NPS_Jewel_Cave_Final_Specifications_SFS_121814.pdf

PDF 3 MB Posted

Attached to
Jewel Cave NM - Book Store Addition
Solicitation number
P15PS00486
Issued by

About this file

NPS Jewel Cave Final Specifications_SFS 121814

View the file

Other files

File Type Posted
Sol_P15PS00486_Amd_000002.pdf PDF
AX-001 _Amendment_2.pdf PDF
NPS_Jewel_Cave_Amendment__2_04032015.docx DOCX document
NPS_Jewel_Cave_Amendment__1_040115.docx DOCX document
Sol_P15PS00486_Amd_000001.pdf PDF
Bid_Schedule.docx DOCX document
P15PS00486_0001_Amendment.docx DOCX document
Site_Visit_Sign_In_Sheet.pdf PDF
Existing_Carpet_-_Spec_Sheet.pdf PDF
Sol_P15PS00486.pdf PDF
Custer_County_Wage_Determinations.docx DOCX document
Jewel_Cave_Visitor_Center_Drawing_Set.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT SPECIFICATIONS December 17, 2014

CONSTRUCTION DOCUMENTS

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

Do not remove this notice Properly destroy documents when no longer needed

Jewel Cave National Monument Exhibit Space and Bookstore Expansion 11149 US Highway 16 B-12 Custer, South Dakota 57730 Project Number: JECA - 176793 Contract Number: P12PC50003 Task Order Number: 06

JEWEL CAVE NATIONAL MONUMENT

Exhibit Space and Bookstore Expansion 11149 US Highway 16 B-12 Custer, South Dakota 57730

Construction Documents – December 17, 2014 sfs architecture 1150 Grand Boulevard, Suite 400

Kansas City, MO 64106

(816) 474.1397

FAX: (816) 421.8024

SFS/#12825-006 SECTION 000101

EXHIBIT SPACE AND BOOKSTORE EXPANSION PROJECT TITLE PAGE

JEWEL CAVE NATIONAL MONUMENT

JECA – 176173

PROJECT TITLE PAGE 000101 - 1

DOCUMENT 000101 - PROJECT TITLE PAGE

PROJECT MANUAL

Jewel Cave National Monument Exhibit Space and Bookstore Expansion 11149 US Highway 16 B-12 Custer, South Dakota 57730

ARCHITECT:

sfs architecture 1150 Grand Boulevard, Suite 400 Kansas City, Missouri 64106 Phone: 816.474.1397

STRUCTURAL ENGINEER:

Walter P. Moore 920 Main Street, Tenth Floor Kansas City, Missouri 64105 Phone: 816.701.2122

MECHANICAL/ELECTRICAL/PLUMBING/COMMUNICATIONS ENGINEER:

Smith & Boucher Engineers 25501 West Valley Parkway, Suite 200 Olathe, Kansas 66061 Phone: 913.345.2127

END OF DOCUMENT 000101

SFS/#12825-006 SECTION 000111

EXHIBIT SPACE AND BOOKSTORE EXPANSION TABLE OF CONTENTS

JEWEL CAVE NATIONAL MONUMENT

JECA - 176173

TABLE OF CONTENTS 011000 - 1

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

DIVISION 00 - BIDDING REQUIREMENTS AND CONTRACT FORMS

000101 PROJECT TITLE PAGE

000111 TABLE OF CONTENTS

000018 STATUTORY DISCLAIMERS

DIVISION 01 - GENERAL REQUIREMENTS

011000 CONTRACT MODIFICATION PROCEDURES

011100 SUMMARY OF WORK

013100 PROJECT MANAGEMENT AND COORDINATION

013216 CONSTRUCTION SCHEDULE

013323 SUBMITTAL PROCEDURES

013523 SAFETY REQUIREMENTS

014000 QUALITY REQUIREMENTS

014200 REFERENCES

015000 TEMPORARY FACILITIES AND CONTROLS

015719.11 INDOOR AIR QUALITY MANAGEMENT

015719.12 NOISE & ACOUSTICS MANAGEMENT

015723 UNDER-AN-ACRE POLLUTION PREVENTION

016700 PRODUCT REQUIREMENTS

017329 CUTTING AND PATCHING

017340 EXECUTION

017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 CLOSEOUT PROCEDURES

017823 OPERATION AND MAINTENANCE DATA

017900 DEMONSTRATION AND TRAINING

018113 SUSTAINABLE DESIGN REQUIREMENTS (NON-LEED)

DIVISION 02 - EXISTING CONDITIONS

024119 SELECTIVE DEMOLITION

DIVISION 03 - CONCRETE

033000 CAST-IN-PLACE CONCRETE

DIVISION 04 - MASONRY

042113 BRICK MASONRY

DIVISION 05 - METALS

051200 STRUCTURAL STEEL FRAMING

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

061000 ROUGH CARPENTRY

JEWEL CAVE NATIONAL MONUMENT

JECA - 176173

TABLE OF CONTENTS 011000 - 2

061600 SHEATHING

061753 SHOP-FABRICATED WOOD TRUSSES

064600 INTERIOR WOOD TRIM AND CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

071416 COLD FLUID-APPLIED WATERPROOFING

072100 THERMAL INSULATION

072413 POLYMER-BASED EXTERIOR INSULATION AND FINISH SYSTEM (EIFS)

072500 WEATHER BARRIERS

074113 BATTEN-SEAM METAL ROOF PANELS

075419 POLYVINYL-CHLORIDE (PVC) ROOFING

076200 SHEET METAL FLASHING AND TRIM

079200 JOINT SEALANTS

079500 EXPANSION CONTROL

DIVISION 08 - OPENINGS

083113 ACCESS DOORS AND FRAMES

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

088000 GLAZING

DIVISION 09 - FINISHES

092900 GYPSUM BOARD

095123 ACOUSTICAL TILE CEILINGS

096813 TILE CARPETING

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

DIVISION 10 - SPECIALTIES

102600 WALL AND DOOR PROTECTION

104416 FIRE EXTINGUISHERS

DIVISION 11 – 22

NOT USED

DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING

230500 COMMON WORK RESULTS FOR HVAC

230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC

230713 DUCT INSULATION

231126 FACILITY LIQUEFIED-PETROLEUM GAS PIPING

233113 METAL DUCTS

233116 NONMETAL DUCTS

233300 DUCT ACCESSORIES

233713 DIFFUSERS, REGISTERS, AND GRILLES

237413 PACKAGED OUTDOOR CENTRAL-STATION AIR-HANDLING UNITS

JEWEL CAVE NATIONAL MONUMENT

JECA - 176173

TABLE OF CONTENTS 011000 - 3

260500 COMMON WORK RESULTS FOR ELECTRICAL

260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES CONTROL

260523 CONTROL-VOLTAGE ELECTRICAL POWER CABLES

260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

260529 HANGERS & SUPPORTS FOR ELECTRICAL SYSTEMS

260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS

260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS

262416 PANELBOARDS

262726 WIRING DEVICES

265100 INTERIOR LIGHTING

END OF TABLE OF CONTENTS

DIVISION 26 - ELECTRICAL

SFS/#12825-006 SECTION 000018

EXHIBIT SPACE AND BOOKSTORE EXPANSION STATUTORY DISCLAIMER

JECA - 176173

PROPERTY OF THE UNITED STATES GOVERNMENT

FOR OFFICIAL USE ONLY

DO NOT REMOVE THIS NOTICE

PROPERLY DESTROY DOCUMENTS WHEN NO LONGER NEEDED

STATUTORY DISCLAIMER 00830-1

It is hereby specified that the documents intended to be authenticated, by the Architect, SFS Architecture, and by the undersigned's seal are limited to:

Specifications:

024119 SELECTIVE DEMOLITION

033000 CAST-IN-PLACE CONCRETE

042113 BRICK MASONRY

051200 STRUCTURAL STEEL FRAMING

061000 ROUGH CARPENTRY

061600 SHEATHING

061753 SHOP-FABRICATED WOOD TRUSSES

064600 WOOD TRIM

071416 COLD FLUID-APPLIED WATERPROOFING

072100 THERMAL INSULATION

072413 POLYMER-BASED EXTERIOR INSULATION AND FINISH SYSTEM (EIFS)

072500 WEATHER BARRIERS

074113 BATTEN-SEAM METAL ROOF PANELS

075419 POLYVINYL-CHLORIDE (PVC) ROOFING

076200 SHEET METAL FLASHING AND TRIM

079200 JOINT SEALANTS

079500 EXPANSION CONTROL

083113 ACCESS DOORS AND FRAMES

084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

088000 GLAZING

092900 GYPSUM BOARD

095123 ACOUSTICAL TILE CEILINGS

096813 TILE CARPETING

099113 EXTERIOR PAINTING

099123 INTERIOR PAINTING

104416 FIRE EXTINGUISHERS

Drawings:

AG001 CODE SUMMARY

AD111 FLOOR PLAN DEMOLITION

A111 FIRST FLOOR PLAN

A121 FIRST FLOOR REFLECTED CEILING PLAN

A131 ROOF PLAN

A201 EXTERIOR ELEVATIONS

A211 INTERIOR ELEVATIONS

A301 BUILDING SECTIONS

A321 WALL SECTIONS

A322 WALL SECTIONS

A511 DETAILS

A601 DOORS, WINDOWS, AND FINISHES

and we hereby disclaim any responsibility for all other drawings, specifications, surveys, reports or other documents or instruments relating to or intended to be used for any part or parts of this project.

SFS/#12825-006 SECTION 011000

EXHIBIT SPACE AND BOOKSTORE EXPANSION CONTRACT MODIFICATION PROCEDURES

CONTRACT MODIFICATION PROCEDURES 011000 - 1

SECTION 01 10 00 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

6. Scheduling

7. Field Office Trailers and associated temporary utilities

CONTRACT MODIFICATION PROCEDURES 011000 - 2

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

CONTRACT MODIFICATION PROCEDURES 011000 - 3

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred.

Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

CONTRACT MODIFICATION PROCEDURES 011000 - 4

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated rental rates shall include the cost of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major overhaul is not included), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

CONTRACT MODIFICATION PROCEDURES 011000 - 5

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. The following percentages establish the maximum allowable markups (OH&P) for contractor self-performed work:

Overhead…………10% Profit………………15%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 011000

SFS/#12825-006 SECTION 011100

EXHIBIT SPACE AND BOOKSTORE EXPANSION SUMMARY OF WORK

SUMMARY OF WORK 011100 - 1

SECTION 01 11 00 - SUMMARY OF WORK

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Contractor use of premises.

3. Public use of site.

4. Occupancy requirements for building.

5. Work Restrictions.

6. Special Construction Requirements.

7. Soils Investigation Report.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Jewel Cave National Monument - Visitor Center.

B. The Work consists of the following:

1. The Work includes: Selective demolition of the existing outdoor pavilion and existing wood deck structure and new construction of an expanded lobby and gift shop. Portions of the existing wood deck structure are to remain in place as structural support for the expansion and the new construction is intended to be a seamless extension of the existing architecture.

C. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to those locations indicated on the plans for the applicable scope of work and to any other predetermined area(s) coordinated with the National Parks Service Contracting Officer at pre-construction meeting.

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

B. Storage of Materials: Confine storage of materials to a staging area which shall be coordinated with the National Park Service Contracting Officer at the preconstruction meeting.

SUMMARY OF WORK 011100 - 2

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways, sidewalks, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Construction Camp: Establishment of a camp within the park will not be permitted.

F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.4 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

1.5 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy the building that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

b. Maintain existing building in a weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and its occupants during construction period.

SUMMARY OF WORK 011100 - 3

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: Coordinate with Contracting Officer.

2. Early Morning Hours: Coordinate with Contracting Officer.

3. Hours for Core Drilling: Coordinate with Contracting Officer.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: During non-business hours. All utility shutdowns to be coordinated with Contracting Officer and on-site management.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.7 SOILS INVESTIGATION REPORT

A. A soils investigation report has not been developed. The Contractor shall perform a soils investigation prior to commencing construction. Coordinate boring locations with Contracting Officer and Structural Engineer.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

SFS/#12825-006 SECTION 013100

EXHIBIT SPACE AND BOOKSTORE EXPANSION PROJECT MANAGEMENT AND COORDINATION

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Coordination Drawings.

3. Requests for Information (RFIs).

4. Project Website.

5. Project meetings.

B. Related Requirements:

1. Section 01 3 216 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

PROJECT MANAGEMENT AND COORDINATION 013100 - 2

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Commissioning activities.

1.3 SUBMITTALS

A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.

1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of the Contract Documents or standard printed data. Include the following information, as applicable:

a. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and electrical systems.

b. Indicate dimensions shown on the Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted equipment and minimum clearance requirements. Provide alternate sketches to the Contracting Officer (CO) for resolution of such conflicts.

c. Indicate space requirements for routine maintenance and for anticipated replacement of components during the life of the installation.

d. Show location and size of access doors required for access to concealed dampers, valves, and other controls.

e. Indicate required installation sequences.

2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 24 by 36 inches (750 by 1000 mm).

3. Number of Copies: Submit PDFs of Drawings in lieu of paper copies.

4. Refer to individual Sections for Coordination Drawing requirements for Work in those

Section

B. Coordination Drawing Organization: Organize coordination drawings as follows:

1. Floor Plans: Show architectural and structural elements, and mechanical, plumbing, fire-protection, fire-alarm, and electrical Work. Supplement plan drawings with section drawings where required to adequately represent the Work.

2. Structural Penetrations: Indicate penetrations and openings required for all disciplines.

3. Mechanical and Plumbing Work: Show the following:

a. Sizes and bottom elevations of ductwork, piping, and conduit runs, including insulation, bracing, flanges, and support systems.

b. Dimensions of major components, such as dampers, valves, diffusers, access doors, cleanouts and electrical distribution equipment.

C. Coordination Digital Data Files: Prepare coordination digital data files according to the following requirements:

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.

2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.

3. Contracting Officer (CO) will furnish Contractor upon request one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.

a. CO makes no representations as to the accuracy or completeness of digital data files as they relate to Drawings.

b. Digital Data Software Program: Drawings are available in AutoCad.dwg.

D. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Storm Water Pollution Prevention Plan.

11. Indoor Air Quality (IAQ) Management Plan.

E. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

PROJECT MANAGEMENT AND COORDINATION 013100 - 4

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT WEB SITE

A. Use the Architect’s Project website for communication throughout the contract period. The Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

PROJECT MANAGEMENT AND COORDINATION 013100 - 5

B. Some documents however are not suitable to be shared using the Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the Project website and shall be coordinated with the Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Architect.

D. All users will be required to have the following software packages:

1. Internet Explorer version 8 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Contractor Performance Evaluation.

12. Display of Hotline posters.

13. Notice to proceed.

14. Correspondence procedures.

15. Project website.

16. Acceptance/rejection of work.

17. Progress meetings.

18. Submittal procedures.

19. NPS Final Accessibility Inspection.

20. Environmental requirements.

21. As-constructed drawings/operation and maintenance (O&M) manuals.

22. Saturday, Sunday, holiday and night work.

23. Reference materials.

24. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

PROJECT MANAGEMENT AND COORDINATION 013100 - 6

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of authorities having jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

PROJECT MANAGEMENT AND COORDINATION 013100 - 7

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Indoor Air Quality (IAQ) Management.

4. Noise & Acoustics Management.

5. Temporary Storm Water Pollution Prevention Environmental Management.

6. Construction Waste Management.

B. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

SFS/#12825-006 SECTION 013216

EXHIBIT SPACE AND BOOKSTORE EXPANSION CONSTRUCTION SCHEDULE

CONSTRUCTION SCHEDULE 013216

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

1.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

F. Resource Loading: The allocation of manpower and equipment necessary for the completion of an activity as scheduled.

G. Fragnet: A partial or fragmentary network that breaks down activities into smaller activities for greater detail.

1.3 SUBMITTALS

A. Electronic Copies: All schedules and reports submitted shall be posted on the project website, provided in the native electronic file format. It is the intent of the Government to limit the number of printed reports to only those reports determined by the project team to be essential.

B. Schedule of Values: After contract award and before the Pre-Construction conference submit a schedule of dollar values based on the Contract Price Schedule.

C. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

D. CPM Reports: Concurrent with CPM schedule, submit a PDF of each of the following computer-generated reports. Format for each activity in reports shall contain activity number, activity description, resource loading, original duration, remaining duration, early start date, early finish date, late start date, late finish date, and total float in calendar days.

1. Activity Report: List of all activities sorted by activity number and then early start date, or actual start date if known.

2. Logic Report: List of predecessor and successor tasks for all activities, sorted in ascending order by activity number and then early start date, or actual start date if known.

3. Total Float Report: List of all activities sorted in ascending order of total float.

E. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies and a PDF.

F. Construction Schedule Revisions and Time Impact Analysis: For each Construction Schedule revision submit two paper copies and a PDF of a Time Impact Analysis. Each Time Impact Analysis shall include a Fragmentary Network (Fragnet), incorporated into the currently accepted Construction Schedule, demonstrating how the Contractor proposes to incorporate a modification, change, delay, or Contractor request.

G. Daily Construction Reports: Submit at weekly intervals.

H. Material Location Reports: Submit at weekly intervals.

I. Site Condition Reports: Submit at time of discovery of differing conditions.

J. Special Reports: Submit at time of unusual event.

1.4 QUALITY ASSURANCE

A. The Contractor shall meet with the Contracting Officer on the day of the preconstruction conference to go over the following:

1. Review software limitations, content and format for reports.

2. Verify availability of qualified personnel needed to develop and update schedule.

3. Discuss constraints, including phasing, work stages, area separations, interim milestones, and partial Government occupancy.

4. Review delivery dates for Government-furnished products.

5. Review schedule for work of separate Government contracts.

6. Review time required for review of submittals and re-submittals.

7. Review requirements for tests and inspections by independent testing and inspecting agencies.

8. Review time required for completion and startup procedures.

9. Review and finalize list of construction activities to be included in schedule.

10. Review baseline schedule comments, resolve issues and progress on incorporating them

11. Review procedures for updating schedule.

12. Discuss reporting requirements and establish a protocol for naming and transmitting electronic schedules.

B. Contractor's Schedule Representative: Before or at the preconstruction conference, designate an authorized representative to be responsible for the preparation and maintenance of the Construction Schedule. A resume outlining the qualifications of the Scheduler shall be submitted to the Contracting Officer for acceptance. The Scheduler shall have prepared and maintained at least 5 previous schedules of similar size and complexity similar to this Contract, demonstrating proficiency in the use of scheduling software. The authorized representative will be responsible for preparing the Baseline Schedule, all required updates, revisions, Time Impact Analyses, and preparation of reports.

1.5 COORDINATION

A. Coordinate preparation and processing of schedules and reports with performance of construction activities and with scheduling and reporting of separate Contractors.

B. Coordinate Construction Baseline Schedule with the Schedule of Values, list of subcontracts, Submittals Schedule, progress reports, payment requests, and other required schedules and reports.

1. In developing the Construction Baseline Schedule, ensure that the Subcontractor’s work at all tiers, as well as the prime Contractor’s work, is included and coordinated.

2. Secure time commitments for performing critical elements of the Work from parties involved.

3. Coordinate each construction activity in the network with other activities and schedule them in proper sequence.

PART 2 - PRODUCTS

2.1 SCHEDULE OF VALUES

A. Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component work activities for each lump-sum item. Do not include mobilization, general condition costs, overhead or profit as a separate item.

B. Do not break down unit price items. Use only the contract price for unit price items.

C. The total cost of all items shall equal the contract price. The Schedule of Values will form the basis for progress payments.

D. An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting Officer before the first progress payment is processed.

2.2 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize…