14Q4816_SOW.pdf
PDF 90 KB Posted
- Attached to
- Install Water and Septic Tanks, McMullen Range Federal contract opportunity
- Solicitation number
- N69450-14-Q-4816
About this file
SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 14-Q-4816_Revised_SOW_Paragraph.pdf | ||
| 14-M-4816_RFI_1.pdf | ||
| Color_Coded_Pass_Aplication _6-24-2011.pdf | ||
| 14Q4816_WDs.pdf | ||
| 14Q4816_RFQ.pdf | ||
| 14Q4816_Photos.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND SE
CONTRACTS DIVISION, PUBLICS WORKS DEPARTMENT
NAVAL AIR STATION, BLDG. 4711
201 NIMITZ AVE., SUITE 103
KINGSVILLE, TEXAS 78363-5119
1. PROJECT: Replace water supply tank and septic tank at Bldg 3028 Dixie Target Site (McMULLEN
Range), Freer, Texas
2. PROJECT REQUIREMENTS: Remove existing non-functional water supply tank and septic tank.
Install a new Water Tank 1,500GL and a new 750GL Septic Tank from BLDG 3028 AT DIXIE TARGET SITE (McMULLEN Range)
3. GENERAL REQUIREMENTS: The Contractor shall provide all labor, materials, equipment, tools, transportation and management necessary to accomplish the project. Report any unforeseen findings to the attention of the Construction Manager (CM) and Construction Engineer Technician (ET) assigned to the project.
3.1. Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature. The COR will be the CM and ET assigned to the project
4. SCOPE OF WORK: The contractor shall remove the existing non-potable water tank and pump. The contractor shall provide and install a new 1,500 GL vertical capacity storage tank. The contractor shall provide and install a new Jet pump. The contractor shall place the jet pump on the concrete pad as close as possible to the wall leaving enough space to allow for servicing. The contractor shall install new PVC piping, fittings, valves, gauges, and all other equipment needed to establish a working non-potable water supply system. The contractor shall insulate the exterior pipes with exterior insulation and cover with an aluminum jacket. The contractor shall install a NEMA 3 non-fused lockable disconnect on the exterior of the BLDG 3028 in accordance to NEC. The contractor shall refer to Part 2 Photo for location of the water tank. All electrical connections shall be water tight. The contractor shall provide and install a new 750 GL reinforced concrete septic tank. The contractor shall provide a detailed drawing of the new septic tank. The drawing will need to include 2 two-way clean outs. The contractor shall use schedule 80 PVC from BLDG 3028 to the septic tank. The contractor shall refer to Part 1 and 2 of the on-site Sewage Facility Soil Evaluation report. The contractor shall refer to Part 3 Photo for the septic tank location.
4.1. DEMOLITION WORK: The contractor shall demolition the existing non-potable water tank, metal stand, pump and PVC. The contractor shall refer to Part 1 Photo for location.
4.2. MATERIAL/EQUIPMENT SPECIFICATION: List of materiel or equipment for the government to approve)
4.2.1. Water tank
4.2.1.1. Corrosion resistant polyethylene construction
4.2.1.2. Black pigmented
4.2.1.3. For water storage only
4.2.1.4. No safe for drinking water
4.2.1.5. 20lb 67” with an 87” diameter
4.2.1.6. Black storage tanks.
4.2.1.7. 1500GL above Ground Water Tank
4.2.2. Pump
4.2.2.1. Pumps up to 8 GPM at 40 PSI
4.2.2.2. 115-volt motor provides high output
4.2.2.3. Corrosion-resistant, jet pump is ideal for depths of 25ft or less
4.2.2.4. Fiberglass-reinforced thermoplastic pump housing is durable
4.2.2.5. Pre-charged 15 gallon equivalent tank features heavy steel construction
4.2.2.6. Pump self primes after the housing is initially filled with water
4.2.2.7. Pressure Switch is pre-set with 30-50 PSI pressure setting
4.2.2.8. Ready to Install
5. APPLICABLE REFERENCE DOCUMENTS:
5.1. Federal, State and/or Local regulations: the most stringent standard shall prevail.
5.2. Unified Facilities Criteria (UFC)
5.3. American National Standards Institute (ANSI)
5.4. National Fire Protection Association
5.5. National Electric Code
5.6. American Society of Heating, Refrigeration and Air Conditioning Engineers
5.7. American Society of Testing and Materials
5.8. U.S. Army Corps of Engineers (EM 385-1-1)
5.9. 29 CFR 1910 (OSHA)
5.10. FAR 52.236-3
5.11. Texas Administrative Code (TITLE 30PART AND CHAPTER 285)
5.12. Texas Health and Safety Code Chapter 366 Subchapter D
6. PRE-AWARD SITE VISIT: Prior to submitting proposals, prospective bidders can and will be expected to visit the job site, inspect the work in place and satisfy themselves as to the character and amount of work to be accomplished. The COR will notify bidders of the scheduled site visit time and date with issuance of solicitation.
7. PERFORMANCE PERIOD: Performance period shall be [60] calendar days. Notice to Proceed is made in writing by the Contracting Officer (KO) LT Joel Overson (361) 516-6107. Performance period shall include material procurement, pre-construction meetings, construction, commissioning, and closeout documentation.
8. LIQUIDATED DAMAGES: FAR 52.211-12
Project Cost Estimated Liquidated Damages Per Calendar Day
$25,000-50,000 $110
$50,000-100,000 $140
$100,000-500,000 $200
Each additional $100,000 Add $50
9. PROJECT SCHEDULE: The Project Schedule shall show submittals, government review periods, material/ equipment delivery, utility outages, on-site construction, inspection, testing, and closeout activities. The Bar Chart shall be time scaled and generated using an electronic spreadsheet program
9.1. The Contractor shall use the critical path method (CPM) to schedule and control project activities. Project schedules shall be prepared and maintained electronically. Save files in applicable format to be importable. Schedule shall be updated at least monthly for any project exceeding 30 calendar days. The schedule shall be built as follows:
9.1.1. The Project Schedule shall show design periods, submittals, government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities shall be driven by work schedules that reflect Saturdays, Sundays and all Federal Holidays as non-work days unless notified.
9.1.1.1. Schedule shall display Start Contract and End Contract milestone activities.
No activities shall be open-ended; each activity shall have predecessor and successor ties.
9.1.1.2. Date/time constraint(s) and/or lags, other than those required by the contract, shall not be allowed unless accepted by the QA. The Contractor shall include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date". The "Contract Completion Date" milestone shall have a "Mandatory Finish" constraint equal to the contract completion date.
10. PRE-CONSTRUCTION MEETING FOR PROJECTS: The Contractor shall participate in the pre-construction meeting to discuss administrative and contract requirements. The Contractor will work with the COR to set up. During the meeting, the Contractor shall discuss the conceptual process of the project with drawings, specifications, catalog cuts, job plans, and all required documents as available at the time of the meeting.
11. PRE-CONSTRUCTION SUBMITTAL REQUIRMENTS: The Contractor shall have the following submitted within 14 days of award and prior to the Pre-Construction Meeting:
11.1. Project Schedule: provide updated schedule if warranted.
11.2. Accident Prevention Plan (must be site specific) with Activity Hazard Analysis (AHA) for each Definable Feature of Work.
11.3. Emergency Action Plan: can be separate or an attachment to Accident Prevention Plan.
11.4. Quality Control Plan: will identify the Contractor’s Organizational Chart and provide associated documentation and methods and testing to ensure quality.
11.5. Material/Equipment Submittal Plan will identify projected dates that material submittals will be forwarded to the government. Manufacturing lead-time shall be afforded for manufacturing of equipment. Contractor must provide proof of manufacturing purchase from vendor to the KO and request a no cost time extension via the Request For Information (RFI) process.
12. SUBMITTAL REGISTER:
12.1. Project Schedule
12.2. Accident Prevention Plan must be site specific
12.3. Activity Hazard Analysis
12.4. Emergency Action Plan
12.5. Quality Control Plan
12.6. Material/Equipment Submittals, (use NASK PWD transmittal form)
12.7. Environmental Plan
12.8. Acceptance Test plan
12.9. Proof of manufacturing purchase from Vendor, as requested.
12.10. Material Safety Data Sheets (MSDS), as applicable.
12.11. Licenses and Permits:
12.11.1. Contractor is required to provide proof of septic tank installation permit
12.12. Digging Permit (14 days prior to digging)
12.13. As-Built Drawings – Contractor shall provide as-built drawings at the completion of the project.
Drawings shall include (1) CD’s containing plans and specifications in AutoCAD and PDF format.
13. SUBMITTALS and PROCEDURES: Provide submittals and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic media of the project schedule in an import format compatible with the government’s scheduling program.
13.1. UPDATED PROJECT SCHEDULES: Update the Project schedule at monthly intervals, if applicable, or as revisions are needed. The updated schedule shall be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the assigned COR.
13.2. THREE-WEEK LOOK AHEAD SCHEDULE: At the start of construction, the Contractor shall prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Project Schedule. The work plans shall be keyed to activity numbers when a Network Analysis type schedule is required and updated each week to show the planned work for the current and following two-week period. Additionally, include upcoming outages, closures, preparatory meetings, and initial meetings. Identify critical path activities on the Three-Week Look Ahead Schedule. The detail work plans are to be bar chart type schedules, maintained separately from the Project Schedule on an electronic spreadsheet program and printed on 8-½ by 11 sheets as directed by the Contracting Officer.
Activities shall not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work. Two hard copies and one electronic file of the 3-Week Look Ahead Schedule shall be delivered to the assigned COR no later than 1000 each Monday and reviewed during the weekly Coordination Meeting (if applicable).
13.3. CORRESPONDENCE AND ACCEPTANCE TEST REPORTS: All correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and Daily Reports, material delivery tickets, photographs, etc.) shall reference the Design and Construction Schedule activities that are being addressed. All test reports (e.g., equipment, concrete, soil compaction, weld, pressure, etc.) shall reference schedule activities that are being addressed.
14. FIRE, SAFETY AND CONFINED SPACE REQUIREMENTS: The Contractor is required to comply with all Station Safety Regulations. The Contractor shall observe all requirements for handling and storage of combustible materials, waste and trash. Open flames aboard the station/hot work (i.e.
welding) require a permit from the fire department, phone number 361-516-6135.
14.1. SAFETY REQUIREMENTS: Contractor shall perform Operational Risk Management (ORM) and Activity Hazard Analysis (AHA) as required by USACE EM 385-1-1. Contractor shall submit the required AHA form to the COR at least one week prior to each new work phase in the project schedule, when new hazards are identified, or when a new work crew is brought on site.
14.1.1. OCCUPATIONAL HEALTH REQUIREMENTS: The contractor shall be responsible for maintaining a safe work environment for assigned personnel for the duration of the tasks. Personnel injuries, regardless of severity, shall be reported immediately to the assigned ET or PAR.
14.1.2. EMERGENCY ACTION PLAN (OSHA 29 CFR 1910.38): The contractor shall develop an emergency action plan in accordance with applicable rules and regulations and it shall be adhered to in the event of an emergency and shall address the following sections. It is the responsibility of the project supervisor, and shift supervisor to educate and brief all personnel on this emergency plan.
14.1.3. CONTRACTORS SAFETY RESOURCES WEB SITE (APP and AHA information):
https://portal.navfac.navy.mil/portal/page/portal/navfac/navfac_ww_pp/navfac_navfacl ant_pp/lant_bl/lant_ci/ci_lant_safetyshack/contr_safety_resources
14.1.4. CONTRACTOR WEIGHT HANDLING EQUIPMENT (WHE) REQUIRMENTS:
(remove paragraph, if not required) The Contractor shall comply with specific activity regulations pertaining to crane safety and operation, notify the Contracting Officer, in advance, of any cranes entering the activity and comply with ASME B30.5 for mobile cranes and ASME B30.22 for articulating boom cranes. Cranes used in construction, demolition, or maintenance shall comply with 29 CFR 1926 and the Corps of Engineers Manual EM 385-1-1. Further requirements will be provided at the Pre-Con, if required.
14.2. WORK IN CONFINED SPACES: In addition to the requirements of Section 06.I of USACE EM 385-1-1, OSHA 29 CFR 1910.146 and OSHA 29 CFR 1926.21(b)(6), comply with the following paragraphs. Any potential for a hazard in the confined space requires a permit system to be used.
14.2.1. Confined Space Signage: Provide permanent signs integral to or securely attached to access covers for permit-required confined spaces provided by this contract.
Signs wording: "DANGER--PERMIT-REQUIRED CONFINED SPACE - DO NOT ENTER -" in bold letters a minimum of 25 mm (one inch) in height and constructed to be clearly legible with all paint removed. The signal word "DANGER" shall be red and readable from 1.52 m (5 feet).
14.2.2. Entry Procedures. Prohibit entry into a confined space by personnel for any purpose, including hot work, until the qualified person has conducted appropriate tests to ensure the confined or enclosed space is safe for the work intended and all potential hazards are controlled or eliminated and documented. (See Section 06.I.06 of USACE EM 385-1-1 for entry procedures.) Review all hazards pertaining to the space with each employee during AHA process.
14.2.3. Forced air ventilation is required for all confined space entry operations. Maintain minimum air exchange requirements to ensure exposure to any hazardous atmosphere is kept below its' action level.
14.2.4. Sewer wet wells require continuous atmosphere monitoring with audible alarm for toxic gas detection.
15. ENVIRONMENTAL PROTECTION REQUIREMENTS: The Contractor shall comply with all applicable environmental protection requirements as well as Federal, State and Local Laws. The Contractor shall comply with the Executive Order 12856, EMERGENCY PLANNING AND https://portal.navfac.navy.mil/portal/page/portal/navfac/navfac_ww_pp/navfac_navfaclant_pp/lant_bl/lant_ci/ci_lant_safetyshack/contr_safety_resources https://portal.navfac.navy.mil/portal/page/portal/navfac/navfac_ww_pp/navfac_navfaclant_pp/lant_bl/lant_ci/ci_lant_safetyshack/contr_safety_resources
COMMUNITY RIGHT-TO-KNOW ACT (EPCRA); Section 313 requires that all releases of the chemicals in the section 40 of the Code of Federal Regulation (CFR) 372 report to the State Emergency Response Commission and EPA. The Contractor is required to provide the amount in pounds of listed chemicals released in the environment to the Contracting Officer.
16. CONTRACT ADMINISTRATIVE REQUIREMENTS:
16.1. REQUIRED INSURANCE: The Contractor shall procure and maintain during the entire period of performance under this contract insurance at a level that satisfies all State minimum requirements for General Liability, Automobile Liability, and Worker’s Compensation.
16.2. LICENSES/PERMITS. Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. Comply with all applicable federal, state, and local laws, and base regulations and procedures. Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see FAR 52.236-7, Permits and Responsibilities). The Contractor will coordinate permit applications with the Navy.
16.3. ACTIVITY REGULATIONS. The Contractor and their employees shall become acquainted with and obey Activity regulations as posted or as requested by the Contracting Officer. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter restricted areas unless required to do so and until cleared for such entry. The Contractor’s equipment shall be conspicuously marked for identification.
16.4. PROPRIETARY RIGHTS. All field notes, design drawings, specifications, and other documents collected and produced as part of this contract shall be considered property of the Government. Data shall not be used, in whole or part, published or unpublished, as a part of any technical or non-technical presentation without written pre-approval of the Contracting Officer.
16.5. PROTECTION OF GOVERNMENT PROPERTY. Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, perform the following:
16.5.1. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.
16.5.2. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
16.5.3. Preserve the natural resources in accordance with the approved environmental protection plan.
16.6. ORAL MODIFICATION. No oral statement by any person other than the Contracting Officer, as provided in the contract clause entitled, “CHANGES AND CHANGED CONDITIONS,” will in any manner or degree modify or otherwise affect the terms of this contract.
16.7. NO WAIVER BY THE GOVERNMENT: The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred shall not be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.
16.8. CONTRACTOR INVOICES: Contractor requests for payment will be processed in accordance with the requirements of FAR 52.232-5 and FAR 52.232-27. Invoices shall adhere to DFARS Clause 252.232-7003 titled "Electronic Submission of Payment Requests”.
16.8.1. Contractor must first be registered in System for Award Management (SAM). SAM integrates the eight current federal procurement systems and the Catalog of Federal Domestic Assistance into a single new, streamlined system. More information is located at https://www.uscontractorregistration.com
16.8.2. This contract/order requires use of the DoD Wide Area Workflow (WAWF) system for the submission of invoices. This web-based system located at https://wawf.eb.mil,provides the technology for Government contractors and authorized Department of Defense (DoD) personnel to generate, capture and process receipt and payment-related documentation in a paperless environment.
Invoices rendered under this contract shall be submitted electronically through WAWF. Submission of hard copy DD250/invoices will no longer be accepted for payment.
16.8.3. The PWD Kingsville WAWF point of contact for this contract is Dana Villarreal and can be reached at 361-516-6210.
16.8.4. If you have any non-project related questions regarding WAWF, please contact the WAWF helpdesk at 866-618-5988 or the NAVFAC WAWF point of contact identified above in section. Please use the Routing Table below when building your invoice in
WAWF:
Field Name in WAWF Data to be entered in WAWF
Pay Official DODAAC N68732
Issue By DODAAC N69450
Admin DODAAC N45974
Inspect By DODAAC N45974
Ship To Code N/A
Ship From Code N/A
Mark For Code N/A
Service Approver (DODAAC) N/A
Accept at Other DODAAC N/A
LPO DODAAC N45974
DCAA Auditor DODAAC N/A
Other DODAAC(s) N/A
16.8.5. Payment will be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments. The Government may withhold payment or reduce payments for the following:
16.8.5.1. Defects in material or workmanship.
16.8.6. Claims the Government may have against the Contractor under or in connection with this contract.
16.8.6.1. Contractor's failure to submit an updated schedule.
16.8.6.2. Payroll violations.
16.8.6.3. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
16.8.7. Payments may be made for materials, stored off construction sites, under the following conditions specified in FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts:
16.8.7.1. Conditions described in Attachment A. Materials adequately insured and protected from theft and exposure.
16.8.7.2. Materials not susceptible to deterioration or physical damage in storage or in transit to the job site are acceptable for progress payments. Items such as steel, machinery, pipe and fittings and electrical cable are acceptable, but items such as gypsum board; glass, insulation and wall covering are not.
16.8.7.3. Materials in transit to the job or storage site are not acceptable for payment.
17. PROJECT EXECUTION REQUIREMENTS:
17.1. QUALITY CONTROL (QC) PLAN: The Contractor shall provide and maintain an effective quality control program that complies with the Contract Clause entitled "Inspection of Construction." The Contractor’s Quality Control Program through inspection and reporting shall document compliance of all work with the standards established by the contract document. The Contractor's Quality Control (CQC) program shall include daily inspections and provide for a daily report of CQC activity. Submit a QC Plan for Government review and acceptance. The QC plan shall include the following:
17.1.1. NAMES, QUALIFICATIONS and RESPONSIBILITIES: Name of individual who will be responsible for QC on site
17.1.2. OUTSIDE ORGANIZATIONS (as applicable): Outside organizations, including architectural and consulting engineering firms and a description of the services these firms will provide.
17.1.3. INITIAL SUBMITTAL REGISTER (DESIGN & CONSTRUCTION): Include submittal reviewer, estimated date of delivery, and identify which design submittals require Government approval prior to construction, and which construction submittals require DOR or Government approval prior to construction.
17.1.4. TESTING LABORATORIES: Accredited laboratories as applicable.
17.1.5. TESTING PLAN AND LOG: Tests required, referenced by specification paragraph number requiring the test, frequency, and person responsible for each test as applicable.
17.1.6. LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, and has the same control requirements and work crews.
17.1.7. COMMUNICATION PLAN: Provide a plan for key decisions and possible problems the Contractor and Government may encounter during the project. At a minimum the Communication Plan shall indicate the frequency of QC meetings and what information is covered in those meetings, key decision points tied to the schedule, and required coordination efforts.
17.1.8. If project is more than 21 days, the Contractor shall use the Three Phases of Control process for construction QC.
17.1.8.1. Preparatory Phase: Review all applicable documents for compliance with all applicable laws, codes, regulations, and the requirements of the contract, including contract drawings and specifications. Determine requirements for testing and certification. Review submittal approvals for materials, equipment, shop drawings, and applicable methods of construction and installation. Include all Preparatory Phase items in the QC Report.
17.1.8.2. Initial Phase: Observe and inspect the initial portion of the work performed under a DFOW to establish the quality of the workmanship, resolve conflicts in construction, ensure that testing is done and certified as required, and to check all work procedures to ascertain the work is in conformance with required safety requirements. Record and report nonconforming work and work not of acceptable quality and requiring correction or rework. Include all Initial Phase items, along with initial phase checklist and, in the QC Report.
17.1.8.3. Follow-Up Phase: Occurs at the completion of each DFOW. Ensure the work is in compliance with contract requirements, quality of workmanship for all work is maintained, and all work performed meets safety requirements. Include all Follow-Up Phase items, including date, in the QC Report.
17.1.9. Contractor must possess a current certificate of completion of the Army Corps of Engineers NAVFAC Contractor Quality Management (CQM) Training. The Contracting Officer may have the option of waiving the requirement only once, if the Contractor is new to NAVFAC contracts.
17.2. SUPERVISION REQUIREMENTS: In accordance with FAR Clause 52.236-6, Superintendence by the Contractor, at all times during performance of this contract and until the work is completed and accepted, the contractor shall directly superintend the work or assign and have on the worksite a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the contractor. The superintendent shall be fluent in English.
17.3. CONTRACTOR PERSONNEL BASE ACCESS REQUIREMENTS:
17.3.1. The base access protocol implemented is the RAPIDGate system. The system provides background checks of contractor personnel. A personnel badge that affords base access for one year will be issued to each Contractor employee that meets background check criteria. There are costs for contractors to participate in the RAPIDGate program which include a fee for the Contractor's firm and a fee per Contractor employee. Costs to participants are recaptured through increased productivity of their employees due to the reduction in waiting times at the Pass and Identification Office and Entry Control Points (ECP). Contractors are not required to participate in the Rapid Gate Program. Those Contractors who chose not to participate will be required to obtain daily passes for base access.
17.3.2. Requests for daily passes must be filled in CNRSE 5200.1 Form 1 & 2 and submitted to the assigned COR a minimum 14 days prior to any new work.
17.4. SCHEDULING WORK PROCEDURES AND OUTAGES: Schedule work construction for minimal impact on normal Government operation that involve designated area.
17.4.1. Prior to construction work, the Contractor shall meet with the assigned COR for construction approval of scheduling and sequence of construction/ or outages.
17.4.2. The Government's normal hours of operation are 0700 to 1630 Monday through Friday, excluding Government holidays.
17.4.3. If the Contractor decides to work other than normal hours/working days, they shall submit a request to the QA for approval 3 days prior to the work.
17.5. UTILITY LOCATIONS AND VERIFICATION PRIOR TO EXCAVATION: If applicable, obtain appropriate digging permit from Base personnel through the FEAD office prior to digging.
Maintain all markings during utility investigation throughout the contract. “At the contractor’s expense, all underground utilities in the work area must be positively identified by a private utility locating service in addition to any station locating service and coordinated with the station utility department.”
17.5.1. Physically verify underground utility locations by hand digging using wood or fiberglass handled tools when any adjacent construction work is expected to come within three feet of the underground system. Use hand digging within three feet of a known utility. If construction is parallel to an existing utility, expose the utility by hand digging every 100 feet if parallel within five feet of the excavation.
17.5.2. UTILITIES WITHIN CONCRETE SLABS: Utilities located within concrete slabs are extremely difficult to identify due to the reinforcing steel used in the construction of these structures. Whenever work involves concrete chipping, saw cutting, or core drilling, the existing utility location must be coordinated with station utility departments in addition to a private locating service. Outages to isolate utility systems shall be used in circumstances where utilities are unable to be positively identified. The use of historical drawings does not alleviate the contractor from meeting this requirement.
17.5.3. CONDUCT OF ELECTRICAL WORK: Follow electrical safety criteria specified in UFC 3-560-01, USACE EM 385-1-1, and NFPA 70E during the conduct of all work.
As delineated in USACE EM 385-1-1 electrical work is to be conducted in a de-energized state unless there is no alternative method for accomplishing the work. In those cases an energized work permit shall be obtained from the Commanding Officer.
17.6. CONTRACTOR WORK SITE:
17.6.1. Contractor shall limit use of the premises for work and for storage of material and equipment associated with the contract. Unless otherwise specified or separately agreed to, Government owned material handling equipment, transportation equipment or general tools will not be available for Contractor’s use.
17.6.2. Clean work area daily and after completion of the work, removing all loose debris and disposing of all non-permanent materials IAW the contractor’s Waste Management Plan. Submit a monthly summary of removed solid waste in weight to assigned ET or
PAR.
17.6.3. TEMPORARY FACILITIES (if applicable): The Contractor may provide his own office facilities/fencing; coordinate and obtain advance approval from the COR. Submit a location plan of temporary facilities indicating requested utility connections. Provide and maintain suitable sanitary facilities within the construction limits of the contract.
Dispose of sanitary waste in accordance with the applicable laws, and local regulation at no cost to the Government.
17.6.4. CONTRACTOR FURNISHED EQUIPMENT: Equipment is subject to the inspection and approval of the COR, prior to and during the life of the contract.
17.7. CONTRACTOR’S PRODUCTION REPORT: Complete the reports weekly unless otherwise requested by the Contracting Officer. Reports at a minimum shall include:
17.7.1. Worker hours by classification, move-on and move-off of construction equipment furnished by the prime, subcontractor or the Government, and materials and equipment delivered to the site.
17.7.2. Safety meetings, checks and inspections.
17.7.3. Disposition of Construction Waste Material (See 17.6.2)
17.7.4. Design and Construction Issues: Including, but not necessarily limited to:
17.7.4.1. Check all Contract Documents for correctness and correlation. If the Contractor notes any discrepancy or ambiguity; immediately notify the assigned COR.
17.7.4.2. Examine the work site as to conditions affecting the work. Field verify the site and scope of work, including but not limited to the measurement and location of all significant items required to perform the work. Failure by the
Contractor to familiarize oneself with available information regarding these conditions prior to bid shall not relieve the Contractor from the responsibility of successfully completing the work.
17.8. CLEANING / REMOVAL/ SALVAGE and DISPOSAL OF WASTE:
17.8.1. Cleaning project area of materials and rubbish, resulting from the contractors work is the property and responsibility of the contractor. Keep the premises free of debris, accumulation of waste materials, rubbish, tools and all surplus materials at all times.
17.8.2. Generated Waste shall be removed from Government property, during and before the completion of the project by the contractor or contractors
17.8.3. Salvage, report and submit with each invoice the amount (by weight) and type of materials salvaged for sale, reused and or recycled. Provide destination, means of transportation, cost of transportation and handling, tipping fee saving and revenue generated for each material.
17.8.4. Disposal of generated waste from project should occur during and before the completion of the project, with all generated debris removed from Government Property upon completion of project. The Contractor shall report/submit with each invoice the amount of waste (by weight) and type of waste materials disposed of in a landfill or incinerator, the tip fee per ton, and the total cost of disposal including transportation costs, container rental costs, etc.
18. WASTE MANAGEMENT: Contractor shall reduce, recycle or salvage as much waste material as possible with a goal of diverting at least 50% of construction waste from landfill. Address waste reduction, recycling and salvage.
19. INSPECTION AND ACCEPTANCE REQUIREMENTS: All work is subject to inspection during the work and upon completion of the work. Any corrective discrepancies need to meet the satisfaction of the Government prior to presenting an invoice for payment. At the 75% completion point, the assigned COR will conduct a RED ZONE checklist review with the Contractor.
19.1. POST- CONSTRUCTION SUBMITTALS:
19.1.1. Shop Drawings
19.1.2. Shop order tech manual
19.1.3. As-Built Drawings (if applicable).The contractor shall provide engineering as-built drawings to reflect all changes to new electrical/mechanical equipment or utility configurations. One hard copy of the drawings and an electronic copy in the latest government version of AutoCAD shall be provided.
19.1.4. Operation and Maintenance Manual (if applicable): The Contractor shall provide three complete sets of Operations and Maintenance Manuals (O&MM) for the system or systems. O&MM sections shall include, at a minimum, the following sections:
General Description, Detailed Description, Systems Description, Operation (all modes), Maintenance, Troubleshooting, Manufacturers Literature (catalog cuts), and Bill of Material.
19.2. WARRANTY:
19.2.1. Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair.
19.2.2. For warranted items, furnish the manufacturers’ original written warranty accompanied by a copy of the supplier’s receipt showing place of purchase, telephone number of supplier, address, delivery order number if applicable, and ticket number.
20. TRANSMITTER REQUIREMENTS: The base policy concerning the use of transmitters such as radios, cell phones, etc., must be adhered to by all Contractor personnel. They must also obey Emissions control (EMCON) restrictions.
21. HAZARDOUS MATERIAL EXCLUSIONS: Notwithstanding any other hazardous material used in this contract, radioactive materials or instruments capable of producing ionizing/non-ionizing radiation (with the exception of radioactive material and devices used in accordance with USACE EM 385-1-1 such as nuclear density meters for compaction testing and laboratory equipment with radioactive sources) as well as materials which contain asbestos, mercury or polychlorinated biphenyls, di-isocynates, lead-based paint are prohibited. The Contracting Officer, upon written request by the Contractor, may consider exceptions to the use of any of the above excluded materials. The Radiation Safety Officer (RSO) must be notified prior to excepted items of radioactive material and devices being brought on base.
************************END OF CONTRACT*****************************