NOVASTAR Ordering Procedures.pdf

PDF 143 KB Posted

Attached to
NOVASTAR DRAFT RFP Federal contract opportunity
Solicitation number
FA860421RB007
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Wright Patterson Air Force Base

About this file

This document provides ordering procedures and tasking requirements for the NOVASTAR contract opportunity. The Department of the Air Force Materiel Command is soliciting proposals for the NOVASTAR multiple award IDIQ contract to provide research, development, and engineering services. The 10-year, $4.7 billion contract will make awards to up to five small businesses and task orders may be set aside exclusively for small businesses. However, contractors that grow out of the small business size standard during contract performance may still compete for non-set-aside task orders. Offerors must submit capability statements by April 23rd if seeking to utilize government facilities to draft proposals in response to the formal RFP expected this summer. The ordering procedures outline the fair opportunity proposal process, including the issuance of fair opportunity proposal requests and task order requirement packages by the contracting officer. Contractors will submit fair opportunity proposals in response and task orders will be issued on various contract types including firm-fixed-price, cost-plus-fixed-fee, and time and materials.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOVASTAR ORDERS and TASKING PROCEDURES (January 2021)

(a) GENERAL. The requirements identified in the Fair Opportunity Proposal Request’s (FOPR) Task Order Requirement Package (TORP) are in specific terms. Any task or subtask not specifically addressed in the TOPR must be assigned by the Procurement Contracting Officer (CO). The Contractor shall not honor any other forms or variations of tasking.

(b) DEFINITIONS. The Fair Opportunity Proposal Request (FOPR) requires the Contractor to act on tasks requested by the CO, and respond in the prescribed manner. The terms used to describe this process are defined as follows:

(1) Fair Opportunity Proposal Request (FOPR). FOPR is a document to communicate the Government's requirements to solicit fair opportunity proposals from prospective Contractors. A FOPR will include an attached TORP.

(2) Task Order Requirement Package (TORP). The TORP identifies the Government's technical requirements and outlines the work to be accomplished. A TORP will be generated by the Government for each task order. This will include a Performance Work Statement (PWS), Contract Data Requirements Lists (CDRLs), Administrative Requirements, Security Requirements, Instructions to offerors, and TO Evaluation Criteria.

(3) Fair Opportunity Proposal (FOP). A FOP is the Contractor's response to a FOPR and TORP within the specified time limit with either a FOP or a written negative reply to the CO. A FOP will contain at a minimum:

(a) Proposed approach for addressing the requirements of the FOPR and TORP;

(b) Technical Merit;

(c) Proposed Cost;

(d) Schedule;

(e) Past Performance; and

(f) Resumes.

It shall also include estimates of person‐hours, materials, subcontracting, and other charges, time of performance/delivery, and the proposed “price” if Firm Fixed Price (FFP) or “estimated costs” if Cost Reimbursable or Time and Materials, for each type of CLIN utilized in each task order. Additional sections may be required to respond to unique Government requirements in the FOPR and TORP.

(4) Task Order. A task order (TO) establishes the specific requirements for work to be performed within the contract and is issued by the CO. The TO binds the Government and contractor(s) in mutual agreement.

(c) TASK FLOW. The task flow to perform the work under the contract shall be as follows:

(1) Orders may be issued at the sole option of the Government during the period set forth in the Ordering Clause hereof. Orders may be issued by the CO during the period set forth in SECTION I, FAR 52.216‐18, "Ordering." All FOPRs, TORPs, and TORP Amendments (corrections, additions, modifications, and deletions) shall be issued to the Contractor by the CO through the transmittal of a FOPR/FOPR Amendments.

(2) Prior to issuance of an order, the Government shall request a proposal by issuing a FOPR and TORP for the contemplated work. Upon receipt of a FOPR and TORP from the CO, the Contractor shall produce a FOP.

(3) Task Orders/CLINs issued under this contract may be accomplished on a FFP, Cost‐Plus Fixed Fee (CPFF), Cost‐Plus Incentive Fee basis (CPIF), Fixed‐Price Incentive Firm (FPIF), Time and Materials, Labor‐Hour or any combination thereof depending on the nature of the task order requirement. If the task order is all one contract type or predominately one type, then the amount on the first page of the task order and the applicable CLINs will be a “price” (FFP), or an “estimated cost” (CR). The total amount of each task order shall establish an estimated cost, or allocated amount for the order, which the contractor exceeds at its own risk. Changes to the price/estimated costs shall be accomplished in accordance with all IDIQ terms and conditions.

(4) Task orders for support and data shall be issued by the CO in writing, dated, and numbered. It shall set forth the following:

(1) the support being ordered,

(2) associated data,

(3) delivery or performance dates,

(4) place of delivery or performance,

(5) packaging and shipping instructions, if any,

(6) the amount of funds obligated,

(7) the industrial resources priorities and allocations (DO/DX) rating, and

(8) identification of the cognizant Program Manager/Technical Monitor. Each task order shall allot specific amounts for CLINs requested in FOPR. Data requirements (CLIN 0009) are not separately priced (NSP). The Contractor shall furnish to the Government reports and data requested, at the price agreed upon based on the negotiated rates set forth in the schedule in the IDIQ or applicable TO.

(5) Coordination. During the FOPR process, contact between the Government and Offeror may be required for the purpose of technical coordination. Technical coordination shall include all verbal and written communications pertaining to clarification of the FOPR/TORP, resolution of technical problems, development of the FOP, and in‐progress review of Contractor efforts and reports. All communication shall be conducted through the CO.

(6) Government Review. The TORP technical monitor and the contract negotiator shall review the FOP and grant approval or disapproval.

(7) Execution. Upon receipt of a signed/awarded task order, commencement of contractor performance shall occur.

(d) CONTRACTOR PERFORMANCE. Execution of Contractor performance shall commence on the date of award of the TO or on the identified start date within the TO. Contractor performance is to be accomplished in strict accordance with the approved FOP in content, approach, and reporting schedule, unless otherwise directed in writing by the CO.