Nay_Aug_Park_Pool_Complex_Feasibility_Study_Update_and_Pool_Complex_Construction_Design.pdf
PDF 421 KB Posted
- Solicitation number
- Not on record
- Issued by
- Lackawanna County, Pennsylvania
About this file
This is a Request for Proposal (RFP) issued by the City of Scranton's Office of Business Administration for a comprehensive Nay Aug Park Pool Complex Feasibility Study Update and Pool Complex Construction Design project. The RFP seeks a qualified Professional Design Consultant to conduct a two-phase project, with Phase 1 focusing on a detailed feasibility study and Phase 2 involving construction design. The initial study must update the April 2021 pool complex feasibility report, engage public participation, analyze community needs, and develop preliminary designs for a pool complex approximately 12,375 square feet with zero-entry recreational and lap swimming areas, a 5,000 square foot spray pad, bathhouse improvements, and support structures. The proposal submission deadline is June 27, 2023, at 10:00 am, with all documents to be submitted electronically through the City's e-Procurement Portal.
The project requires a comprehensive approach, including market analysis, demographic research, financial projections, and design considerations with an emphasis on accessibility, green design, and community engagement. The consultant must provide a detailed cost estimate, develop construction documents, obtain necessary permits, and potentially assist with grant applications. Financial analysis should project operating costs, revenue streams, and potential funding sources for five years, including options like general fund support, capital campaigns, charitable contributions, facility-generated revenue, and potential partnerships. The project is funded through local government resources, with the expectation that the selected consultant will help identify and secure additional funding mechanisms. The total project is anticipated to be completed in approximately 11 months, with Phase 1 estimated at 4 months and Phase 2 at 7 months, contingent on city approval after the feasibility study.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
REQUEST FOR PROPOSAL
LSA - grant
NAY AUG PARK POOL COMPLEX FEASIBILITY STUDY
UPDATE AND POOL COMPLEX CONSTRUCTION
DESIGN
City of Scranton
340 N Washington Ave
Scranton, PA 18503
RELEASE DATE: June 9, 2023
DEADLINE FOR QUESTIONS: undefined
RESPONSE DEADLINE: June 27, 2023, 10:00 am
RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:
https://secure.procurenow.com/portal/scrantonpa https://secure.procurenow.com/portal/%7bproject.government.code%7d
City of Scranton
REQUEST FOR PROPOSAL
Nay Aug Park Pool Complex Feasibility Study Update and Pool
Complex Construction Design
I. INTRODUCTION
II. GENERAL INFORMATION
III. GENERAL CONDITIONS
IV. PROBLEM STATEMENT
V. CRITERIA FOR SELECTION
VI. PROPOSAL REQUIREMENTS
VII. SCOPE OF WORK
Request For Proposal #LSA - grant Title: Nay Aug Park Pool Complex Feasibility Study Update and Pool Complex Construction Design
1. INTRODUCTION
1.1. Summary
The Office of Business Administration for the City of Scranton is seeking separate sealed proposals for an individual or firm to provide a Nay Aug Park Pool Complex Feasibility Study
Update and Pool Complex Construction Design and will be received online by the City of
Scranton Controller via the City’s e-Procurement Portal until 10:00 a.m., on Tuesday, June 27, 2023 at which time such proposals will be opened in City Council Chambers, 2nd Floor and made available for public viewing at www.youtube.com/user/electriccitytv570 for the following:
CITY OF SCRANTON
Nay Aug Pool Complex Feasibility Study Update and Pool Complex Construction Design
Proposals shall be made upon the specifications included in the official Proposal Request which may be obtained by visiting the City of Scranton’s e-Procurement Portal, https://secure.procurenow.com/portal/scrantonpa. If you intend to submit a proposal, you shall register on the City’s e-Procurement Portal. Once registered, companies may view and click
"Follow" to be a prospective Respondent for this solicitation and will appear on the follower’s list. Companies that fail to follow this project will not receive automatic addenda notifications, nor will they be able to draft a response in the City’s e-Procurement Portal, and therefore will be unable to participate or be considered for this RFP.
All proposal documents and supplementary documents must be uploaded and submitted using the City’s e-Procurement Portal prior to 10:00 am on June 27, 2023, as instructed in this solicitation. Once file(s) have been uploaded and the submission status shows as “Submitted,” the submission is complete. At that point, the Respondent's representative who is registered with the City will receive an email confirmation from the City’s e-Procurement Portal.
All proposals must be accompanied by a certificate of insurance, and signed affirmative action, non-segregated facilities, non-collusion affidavits, and disclosure by current contractor.
All communications regarding technical, scope, and/or project related questions and requests for clarifications, changes, exceptions, and deviations to the terms and conditions set forth in this
RFP shall be submitted via “Q&A” through the City’s e-Procurement Portal, before the deadline of 2:00 p.m. on Thursday, June 22, 2023 and according to these specifications herein.
If a Respondent encounters any technical difficulties utilizing the City's e-Procurement Portal, a representative may contact OpenGov, the Software Administrator, using the real-time chat function on the website (located in lower right-hand corner of the screen), or via email at support@procurenow.com. It is still the Respondent's responsibility to ensure that their response is submitted before the deadline.
1.2. Background
fo https://www.youtube.com/user/electriccitytv570
1.3. Contact Information
Eileen Cipriani
Director
Email: ecipriani@scrantonpa.gov
Phone: (570) 407-0173
Department:
Business Administration
Department Head:
Eileen Cipriani
Business Administrator
1.4. Timeline
Release Project Date June 9, 2023
Question Response Deadline June 22, 2023, 2:00pm
Proposal Submission Deadline June 27, 2023, 10:00am mailto:ecipriani@scrantonpa.gov tel:(570)407-0173
2. GENERAL INFORMATION
A. PURPOSE
1. This Request for Proposals (RFP) provides interested parties with sufficient information to prepare and submit proposals for consideration by the City of Scranton for Nay Aug Park Pool Complex Feasibility Study Update and Pool Complex
Construction Design.
B. ISSUING OFFICE
1. This RFP is issued for the City of Scranton. The submittal of proposals must be submitted no later than 10:00 am on Tuesday, June 27, 2023 to the City of Scranton
Controller via the City’s e-Procurement Portal. Hard copy (mailed or hand delivered), Fax, or e-mail submittals will not be accepted or considered.
2. A pre-proposal conference will not be held.
3. Proposals will be handled confidentially by the City during the pre-award process.
4. The proposal shall be binding for a period of sixty (60) days from the due date for submission.
5. The City will not be responsible for any expenses incurred by an entity submitting a proposal in connection with this procurement.
6. Bonds: N/A
C. GENERAL CONSIDERATIONS
1. QUESTIONS
a. Questions about this project shall be submitted in writing via “Q&A” through the
City’s e-Procurement Portal, before NO VALUE on TBD.
b. All questions must be received before the deadline set forth above. Inquiries received afterwards will not receive responses.
c. No telephone calls with questions will be taken.
2. ADDENDA
a. To ensure consistent interpretation of certain items, answers to questions the City deems to be in the interest of all will be made available to all Respondents.
b. Responses to questions will be issued in the form of an Addendum to the RFP.
c. Unless otherwise specified, any addenda issued while this RFP is open and still accepting Proposals must be acknowledged electronically via the City’s e-
Procurement Portal, which will be made part of the proposal. Addenda notifications will be provided to those listed on the Follower’s List via email.
3. GENERAL CONDITIONS
A. No verbal information to Respondents will be binding on the City. The written requirements will be considered clear and complete, unless written attention is called to any apparent discrepancies or incompleteness before the opening of the proposals. All alterations to the RFP will be made in the form of a written communication emailed to all prospective Respondents. The communications shall then be considered to be part of the
RFP.
B. Submission of a proposal will be considered as conclusive evidence of the Respondent’s complete examination and understanding of the request.
C. In the event a Respondent is unable to submit a timely response in accordance with the instructions herein due to personal or company internet or hardware limitations, settings or restrictions, internet speed, power outage, network connection, or use of a malfunctioning electronic device, or the like, neither the City, nor the Software
Administrator, will be held responsible. Companies shall be solely responsible for ensuring the capability of their computer system while responding to this solicitation, and for the stability of their internet service. Uploading large documents may take significant time depending on the size of the file(s) and the Internet connection speed that the
Respondent representative is using to submit a response. Failure of the Respondent to successfully submit an electronic proposal before the deadline indicated herein shall be at the Respondent’s sole risk, and no relief will be given for late and/or improperly submitted proposals.
D. The City of Scranton reserves the right to reject any and all proposals submitted and to request additional information from any Respondent. The City of Scranton reserves the right to waive minor irregularities in the procedures or proposals if it is deemed in the best interests of the City of Scranton. The City may elect, at its sole and absolute discretion, to award a Contract based on the initial proposals, or, to open negotiations, either written or oral, with one or more Respondents to address performance, technical, pricing, delivery, or other provisions. If negotiations are opened, the City may elect, at its sole and absolute discretion, to conclude negotiations at any time if it is determined to be in its best interest, or they will be closed upon settlement of all questions and clarifications. Proposals may be rejected and negotiations terminated by the City. The award will be based on the offers submitted, as well as any and all negotiations conducted. The City further reserves the right to reject all proposals and seek new proposals when such procedure is considered to be in the best interest of the City.
E. The award will be made to that responsive and responsible Respondent whose proposal, conforming to requirements of the request, will be most advantageous to the City, price and other factors considered. The award may or may not be made to the firm with the lowest cost.
F. The City shall have the right, without invalidating the contract, to make additions to or deductions from the items or work covered by the RFP. In case such deductions or additions are made, an equitable price adjustment shall be made between the City and the
Respondent. Any such adjustments in price shall be made in writing.
G. After notice from the City, the selected Respondent will be required to enter into a contract upon receipt of a Notice of Award. If a contract is not executed by the selected
Respondent, then the City reserves the right to retract the Notice of Award and enter into a contract with another Respondent.
H. Proposal forms must be in typewritten form and submitted electronically. Unsigned or incomplete proposals will not be accepted. Respondents are expected to examine the content of the request and respond accordingly. Failure to do so will be at the
Respondent’s risk.
I. No proposal will be accepted from or contract awarded to any person, firm or corporation that is in arrears or is in default to the City upon any contract, or that is a defaulter, as surety or otherwise, upon any obligation to the City or who had failed to faithfully perform any previous contract with the City.
J. Unless otherwise specified, all formal proposals submitted shall be binding for ninety
(90) calendar days following the proposal opening date and may be extended at the agreement of both parties.
K. AUTHORITY
1. The Department of Business Administration has the sole responsibility to respond to inquiries regarding the RFP.
L. COMPLIANCE WITH LAWS
1. The individual or firm selected shall at all times observe and comply with all laws, ordinances, regulations and codes of the federal, state, City and other local government agencies, which may in any manner affect the performance of the contract.
M. CONTRACTOR COMPLIANCE
1. If applicable, each Respondent is required to be in compliance with the City of
Scranton local tax requirements. Failure to be in compliance with City of Scranton local tax requirements may result in proposal disqualification and/or voiding of any contract that may result therefrom.
N. CONTRACT
1. The party selected for services will execute the City of Scranton’s contract provided by the Law Department.
O. CONTRACT TERMINATION
1. A contract may be canceled by the City by giving the Respondent written notice of intent to cancel.
P. CONTROLLING LAW
1. This RFP is governed by, and will be construed and enforced in accordance with the laws of the Commonwealth of Pennsylvania without regard to any conflict of law provisions.
Q. PROPOSAL INSURANCE REQUIREMENTS
1. The Successful Respondent, at the time of execution of the contract, shall also furnish the City with insurance certificates of adequate limits, as later indicated, to protect the
City of Scranton, its agents, and employees from any litigation involving Worker’s
Compensation, Public Liability and Property Damage, involved in the work. All subcontractors must also furnish copies of their liability insurance and Worker’s
Compensation Insurance certificates to the City. No subcontractor will be allowed to perform any work under this contract by the City unless such certificates are submitted to and approved by the City beforehand.\
2. The status of the Respondent in the work to be performed is that of any independent
Respondent and as such, he shall properly safeguard against any and all injury or damage to the public, to public and private property, materials and things, and as such he alone shall be responsible for any and all damage, loss or injury to persons or property that may arise, or be incurred, in or during the conduct or progress of said work without regard to whether or not the Respondent, subcontractors, agents, or employees have been negligent, and the
3. Respondent shall keep the City free and discharged of and from any and all responsibility and liability therefore of any sort or kind. The Respondent shall assume all responsibility for risks or casualties of every description, for any or all damage, loss or injury to persons or property arising out of the nature of the work from the action of the elements, or from any unforeseen or unusual difficulty, including all legal defense costs incurred by the City. The Respondent shall assume and be liable for all blame and loss of whatsoever nature by reason of neglect or violation of any
Federal, State, County or Local laws, regulations, or ordinances; the Respondent shall indemnify and save harmless the City from all suits or actions at law of any kind whatsoever in connection with this work and shall if required by the City, produce evidence of settlement of any such action before final payment shall be made the
City. Respondent’s Liability Insurance Certificate shall include the save harmless clause and shall be filed with the City.
4. The Respondent shall maintain such insurance as will protect the Respondent from claims under worker’s compensation acts and from claims for damages because of bodily injury, including death, and property damage, which may arise from and during operations under this Contract, whether such operations be by himself, by any subcontractor or anyone directly, or indirectly employed by either of them.
Respondent’s liability insurance shall be in the names of the Respondent and the City as their respective interests may appear. Each policy and Certificate of Insurance shall contain an endorsement naming the City of Scranton as additionally insured.
Certificates of such insurance shall be filed with the City.
5. The minimum amount of liability insurance to be maintained by the Respondent during the life of the contract shall be as follows:
6. Workers' Compensation - Statutory.
7. Employer's Liability - in minimum amount of $500,000.
8. Professional Liability – in minimum amounts of $1,000,000 per occurrence and
$1,000,000 aggregate.
9. Comprehensive General Liability (including Blanket Contractual Liability Insurance)
– in minimum amounts of $1,000,000 each person, $1,000,000 each occurrence and
$2,000,000 aggregate for Bodily Injury; $500,000 each occurrence for Property
Damage; $500,000 for Personal Injury.
10. Comprehensive Automobile Liability - N/A
11. Prior to commencement of performance of this Agreement, Respondent shall furnish to the City a certificate of insurance evidencing all required coverage in at least the limits required herein, naming the City of Scranton, its elected officials, agents, and employees as additional insureds under the Comprehensive General Liability coverage, and providing that no policies may be modified or cancelled without thirty
(30) days advance written notice to the City. Such certificate shall be issued to City of
Scranton, Law Department, 340 North Washington Avenue, Scranton, PA 18503. All policies shall be in effect with companies holding an A.M. Best rating of “A-” or better and shall be licensed to do business in the Commonwealth of Pennsylvania.
Such companies shall also be acceptable to the City.
12. Please forward a certificate of insurance verifying these insurance requirements.
13. All subcontractors performing work under this contract must furnish to the City a copy of their Certificate of Insurance for Worker’s Compensation and liability for bodily injury and property damage.
R. RESPONDENT’S ETHICS AND COLLUSION
1. Collusive Bidding: Any firm that submits more than one proposal in such a manner as to make it appear that one of the proposals submitted is competitive with that of a different Respondent, or any two or more firms that agree to fix their respective proposals in such a manner as to be awarded the contract shall be disqualified from further consideration of award of this contract and shall be subject to any applicable penalties under the law.
2. Bribery: Any firm that attempts to influence a City official to award this contract to such Respondent’s firm by promising to provide or by providing to such City official any gratuity, entertainment, commission or any other gift, in exchange for a promise to award the contract to such firm shall be disqualified from further consideration of award of this contract and shall be subject to any applicable penalties under the law.
3. Conflict of Interest: Any firm that knows of any City official having a material direct or indirect financial interest in such Respondent’s firm shall be required to submit a written statement, along with the Form of Proposal, detailing such interest.
Failure to disclose a known such financial interest shall result in the firm’s disqualification from further consideration of award of this contract.
S. INDEMNIFICATION
1. This agreement shall be binding on the parties hereto, their heirs, successors and assigns.
T. OPEN RECORDS LAW/PUBLIC INFORMATION
1. Under the Pennsylvania Right-to-Know Law (the “Law”), 65 P. S. Section 67.101 et.
seq., a record in the possession of the City is presumed to be a public record subject to disclosure to any legal resident of the United States, upon request, unless protected by a statutory exception.
2. Any contract dealing with the receipt or disbursement of funds by the City or the
City’s acquisition, use or disposal of services, supplies, materials, equipment or property is subject to disclosure under the Law. The following are not subject to disclosure under an exception in the Law:
a. A proposal pertaining to the City’s procurement or disposal of supplies, services or construction prior to the award of a contract or prior to the opening and rejection of all proposals; and
b. Financial information of a Respondent requested in an invitation to bid or RFP to demonstrate the Respondent’s economic capability.
U. TRANSFERS AND ASSIGNMENTS
1. Respondent shall not, without written consent of the City, assign, hypothecate or mortgage this agreement. Any attempted assignment, hypothecation or mortgage without the consent of the City shall render this agreement null and void.
2. Neither this agreement nor any interest therein shall be transferable in proceedings in attachment or execution against Respondent or in voluntary or involuntary proceedings in bankruptcy or insolvency or receivership taken by or against the respondent, or by any process of law including proceedings under Chapter X and XI of the Bankruptcy Act.
4. PROBLEM STATEMENT
The RFP format for professional services enables the City to thoroughly evaluate the conditions for selection such as prior class action legal experience with sufficient flexibility in awarding the contract.
A. REJECTION OF PROPOSALS
1. The City of Scranton reserves the right to reject any and all proposals received resulting from this request and to negotiate with those Respondents deemed finalists.
B. INCURRING COSTS
1. The City of Scranton will not be liable for costs incurred by the selected Respondent prior to the issuance of a contract.
C. PRE-PROPOSAL CONFERENCE
1. A pre-proposal conference will not be held.
D. REFERENCES
1. As a requirement for consideration, proposals must include at least two (2) references, including contact information, who can attest to the attributes of the Respondent.
5. CRITERIA FOR SELECTION
A. EVALUATION PROTOCOL
1. All Responses received by the City of Scranton will be reviewed by the Department of Business Administration. A City selection review group will review the merits of content and select the Response which most closely meets the requirements of the
RFP. The final selection may not be the lowest cost Response but that which most closely meets the requirements of the City.
2. Upon receipt by the due date of responses to this RFP by qualified Respondents, the
City will evaluate the Responses for completeness and adherence to the provisions of the RFP. A City selection review group will evaluate all Responses submitted based on the following areas and weighting, and the City shall give consideration to the review group’s evaluation in selecting a Respondent. The City reserves the right to request additional information or clarifications.
3. The City will then schedule interviews with the selected firms if necessary. The selected firms will be given the opportunity to discuss in more detail their qualifications, past experience, proposed work plan and fee Response.
4. The City reserves the right to waive the interview process and evaluate the offerors based on their Responses and fee schedules alone and open fee schedules before or prior to interviews.
5. The City will determine whether the final scope of the project to be negotiated will be entirely as described in this RFP, a portion of the scope, or a revised scope.
6. Recovered material preference program. This preference program will be a case-by-case policy development in which the vendor offering an item composed of the highest percentage of recovered materials, as applicable, will be given a preference score. This score will be taken into account in the final award.
B. SELECTION BASED ON QUALIFICATIONS
1. The Response selected by the City Department of Business Administration will be deemed to respond most favorably to the requirements of the Request.
No. Evaluation Criteria Scoring Method Weight (Points)
1. Completeness and quality of the Response 0-5 Points 10 (10% of Total)
2. Responsiveness to the requirements set forth in the solicitation 0-5 Points 25
(25% of Total)
3. Professional qualifications and experience 0-5 Points 25 (25% of Total)
4. Proposed work plan 0-5 Points 25 (25% of Total)
5. Project fee and per hour rate for staff 0-5 Points 15 (15% of Total)
6. PROPOSAL REQUIREMENTS
Proposals must meet the identified criteria and format. Consideration will be based on compliance with those requirements. All other information considered relevant by the
Respondent will be included as addenda information to the proposal.
6.1. ............................................................................................................................ RF
P CONTENT*
A. STATEMENT OF SERVICES RENDERED
o The Respondent will identify the scope of services provided to the City of Scranton for its project.
o The Respondent will identify how they will be responsive to each of the requirements outlined above.
o Include information which will assist the City to determine the Respondent’s capability of performing the work.
B. MANAGEMENT SUMMARY
o Provide a narrative description of the proposed effort and a list of services delivered by the Respondent.
C. ACTION PLAN
o Describe in narrative form a proposed plan of action for accomplishing the objectives of the project. A detailed timeline for implementation, the reaching of each milestone of the project, and completion must be provided. The City retains the right to negotiate the timing of the project’s implementation and completion, as well as the right to reject any proposal containing a timeline not in conformity with the City’s proposed implementation and completion dates.
D. EXPERIENCE
o Include examples of experience. The documentation of experience should include primary and secondary services, if applicable, and any pertinent experience of the support staff.
o References related to prior activities should be listed as addenda information, including contact information.
E. PERSONNEL
o Include the names of executive and professional personnel who will be assigned including support staff. Resumes for those assigned directly to the activities of this project may be uploaded as addenda information. Do not list firm personnel who will not be assigned to represent the City.
F. REGISTRATION
o Respondents must be duly registered with the applicable federal, state, or local oversight body(s) required to fulfill the scope of services outlined herein. That registration must remain valid and current throughout any period of representation of the City. Copies demonstrating proof of all required registrations, certifications, and/or licenses from applicable federal, state, or local oversight body(s) may be uploaded in this section.
*Response required
6.2. ............................................................................................................................ Oth er Documents
Please upload any additional supporting documents here.
6.3. ............................................................................................................................ CO
ST AND PRICE*
Respondents shall submit a document that includes all associated costs and hourly rates applicable to fulfill the scope of services outlined herein.
The Proposal shall include a detailed cost sheet showing the hours, labor costs, expenses and total cost for each task in the project. The Cost Proposal shall include a not-to-exceed budget for reimbursable expenses, including, but not limited to mileage and document reproduction. If applicable, the cost proposal shall also estimate all potential fees associated with obtaining all permits required to complete the project in accordance with applicable laws. Expenses for telephone, facsimile and computer charges will not be allowed.
If the Proposer anticipates additional services not addressed in the Request for Proposal which, in its opinion, will be required to complete the project, such additional services shall be noted, with a general explanation, a brief justification for the services, and a corresponding proposal for the same.
Unless otherwise approved in writing by the City’s Business Administrator, the proposer selected shall not be entitled to any payment from the City in excess of the not-to-exceed fee provided.
The selected Respondent(s) shall submit invoices to the City for fees in performing the contracted services on a time and materials, not-to-exceed fee basis.
*Response required
6.4. ............................................................................................................................ YE
ARS OF EXPERIENCE*
Include the number of years of experience that the Respondent (as an entity, if applicable) has been performing the services listed under the Scope of Services.
Respondents are required to have a minimum of 5 years of experience under their current business name.
*Response required
6.5. ............................................................................................................................ RE
LATIONSHIPS*
The Response must identify any relationships of the firms and its principals and assigned employees with any official of the City of Scranton. Respondents shall identify any relationships here, or type "N/A" if respondent has no such relationships meeting this criteria.
*Response required
6.6. ............................................................................................................................ AF
FIDAVITS
The following affidavits are required by the City of Scranton:
• Affirmative Action Certificate
• Certificate of Non-Segregated Facilities
• Non-Collusion Affidavit
• Disclosures by Current Contractor
6.6.1. Affirmative Action Certification*
During the term of this contract, Respondent agrees as follows:
(1) Respondent shall not discriminate against any employee, applicant for employment, independent contractor or any other person because of race, color, religious creed, ancestry, national origin, age, sex or handicap. Respondent shall take affirmative action to insure that applicants are employed, and that employees or agents are treated during employment, without regard to their race, color, religious creed, ancestry, national origin, age, sex or handicap. Such affirmative action shall include, but is not limited to the following: employment, upgrading, demotion or transfer; recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training. Respondent shall post in conspicuous places, available to employees, agents, applicants for employment, and other persons, a notice to be provided by the contracting agency setting forth the provision of this affirmative action certification.
(2) Respondent shall, in advertisements or requests for employment placed by it or on its behalf, state all qualified applicants will received consideration for employment without regard to race, color, religious creed, ancestry, national origin, age, sex or handicap.
(3) Respondent shall send each labor union or workers’ representative with which it has a collective bargaining agreement to other contract or understanding, a notice advising said labor union or worker’s representative of its commitment to this affirmative action certification. Similar notice shall be sent to every other source of recruitment regularly utilized by Respondent.
(4) It shall be no defense to a finding of noncompliance with this affirmative action certification that Respondent has delegated some of its employment practices to any union, training program, or other source of recruitment which prevents it from meeting its obligations. However, if the evidence indicates that the Respondent was not on notice of the third-party discrimination or made a good faith effort to correct it, such a factor shall be considered in mitigation in determining appropriate sanctions.
(5) Where the practices of a union or of any training program or other source of recruitment will result in the exclusion of minority group persons, so Respondent will be unable to meet its obligations under this affirmative action certification, Respondent shall then employ and fill vacancies through other affirmative action employment procedures.
(6) Respondent shall comply with all state and federal laws prohibiting discrimination in hiring or employment opportunities. In the event of Respondent’s noncompliance with affirmative action certification of this contract or with any such laws, this contract may be terminated or suspended, in whole or in part, and Respondent may be declared temporarily ineligible for further City of Scranton contracts, and other sanctions may be imposed and remedies invoked.
(7) Respondent shall furnish all necessary employment documents and records to, and permit access to its books, records, and accounts by, the City of Scranton Department of Business
Administration, for purposes of investigation to ascertain Compliance with the provision of this certification. If Respondent does not possess documents or records reflecting the necessary information requested, it shall furnish such information on reporting forms supplied by the City of Scranton Department of Business Administration.
(8) Respondent shall actively recruit minority subcontractors or subcontractors with substantial minority representation among their employees.
(9) Respondent shall include the provisions of this affirmative action certification in every subcontract, so that such provisions will be binding upon each subcontractor.
(10) Respondent’s obligations under this clause are limited to the Respondent’s facilities within Pennsylvania, or where the contract id for purchase of goods manufactured outside of
Pennsylvania, the facilities at which such goods are actually produces.
☐ Please confirm
6.6.2. Certificate of Non-Segregated Facilities*
The Respondent certifies that he does not maintain or provide for his employees and segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location under his control where segregated facilities are maintained. The Respondent certifies further that he will not maintain or provide for his employees any segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location under his control where segregated facilities are maintained. The Respondent agrees that a breach of this certification will be a violation of the Equal opportunity clause in any contract resulting from acceptance of his bid.
As used in this certification, the term “segregated Facilities,” means any waiting rooms, work areas, restrooms and washrooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing directive or are in fact segregated on the basis of race, color, religion, or national origin, because of habit, local custom, or otherwise. The
Respondent agrees that (except where he has obtained identical certifications from subcontractors for specific time periods) he will obtain identical certifications from proposed subcontractors prior to the award of sub-contracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause, and that he will retain such certification in his files.
NOTE: The penalty for making false statements in offers is prescribed in 18 U.S.C. §1001.
☐ Please confirm
*Response required
6.6.3. Non-Collusion Affidavit*
Please download, complete, and upload the below document.
• Non-Collusion_Affidavit.pdf
*Response required
6.6.4. Disclosures by Respondent*
Please download, complete, and upload the below document.
• Disclosures_by_Respondent.pdf
*Response required
6.7. ............................................................................................................................ IN
SURANCE COVERAGE
All Responses submitted to the City of Scranton shall include the following:
6.7.1. A statement of the prospective Respondent’s insurance coverage.* https://government-project.s3.us-west-2.amazonaws.com/19819/4d4743d2-0628-4302-b1df-887d39c6fad6_Non-Collusion_Affidavit.pdf?AWSAccessKeyId=AKIARC2J5PZDGOGWDMYG&Expires=1686387600&Signature=rjZ9HQbFSYBS3lbjVx668Pg8%2Fw4%3D&response-content-disposition=attachment%3B%20filename%3D%22Non-Collusion_Affidavit.pdf%22 https://government-project.s3.us-west-2.amazonaws.com/19819/14af9e36-98b4-41f5-a312-bd9851285ca1_Disclosures_by_Respondent.pdf?AWSAccessKeyId=AKIARC2J5PZDGOGWDMYG&Expires=1686387600&Signature=V9mEiA8l6LIGIoDUpigokiR4VO0%3D&response-content-disposition=attachment%3B%20filename%3D%22Disclosures_by_Respondent.pdf%22
The City requires the successful Respondent to carry the types and amounts of insurance listed hereinabove. All insurance coverages should name the City of Scranton as an additional insured. All insurance coverages must be kept effective during the contract period. The loss of insurance coverages could result in contract termination.
*Response required
6.7.2. A statement of assurance attesting that the prospective Respondent is not currently in violation of any regulatory rules and regulations that may impact its operations.*
*Response required
6.7.3. A statement that the prospective Respondent is not involved in any current litigation against the City of Scranton.*
7. SCOPE OF WORK
7.1. Nay Aug Park Pool Complex Feasibility Study Update and Pool Complex Construction
Design
A. PURPOSE, GOALS, AND OBJECTIVES
The City of Scranton is seeking proposals for a qualified Professional Design Consultant who will conduct a comprehensive Nay Aug Park Pool Complex Feasibility Study Update and Pool
Complex Construction Design, in accordance with PA DCNR Pool Complex Feasibility guidance. The lead consultant or consulting team must have documented expertise for study and construction of swimming pools and related amenities (bathhouse, concessions, parking, etc.). A professional with applied pool management experience must be part of the consultant team. The city requires that the Pool Feasibility Study and Pool Complex Construction Design be under seal of a licensed professional who is authorized by Pennsylvania law to seal such documents.
Depending on the aspect of the project, the professional could be a landscape architect, architect, or engineer.
Phase 1 – Study
The first phase of the project will include a thorough review of the Nay Aug Pool Complex
Feasibility Study of April 2021 and an update to data and estimates determined in the study. Beyond the technical engineering evaluation and any proposed physical improvement recommendations to the site, the consultant must engage the public and conduct a detailed users’ needs analysis. Lifestyles and aquatic recreation opportunities and trends have changed radically over the last twenty years with the advent of commercial water parks, wave pools, themed splashpads and elaborate spray structures. Examining current national trends, future industry projections, and assessing local needs and demographics will be key components of a successful project. The vendor will present the city with preliminary designs and cost estimates based on the study findings.
The city administration’s initial vision is a pool complex that has a pool of approximately 12, 375 square feet, with both zero-entry recreational swimming area and lap swimming area, a spray pad of approximately 5,000 square feet, improvements to the existing bath house, and a support structure/mechanical building. The pool will be a combination leisure pool and lap pool.
There is a potential that the city may determine a phased approach to constructing the pool complex may be in order, but design for pool, splash pad and amenities will be completed in this project. Anticipate Completion of Phase one in 4 months of contract execution.
Phase 2 - Construction
If the feasibility study findings and preliminary design drawings are approved by the city, the city will authorize the vendor to proceed on Phase 2 of the contract. Phase 2 will include production of construction designs, bid documents, construction oversight, project documents, and permitting with state and local agencies. Anticipate at least 50% completion of Phase Two in
7 months of contract execution.
PHASE 1 – STUDY PHASE
B. PUBLIC PARTICIPATON
The project shall begin with a meeting with city administration and city council members. Public participation is required throughout the planning process to help determine and prioritize community needs. Community involvement and engagement must prioritize diversity, equity, and inclusion to ensure feedback and recommendations that are comprehensive, appropriate, and accountable. A narrative should be produced with the participation data collected and must include a detailed summary of the public participation methods, results, and conclusions (i.e.
areas of consensus and/or contention); raw data should be included in the appendix.
1. At minimum, public participation must include:
*a.) Study Committee (5-9 people) – A representative and diverse study committee must be formed and meet with the planning consultant on a regular basis to provide guidance and review of the work. This committee will be formed by the city with guidance from the vendor.
*b). Public Meetings – At least four public meetings must be held and at least one must be with elected officials. The appropriate number and type of meetings will vary depending on the project scope and community needs.
*c.) Key Person Interviews (10-20 interviews) – A key person interview is a one-on-one discussion about a specific topic with an individual recognized or designated as a community leader. The Study Committee should help to determine potential interviewees. Consider conducting 10-20 interviews
2. Additional recommended public participation:
*a.) Citizen Survey – A random sample citizen survey is a type of opinion poll that asks residents for their perspectives on specific topics. Describe the survey method to be used (i.e. written, telephone, internet, etc.) and the anticipated number of survey questionnaires.
*b.) Citywide Focus Group – A focus group provides community input from individuals with common interests. Consider focus groups comprised of neighborhood residents, elected officials, organized sports organizations, etc.
*c.) Planning Document Review – Review previous and consider the results of recent public participation efforts regarding parks, recreation, and open space.
C. MARKET ANALYSIS
1. Demographic characteristics and community profile – Project a reasonable service area (using census tracts or locally recognized neighborhoods) for the proposed facility, and determine existing and projected breakdowns for:
*a.) Population, age, educational level, ethnicity, gender, income level
*b.) Businesses and schools
*c.) Socio-economic trends
*d.) Emerging and programmatic trends
2. Comparison with national, regional, and local participation statistics/trends
3. Review existing research, studies, and plans.
4. Inventory of other municipal facilities – Provide a map which shows the names and locations of local similar facilities; include an assessment of overall facilities and programs offered, quality, size, fees, attendance numbers.
5. Demand analysis – Provide both usage and growth rates (local, state, and national levels) for the proposed facility.
D. PROGRAMMING ANALYSIS
1. General description and numbers of current and anticipated programs
2. Project component/program recommendation/prioritization
*a.) Validate or adjust any existing facility program.
*b.) Determine sizing and space allocation requirements.
*c.) Component/Program relationships and interaction
3. Develop program goals.
ESITE ANALYSIS
1. Consider the following:
*a.) Acreage, boundaries, geological and soils features, steep slopes (in excess of 15%), topography, surrounding property and uses
*b.) Flood plains, stream corridors, subsurface and water table, wetlands
*c.) Vegetation and wildlife
*d.) Climatic impacts
*e.) Utilities (water, sewer, electric)
*f.) Access, barriers, traffic, parking
*g.) Environmental impact (light, air and sound pollution and stormwater management), compatibility with existing development
2. Analyze compliance with the following:
*a.) Accessibility compliance with the Architectural Barriers Act of 1968, Section 504 of
Rehabilitation Act of 1973, and Americans with Disabilities Act of 1990.
*b.) Codes and/or recommended standards. (electrical code, PA Construction Code, Uniform
Construction Code, 2010 ADA Standards for Accessible Design, etc.)
*c.) Address occupancy and safety requirements.
3. Consider existing development on site.
4. Address and evaluate surrounding land use and community presence. Identify any potential impacts the new recreation facility may have in the community.
5. Address Emergency Action Plan
F. GREEN DESIGN CONSIDERATIONS
1. Evaluate renewable energy sources and the best green technology solutions.
*a.) Solar
*b.) Wind
*c.) Geothermal
*d.) Heating and cooling energy reduction strategies (ex. tree planting)
2. Describe the green and sustainable practices to be included in the project
*a.) Provide analysis of the green elements; including cost comparisons for these elements vs.
traditional development
*b.) Determine current carbon footprint and potential reduction
*c) Complete an energy audit
*d.) Reduced water usage (conservation measures, rainwater collection techniques, etc.)
*e.) Integrate stormwater best management practices where possible
3. List materials that can be used in design and construction that are eco-friendly, made of regional content, and are recyclable. These may include flooring, carpeting, paint, stain, insulations, wall and ceiling panels, windows, cabinets, etc.
4. Provide a cost benefit analysis of green technologies and design elements
G. LAYOUT AND DESIGN
*a.) DCNR Park Site Development Drawing Checklist https://elibrary.dcnr.pa.gov/GetDocument?docId=1741853&DocName=Site%20Development%20Drawing%20Checklist%20Park.doc
*b.) Conceptual design plans/perspectives
*c.) Analyze spatial relationship of components
H. FINANCIAL & POOL MANAGEMENT ANALYSIS
The acquisition/development of a new facility will require additional funds above and beyond the present budget, not only for capital expenses, but also for operating expenses such as administration, personnel, programming, and maintenance. Since not all of these costs can be covered by the current budget and staff, they must be accounted for in evaluating the financial feasibility of the new facility rather than making the assumption that the existing staff and budget can absorb these items.
*a.) Design costs
*b.) Development costs: site preparation, recreational components, support facilities, utilities, amenities
*c.) Initial capital outlay (equipment)
1.Debt service
Operation and maintenance costs (project by major budget category for 5 years)
*a.) Administration: insurance, membership to professional organizations, office supplies, phone, programming, public relations, rentals, training
*b.) Personnel: by position, salaries/wages/benefits, contractual services
*c.) Supplies and material: utilities, mechanical, office, custodial, concession and retail items
*d.) Maintenance equipment
2. Revenue (project for 5 years)
*a) Daily admission or entrance fees
*b.) Memberships (optional)
*c.) Facility rental, special fees/permits
*d.) Programs and services
*e.) Sales (concession stand, vending, game machines, locker rental, etc.)
*f.) General municipal fund support
*g.) Fundraising
*h.) Other sources of income i.) Provide cost benefit analysis of proposed capital improvement
I. TOTAL PROJECT COST and/or PHASED CAPITAL DEVELOPMENT PROGRAM
If the proposed development cannot realistically be carried out as one complete project, develop a phased and prioritized multi-year capital development program. This should explain the strategy for the phasing, identify which areas and facilities are to be developed in which years, and provide the costs associated with each phase.
J. FINANCIAL OPTIONS
Based on projected costs for design, development and operation, and projected revenue, provide the various financial options for obtaining the necessary funds to design, build, operate and maintain the facility. Project for five years, and include dollar amounts from each suggested financial source. Include in this discussion, based on input from public meetings, surveys, meetings with public officials and agency staff, only the viable and significant sources of likely funds, such as:
1. General fund support
2. Capital campaign
3. Charitable contributions (gifts, endowments, trusts, donations, etc.)
4. Applicable grants- including consultant assisting preparation of scope for grant applications
5. Facility generated revenue
6. Partnerships- nonprofit, public and private sector support
K. SUMMARY OF FINDINGS, DELIVERABLES, AND RECOMMENDATIONS
Provide a detailed summary of study findings and recommendations of sections1 through 13.
1.Base drawing of the facility
2.Summary narrative
3.Cost estimate by category of work
4.Marketing survey
5.Marketing Survey Report and Response analysis:
*a.)Demographics
*b.)Participation
*c.)Alternative providers & trends of Three proposed schemes
6.Completion of conceptual and schematic designs and associated estimates of probable construction costs.
7.Draft scope of work and assist in grant application for funding opportunity.
8.Attendance of City Council meetings necessary for approval of and input on final proposed concept design
9.Attendance Estimates, Fee Structure, Sources of Income, Operating Cost Projections, Revenue
Generation Projections, Revenue Expenditure Comparisons, Project
Recommendations/Profitability of Components. Order of magnitude capital cost projection for each scheme
10.Presentation preparation (PowerPoint or equal)
13.Drawings and photographs of existing conditions
PHASE 2 - CONSTRUCTION
L. CONSTRUCTION PHASE: This phase is contingent on city approval of a conceptual design proposed in the study phase and will commence upon written notice by the city. The scope of work for this phase of the project should include, but is not limited to, the following:
1.Cost Estimation:
*a.) Prepare a detailed cost estimate for the proposed design, including materials, labor, and any additional expenses associated with the construction and implementation of the public pool complex.
2. Design:
*a.) Provide complete multi-discipline design services for the pool structures, including the pool, splash pad, and related amenities.
*b.) Completion of design development and construction documents, including plans and specifications.
*c) Design the mechanical and electrical systems required for the pool complex, including filtration systems, water supply and drainage, lighting, and electrical distribution.
*d.) Submit and review design documents and cost estimates and construction cost estimates with City staff at 50 percent and 100 percent completion of each milestone.
*e) Finalize documents based on feedback from City staff and all authorities having jurisdiction.
*f.) Submit all project documents necessary to the City of Scranton Code Enforcement
Department, PA Department of Environmental Protection, Lackawanna
Conservation District, Department of Conservation and Natural Resources, PA Department of Health and obtain all permits
*g.) Prepare bid documents and assist City staff with bidding project for construction.
Incorporate bid addenda, as required, to issue a conformed “For Construction Set” after the bid phase is completed. RFP DESIGN, CONSTRUCTION FOR CITY
OF SCRANTION NAY AUG POOL COMPLEX
3. Construction administration:
*a.)The Consultant shall provide a full range of Construction Management services including, but not limited to:
*b.)Leading construction meetings, preparation and management of construction documentation, monitoring of…
This is the start of the file's text. The full file is on GovTribe.