This document contains an amendment to a federal solicitation and the related federal contract opportunity. The amendment provides responses to industry questions about the solicitation and makes minor revisions. Key details include:

  • The solicitation is for operational and logistics support services for open ocean special projects for the Naval Undersea Warfare Center Division in Newport, Rhode Island. The contract will be a cost-plus-fixed-fee, indefinite delivery/indefinite quantity agreement for a period of five years.

  • The amendment answers nine questions from industry, clarifies that a facility clearance is not required, and extends the closing date for proposals to March 23, 2020. It also revises the description for CLIN 0002 to specify that offerors must provide the maximum fee rate charged for task orders.

  • The related federal contract opportunity provides additional context, stating the solicitation number, pre-solicitation status, description of services sought, NAICS code of 541990, $15 million small business size standard, and point of contact for any questions.

View the file

Other files

File Type Posted
N66660420R02340003.pdf PDF
N66660420R02340001.pdf PDF
Attachment #2 - List of Key Personnel.pdf PDF
Exhibit A_CDRLS and Addendum.pdf PDF
N66660420R0234.pdf PDF
Attachment #1 - PRS Table.pdf PDF
N6660418R0217_DRAFT_Statement_of_Work.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See Page 2

1. CONTRACT ID CODE PAGE OF PAGES

U 1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Mar-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6660420R0234

X 9B. DATED (SEE ITEM 11)

12-Feb-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Mar-2020

CODE

NAVAL UNDERSEA WARFARE CTR. DIV., NPT.

CHRISTOPHER R. HEBERT, CODE 0223

CONTRACTS DEPARTMENT

1176 HOWELL STREET, BLDG. 1258

NEWPORT RI 02841

N66604 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6660420R0234

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The following have been modified:

GENERAL INFORMATION

Distribution: FILE, KR, NUWC 01, DCMA:TBD, DFAS: TBD, COR: TBD, PI: TBD, TDAA: TBD

NUWCDIVNPT PID#: N66604-20-RFPREQ-NPT-70-0004

NUWCDIVNPT POC: Christopher Hebert (Phone: (401) 832 – 7168; Email: christopher.r.hebert@navy.mil)

Amendment 0002:

The purpose of this amendment is to answer industry questions:

Industry Question(s) Government Answer(s) Question #1: Is it the intention of the government for offerors to insert the minimum obligated amount of $1,000.00 in Section B for CLIN 0001 although this conflicts with the C‐242‐ H002 POST AWARD MEETNG clause?

Response #1: Yes, offerors shall insert $1,000.00 as the CLIN 0001 FFP.

This does not conflict with Clause C-242-

H002 POST AWARD MEETING

(NAVSEA) (OCT 2018).

Question #2: D‐211‐H001 clause references handling classified reports in accordance with the NISPOM. Will an FCL be required to perform this contract?

The existing one requires one.

Response #2: Clause D-211-H001

PACKAGING OF DATA (NAVSEA) (OCT

2018) includes instructions for both unclassified data and classified data. The portion of the clause pertaining to unclassified data is applicable to this solicitation. A Facility Clearance is not required.

Question #3: Page 35, (b) Contract Personnel Administration references utilizing a Common Access Cards (CACs), obtaining a CAC at a minimum requires a National Agency Check with Inquiries (NACI). Will a clearance be required for the STR?

Response #3: A clearance is not required for the STR.

Question #4: Is it the intention of the government when offerors fill‐in respective given CLIN amounts, it will be accepted in the form as the “Completed RFP” as referenced in 1.3c Proposal format table? Additionally, Response #4: The contractor shall provide the Maximum Fee Rate in Section B, CLIN 0002.

Yes, “completed RFP” in the table in 1.3(c) and “fill-in information for all does the part “(e) Offerors shall provide fill‐in information for all clauses/provisions that require it” correlate as the “Completed RFP” referenced in the 1.3c Proposal format table?

clauses/provisions” in 1.3(e) are referring to offerors being required to complete all fill-ins on the SF-33 and submit it with the proposal.

Question #5: Are each Factors to be submitted separately?

Response #5: Responses to all factors are to be submitted as “Proposal Part I-Technical” as stated in the table in section 1.3(c) of INSTRUCTIONS TO OFFERORS in section L.

Question #6: For this section, (Factor 4), is it the intention of the government to receive the filled‐in section “(a) Maximum Fee Rate” as part as the “Completed RFP” or as a separate volume/document?

Response #6: The contractor shall identify the Maximum Fee Rate in CLIN 0002.

A separate volume/document is not required in accordance with 1.3 Proposal Format.

Question #7: PWS 4.2 Aircraft Services: Of the 12- 15 exercises annually, how many do the rotary and fixed wing aircraft typically participate in?

Response #7: The exact required number of rotary and fixed wing aircrafts utilized are unknown at this time. In FY 18 and FY 19, 11 of 20 task orders were for spotter plane services.

Question #8: Deadline for Questions:

Will the Government consider extending the deadline for questions to 02 March 2020 to allow for further proposal development?

Response #8: The Government will not extend the deadline for receipt of questions. In accordance with Clause L-

215-H007 SUBMISSION OF

QUESTIONS BY OFFERORS –

ALTERNATE I (NAVSEA)

(MAR 2019) questions may be submitted after the deadline but the Government makes no guarantee that questions received after the date will be answered.

Question #9: Posting Q&As: Will the Government be posted questions received and answers issued on the Beta SAM website?

Response #9: In accordance with Clause L- 215- H007 (c) All proposed questions and answers will be posted to Beta.SAM.gov via an amendment to the solicitation.

SECTION B-

As a result of industry questions the extended description for CLIN 0002 is revised as follows:

FROM:

Operational and Logistics Support

CPFF

Operational and Logistics Support for Ocean Projects in accordance with the Statement of Work.

TO:

Operational and Logistics Support

CPFF

Operational and Logistics Support for Ocean Projects in accordance with the Statement of Work.

The Contractor agrees that the maximum Fixed Fee rate that shall be charged against all Task Orders (excluding the Post Award Conference) Task Orders under this contractor shall not exceed (______%).

The closing date and time are not extended as a result of this amendment.

All other solicitation terms and conditions remain unchanged.

Amendment 0001:

The purpose of this amendment is to:

1. Extend the closing date and time from 02:00 PM EST 16 March 2020 to 02:00 PM EST 23 March 2020.

All other solicitation terms and conditions remain unchanged.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0002

The CLIN extended description has changed from:

Operational and Logistics Support for Ocean Projects in accordance with the Statement of Work.

To:

Operational and Logistics Support for Ocean Projects in accordance with the Statement of Work.The Contractor agrees that the maximum Fixed Fee rate that shall be charged against all Task Orders (excluding the Post Award Conference) Task Orders under this contractor shall not exceed (______%).

(End of Summary of Changes)