The document is a procurement guidance document from the Arizona Department of Transportation (ADOT) Procurement division, detailing the ordering process for contracts with not-to-exceed pricing. It provides comprehensive instructions for state agencies and requisitioners on how to utilize task assignment-based contracts with fixed price line items.
The contracts are structured with line items that have fixed, maximum unit prices that cannot be changed in the procurement system (APP). Contractors can provide quotes for task assignments at or below these predetermined unit prices, with a $0.00 'Task Assignment' line that can be modified to reflect the total task price. The process requires requisitioners to identify work scope, locate available contractors, distribute task assignment requests, collect and review quotes, select a contractor based on price and other factors, and then create a requisition in APP with all contractor responses attached. The goal is to maximize cost savings by requesting quotes from all available contractors, with Procurement reviewing submissions to ensure competitive pricing and proper procedure.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
These types of contracts are task assignment based.
They contain line items with fixed prices that are identified as not-to-exceed or maximum unit price. For those line items, contractors may provide quotes on a task assignment request where the unit price is equal to or less than the unit price found in APP. Please note that these unit prices cannot be changed in APP. So, each contract also has a ‘Task Assignment’ line with a $0.00 which can be modified by the requisitioner to reflect the total price for the task assignment.
Each contract will contain specific guidance on the task assignment process. It is important to become familiar with these task assignment requirements. For additional information and help, please reach out to the assigned Contract Owner listed in APP.
1. Identify work to be completed (project scope/ specifications).
2. Identify available contractors that can provide service in the area needed.
3. Distribute task assignment request, as found in the contract, to available contractors.
4. Receive contractor responses and review.
5. Select contractor to perform work based on price and other factors.
6. Create requisition in APP
a. All responses from contractors that are not selected must be attached to the requisition header. If a contractor does not respond, attach the email you sent to them in place of the quote.
b. Attach the selected contractors quote/task assignment response to line item #1.
A not-to-exceed price is the price ceiling identified for a specific contract line item. It is the maximum price that the supplier is allowed to charge for that particular product or service. Contracts that use not-to-exceed pricing are firm-fixed price contracts where, depending on task or site conditions, contractors can quote lower unit prices for those line items that are identified as not-to-exceed.
What does not-to-exceed mean?
Procurement
Ordering Process for Contracts with Not-to-Exceed Pricing
Get Quotes
You will get the most benefit out of these contracts by requesting quotes from all available contractors. For example, a contractor may have another job already scheduled close by and would be able to pass some savings to you by reducing unit prices.
Once a requisition is received, Procurement will review all the quotes submitted by the contractors. The Procurement Officer will confirm:
Quotes were requested from all awarded contractors
Services being performed Pricing
If multiple quotes were not requested, Procurement may reach out to understand why not.
Revised 11/2022