Project Specifications Mammoth Cave Trails
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Cave_Trail_Lower_Dirt_Removal_and_Placement_Areas.pdf | ||
| Questions.docx | DOCX document | |
| SF-30_Amendment_00002_-_P15PS01388.pdf | ||
| Revised_Bid_Schedule.pdf | ||
| HAZARDOUS_MATERIALS_IDENTIFICATION_LISTING.doc | DOC document | |
| Proposed_Equals.doc | DOC document | |
| SF_1442_-_P15PS01388.pdf | ||
| SF30_-_P15PS01388.pdf | ||
| 4_-_SECTION_01_27_00_-_DEFINITION_OF_CONTRACT_LINE_ITEMS_-_REV.pdf | ||
| Questions.docx | DOCX document | |
| General_References.doc | DOC document | |
| SubContracting_Plan.pdf | ||
| P15PS01388__Final.pdf | ||
| MACA_135_117632_A_Full_Combined_Set.pdf | ||
| Past_Performance_Questionnaire_-_MACA.pdf | ||
| Wage_Decision_-_KY150147_(5-22-15).docx | DOCX document | |
| MACA_150067_Pre-solicitation_Notice.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Mammoth Cave National Park Mammoth Cave, Kentucky
REHABILITATE HISTORIC CAVE TRAIL
PMIS #: 150067
PROJECT SPECIFICATIONS
100% FINAL CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
DENVER SERVICE CENTER
JUNE 2015
MACA 150067 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00 Contract Modification Procedures
01 11 00 Summary of Work
01 27 00 Definition of Contract Line Items
01 31 00 Project Management & Coordination
01 32 16 Construction Schedule
01 33 23 Submittal Procedures
01 35 13.22 Archeological Protection
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 42 00 References
01 50 00 Temporary Facilities and Controls
01 57 19.11 Indoor Air Quality Management
01 57 19.12 Noise & Acoustics Management
01 57 23 Under-An-Acre Pollution Prevention
01 67 00 Product Requirements
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 78 23 Operation and Maintenance Data
01 81 13 Sustainable Design Requirements for NON-LEED™ Projects
DIVISION 03 - CONCRETE
03 30 53 Miscellaneous Cast-In-Place Concrete
DIVISION 05 - METALS
05 50 00 Metal Fabrication
05 52 13 Pipe and Tube Railings
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 63 Exterior Carpentry
06 60 00 Fiberglass Reinforced Polymer (FRP) Products
DIVISION 26 - ELECTRICAL
26 00 00 Miscellaneous Electrical Requirements
DIVISION 31 - EARTHWORK
31 20 00 Earth Moving
MACA 150067 TOC-2
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 14 00 Unit Paving
DIVISION 33 - UTILITIES
33 46 00 Subdrainage
MACA - 150067 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
MACA - 150067 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
MACA - 150067 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate
MACA - 150067 01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
MACA - 150067 01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit……………………6%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
MACA - 150067 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
MACA - 150067 01 11 00 - 1
050611 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
1.GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Contractor use of premises.
4. Public use of site.
5. Work Restrictions.
6. Special Construction Requirements.
7. Soils Investigation Report.
8. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The project is located in the Historic Tour portion of Mammoth Cave. Access to the project site is through the Historic Entrance as shown on the site plans.
B. The Work consists of the following:
1. This project will reconstruct unsafe portions of the cave tour trail along the Historic Tour route within Mammoth Cave. The project will NOT include the following areas:
a. Historic Entrance to Rotunda (Demonstration Area) - Station U0+00 to Station
U6+45 except for transitions to new improvements
b. Previously constructed demonstration area between Methodist Church and
Wandering Willies Spring (Station U13+05 to Station U20+20) except for transitions to new improvements
c. Bridge over the Side Saddle Pit (Station L5+62 to Station L5+78)
d. Bridge over the Bottomless Pit (Station L7+90 to Station L8+10)
e. Mammoth Dome & Tower except for the Ruins of Karnak
f. Rafinesque Avenue
2. The existing trails will be reconstructed using concrete pavers, concrete paving, or other suitable/sustainable materials as noted in the site plans. Much of the trail will have a lint guard and/or a trail edge. The project includes removal of dust and surface dirt from the existing trail surfaces, installation/replacement of steps, elevated walkways, upgrade of safety rails, and installation of lint guards along most of the edges of the trails.
C. Project will be constructed under a single prime contract. The Base Bid work is to be completed in the first season of work between September 8, 2015 and May 20, 2016. Bid Options included in the contract award can be completed, or a portion thereof as approved by the CO, in the first season or completed during the second season (September 6, 2016 to May 19, 2017).
MACA - 150067 01 11 00 - 2
1.3 WORK SCHEDULE PLAN
A. A four hour pre-bid site meeting shall be facilitated by the government. The meeting will start in the Training Center and will include a Cave Trail walk through.
B. Contractor shall submit detailed Work Schedule Plan to the Contracting Officer (CO) for approval prior to beginning work.
C. Period of highest visitation (No Construction Allowed):
1. Period from Memorial Day weekend through Labor Day weekend (May 26, 2016 to September 6, 2016 and May 25, 2017 to September 5, 2017).
2. During this period contractor will not be allowed to work within the cave.
3. Contractor will be required to move all stored construction materials out of the cave prior to Memorial Day 2016 and 2017.
D. Period of lower visitation (Portion of Trail to Be Open to the public Every Day):
1. Fall Break Season: October 3, 2015 to October 18, 2015 and October 1, 2016 to October 16, 2016.
2. Spring Break Season: Spring Break season: March 19, 2016 to April 10, 2016 and March 18, 2017 to April 16, 2017.
3. Section of trail from Historic Entrance to the entrance of Rafinesque Trail (Station U0+00 to Station U5+00 and B5+60 to B11+33) shall remain open for tours at all times during visitation hours.
4. The portion of the upper historic trail (Station U6+00 to U28+63) will be closed to public during this period.
5. The entire lower historic trail (Station L0+00 to L28+17) will be closed to public during this period.
E. Period of lowest visitation (Portion of Trail to Be Open to the public on Saturdays & Sundays only):
1. Period from after Labor Day to Fall Break (September 2, 2015 to October 2, 2015 and
September 7, 2016 to September 30, 2016).
2. Period from after Fall Break to Spring Break (October 19, 2015 to March 18, 2016 and
October 16, 2016 to March 17, 2017).
3. Period from end of Spring Break to before Memorial Day (April 11, 2016 to May 25, 2016 and April 17, 2017 to May 24, 2017).
4. Section of trail from Historic Entrance to the entrance of Rafinesque Trail (Station
U0+00 to Station U5+00 and B5+60 to B11+33) shall remain open for tours at all times during visitation hours on Saturdays and Sundays.
5. The portion of the upper historic trail (Station U6+00 to U28+63) will be closed to public during this period.
6. The entire lower historic trail (Station L0+00 to L28+17) will be closed to public during this period.
F. Park will need full access for the public to Methodist Church and Rafinesque Hall for Cave Sing event on the first weekend in December (2016 and 2017). Contractor shall wrap up work within this area in a way that it is safe for the public to reach these locations.
MACA - 150067 01 11 00 - 3
G. Contractor shall move the materials through the Upper Historic during non-cave tour hours, unless otherwise approved by the Contracting Officer. During the Period of Lowest Visitation the contractor may move materials through the Upper Historic while taking appropriate accommodations and protections for the visitors.
H. Mammoth Cave will limit publication of cave tour schedules, for the non-summer, fall break, and spring break periods to 2 months ahead of schedule. The Contractor shall provide schedule information to support this schedule and then stick to the schedule provided.
1.4 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated on the site plans. Limits of Construction are to be edge of existing cave trails for this section. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. The lower level of the Historic Tour Route will be closed to the public during portion of the construction of this project. However, the upper level of the Historic Tour Route will remain open and in use for tours. The Contractor's activities shall in no way have any negative impact on these tours, and the Contractor's use of the upper Historic area will be subject to the approval of the Contracting Officer. Contractor shall maintain access in the lower Historic area for National Park Service administrative and other official business throughout the construction phase. Contractor shall implement all measures necessary to minimize disruption to tours in other parts of the cave and in particular to the tours accessing the cave through the same entrance used by the Contractor's personnel.
2. The Contractor will be expected to observe all of the requirements of Mammoth Cave
National Park regarding construction in the cave. Included among these requirements are no tobacco use of any form; removal of demolition materials on a daily basis; protection of the cave features, control of dust and noise, and White Nose Syndrome protocols.
3. Smoking within buildings, temporary storage sheds or within the cave or within 200 feet of cave entrances is strictly prohibited. Any Contractor employees that are caught smoking on the project in these areas will be promptly removed from the cave and will be banned from working on the project. All other uses of tobacco are prohibited
4. There are sensitive natural and cultural features in the cave. The Contractor's employees will only be permitted to be off the cave trails where it is necessary to carry out the work of this project. Removing or damaging any natural and/or cultural feature of the cave is a violation of Federal Law and those caught doing so will be prosecuted to the full extent of the law. The terms removing or damaging are inclusive of writing, marking, adding graffiti, or otherwise defacing cave features. Reference Federal Regulation 36 CFR 7.36 for specific language regarding "off trail" restrictions.
5. Only Contractor employees specifically working on the job during normal Contractor working hours will be permitted in the cave. Neither Contractor nor Contractor's employees shall be allowed to bring along family members or friends to the jobsite.
MACA - 150067 01 11 00 - 4
6. Contractor employees will be permitted to carry in sack lunches provided that there is no cooking or warming equipment used, and that all wrappers, trash and leftovers are carried out on the same day as such is brought in.
7. Contractor will be allowed to concurrently use multiple work crews within the project work limits during the work periods defined above.
B. Storage of Materials: Confine storage of materials to those locations designated and/or approved by the CO. Do not store materials in the passageway within the cave without approval from the
CO.
C. Preservation of Natural Features: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Contractor will be responsible for the costs of repair work to any cave walls and features damaged as a result of his operations.
1. Protect cave walls and other features during the movement of materials through the cave passageways. Use padded blankets as necessary to protect the cave walls. Defacing a national monument, including writing a name on the cave wall is a felony offense.
2. Provide temporary barriers to prevent unauthorized personnel from construction area. See Section 015000 for further requirements.
3. Do not drill into or set bolts or other anchoring devices in cave walls and ceilings.
4. Do not fasten ropes, cables, or other supports to cave walls or features.
5. Carefully supervise work near cave features to prevent damage.
6. Protect surrounding cave features and adjacent passageways from dust created by the construction process. Contractor shall construct a dust enclosure where digging, cutting and/or other dust generating activities are occurring. A filter system will be required to ensure dust does not contaminate the cave. Enclose the immediate construction areas with plastic barriers to prevent the migration of dust and debris into the adjoining cave passages. Construct containment enclosures and use sheeting as necessary to protect walls and cave floor and ceiling. Attaching dust mitigation enclosure to the cave walls or ceilings is prohibited. Prior to construction of containment enclosures, contractor shall submit containment plan for approval by the Contracting Officer.
7. All waste materials, including metal shavings and dust, from drilling, sawing etc. must be collected and properly disposed of outside the Park.
8. Implement methods for minimization of dust from construction activities such as rock excavation; drilling dowels and rock anchors; and concrete mixing. Dust control methods used shall be at the discretion of the Contractor and may include collection and filtration;
vacuuming; and misting. The Contracting Officer may stop work on the Project until satisfactory dust minimization measures have been implemented.
D. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
MACA - 150067 01 11 00 - 5
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
3. Contractor shall take extra care to not damage existing grass pavers, exposed aggregate concrete and asphalt from parking lot to the historic entrance. Contractor shall be responsible repair the damaged areas at no additional time or cost to the government.
E. Construction Camp: Establishment of a camp within the park will not be permitted.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from Park. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
1.5 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 6 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Work during weekend will be considered on a case by case basis and must be approved by the CO in writing.
2. Early Morning Hours: Work during early morning hours will be considered on a case by case basis and must be approved by the CO in writing.
3. Overnight Hours: Work during overnight hours will be considered on a case by case basis and must be approved by the CO in writing. Overnight work is to be coordinated with the CO and Archeologist, and will only be allowed if the archeologist is available to be present or no ground disturbing work will be performed.
4. Work during Federal Holidays and/or day the park is closed due to inclement weather will not be allowed unless approved by CO in writing.
B. Tobacco Products
1. No tobacco products will be allowed within the construction zone and/or in the cave. Any member of the contractor's staff caught using any tobacco products (including E cigarettes) will be immediately removed from the site. It is up to the contractor to ensure compliance with this requirement.
2. Tobacco products must be properly disposed of when used outside of the construction zone. Disposing of cigarette butts on the ground and/or spitting chewing tobacco onto the ground will be considered littering. The offending person will be ticketed by law enforcement and removed from the site.
MACA - 150067 01 11 00 - 6
C. Restrooms at Great Relief Hall
1. Contractor’s crew will be allowed to use existing restrooms within the cave at the Great Relief Hall. Contractor shall be responsible for cleaning the restrooms, monitoring the sewage collection tank, and having the sewage collection tank pumped as needed during the course of the project.
D. All food, food containers, bags, plastic bottles, napkins, etc. must be removed at the end of each day.
E. Friends and family are not allowed on the job site -- above or below ground. Only those people working on this project will be allowed within the limits of construction.
F. When working in the cave, the contractor will limit his activities to those areas authorized by the
Contracting Officer. Wandering/exploring beyond those limits constitutes grounds for removal from this project.
G. In the cave, digging or any other activity that results in ground disturbance is not allowed without the approval of the on-site Archeologist.
H. Existing Utilities
1. Contractor shall be responsible for locating and preventing damage to any power, lighting, fiber optic cable, and telephone system potentially impacted by the work of this Contract. If damage occurs, repair system at no additional expense to the Government.
2. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
I. The contractor shall clean their footwear (boots) every time they enter and leave the cave. All members of the contractor's crew and/or sub-contractors will be required to sign a document stating they will clean their footwear before entering any other cave. Contractor shall also decontaminate any equipment brought out of the cave per the park White-Nose Syndrome Response Plan (https://www.whitenosesyndrome.org/sites/default/files/http___www.nps_.gov_maca_parkmgmt_l oader.pdf).
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by the NPS will be used for purposes of managing communication and documents during the construction stage.
1. See Section 01 31 00 “Project Management and Coordination” for requirements on using the Project Website.
B. Special Events:
1. Park will need full access for the public to Methodist Church and Rafinesque Hall for Cave Sing event on 1st Sunday in December (2015 and 2016). Contractor shall wrap up
MACA - 150067 01 11 00 - 7
work within this area in a way that it is safe for the public to reach these locations. The contractor is to complete the work and safely open the section of trail from the Historic Entrance to the Methodist Church and Rafinesque Hall on the Wednesday prior to the first Sunday in December (2015 and 2016). No items shall be stored from the Historic Entrance to the Methodist Church.
1.8 WEIGHT LIMITATIONS ON CAVE TRAIL PAVERS
A. Inside the Historic Section of the cave, there are three segment of trails covered with concrete pav-ers. The following restrictions apply to the delivery of materials across these pavers:
1. When using a self-propelled vehicle, the Contractor shall cover the pavers with 3/4-inch plywood before work begins, and remove it at the conclusion of the project.
2. Hand-pulled carts with a total weight over 500 pounds, and/or a cart with tires less than
3-inches wide, will require the installation and removal of the plywood covering. The plywood covering must be installed in a way not to pose a hazard or tripping hazard to employees or visitors.
3. Contractor will be responsible for the replacement of any pavers damaged or displaced by the construction activities
4. Exceptions to these limitations are subject to the approval of the Contracting Officer.
1.9 USE OF POWER EQUIPMENT INSIDE THE CAVE
A. The use of all equipment inside the cave is subject to the approval of the Contracting Officer. Spe-cific restrictions are as follows:
1. No internal combustion powered equipment is allowed.
2. Propane equipment is allowed subject to the Contracting Officer's approval.
3. Electric powered equipment is allowed.
4. Welding is discouraged inside the cave. However, it may be approved by the Contracting
Officer with a 7-day advance notice in situations where no reasonable alternative exists.
See Specification Section 055000 - METAL FABRICATION for welding requirements.
5. All waste materials, including metal shavings and dust, from drilling, sawing, etc. must be collected and properly disposed of outside the Park. Construct containment enclosures and use sheeting as necessary to protect walls and cave floor. Prior to construction of containment enclosures, Contractor shall submit Containment Plan for approval by Con-tracting Officer.
MACA - 150067 01 11 00 - 8
1.10 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
B. Existing cave features and confined passageways limit the size of structural members that can be delivered to the project site. The maximum length of each member(s) that can be transported throughout the cave shall be field verified by the contractor. Contractor shall verify the access route dimensions and ensure that the trail components are manufactured to dimensions that will fit through the passageways.
1.11 CONSTRUCTION MATERIALS
A. All materials shall be of new material and be Contractor-furnished.
1.12 SALVAGED MATERIALS
A. All structural steel and other materials removed as part of this contract will become property of the Contractor and shall be removed from the Park.
1.13 CONTRACTOR’S EMPLOYEE BADGES AND VEHICLE IDENTIFICATION:
Badges and Vehicle Identification requirements are as follows:
1. Contractor shall provide identification cards for all employees working on-site. These cards must be visible at all times for all employees working at Mammoth Cave.
2. All vehicles owned by the Contractor or his employees that will be used to support this Contract must have a Mammoth Cave National Park Vehicle Identification Tag. Contrac-tor shall provide vehicle identification tags for his employees. Vehicles shall not be used on-site without this identification tag.
1.14 CAVE ACCESS KEYS
Special emphasis is placed on key control. Contractor will be provided with a maximum of four keys. All keys will be issued to the Contractor, not to individual Contractor employees. If a key is lost by a Contractor's employee, all locks affected will be re-keyed and ALL keys will be re-vised/reissued. This is a very expensive process and the Contractor will be held financially liable for re-keying and reissue at a cost of $400 per key. The Contractor is responsible to ensure all keys are returned at the end of the project.
MACA - 150067 01 11 00 - 9
2 PRODUCTS (Not Used)
3 EXECUTION
3.1 The contractor is to keep the entrance gate in the closed position and locked at all times, unless contractor employees are working within 15 feet of the gate.
END OF SECTION 01 11 00
MACA - 150067 01 27 00 - 1
050611 DEFINITION OF CONTRACT LINE ITEMS
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1A through 1K, (Base Bid No. 1) Improvements to Upper Historic
Trail
1. This item consists of all labor and materials required for improvements to the trail plans of
Methodist Church (approximate Station U12+00 to U13+00) and Wandering Willie’s
Spring (approximate Station U20+20) to the top of Steps of Time (Station U28+00) per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 2A through 2E, (Base Bid No. 2) Improvements to Upper Historic
Trail – Little Bat Avenue
1. This item consists of all labor and materials required for improvements to the trail plans of for Little Bat Avenue from the top of Mammoth Dome Tower (Station B0+00) to end of previously completed demonstration project approximate (Station B5+60).
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
C. Contract Line Item No. 3A through 4L, (Bid Option No. 1) Improvements to Lower Historic
Trail Station L+00 to L12+30
1. This item consists of all labor and materials required for improvements to the trail plans from bottom of Steps of Time (Station L0+00) to Entrance to Fat Man’s Misery
(approximate Station L12+30) per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
MACA - 150067 01 27 00 - 2
050611 DEFINITION OF CONTRACT LINE ITEMS
3. Payment will be made at the contract lump sum price.
D. Contract Line Item No. 4A through 4K, (Bid Option No. 2) Improvements to Lower Historic
Trail Station L14+50 to L19+50
1. This item consists of all labor and materials required for improvements to the trail plans from the Exit to Fat Man’s Misery (Station L14+50) to Top of Steps at Vanderbilt Hall
(approximate Station L19+50) per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
E. Contract Line Item No. 5A through 5C, (Bid Option No. 3) Improvements to Lower Historic
Trail Station L19+50 to L28+20
1. This item consists of all labor and materials required for improvements to the trail plans from Top of Steps at Vanderbilt Hall (approximate Station L19+50) to Base of Mammoth
Dome Tower (L28+20) per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
F. Contract Line Item No. 6A through 6D, (Bid Option No. 4) Improvements to Ruins of
Karnak
1. This item consists of all labor and materials required for construction of slab on grade platform at Ruins of Karnak at Mammoth Dome Tower per the site plans and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
G. Contract Line Item No. 7A through 7G, (Base Bid No. 5) Demolition of Existing Boardwalk and Improvements to Trail
1. This item consists of all labor and materials required for demolition and removal of existing boardwalk and all of its components (decking, railings, columns, foundation, etc.) from
Rotunda to Methodist Church (approximately Station U6+50 to Station U12+00). Work of this item shall include the complete removal from the cave and removal from the Park of all demolished materials. This item also includes all labor and materials required for improvements to the trail below existing boardwalk per the drawings and specifications.
2. Measurement for payment will be lump sum or percentage complete of line item per scheduled value.
3. Payment will be made at the contract lump sum price.
END OF SECTION 01 27 00
MACA - 150067 01 31 00 - 1
060613 PROJECT MANAGEMENT AND COORDINATION
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative provisions for coordinating construction operations on
Project including, but not limited to, the following:
1. Construction Coordination.
2. Coordination Drawings.
3. Requests for Information (RFIs).
4. NPS/DSC SharePoint Project Website.
5. Project meetings.
6. Environmental Coordination.
7. Permits
B. Related Requirements:
1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.
2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
MACA - 150067 01 31 00 - 2
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's Construction Schedule.
2. Preparation of the Schedule of Values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
5. Progress meetings.
6. Permit requirements.
7. Pre-installation conferences.
8. Project closeout activities.
9. Commissioning activities.
1.3 SUBMITTALS
A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.
1. Letter designating Project Superintendent.
2. Construction Schedule.
3. A comprehensive breakdown of the Schedule of Values.
4. Accident Prevention Plan.
5. A list of Subcontractors for this project.
6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.
7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.
8. Waste Management Plan.
9. Quality Control Plan.
10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).
11. Indoor Air Quality (IAQ) Management Plan.
12. Contractors Commissioning Plan.
13. White Nose Syndrome training certification. The contractor shall submit written certification that each employee working in the cave has received training in White Nose
Syndrome (WNS).
B. All items listed must be provided to the Contracting Officer before the Pre-Construction
Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to
Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.
Work shall not commence until written Notice to Proceed has been issued.
MACA - 150067 01 31 00 - 3
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.
1. CO will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially.
2. Date.
3. RFI subject.
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the
Contract Time or the Contract Sum, Contractor shall state impact in the RFI.
8. Contractor's signature.
9. Requested date for response.
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:
1. Enter the general information at the top of the form.
2. Under the “Action” section at the bottom of the form, select “Question” then select
“CMR” in the drop-down of the “Send to” box.
3. Enter the details of the question and attach related documents.
4. Select “Submit Form” at the bottom of the page.
D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in the Contract
Documents.
e. Requests for adjustments in the Contract Time or the Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
MACA - 150067 01 31 00 - 4
2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.
3. CO's action on RFIs may result in the need for a change to the Contract Time or the
Contract Sum. All contract changes will be processed following the terms and conditions of the contract.
1.5 PROJECT WEB SITE
A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:
1. Project directory.
2. Project correspondence.
3. Meeting agendas and minutes.
4. Contract modifications forms and logs.
5. RFI form and processing.
6. Task and issue management.
7. Photo documentation.
8. Baseline schedule, schedule updates and calendar management.
9. Submittal form and processing.
10. Payment coordination documentation.
11. Drawing and specification document hosting, viewing, and updating.
12. Online document collaboration.
13. Reminder and tracking functions.
14. Archiving functions.
15. Notification of submittal and RFI statuses and current responsible party.
16. Permits and addendums
B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.
C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:
http://www.nps.gov/dscw/precon_spproj.htm
MACA - 150067 01 31 00 - 5
1. Roles & Responsibilities/ Lines of Authority.
2. Park rules and regulations.
3. Jobsite Safety.
4. Resolution of comments on required Division 01 documents.
5. Coordination of Subcontractors.
6. Labor law application.
7. Modifications.
8. Payments to Contractor.
9. Payroll reports.
10. Contract time.
11. Liquidated damages.
12. Contractor Performance Evaluation.
13. Display of Hotline posters.
14. Notice to proceed.
15. Correspondence procedures.
16. NPS/DSC SharePoint Project website.
17. Acceptance/rejection of work.
18. Progress meetings.
19. Submittal procedures.
20. NPS Final Accessibility Inspection.
21. Environmental requirements.
22. Permit requirements.
23. As-constructed drawings/operation and maintenance (O&M) manuals.
24. Saturday, Sunday, holiday and night work.
25. Reference materials.
26. Value engineering.
B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the
Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.
All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:
a. Approval of minutes of previous meetings.
b. Submittal status.
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications.
f. Work in progress and projected.
1) Status of required inspections (Special Inspections,…