JELA_Lighting_Projects_Clauses_.docx

DOCX document 94 KB Posted

Attached to
Replace Deficient Lighting Jean Lafitte NHP&P Federal contract opportunity
Solicitation number
P15PS01272
Issued by
Department of the Interior National Park Service

About this file

Contract Clauses

View the file

Other files for this federal contract opportunity

Other files attached to Replace Deficient Lighting Jean Lafitte NHP&P, newest first.
File Type Posted
Sol_P15PS01272.pdf PDF
Option_Bid_Item-3-Install_Showers_at_Ed_Center.pdf PDF
177176-177191-Projects-SOW.pdf PDF
-Option_Bid_Item-1-Rebuild_Water_Hydrants-WACC.pdf PDF
Construct_Boat_Storage_Building_at_Jones_Point.pdf PDF
The_National_Park_Service_JELA_Lighting.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P15PS01272 Replace Deficient Lighting Jean Lafitte NHP&P

A - Solicitation/Contract Form7
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)7
7
52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)7
52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999)7
52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)7
52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)8
52.236-5 Material and Workmanship. (APR 1984)11
52.236-7 Permits and Responsibilities. (NOV 1991)11
52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)11
52.236-10 Operations and Storage Areas. (APR 1984)11
52.236-12 Cleaning Up. (APR 1984)11
52.236-13 Accident Prevention. (NOV 1991) - Alternate I (NOV 1991)11
52.236-14 Availability and Use of Utility Services. (APR 1984)11
52.242-14 Suspension of Work. (APR 1984)11
52.246-21 Warranty of Construction. (MAR 1994)11
52.249-10 Default (Fixed-Price Construction). (APR 1984)11
B - Supplies or Services/Prices11
C - Description/Specifications11
SCOPE OF WORK11
D - Packaging and Marking17
E - Inspection and Acceptance17
52.246-12 Inspection of Construction. (APR 1996)17
F - Deliveries or Performance19
Not used19
G - Contract Administration Data19
DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)19
Contract Administration Data19
WORK HOURS20
H - Special Contract Requirements21
Davis-Beacon Wage Determination21
52.222-99 - Establishing a Minimum Wage for Contractors. (DEVIATION) (JUNE 2014)24
I - Contract Clauses25
52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUL 2013)25
52.204-13 System for Award Management Maintenance. (JUL 2013)25
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (AUG 2013)25
52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013)27
52.222-3 Convict Labor. (JUN 2003)27
52.222-6 Construction Wage Rate Requirements. (MAY 2014)27
52.222-8 Payrolls and Basic Records. (MAY 2014)27
52.222-9 Apprentices and Trainees. (JUL 2005)27
52.222-10 Compliance with Copeland Act Requirements. (FEB 1988)27
52.222-11 Subcontracts (Labor Standards). (MAY 2014)27
52.222-12 Contract Termination - Debarment. (MAY 2014)27
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)27
52.222-14 Disputes Concerning Labor Standards. (FEB 1988)27
52.222-15 Certification of Eligibility. (MAY 2014)27
52.222-21 Prohibition of Segregated Facilities. (FEB 1999)27
52.222-26 Equal Opportunity. (MAR 2007)27
52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014)27
52.222-50 Combating Trafficking in Persons. (FEB 2009)27
52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997)27
52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011)27
52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011)27
52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008)27
52.228-2 Additional Bond Security. (OCT 1997)27
52.228-5 Insurance - Work on a Government Installation. (JAN 1997)27
52.228-11 Pledges of Assets. (JAN 2012)27
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)27
52.228-13 Alternative Payment Protections. (JUL 2000)27
52.228-14 Irrevocable Letter of Credit. (MAY 2014)28
52.232-23 Assignment of Claims. (MAY 2014)32
52.232-27 Prompt payment for construction contracts. (MAY 2014)32
52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013)32
52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013)32
52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013)32
52.233-1 Disputes. (MAY 2014) - Alternate I (DEC 1991)32
52.233-3 Protest after Award. (AUG 1996)32
52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004)32
52.236-26 Preconstruction Conference. (FEB 1995)32
52.244-6 Subcontracts for Commercial Items. (JUL 2014)32
52.252-2 Clauses Incorporated by Reference. (FEB 1998)32
1452.203-70 Restriction on Endorsements (JUL 1996)32
1452.204-70 Release of Claims (JUL 1996)32
1452.228-70 Liability Insurance (JUL 1996)32
1452.215-71 Use and Disclosure of Proposal Information32
J - List of Documents, Exhibits and Other Attachments32
List of Documents, Exhibits, and Other Attachments32
K - Representations, Certifications, and Other Statements of Bidders33
52.204-8 Annual Representations and Certifications. (MAY 2014)33
52.236-28 Preparation of Proposals - Construction. (OCT 1997)37
L - Instructions,Conditions, and Notices to Bidders37
Email Proposals37
Required Submissions (documents attached to solicitation package):37
52.204-7 System for Award Management. (JUL 2013)37
52.214-34 Submission of Offers in the English Language. (APR 1991)37
52.214-35 Submission of Offers in U.S. Currency. (APR 1991)37
52.215-1 Instructions to Offerors - Competitive Acquisition. (JAN 2004)37
52.215-5 Facsimile Proposals. (OCT 1997)37
52.216-1 Type of Contract. (APR 1984)37
52.222-5 Construction Wage Rate Requirements-Secondary Site of the Work. (MAY 2014)37
52.236-27 Site Visit (Construction). (FEB 1995)38
52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)39
M - Evaluation Factors for Award39
Evaluation Factors for Award39

P15PS00171

Remodel Residence Bathrooms – Mount Rushmore

A - Solicitation/Contract Form

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)

(End of Clause)

52.222-23 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction. (FEB 1999)

52.222-27 Affirmative Action Compliance Requirements for Construction. (FEB 1999) 52.225-10 Notice of Buy American Requirement - Construction Materials. (MAY 2014)

(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American-Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).

(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.

(c) Evaluation of offers. (1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.

(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.

(d) Alternate offers. (1) When an offer includes foreign construction material not listed by the Government in this solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.

(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.

(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested-

(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or

(ii) May be accepted if revised during negotiations. (End of provision) 52.232-5 Payments Under Fixed-Price Construction Contracts. (MAY 2014)

52.236-5 Material and Workmanship. (APR 1984)

52.236-7 Permits and Responsibilities. (NOV 1991)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR 1984)

52.236-10 Operations and Storage Areas. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-13 Accident Prevention. (NOV 1991) - Alternate I (NOV 1991) 52.236-14 Availability and Use of Utility Services. (APR 1984) 52.242-14 Suspension of Work. (APR 1984)

52.246-21 Warranty of Construction. (MAR 1994)

52.249-10 Default (Fixed-Price Construction). (APR 1984)

B - Supplies or Services/Prices

C - Description/Specifications SCOPE OF WORK

See attached SOW.

D - Packaging and Marking

Not Used

E - Inspection and Acceptance 52.246-12 Inspection of Construction. (APR 1996)

(a) Definition. "Work" includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not -

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer's written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may -

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor's right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government's rights under any warranty or guarantee.

(End of clause)

F - Deliveries or Performance

Not used

G - Contract Administration Data

DOI ELECTRONIC INVOICING Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (April 2013)

Payment requests must be submitted electronically through the U. S. Department of the Treasury's Invoice Processing Platform System (IPP).

"Payment request" means any request for contract financing payment or invoice payment by the Contractor.

To constitute a proper invoice, the payment request must comply with the requirements identified in the applicable Prompt Payment clause included in the contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial item contracts. The IPP website address is: https://www.ipp.gov.

Under this contract, the following documents are required to be submitted as an attachment to the IPP invoice: The contractor shall upload supporting documents to IPP that show sufficient detail for payment.

The Contractor must use the IPP website to register, access and use IPP for submitting requests for payment. The Contractor Government Business Point of Contact (as listed in SAM will receive enrollment instructions via email from the Federal Reserve Bank of Boston (FRBB) within 3 - 5 business days of the contract award date. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email ippgroup@bos.frb.org or phone (866) 973-3131.

If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment, the Contractor must submit a waiver request in writing to the Contracting Officer with its proposal or quotation.

(End of Template)

Contract Administration Data

(a) The Contracting Specialist and Contracting Officer: Yancey Davis National Park Service-NATR MABO 2680 Natchez Trace Parkway Tupelo, MS 38804

(662) 680-4044 yancey_davis@nps.gov

(b) The Contracting Officer (CO) is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely with the CO. In the even the contractor effects any such change at the direction of any person other than the CO, the change will be considered made without authority and no adjustment will be made in the contract price to cover increase in costs incurred as a result thereof.

(c) Contractual problems, of any nature, which might occur during the life of the contract, must be handled in conformance with very specific public laws and regulations (e.g., Federal Acquisition Regulation), and must be referred to the CO for resolution. Only the CO is authorized to formally resolve such problems. Therefore, the contractor is hereby directed to bring all such contractual problems to the immediate attention of the CO.

(d) Any request for contract changes/modifications shall be submitted to the CO.

(e) The contractor and the Government may agree to perform a no-cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated line items. An example of a field change is: rerouting planned location of a sidewalk to avoid a tree (when quantities are not changed). All field changes must be approved by the CO prior to execution.

(f) All correspondence concerning this contract, such as requests for information (RFI), explanation of terms, and contract interpretation, shall be submitted to the CO.

FINAL PAYMENT

Final payment will be made only after receipt of all payrolls to include subcontractors, SF 1413 Statement of Acknowledgement for each subcontractor, project schedule, updated progress reports, material submittals, test reports, as-built drawings, and release of claims. Contractor must provide a signed copy of the 'Release of Claims' to the Contract Administrator upon submittal of final invoice.

AVAILABILITY OF UTILITIES SERVICES

Notwithstanding the provisions of contract clause FAR 52.236-14, Availability and Use of Utility Services, all reasonable required amounts of water, gas, electricity, etc., essential to contract performance shall be made available, at no cost to the contractor, from existing systems, outlets, and supplies. All temporary connections, outlets, and distribution lines as may be required will be installed by the contractor at the contractor's own expense.

UTILITIES CONSERVATION

The contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor.

OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) INSPECTIONS

The contractor shall be subject to inspections under the OCCUPATIONAL SAFETY AND HEALTH ACT (OSHA) program by inspectors of the Department of Labor.

FEDERAL HOLIDAYS

The following federal holidays are observed by the National Park Service:

New Year Day1 January
Martin Luther King Birthday3rd Monday in January
Presidents Day3rd Monday in February
Memorial DayLast Monday in May
Independence Day4 July
Labor Day1st Monday in September
Columbus Day2nd Monday in October
Veterans Day11 November
Thanksgiving Day4th Thursday in November
Christmas25 December

Note: Any of the above holidays falling on a Saturday will be observed on the preceding Friday; holiday falling on Sunday will be observed on the following Monday.

H - Special Contract Requirements Davis-Bacon Wage Determination

General Decision Number: LA150007 01/02/2015 LA7

Superseded General Decision Number: LA20140007

State: Louisiana

Construction Type: Heavy

Counties: Jefferson, Orleans, Plaquemines, St Bernard, St Charles, St James, St John the Baptist and St Tammany Counties in Louisiana.

HEAVY CONSTRUCTION PROJECTS (Includes flood control, water & sewer lines, and water wells. Also includes elevated storage tanks in all listed parishes except Plaquemines and St. James.

Excludes industrial construction-chemical processing, power plants, and refineries.)

Note: Executive Order (EO) 13658 establishes an hourly minimum wage of $10.10 for 2015 that applies to all contracts subject to the Davis-Bacon Act for which the solicitation is issued onor after January 1, 2015. If this contract is covered by theEO, the contractor must pay all workers in any classification listed on this wage determination at least $10.10 (or the applicable wage rate listed on this wage determination, if itis higher) for all hours spent performing on the contract. TheEO minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/02/2015

CARP0729-001 07/01/2012

Rates Fringes

MILLWRIGHT.......................$ 25.80 9.50

CARP1846-006 07/01/2014

Rates Fringes

CARPENTER

(formbuilding/formsetting and Piledrivers).....................$ 23.46 8.05

ELEC0130-005 06/01/2014

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JAMES, AND ST. JOHN THE BAPTIST PARISHES

Rates Fringes

ELECTRICIAN (including low voltage wiring)..................$ 29.60 9.77

ELEC1077-002 06/01/2014

ST. TAMMANY PARISH

Rates Fringes

ELECTRICIAN (including low voltage wiring)..................$ 22.80 7.50

ENGI0406-018 07/01/2009

Rates Fringes

OPERATOR: Power Equipment Bulldozer...................$ 21.26 6.70 Mechanic....................$ 23.31 6.70

* PLAS0567-003 07/01/2014

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JOHN THE BAPTIST, and ST. TAMMANY PARISHES

Cement Mason/Concrete Finisher...$ 21.43 6.19

PLAS0812-003 06/01/2004

ST. JAMES PARISH

Rates Fringes

Cement Mason/Concrete Finisher...$ 21.85 0.00

PLUM0060-002 06/02/2014

JEFFERSON, ORLEANS, PLAQUEMINES, ST. BERNARD, ST. CHARLES, ST.

JAMES (Southeastern Portion), ST. JOHN THE BAPTIST, and ST.

TAMMANY PARISHES

Plumbers (excluding pipe laying)..........................$ 28.13 11.16

PLUM0198-005 01/01/2014

ST. JAMES PARISH (Northwestern Portion)

Rates Fringes

PLUMBER (excluding pipe laying)..........................$ 25.54 10.73

SULA2004-007 05/13/2004

Rates Fringes

CARPENTER (all other work).......$ 13.75 2.60

Laborers:

Common/Landscape............$ 9.88 0.00 Fence.......................$ 11.24 0.00 Flagger.....................$ 8.58 0.00 Mason Tender................$ 7.25 0.00 Pipelayer...................$ 9.84 0.00

PIPEFITTER (excluding pipelaying)......................$ 17.52 4.51

Power equipment operators:

Backhoe/Excavator...........$ 14.42 0.00 Crane.......................$ 16.34 3.30 Dragline....................$ 16.50 0.00 Front End Loader............$ 13.89 0.00 Oiler.......................$ 10.03 0.00

Truck drivers:

Dump........................$ 11.01 0.00 Pickup......................$ 12.25 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added afteraward only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate wereprevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1,2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governingthis classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate thatno one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union andnon-union rates. Example: SULA2012-007 5/13/2014.

SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updateed and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date or the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION

52.222-99 - Establishing a Minimum Wage for Contractors. (DEVIATION) (JUNE 2014)

This clause implements Executive Order 13658, Establishing a Minimum Wage for Contractors, dated February 12, 2014, and OMB Policy Memorandum M-14-09, dated June 12, 2014.

(a) Each service employee, laborer, or mechanic employed in the United States (the 50 States and the District of Columbia) in the performance of this contract by the prime Contractor or any subcontractor, regardless of any contractual relationship which may be alleged to exist between the Contractor and service employee, laborer, or mechanic, shall be paid not less than the applicable minimum wage under Executive Order 13658. The minimum wage required to be paid to each service employee, laborer, or mechanic performing work on this contract between January 1, 2015, and December 31, 2015, shall be $10.10 per hour.

(b) The Contractor shall adjust the minimum wage paid under this contract each time the Secretary of Labor’s annual determination of the applicable minimum wage under section 2(a)(ii) of Executive Order 13658 results in a higher minimum wage. Adjustments to the Executive Order minimum wage under section 2(a)(ii) of Executive Order 13658 will be effective for all service employees, laborers, or mechanics subject to the Executive Order beginning January 1 of the following year. The Secretary of Labor will publish annual determinations in the Federal Register no later than 90 days before such new wage is to take effect. The Secretary will also publish the applicable minimum wage on www.wdol.gov (or any successor website). The applicable published minimum wage is incorporated by reference into this contract.

(c) The Contracting Officer will adjust the contract price or contract unit price under this clause only for the increase in labor costs resulting from the annual inflation increases in the Executive Order 13658 minimum wage beginning on January 1, 2016. The Contracting Officer shall consider documentation as to the specific costs and workers impacted in determining the amount of the adjustment.

(d) The Contracting Officer will not adjust the contract price under this clause for any costs other than those identified in paragraph (c) of this clause, and will not provide price adjustments under this clause that result in duplicate price adjustments with the respective clause of this contract implementing the Service Contract Labor Standards statute (formerly known as the Service Contract Act) or the Wage Rate Requirements (Construction) statute (formerly known as the Davis Bacon Act).

(e) The Contractor shall include the substance of this clause, including this paragraph (e) in all subcontracts.

(End of clause)

I - Contract Clauses

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards. (JUL 2013) 52.204-13 System for Award Management Maintenance. (JUL 2013)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment. (AUG 2013)

52.219-28 Post-Award Small Business Program Rerepresentation. (JUL 2013) 52.222-3 Convict Labor. (JUN 2003) 52.222-6 Construction Wage Rate Requirements. (MAY 2014) 52.222-8 Payrolls and Basic Records. (MAY 2014) 52.222-9 Apprentices and Trainees. (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements. (FEB 1988) 52.222-11 Subcontracts (Labor Standards). (MAY 2014) 52.222-12 Contract Termination - Debarment. (MAY 2014)

52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations. (MAY 2014)

52.222-14 Disputes Concerning Labor Standards. (FEB 1988) 52.222-15 Certification of Eligibility. (MAY 2014) 52.222-21 Prohibition of Segregated Facilities. (FEB 1999) 52.222-26 Equal Opportunity. (MAR 2007) 52.222-36 Equal Opportunity for Workers with Disabilities. (JUL 2014) 52.222-50 Combating Trafficking in Persons. (FEB 2009) 52.223-3 Hazardous Material Identification and Material Safety Data. (JAN 1997) 52.223-5 Pollution Prevention and Right-to-Know Information. (MAY 2011) 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. (AUG 2011) 52.225-13 Restrictions on Certain Foreign Purchases. (JUN 2008) 52.228-2 Additional Bond Security. (OCT 1997)

52.228-5 Insurance - Work on a Government Installation. (JAN 1997) 52.228-11 Pledges of Assets. (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)

52.232-23 Assignment of Claims. (MAY 2014)

52.232-27 Prompt payment for construction contracts. (MAY 2014)

52.232-33 Payment by Electronic Funds Transfer - System for Award Management. (JUL 2013) 52.232-39 Unenforceability of Unauthorized Obligations. (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. (DEC 2013) 52.233-1 Disputes. (MAY 2014) - Alternate I (DEC 1991) 52.233-3 Protest after Award. (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-26 Preconstruction Conference. (FEB 1995) 52.244-6 Subcontracts for Commercial Items. (JUL 2014) 52.252-2 Clauses Incorporated by Reference. (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/

(End of clause)

1452.203-70 Restriction on Endorsements (JUL 1996)

1452.204-70 Release of Claims (JUL 1996)

1452.228-70 Liability Insurance (JUL 1996)

1452.215-71 Use and Disclosure of Proposal Information

J - List of Documents, Exhibits and Other Attachments List of Documents, Exhibits, and Other Attachments

K - Representations, Certifications, and Other Statements of Bidders 52.204-8 Annual Representations and Certifications. (MAY 2014) L - Instructions,Conditions, and Notices to Bidders 52.204-7 System for Award Management. (JUL 2013)

52.216-1 Type of Contract. (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation. (End of provision)

52.236-27 Site Visit (Construction). (FEB 1995)

52.252-1 Solicitation Provisions Incorporated by Reference. (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es): http://farsite.hill.af.mil/

(End of provision)

M - Evaluation Factors for Award

Evaluation Factors for Award

a. BASIS FOR CONTRACT AWARD: This acquisition will utilize Lowest Price Technically Acceptable (LPTA) source selection procedures in accordance with FAR 15.101-2, as supplemented. This is a competitive LPTA best value source selection in which technical acceptability is considered the most important factor. By submission of its offer, the Offeror accepts all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. All technically acceptable offerors, with satisfactory past performance, shall be treated equally except for their prices. Failure to meet a requirement may result in an offer being determined technically unacceptable. Offerors must clearly identify any exception to the solicitation and conditions and provide complete accompanying rationale.

The Government intends to select ONE contractor for award of this effort.

For the purpose of award, the government shall evaluate offers based on the evaluation factors described below:

FACTOR 1 Technical Acceptability (Pass/Fail) FACTOR 2 Satisfactory Past Performance (Pass/Fail) FACTOR 3 Cost/Price

Factor 1 - Technical Acceptability: Bidders must submit a technical proposal that demonstrates contractors understanding of the project and the proposed technical solution. Qualification Statement Factor 2 – Satisfactory Past Performance: Have satisfactory past performance. Offerors shall not submit past performance information unless required as part of the response to Factor 3 – Price Evaluation.

The government may seek relevant performance information on all responsive and otherwise Technically Acceptable Offerors through sources such as DCMA offices, CPARS or PPRS or other government data bases and other sources that are available. The government shall not be limited in its search for performance data. The offeror shall not submit performance data for this factor. When performance is evaluated, the outcome is either satisfactory or unsatisfactory. Unsatisfactory performance will disqualify an offeror from award.

Factor 3 - Price Evaluation. The government shall conduct a price evaluation of all technically acceptable offers with satisfactory past performance including any option prices if applicable.

b. Rejection of Unrealistic Offers: The Government may reject any proposal that is evaluated to be unrealistic in terms of program commitments, including contract terms and conditions, or unrealistically high or low in cost/price when compared to Government estimates, or are unbalanced, such that the proposal is deemed to reflect an inherent lack of competence or failure to comprehend the complexity and risks of the program.

c. Source Selection Decision: The government shall select the source based upon a best value evaluation of the offeror’s technical acceptability, satisfactory past performance and price. The government shall choose the lowest realistically priced, responsive, with satisfactory performance, and technically acceptable offer for award.