Revised_Bid_Schedule.pdf
PDF 46 KB Posted
- Attached to
- Mammoth Cave - Reconstruct Cave Trails Federal contract opportunity
- Solicitation number
- P15PS01388
About this file
Revised Bid Schedule - P15PS01388 Amendment 00001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions.docx | DOCX document | |
| SF-30_Amendment_00002_-_P15PS01388.pdf | ||
| Cave_Trail_Lower_Dirt_Removal_and_Placement_Areas.pdf | ||
| 4_-_SECTION_01_27_00_-_DEFINITION_OF_CONTRACT_LINE_ITEMS_-_REV.pdf | ||
| Proposed_Equals.doc | DOC document | |
| SF_1442_-_P15PS01388.pdf | ||
| SF30_-_P15PS01388.pdf | ||
| Questions.docx | DOCX document | |
| General_References.doc | DOC document | |
| HAZARDOUS_MATERIALS_IDENTIFICATION_LISTING.doc | DOC document | |
| SubContracting_Plan.pdf | ||
| P15PS01388__Final.pdf | ||
| MACA_150067_-_PROJECT_SPECIFICATIONS_06.10.15_DSC.pdf | ||
| MACA_135_117632_A_Full_Combined_Set.pdf | ||
| Past_Performance_Questionnaire_-_MACA.pdf | ||
| Wage_Decision_-_KY150147_(5-22-15).docx | DOCX document | |
| MACA_150067_Pre-solicitation_Notice.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P15PS01388 Amendment 0001
SECTION B – SUPPLIES OR SERVICES AND PRICES
PRICE SCHEDULE
Title: MACA 150067 Restore Cave Trail Solicitation No.: P15PS01388 Amdendment 0001
DATE:
COMPANY NAME:
CONTACT NAME:
PHONE:
E-MAIL:
Fore detailed line item descriptions see Section 01 27 00 – Definition of Contract Line Items
CLIN Description Qty. Unit Unit Price Extended Price
10 Mobilization and Demobilization for Season 1 1 LS
TOTAL LINE ITEM PRICE (Contract Line item number 10) :
20A Concrete Pavers with sand leveling course 9990 SF
20B Concrete Bands 18 EA
20C Concrete Chase 37 LF
20D 18” Ht. Composite Lint Guard 1110 LF
20E Non-Ground Penetration Lint Guard 696 LF
20F Handrails 230 LF
20G Aggregate Fill 24 CY
20H FRP Trail Grating 92 SF
20I Concrete Steps No. 1 – Including Handrail 1 LS
20J Concrete Steps No. 2A – Including Handrail 1 LS
TOTAL LINE ITEM PRICE (Contract Lines item numbers 20A through 20J) :
30A Concrete Paving 2840 SF
30B Typical 12” Ht. Composite Lint Guard 1126 LF
30C Handrails 22 LF
30D Aggregate Fill 10 CY
TOTAL LINE ITEM PRICE (Contract Lines item numbers 30A through 30D):
TOTAL BASE BID PRICE (Contract Line items 10, 20A through 20J and 30A through 30D) :
40 Bid Option 0 - Mobilization / Demobilization (Season 2) 1 LS
TOTAL LINE ITEM PRICE (Contract Line item number 40):
50A Bid Option 1 - Concrete Paving 4100 SF
50B Bid Option 1 – Concrete Chase 18 LF
50C Bid Option 1 – Concrete Steps No. 1B – Including Handrails
1 LS
50D Bid Option 1 – Concrete Steps No. 2 – Including Handrails
1 LS
50E Bid Option 1 – Concrete Steps No. 3 – Including Handrails
1 LS
50F Bid Option 1 – Handrail 360 LF
50G Bid Option 1 – Retrofit of Existing Handrail 178 LF
50H Bid Option 1 – Typical 12” Ht. Composite Lint Guard 316 LF
50I Bid Option 1 - Stainless Steel Gate 1 EA
50J Bid Option 1 – FRP Trail Grating – Including Concrete Base
78 SF
50K Bid Option 1 – Concrete Slip Resistant Surface 200 SF
50L Bid Option 1 – Aggregate Fill 12 CY
TOTAL BID OPTION No. 1 PRICE (Contract Lines item numbers 50A through 50L) :
60A Bid Option 2 – Concrete Pavers with sand leveling course
2332 SF
60B Bid Option 2 – Concrete Bands 7 EA
60C Bid Option 2 – Concrete Chase 8 LF
60D Bid Option 2 – Concrete Paving 295 SF
60E Bid Option 2 – 18” Ht.
Composite Lint Guard 570 LF
60F Bid Option 2 – 12” Ht.
Stainless Steel Mesh Lint Guard
206 LF
60G Bid Option 2 – Handrail 215 LF
60H Bid Option 2 – Concrete Steps No. 6 – Including Handrail
1 LS
60I Bid Option 3 – Concrete Steps No. 7 – Including Handrail
1 LS
60J Bid Option 2 – FRP Steps No. 1 1 LS
60K Bid Option 2 – Stainless Steel Gate 2 EA
60L Bid Option 2 – Aggregate Fill 6 CY
60M Bid Option 2 – River Hall FRP Grate Walkway 1 LS
TOTAL BID OPTION No. 2 PRICE (Contract Lines item numbers 60A through 60M) :
70A
Bid Option 3 – 12” Ht.
Composite Lumber Lint Guard Outboard of Existing Trail
1104 LF
70B
Bid Option 3 – 12” Ht.
Composite Lumber Lint Guard Inboard of Existing Trail
466 LF
70C Bid Option 3 – Clean Existing Concrete Surface 1 LS
TOTAL BID OPTION No. 3 PRICE (Contract Lines item numbers 70A through 70C) :
80A Bid Option 4 – Reinforced Concrete 10 CY
80B Bid Option 4 – Aggregate Fill 26 CY
80C Bid Option 4 – FRP Steps 1 LS
80D Bid Option 4 – FRP Tube Guardrail 104 LF
TOTAL BID OPTION No. 4 PRICE (Contract Lines item numbers 80A through 80D) :
90A Bid Option 5 – Demolition of Existing Boardwalk 1 LS
90B Bid Option 5 – Concrete Pavers with sand leveling course
6830 SF
90C Bid Option 5 – Concrete Bands 16 EA
90D Bid Option 5 – Concrete Chase 30 LF
90E Bid Option 5 – 18” Ht.
Composite Lint Guard (with existing and new posts)
1120 LF
90F Bid Option 5 – Handrails 164 LF
90G Bid Option 5 – Aggregate Fill 46 CY
TOTAL BID OPTION No. 5 PRICE (Contract Lines item numbers 90A through 90G) :
TOTAL PROPOSED PRICE-BASE PLUS ALL OPTIONS
All measurement and payment information is in the project specifications, Section 012700
PRICE SCHEDULE GENERAL NOTES
1. Offerors shall submit a price for all line items; failure to do so may render the offer unacceptable.
2. Refer to attached project specifications for definitions of the line items.
3. On lump-sum line items, provide total price only.
4. If no item exists for a portion of the work, include the price in a related line item.
5. In case of error in extension of prices, unit price governs.
6. In case of error in summation, the total of the corrected amounts govern.
7. The Government reserves the right to award any or no options at the time of award.
8. Contractor acknowledges the quantity of a unit-priced item in this contract is an estimated quantity. Refer to clause 52.211-18 in section “F” of this solicitation for additional information.
9. Bonding Requirements: All bonds including bid bonds shall be obtained in accordance with the contract clauses. Offerors are now advised that the Government will inspect, accept and take possession of completed work and release the bonding for that work upon the completion of each construction season in accordance with FAR 28.203-5.
File details come from the government source that posted it. Updated .