L-3_Contractor_Performance_Assesment_Questionnaire_.doc

DOC document 51 KB Posted

Attached to
Fleet Weapons Support (FWST) Federal contract opportunity
Solicitation number
N6893617R0011
Issued by
Department of the Navy Naval Air Systems Command Naval Air Warfare Center

About this file

L-3 Contractor Performance Assesment Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Fleet Weapons Support (FWST), newest first.
File Type Posted
L-1_Cost_Spreadsheet_2.xls XLS spreadsheet
17-R-0011_Solicitation_5.doc DOC document
L-2_Past_Performance_Information_Form_2.pdf PDF
Q&A_Document.doc DOC document
N68936-17-R-0011,_Amendement_01,_Conformed_Copy.pdf PDF
17-R-0011_Solicitation.doc DOC document
L-2_Past_Performance_Information_Form.pdf PDF
L-3_Contractor_Performance_Assesment_Questionnaire_.doc DOC document
L-1_Cost_Spreadsheet.xls XLS spreadsheet
Exhibit_1-_CDRLs.pdf PDF
Exhibit_1-_CDRLs.pdf PDF
L-1_Cost_Spreadsheet.xls XLS spreadsheet
L-2_Past_Performance_Information_Form.pdf PDF
17-R-0011_Solicitation_2.doc DOC document
Past_Performance_Information_Form.pdf PDF
Cost_Spreadsheet.xls XLS spreadsheet
L-4_Fully_Burdened_Labor.xls XLS spreadsheet
17-R-0011_Solicitation_-_Draft.docx DOCX document
Contractor_Performance_Assessment_Questionaire.docx DOCX document
CDRL.pdf PDF
Show all 20

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section L, Attachment L-3

Solicitation N68936-17-R-0011

Contractor Performance Assessment Questionnaire (CPAQ) Within 2 weeks from receipt of this questionnaire return this form to Contract Specialist Eric Price, at eric.m.price@navy.mil.

1. CONTRACTOR IDENTIFICATION

a. Contractor: _______________________

b. Program Title: _____________________

c. Contract Number: __________________

d. Type of Contract: ____________ Percent Complete: ____________

e. Award Fee (if applicable): _________ Percent of Award Fee Received: _________ Note: Whether identified or not, if you have any knowledge of other contracts for the identified contractor, you are requested to complete a questionnaire for each contract or subcontract similar to this acquisition.

2. RESPONDENT IDENTIFICATION

a. Name: ________________________________________________

b. Agency: _______________________________________________

c. Position: _______________________________________________

d. Relation to Program: _____________________________________

e. Phone/Fax Number/Email Address: _________________________

f. Date Questionnaire Completed: ____________________________

3. PROGRAM CHARACTERISTICS

3a. Please provide a short description of the subject contract.

3b. Please check those activities, which are applicable to your program:

(1) NAVAIR and NAVSEA Weapons

a. AARGM__

b. HARM__

c. JAGM__

d. Hellfire__

e. Maverick__

f. Rockets__

g. Guns__

h. Sidewinder__

i. JSOW__

j. Harpoon__

k. SLAM__

l. AMRAAM__

m. JDAM__

n. Laser Guided Bombs__

o. Rolling Airframe Missile (RAM)__

p. Evolved Sea Sparrow Missile (ESSM)__

q. Standard Missile__

(2) Logistics Elements

a. Product Support Management___

b. Supply Support___

c. Packaging, Handling, Storage, and Transportation (PHS&T)___

d. Maintenance Planning and Management___

e. Design Interface___

f. Sustaining Engineering___

g. Technical Data and Configuration Control___

h. Computer Resources___

i. Facilities and Infrastructure ___

j. Support Equipment__

k. Training and Training Support__ l.

Administration and Project Oversight__

(3) Subcontractor Management (if proposed subcontractors)

a. Ability to fund subcontractors and how that process ensures timely subcontractor payments with no loss of productivity to the Government.____

b. Experience assembling teams, selecting subcontractors, maintaining subcontractor relationships, communication information to the subcontractor, managing subcontractor performance, and resolving problems.____

4. PERFORMANCE LEVELS

4.1 PERFORMANCE GRADES (Use these grades to provide the overall rating where requested below).

Exceptional - Performance meets contractual requirements and exceeds many to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.

Very Good - Performance meets contractual requirements and exceeds some to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.

Satisfactory - Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.

Marginal - Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully implemented.

Unsatisfactory - Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

4.2 QUESTIONS

4.2.1. TECHNICAL AND QUALITY PERFORMANCE

a. What kind of technical performance problems or strengths were experienced by the contractor?

b. What was the cause of these technical problems or strengths?

c. To what extent have corrective actions been taken to correct problem(s) identified above and to what extent have the corrective actions been effective? Describe the progress made to date. Also explain to what extent the corrective actions addressed the root cause of the problem(s) and led to systemic improvement such that similar problems would not reoccur.

d. Overall, the contractor's technical performance is rated ________________________.

Exceptional Very Good Satisfactory Marginal Unsatisfactory

4.2.2: SCHEDULE PERFORMANCE

a. What kinds of delivery/schedule problems or strengths were experienced by the contractor?

b. What was the cause of these delivery/schedule problems or strengths?

c. To what extent have corrective actions been taken to correct problem(s) identified above and to what extent have the corrective actions been effective? Describe the progress made to date. Also explain to what extent the corrective actions addressed the root cause of the problem(s) and led to systemic improvement such that similar problems would not reoccur.

d. Overall, the contractor's delivery/schedule performance is rated _________________.

Exceptional Very Good Satisfactory Marginal Unsatisfactory

4.2.3. COST PERFORMANCE

a. What kinds of Cost problems or strengths were experienced by the contractor?

b. If the contractor experienced an overrun please provide the percentage. _________

c. What was the cause of these Cost problems or strengths?

d. If available, provide earned value cost performance measures including indices for cost efficiency (CPI) and schedule efficiency (SPI). Based on this information, please provide a narrative assessment of their performance.

e. To what extent have corrective actions been taken to correct problem(s) identified above and to what extent have the corrective actions been effective? Describe the progress made to date. Also explain to what extent the corrective actions addressed the root cause of the problem(s) and led to systemic improvement such that similar problems would not reoccur.

f. Overall, the contractor's Cost performance is rated ________________________.

Exceptional Very Good Satisfactory Marginal Unsatisfactory 4.2.4

MANAGEMENT

4.2.4.1

MANAGEMENT RESPONSIVENSS

What was the contractor’s record of timeliness, completeness and quality of problem identification, corrective action plans, proposal submittals (especially responses to change orders, engineering change proposals, or other undefinitized contract actions), the contractor's history of reasonable and cooperative behavior, effective business relations, and customer satisfaction?

4.2.4.2

SUBCONTRACT MANAGEMENT

What was the contractor’s success with timely award and management of subcontracts, including whether the contractor met or exceeded small business, small disadvantaged business, small business HUBZone, veteran-owned small business, service disabled veteran owned small business, women-owned small business participation and subcontracting goals?

4.2.4.3

PROGRAM MANAGEMENT AND OTHER MANAGEMENT

a. To what extent does the contractor discharge their responsibility for integration and coordination of all activity needed to execute the contract; identify and apply resources required to meet schedule requirements; assign responsibilities for tasks/actions required by contract; and communicate appropriate information to affected program elements in a timely manner?

b. What were the contractor’s risk management practices, especially the ability to identify risks and formulate and implement risk mitigation plans?

c. If applicable, identify and provide information on any other areas that are unique to the contract, or that cannot be captured elsewhere under the Management Assessment.

4.2.4.5 Overall Management Assessment

Overall, the contractor's management performance is rated____________________.

Exceptional Very Good Satisfactory Marginal Unsatisfactory

4.2.5 Small Business Utilization

If this contract contains a small business subcontracting goal, assess compliance with all terms and conditions in the contract relating to Small Business participation (including FAR 52.219-8, Utilization of Small Businesses and FAR 52.219-9, Small Business Subcontracting Plan (when required). Assess any small business participation goals which are stated separately in the contract Assess achievement on each individual goal stated within the contract or subcontracting plan including good faith effort if the goal was not achieved. Check one of the boxes below, noting however when applying the rating definitions for this assessment equate “small business goals” to requirements.

Exceptional Very Good Satisfactory Marginal Unsatisfactory

4.2.6. OTHER. Is there any other information regarding this acquisition that you think would be helpful to our evaluation? If so please explain. Examples of additional information that could be helpful to our evaluation include information on (1) problems or strengths with regard to key personnel and (2) the kind of business relationship problems or strengths with regard to management of subcontracts, cooperation with business partners/customers, customer satisfaction, etc.

4.3 SUMMARY: If you had the option, knowing what you know today, would you (pick one), 1) definitely would not, 2) probably would not, 3) might, 4) might not, 5) probably would, 6) definitely would award this contract to this contractor, given the choice? Please explain.

Signature _____________________________________________ Date _____________

Please note that electronic signatures are acceptable. An e-mail from the originator of this document will suffice. Signatures (electronic or hand written) verify that the signatory completed this form and agrees with the information contained within it.

PAGE

File details come from the government source that posted it.