HYPERLINK \l "_Toc363553496" Solicitation/Contract Form2
HYPERLINK \l "_Toc363553497" Supplies or Services/Prices2
HYPERLINK \l "_Toc363553498" Description/Specifications2
HYPERLINK \l "_Toc363553499" Packaging and Marking2
HYPERLINK \l "_Toc363553500" Inspection and Acceptance2
HYPERLINK \l "_Toc363553501" Deliveries or Performance3
HYPERLINK \l "_Toc363553502" Contract Administration Data3
HYPERLINK \l "_Toc363553503" Special Contract Requirements3
HYPERLINK \l "_Toc363553504" Contract Clauses3
HYPERLINK \l "_Toc363553505" 52.216-24 Limitation of Government Liability. (APR 1984)3
HYPERLINK \l "_Toc363553506" 52.216-25 Contract Definitization. (OCT 2010)3
HYPERLINK \l "_Toc363553507" DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (September 2011)4
HYPERLINK \l "_Toc363553508" List of Documents, Exhibits and Other Attachments5
HYPERLINK \l "_Toc363553509" Representations, Certifications, and Other Statements of Bidders5
HYPERLINK \l "_Toc363553510" Instructions,Conditions, and Notices to Bidders5
HYPERLINK \l "_Toc363553511" Evaluation Factors for Award5

Performance and payment bonds and alternative payment protections for construction contracts.5

Solicitation/Contract Form

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

The Contractor shall be required to (a) commence work under this contract within [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than [* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date]. The time stated for completion shall include final cleanup of the premises.

(End of clause)

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) - Alternate I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than [* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.]. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by [Contracting Officer insert date]. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of clause)

* The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

28.102 Performance and payment bonds and alternative payment protections for construction contracts

52.232-5 Payments under Fixed-Price Construction Contracts. (SEP 2002)

52.236-5 Material and Workmanship. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

Supplies or Services/Prices

Description/Specifications

Packaging and Marking

Inspection and Acceptance

Deliveries or Performance

Contract Administration Data

Special Contract Requirements

Contract Clauses

52.203-5 Covenant Against Contingent Fees. (APR 1984)

52.203-7 Anti-Kickback Procedures. (OCT 2010)

52.216-24 Limitation of Government Liability. (APR 1984)

(a) In performing this contract, the Contractor is not authorized to make expenditures or incur obligations exceeding [0]dollars.

(b) The maximum amount for which the Government shall be liable if this contract is terminated is [0]dollars.

(End of clause)

52.216-25 Contract Definitization. (OCT 2010)

(a) A [Construction] definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a , fixed-price proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.

(b) The schedule for definitizing this contract is (insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data:) []

(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) of this section, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with Subpart 15.4 and Part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.

(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by-

(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);

(ii) All clauses required by law as of the date of the Contracting Officer's determination; and

(iii) Any other clauses, terms, and conditions mutually agreed upon.

(2) To the extent consistent with subparagraph (c)(1) of this section, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.

(End of clause)

52.217-8 Option to Extend Services. (NOV 1999)

The Government may require continued performance of any services within the limits and at the rates specified in the contract. These rates may be adjusted only as a result of revisions to prevailing labor rates provided by the Secretary of Labor. The option provision may be exercised more than once, but the total extension of performance hereunder shall not exceed 6 months. The Contracting Officer may exercise the option by written notice to the Contractor within 30 days.

(End of clause)

52.222-6 Davis-Bacon Act. (JUL 2005)

52.222-8 Payrolls and Basic Records. (JUN 2010)

52.222-50 Combating Trafficking in Persons. (FEB 2009)

52.223-14 Reserved

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)

52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)

52.232-27 Prompt Payment For Construction Contracts. (OCT 2008)

52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)

52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)

52.237-2 Protection of Government Buildings, Equipment, and Vegetation. (APR 1984)

52.244-6 Subcontracts for Commercial Items. (DEC 2010)

1428.306 Insurance under fixed-price contracts.

DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (September 2011)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice [CO to edit and include the documentation required under this contract]:

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in CCR) will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

I.2 1452.228-70 Liability Insurance – Department of the Interior July 1996

(a) The Contractor shall procure and maintain during the term of this contract and any extension thereof liability insurance in form satisfactory to the Contracting Officer by an insurance company which is acceptable to the Contracting Officer. The named insured parties under the policy shall be the Contractor and the United States of America. The amounts of the insurance shall be not less than as follows:

$ 50,000 each person $50,000 each occurrence $100,000 property damage

(b) Each Policy shall have a certificate evidencing the insurance coverage. The insurance Company shall provide an endorsement to notify the Contracting Officer 30 days prior to the effective date of cancellation or termination of the policy or certificate; or modification of the policy or certificate which may adversely affect the interest of the Government in such insurance. The certificate shall identify the contract number, the name and address of the Contracting Officer, as well as the insured, the policy number and a brief description of the contract services to be performed. The contractor shall furnish the Contracting Officer with a copy of the acceptable insurance certificate prior to beginning the work

List of Documents, Exhibits and Other Attachments

Representations, Certifications, and Other Statements of Bidders

Instructions,Conditions, and Notices to Bidders

Evaluation Factors for Award

Other files for this federal contract opportunity

Other files attached to Jefferson Memorial Safety Netting, newest first.
File Type Posted
Sol_P15PS01309_Amd_000002.pdf PDF
Sol_P15PS01309_Amd_000001.pdf PDF
davis_bacon_building_wages_new.pdf PDF
DebrisNetting_Bid_Form_03-20-15.xls XLS spreadsheet
construction_clauses.rtf RTF text file
Sol_P15PS01309.pdf PDF
JEME_Bid_Documents_04-16-15.pdf PDF
evaluation_criteria_jefferson_memorial.rtf RTF text file
Jefferson_Memorial_Debris_netting_SOW_04-16-15.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .