule.

10. Review baseline schedule comments, resolve issues and progress on incorporating them.

11. Review procedures for updating schedule.

12. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

May 29, 2015 01 32 16 - 3 Construction Schedule

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than thirty (30) days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from

May 29, 2015 01 32 16 - 4 Construction Schedule completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3. Processing: Process data to produce output data on a computer-drawn, time-scaled network. Revise data, reorganize activity sequences, and reproduce as often as necessary to produce the CPM schedule within the limitations of the Contract Time.

4. The Construction Baseline Schedule as developed shall show the sequence and interdependence of activities required for complete performance of the work. Ensure all work sequences are logical and the Construction Baseline Schedule shows a coordinated plan of the work.

5. Resource loading of each activity shall include all personnel by labor category and equipment type and capacity proposed to complete the activity in the duration shown.

6. Consider seasonal weather conditions in planning and scheduling all work influenced by high and low ambient temperatures, wind, or precipitation to ensure completion of all work within the contract time.

7. Time Frame: Proposed duration assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity.

a. An early finish date may be shown but the late finish date must be the same date as the last day of the contract period. An early completion schedule must contain the following:

1) Insert an activity titled “Project Float” as a successor to the last activity in the early project completion schedule network.

2) Add a milestone titled “Contract End Date” as a successor to the activity “Project Float”.

3) Add duration to the activity “Project Float” as required so the milestone “Contract End Date” equals the last day of the Contract Period.

b. Contract completion date shall not be changed by submission of a schedule that shows an early completion date.

c. The Contractor shall limit use of lead or lag duration’s between schedule activities.

May 29, 2015 01 32 16 - 5 Construction Schedule

d. Project Calendars: Develop and incorporate the following calendars:

1) Administrative Calendar: Include a calendar that is based on a seven (7) day week to be used on any activities that are based on calendar days. Apply this calendar to administrative tasks or any other tasks that are not affected by non-working days (Federal Holidays, weather, etc.).

2) Project Calendar: Include a calendar that is based on the planned work week for the project. Include Federal Holidays, weekends, and any other non-work days indicated in the contract documents. Apply this calendar to activities which are not anticipated to be affected by weather.

3) Weather Calendar: Utilize the Project Calendar and show anticipated normal downtime related to weather as non-working time. Weather days shall be based on data for the local area from a reliable source like the National Oceanic and Atmospheric Administration (NOAA), National Park Service records, or source acceptable to the Contracting Officer. Apply this calendar to activities that are anticipated to be affected by weather.

e. Activity Duration: Define activities so no activity is longer than fifteen (15) days, except for non-construction activities including mobilization, shop drawings and submittals, fabrication and delivery of materials and equipment.

f. Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than sixty (60) calendar days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

8. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected.

a. Phasing: Arrange list of activities on schedule by phase.

b. Work Restrictions: Show the effect of the following items on the schedule:

1) Limitations of continued occupancies.

2) Uninterruptible services.

3) Partial occupancy before Substantial Completion.

4) Use of premises restrictions.

5) Seasonal variations.

6) Environmental control.

c. Work Stages: Indicate important stages of construction for each major portion of the Work.

1) Subcontract awards.

2) Submittals.

3) Purchases.

4) Fabrication.

5) Sample testing.

May 29, 2015 01 32 16 - 6 Construction Schedule

6) Deliveries.

7) Installation.

8) Tests and inspections.

9) Adjusting.

10) Curing.

9. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and the following interim milestones:

a. Hazardous Materials Testing

b. Grading

c. Concrete Paving

d. Aluminum and Timber edging of paths and picnic units

e. Compacted Aggregate Paving

f. Asphalt Paving

g. Site Furnishings – Bollards and TRash

h. Site Furnishings - Vault Toilet

i. Pavement Markings

C. Joint Review, Revision, and Acceptance:

1. Within seven (7) calendar days of receipt of the Contractor's proposed Construction Baseline Schedule, the Contracting Officer and Contractor shall meet for joint review, correction, or adjustment of the initial Construction Baseline Schedule. Any areas which, in the opinion of the Contracting Officer, conflict with timely completion of the project shall be subject to revision by the Contractor.

2. Within seven (7) calendar days after the joint review between the Contractor and Contracting Officer, the Contractor shall revise and resubmit the Construction Baseline Schedule in accordance with agreements reached during the joint review.

3. In the event the Contractor fails to define any element of work, activity, or logic, and the Contracting Officer review does not detect this omission or error, such omission or error, when discovered by the Contractor or Contracting Officer, shall be corrected by the Contractor within seven (7) calendar days and shall not affect the contract period.

4. Upon acceptance of the Construction Baseline Schedule by the Contracting Officer, save the schedule as a baseline and update on a monthly basis. The construction schedule update will be used to evaluate the Contractor's monthly applications for payment based upon information developed at the monthly Construction Schedule update meeting.

D. Recovery Schedule: When…