About this file
This Quality Assurance Surveillance Plan outlines performance criteria for a contractor providing support services to the Ozone Depleting Substances Reserve Program Office. The contractor must meet acceptable quality levels for 27 deliverables focused on administrative, analytical, IT, logistics, and monitoring functions. Performance will be evaluated on timeliness and quality using a rating system of exceptional, very good, satisfactory, marginal, and unsatisfactory. Remedies for failing to meet quality levels include cure notices, show cause notices, and potential termination for poor performance. The related federal contract opportunity is a solicitation from the Defense Logistics Agency to provide the support services outlined in the Quality Assurance Surveillance Plan to the Ozone Depleting Substances Reserve Program Office located in Richmond. Interested offerors should review all attachments for details on requirements.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFP ODS Support - 21-R-0005 - 4-5-21.pdf | ||
| SF1449_SP4703-21-R-0005 - 4-5-21.pdf | ||
| Past Performance Questionnaire - Template.pdf | ||
| Schedule B - 3-22-21.xlsx | XLSX spreadsheet | |
| ODS Support Required Submission Docs - 3-22-21.docx | DOCX document | |
| SF1449_SP4703-21-R-0005 - 3-22-21.pdf | ||
| RFP ODS Support - 21-R-0005 - 3-22-21.docx | DOCX document | |
| 21-R-0005 QAs - 3-22-21.xlsx | XLSX spreadsheet | |
| ODS Support PWS - 3-22-21.docx | DOCX document | |
| ODS Support Required Submission Docs.docx | DOCX document | |
| Schedule B.xlsx | XLSX spreadsheet | |
| Past Performance Questionnaire - Template.pdf | ||
| RFP ODS Support - 21-R-0005.pdf | ||
| SF1449_SP4703-21-R-0005.pdf | ||
| Key Personnel Template.pdf | ||
| Synopis-Solicitation ODS Support.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Quality Assurance Surveillance Plan DOS Support Service for ODS Reserve Program at Richmond
The Contracting Officer’s Representative (COR) will monitor vendor performance and complete the quality assurance worksheet below. The quality assurance worksheet will be submitted directly to the contract specialist and contracting officer (KO) within 72 hours of the completion of performance.
If a rating other than satisfactory is identified, the COR must document and provide to the contract specialist sufficient information to properly articulate the deficiencies to the vendor so corrective action may be taken.
The COR referred to in this QASP is identified on the contract.
Table 1: Performance Criteria for Performance Deliverables
Deliverable Reference Task Title Deliverable
Acceptable Quality Level
(AQL)
Method Used/Frequency
2.3.1.1 Administrative
and Analytical
Advise/notify ODS Office of service requirements or policy changes/modification.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.2 Administrative
and Analytical
Advise/notify ODS Office of new domestic and international studies, policies, and agreements pertaining to ODS. Advise effective processes for ODS banking or destruction/conversion.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.3 Administrative
and Analytical
Provide complete documentation and staffing of documentation of new agreement or change/ modification of existing Inter/Intra-Agency Service Agreements and Operating Agreements between the ODS Reserve and foreign governments and their contractors.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.4 Administrative
and Analytical
Maintain, update, and prepare, and provide new document on ODS-Related Policies, Processes and Procedures Documents and Flow Charts. Policies and procedures should be reviewed annually and updated as needed.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.5 Administrative
and Analytical
Provide revised script, query or reports format to Government for review and approval.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.6 Administrative
and Analytical
Provide preliminary transaction and inventory reports.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.7 Administrative
and Analytical
Execute manual Issue/ Receipt transactions as required to adjust Service/Agency inventories
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.8 Administrative
and Analytical
Provide final versions of transaction and inventory reports
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.9 Administrative
and Analytical
Prepare and submit Monthly Contractor Performance Status Report
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.A Administrative and Analytical
Provide ODS Inventory Glideslope 95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.B Administrative and Analytical
Provide ODS Physical Inventory Consolidated Count Report
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.C Administrative and Analytical
Provide ODS Requisitioners Issues Report, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.D Administrative and Analytical
Provide ODS Requisitioners Fire Extinguisher Issue Report, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.E Administrative and Analytical
Provide ODS Customer Return Transaction Report, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.F Administrative and Analytical
Provide ODS BSM Requisitioners Issues Report - Rejects, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.G Administrative and Analytical
Provide ODS Repackaging Depot Receipts Report, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.H Administrative and Analytical
Provide ODS Ready for Issue Summary by Service Report, by Service
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.I Administrative and Analytical
Provide ODS Service Inventory Balance Report, by Service
95% of deliverables submitted on-time.
2.3.1.10.J Administrative and Analytical
Provide ODS Inventory Site Distribution Report
95% of deliverables submitted on-time.
100% COR
inspection
2.3.1.10.K Administrative and Analytical
Provide ODS Inventory History by Product and Service Report
95% of deliverables submitted on-time.
100% COR
inspection
2.3.2.1 Information
Technology
Update VO Division (ODS Reserve) Web Site.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.2.2 Information
Technology
Provide System Queries related to ODS Product Inventory Status, and Issue and Receipt Transaction history as required.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.1 Logistics &
Warehousing and Leak Monitoring
Verify and check Receipt and In-Checking of ODS Turn-Ins within RCN timelines.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.2 Logistics &
Warehousing and Leak Monitoring
Coordinate reclamation or destruction requirement with contractor transportation planner.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.3 Logistics &
Warehousing and Leak Monitoring
Coordinate delivery/receipt of reclaimed product cylinders or empty GFM cylinders and check for completeness.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.4 Logistics &
Warehousing and Leak Monitoring
Execute Re-warehousing and Special Projects as required.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.5 Logistics &
Warehousing and Leak Monitoring
Provide leak monitor/detection report of ODS products.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.3.6 Logistics &
Warehousing and Leak Monitoring
Maintain cylinder storage in all warehouses to be compliant with Location Identification Program (LIP) composite locations, and meeting HCC separation requirements for empty (N1) and full (G3) cylinder coding.
95% of deliverables submitted on-time.
100% COR
inspection
2.3.4.1 ODSR
Electronic Monitoring System (EMS) maintenance
Provide monthly ODSR Electronic Monitoring System (EMS) maintenance status report
95% of deliverables submitted on-time.
2.3.4.2 ODSR
Electronic Monitoring System (EMS) maintenance
Provide Monthly Report on maintenance expenses for equipment, subscriptions, and spare parts purchased to support the ODSR EMS at Yorktown, San Joaquin (Tracy), Warner Robins, and Melbourne Australia.
95% of deliverables submitted on-time.
100% COR
inspection
2.4.5 Contractor
Quality Control Plan
(QCP)
Contractor Quality Control Plan (QCP) Must be delivered on time.
100% COR
inspection
2.12 Final Results
Briefing
Final Results Briefing Must be delivered on time.
100% COR
inspection
Quality Assurance Rating Scheme
Rating Description Exceptional
(EXCP)
Performance meets contractual requirements and exceeds many to the government's benefit. The contractual performance of the element or sub-element being evaluated was accomplished with few minor problems for which corrective actions taken by the Contractor were highly effective. Note: To justify an Exceptional rating, identify multiple significant events and state how these events were of benefit to the government. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.
Very Good
(VGD)
Performance meets contractual requirements and exceeds some to the government's benefit. The contractual performance of the element or sub-element being evaluated was accomplished with some minor problems for which corrective actions taken by the Contractor were effective. Note: To justify a Very Good rating, identify a significant event and state how it was a benefit to the government. There should have been no significant weaknesses identified.
Satisfactory
(SAT)
Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the Contractor appear, or were, satisfactory. Note: To justify a Satisfactory rating, there should have been only minor problems or major problems that the Contractor recovered from without impact to the contract or order. There should have been NO significant weaknesses identified. A fundamental principle of assigning ratings is that Contractors will not be evaluated with a rating lower than Satisfactory solely for not performing beyond the requirements of the contract or order.
Marginal
(MRGL)
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being evaluated reflects a serious problem for which the Contractor has not yet identified corrective actions. The Contractor's proposed actions appear only marginally effective or were not fully implemented. Note:
To justify Marginal performance, identify a significant event in each category that the Contractor had trouble overcoming and state how it impacted the government. A Marginal rating should be supported by referencing the management tool that notified the Contractor of the contractual deficiency (e.g. management, quality, safety, or environmental deficiency report or letter).
Unsatisfactory
(UNSAT)
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the Contractor's corrective actions appear or were ineffective. Note: To justify an Unsatisfactory rating, identify multiple significant events in each category that the Contractor had trouble overcoming and state how these events impacted the government. A singular problem, however, could be of such serious magnitude that it alone constitutes an Unsatisfactory rating. An Unsatisfactory rating should be supported by referencing the management tools used to notify the Contractor of the contractual deficiencies (e.g. management, quality, safety, or environmental deficiency reports or letters).
Not Applicable
(NA)
Performance not observed during this performance period.
REMEDIES FOR CONTRACTOR NOT MEETING ACCEPTABLE QUALITY LEVELS OF PERFORMANCE OBJECTIVES WITHIN
CONTRACT PERIOD:
FIRST VIOLATION: KO will issue cure notice to the contractor.
SECOND VIOLATION: KO will issue show cause notice to the contractor.
THIRD VIOLATION: KO will terminate contract for cause.
The government will evaluate the contractor’s performance under this contract using the method of surveillance specified in Table 1, Performance Criteria for Performance Deliverables. All surveillance observations will be recorded by the government. Those observations indicating defective performance must be initialed by the contractor’s designated representative. The contractor must designate at least one employee for this purpose. If no such designated employee is available, recorded observation must so state.
The following evaluation form will be filled out by the COR and delivered to the contract specialist and KO for inclusion in the contract file.
Quality Assurance Worksheet
Deliverable Reference Deliverable EXCP VGD SAT MRGL UNSAT NA
2.3.1.1 Advise/notify ODS Office of service
requirements or policy changes/modification.
2.3.1.2 Advise/notify ODS Office of new domestic and
international studies, policies, and agreements pertaining to ODS. Advise effective processes for ODS banking or destruction/conversion.
2.3.1.3 Provide complete documentation and staffing
of documentation of new agreement or change/ modification of existing Inter/Intra- Agency Service Agreements and Operating Agreements between the ODS Reserve and foreign governments and their contractors.
2.3.1.4 Prepare, update, and maintain ODS-Related
Policies, Processes, and Procedures Documents and Flow Charts. Policies and procedures should be reviewed annually and updated as needed.
2.3.1.5 Provide revised script, query, or
reports format to government for review and approval.
2.3.1.6 Provide preliminary transaction and inventory
reports.
2.3.1.7 Execute manual Issue/Receipt transactions as
required to adjust Service/Agency inventories
2.3.1.8 Provide final versions of transaction and
inventory reports
2.3.1.9 Prepare and submit Monthly Contractor
Performance Status Report
2.3.1.10.A Provide ODS Inventory Glideslope
2.3.1.10.B Provide ODS Physical Inventory Consolidated Count Report
2.3.1.10.C Provide ODS Requisitioners Issues Report, by Service
2.3.1.10.D Provide ODS Requisitioners Fire Extinguisher Issue Report, by Service
2.3.1.10.E Provide ODS Customer Return Transaction Report, by Service
2.3.1.10.F Provide ODS BSM Requisitioners Issues Report
- Rejects, by Service
2.3.1.10.G Provide ODS Repackaging Depot Receipts Report, by Service
2.3.1.10.H Provide ODS Ready for Issue Summary by Service Report, by Service
2.3.1.10.I Provide ODS Service Inventory Balance Report, by Service
2.3.1.10.J Provide ODS Inventory Site Distribution Report
2.3.1.10.K Provide ODS Inventory History by Product and Service Report
2.3.2.1 Update VO Division (ODS Reserve) Web Site
2.3.2.2 Provide System Queries related to ODS
Product Inventory Status, and Issue and Receipt Transaction history as required
2.3.3.1 Verify and check Receipt and In-Checking of
ODS Turn-Ins within RCN timelines
2.3.3.2 Coordinate reclamation or destruction
requirement with contractor transportation planner
2.3.3.3 Coordinate delivery/receipt of reclaimed
product cylinders or empty GFM cylinders and check for completeness of related paperwork/supply documentation
2.3.3.4 Execute Re-warehousing and Special Projects
as required
2.3.3.5 Provide leak monitor/detection report of ODS
products for all ODS product cylinders at DDRV and Yorktown, VA
2.3.3.6 Maintain cylinder storage in all warehouses to
be compliant with all current ODSR policies and procedures along with any DDRV cylinder storage requirements.
2.3.4.1 Provide monthly ODSR Electronic Monitoring
System (EMS) maintenance status report
2.3.4.2 Provide Monthly Report on maintenance
expenses for equipment, subscriptions, and spare parts purchased to support the ODSR EMS at Yorktown, San Joaquin (Tracy), Warner Robins, and Melbourne Australia
2.4.5 Contractor Quality Control Plan (QCP)
2.13 Final Results Briefing
OVERALL EXCP VGD SAT MRGL UNSAT
Overall, how would you rate contractor’s performance
Comments:
Prepared by: _________________________________________Rating Period: __________________________
(COR)
File details come from the government source that posted it. Updated .