Revised_Bid_Schedule.pdf

PDF 46 KB Posted

Attached to
Mammoth Cave - Reconstruct Cave Trails Federal contract opportunity
Solicitation number
P15PS01388
Issued by
Department of the Interior National Park Service

About this file

Revised Bid Schedule - P15PS01388 Amendment 00001

View the file

Other files for this federal contract opportunity

Other files attached to Mammoth Cave - Reconstruct Cave Trails, newest first.
File Type Posted
Questions.docx DOCX document
SF-30_Amendment_00002_-_P15PS01388.pdf PDF
Cave_Trail_Lower_Dirt_Removal_and_Placement_Areas.pdf PDF
4_-_SECTION_01_27_00_-_DEFINITION_OF_CONTRACT_LINE_ITEMS_-_REV.pdf PDF
Proposed_Equals.doc DOC document
SF_1442_-_P15PS01388.pdf PDF
SF30_-_P15PS01388.pdf PDF
Questions.docx DOCX document
General_References.doc DOC document
HAZARDOUS_MATERIALS_IDENTIFICATION_LISTING.doc DOC document
SubContracting_Plan.pdf PDF
P15PS01388__Final.pdf PDF
MACA_150067_-_PROJECT_SPECIFICATIONS_06.10.15_DSC.pdf PDF
MACA_135_117632_A_Full_Combined_Set.pdf PDF
Past_Performance_Questionnaire_-_MACA.pdf PDF
Wage_Decision_-_KY150147_(5-22-15).docx DOCX document
MACA_150067_Pre-solicitation_Notice.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P15PS01388 Amendment 0001

SECTION B – SUPPLIES OR SERVICES AND PRICES

PRICE SCHEDULE

Title: MACA 150067 Restore Cave Trail Solicitation No.: P15PS01388 Amdendment 0001

DATE:

COMPANY NAME:

CONTACT NAME:

PHONE:

E-MAIL:

Fore detailed line item descriptions see Section 01 27 00 – Definition of Contract Line Items

CLIN Description Qty. Unit Unit Price Extended Price

10 Mobilization and Demobilization for Season 1 1 LS

TOTAL LINE ITEM PRICE (Contract Line item number 10) :

20A Concrete Pavers with sand leveling course 9990 SF

20B Concrete Bands 18 EA

20C Concrete Chase 37 LF

20D 18” Ht. Composite Lint Guard 1110 LF

20E Non-Ground Penetration Lint Guard 696 LF

20F Handrails 230 LF

20G Aggregate Fill 24 CY

20H FRP Trail Grating 92 SF

20I Concrete Steps No. 1 – Including Handrail 1 LS

20J Concrete Steps No. 2A – Including Handrail 1 LS

TOTAL LINE ITEM PRICE (Contract Lines item numbers 20A through 20J) :

30A Concrete Paving 2840 SF

30B Typical 12” Ht. Composite Lint Guard 1126 LF

30C Handrails 22 LF

30D Aggregate Fill 10 CY

TOTAL LINE ITEM PRICE (Contract Lines item numbers 30A through 30D):

TOTAL BASE BID PRICE (Contract Line items 10, 20A through 20J and 30A through 30D) :

40 Bid Option 0 - Mobilization / Demobilization (Season 2) 1 LS

TOTAL LINE ITEM PRICE (Contract Line item number 40):

50A Bid Option 1 - Concrete Paving 4100 SF

50B Bid Option 1 – Concrete Chase 18 LF

50C Bid Option 1 – Concrete Steps No. 1B – Including Handrails

1 LS

50D Bid Option 1 – Concrete Steps No. 2 – Including Handrails

1 LS

50E Bid Option 1 – Concrete Steps No. 3 – Including Handrails

1 LS

50F Bid Option 1 – Handrail 360 LF

50G Bid Option 1 – Retrofit of Existing Handrail 178 LF

50H Bid Option 1 – Typical 12” Ht. Composite Lint Guard 316 LF

50I Bid Option 1 - Stainless Steel Gate 1 EA

50J Bid Option 1 – FRP Trail Grating – Including Concrete Base

78 SF

50K Bid Option 1 – Concrete Slip Resistant Surface 200 SF

50L Bid Option 1 – Aggregate Fill 12 CY

TOTAL BID OPTION No. 1 PRICE (Contract Lines item numbers 50A through 50L) :

60A Bid Option 2 – Concrete Pavers with sand leveling course

2332 SF

60B Bid Option 2 – Concrete Bands 7 EA

60C Bid Option 2 – Concrete Chase 8 LF

60D Bid Option 2 – Concrete Paving 295 SF

60E Bid Option 2 – 18” Ht.

Composite Lint Guard 570 LF

60F Bid Option 2 – 12” Ht.

Stainless Steel Mesh Lint Guard

206 LF

60G Bid Option 2 – Handrail 215 LF

60H Bid Option 2 – Concrete Steps No. 6 – Including Handrail

1 LS

60I Bid Option 3 – Concrete Steps No. 7 – Including Handrail

1 LS

60J Bid Option 2 – FRP Steps No. 1 1 LS

60K Bid Option 2 – Stainless Steel Gate 2 EA

60L Bid Option 2 – Aggregate Fill 6 CY

60M Bid Option 2 – River Hall FRP Grate Walkway 1 LS

TOTAL BID OPTION No. 2 PRICE (Contract Lines item numbers 60A through 60M) :

70A

Bid Option 3 – 12” Ht.

Composite Lumber Lint Guard Outboard of Existing Trail

1104 LF

70B

Bid Option 3 – 12” Ht.

Composite Lumber Lint Guard Inboard of Existing Trail

466 LF

70C Bid Option 3 – Clean Existing Concrete Surface 1 LS

TOTAL BID OPTION No. 3 PRICE (Contract Lines item numbers 70A through 70C) :

80A Bid Option 4 – Reinforced Concrete 10 CY

80B Bid Option 4 – Aggregate Fill 26 CY

80C Bid Option 4 – FRP Steps 1 LS

80D Bid Option 4 – FRP Tube Guardrail 104 LF

TOTAL BID OPTION No. 4 PRICE (Contract Lines item numbers 80A through 80D) :

90A Bid Option 5 – Demolition of Existing Boardwalk 1 LS

90B Bid Option 5 – Concrete Pavers with sand leveling course

6830 SF

90C Bid Option 5 – Concrete Bands 16 EA

90D Bid Option 5 – Concrete Chase 30 LF

90E Bid Option 5 – 18” Ht.

Composite Lint Guard (with existing and new posts)

1120 LF

90F Bid Option 5 – Handrails 164 LF

90G Bid Option 5 – Aggregate Fill 46 CY

TOTAL BID OPTION No. 5 PRICE (Contract Lines item numbers 90A through 90G) :

TOTAL PROPOSED PRICE-BASE PLUS ALL OPTIONS

All measurement and payment information is in the project specifications, Section 012700

PRICE SCHEDULE GENERAL NOTES

1. Offerors shall submit a price for all line items; failure to do so may render the offer unacceptable.

2. Refer to attached project specifications for definitions of the line items.

3. On lump-sum line items, provide total price only.

4. If no item exists for a portion of the work, include the price in a related line item.

5. In case of error in extension of prices, unit price governs.

6. In case of error in summation, the total of the corrected amounts govern.

7. The Government reserves the right to award any or no options at the time of award.

8. Contractor acknowledges the quantity of a unit-priced item in this contract is an estimated quantity. Refer to clause 52.211-18 in section “F” of this solicitation for additional information.

9. Bonding Requirements: All bonds including bid bonds shall be obtained in accordance with the contract clauses. Offerors are now advised that the Government will inspect, accept and take possession of completed work and release the bonding for that work upon the completion of each construction season in accordance with FAR 28.203-5.