Question and Answers - P15PS01388 Amendment 00001

View the file

Other files for this federal contract opportunity

Other files attached to Mammoth Cave - Reconstruct Cave Trails, newest first.
File Type Posted
Questions.docx DOCX document
SF-30_Amendment_00002_-_P15PS01388.pdf PDF
Cave_Trail_Lower_Dirt_Removal_and_Placement_Areas.pdf PDF
4_-_SECTION_01_27_00_-_DEFINITION_OF_CONTRACT_LINE_ITEMS_-_REV.pdf PDF
General_References.doc DOC document
Proposed_Equals.doc DOC document
SF_1442_-_P15PS01388.pdf PDF
SF30_-_P15PS01388.pdf PDF
Revised_Bid_Schedule.pdf PDF
HAZARDOUS_MATERIALS_IDENTIFICATION_LISTING.doc DOC document
SubContracting_Plan.pdf PDF
P15PS01388__Final.pdf PDF
MACA_135_117632_A_Full_Combined_Set.pdf PDF
Past_Performance_Questionnaire_-_MACA.pdf PDF
Wage_Decision_-_KY150147_(5-22-15).docx DOCX document
MACA_150067_-_PROJECT_SPECIFICATIONS_06.10.15_DSC.pdf PDF
MACA_150067_Pre-solicitation_Notice.pdf PDF
Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Bid date is set for July 10th. Is this date firm or is an addendum issued/to be issued extending the bid date? We just found out about the project and are requesting additional time for the bid.

Answer 1: The response date for this solicitation will be extended July 14, 2015 at 16:00 MST, effective in Amendment 00001.

2. Will a prebid be held? There were conflicting notes about this. In the project specifications, section 01 11 00 Summary of work, it states a four hour prebid site meeting shall be facilitated and include a cave tour. Other notes in the solicitation state no prebid. Please clarify.

Answer 2: There will be no pre-bid site meeting for this solicitation. See Pages 133/134, reference Provision 52.236-27.

3. We have performed work/are prequalified with multiple state and federal agencies. Are there any prequalification requirements for the National Park Service/Department of Interior?

Answer 3: No.

4. While working on our proposal for this project we have noticed that Standard Form 1442 is missing information in Blocks 3, 5 and 7; which we typically find completed by the issuer. Was this information intentionally omitted?

Answer 4: Amendment 00001 will have more complete information listed that will be pertinent to this solicitation.

5. In essence, it appears to me that what NPS is requesting is a Bid in accordance with the CLINs of Section B. It appears that what NPS wants submitted to be able to be considered for bidding is the following:

· Section A Filled Out

· Section B Filled Out

· Section J All Attachments Filled Out

· Section K Certification of Size Submitted Answer 5: Please reference Section L – Instructions, Conditions, and Notices to Offerors and Sub Section B: Submission of Offers.