Enviro Testing PWS 20180907.docx

DOCX document 1 MB Posted

Attached to
Enviromental Services for Unmanned Maritime Systems
Solicitation number
N66001-18-T-2006
Issued by

View the file

Other files

File Type Posted
Amend 0002 Ques and Answers.docx DOCX document
Enviromental_Testing_CDRL_20180813.pdf PDF
Enviro_Testing_PWS_20180813.docx DOCX document
Enviro_Testing_PWS_20180813.docx DOCX document
Enviromental_Testing_CDRL_20180813.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT

Unmanned Maritime Systems Support Component Environmental Testing of the MK 18 Mod 2 Unmanned Underwater Vehicle (UUV) System Revised 7 September 2018

INTRODUCTION

Space and Naval Warfare Systems Center Pacific (SSC PAC), San Diego is procuring program services in support of Explosive Ordnance Disposal Unit Expeditionary Mine Countermeasures (EOD ExMCM) companies.

Background The MK 18 Mine Countermeasures Unmanned Underwater Vehicle (MCM UUV) project is in the process of fielding in support of the EOD ExMCM companies. There are two basic vehicles: the MK 18 Mod 1, based on the Hydroid REMUS 100 UUV, and the MK 18 Mod 2, based on the Hydroid REMUS 600 UUV. U.S. naval forces have deployed and operated MK 18 Mod 1 systems for approximately 8 years. Initial MK 18 Mod 2 systems have been operating in the Middle East out of Bahrain since 2012, operated by civilian contractor personnel. These MK 18 Mod 2 systems have been turned over to, and are now being operated by, EOD ExMCM Companies. Additional MK 18 UUV systems have been purchased and delivered in support of an expanding MCM mission in the EOD community. MK 18 operations are accompanied by a host of support equipment such as shelters, launch and recovery systems, maintenance vans, etc.

The baseline Mod 2 UUV is equipped with an EdgeTech Side Look Sonar (SLS) package that addresses MCM Search-Classify-Map (S-C-M). It also comes equipped with a downward-looking video camera, providing imagery beneath the UUV that is used for visual identification of mines during Reacquire and Identify (R-I) mission types.

The MK 18 Mod 2 UUV Block B upgrade includes replacing the MK 18 Mod 2 UUV’s EdgeTech Sonar and Video Camera Payloads with the Small Synthetic Aperture Minehunter Version 2 (SSAM2) Payload, which will provide enhanced performance by increasing resolution and range while adding the possibility of a buried target detection capability.

Another upgrade to the baseline system is the Autonomous Topographic Large Area Survey (ATLAS) Forward Looking Sonar (FLS) and is entitled MK 18 Mod 2A IPOE. The ATLAS FLS is intended to provide a large area coverage capability for IPOE missions as well as in-volume mine detection. The ATLAS FLS is packaged as a field-configurable plug-and-play module for the baseline vehicle Scope The contractor shall provide support for the EOD UUV program under the cognizance of SSC PAC. The contractor shall provide the technical and logistical support necessary to determine if the Equipment Under Test (EUT) listed in Section 3.2 meet the environmental standards and electromagnetic environmental effects (E3) standards listed in Error! Reference source not found.. Specific tasks are outlined in Sections 3.5 through 3.7.

System Description Three unique configurations of the MK 18 Mod 2 UUV are under test; the baseline, Small Synthetic Aperture Minehunter Version 2 (SSAM2), and Autonomous Topographic Large Area Survey (ATLAS). The baseline MK 18 Mod 2 Increment I UUV (Figure 1) is equipped with side scan sonar, a video camera, and a host of other sensors to aid in its primary MCM mission.

Figure 1 Baseline MK 18 Mod 2 UUV A sensor upgrade to the baseline MK 18 Mod 2 includes replacing the MK 18 Mod 2 UUV’s EdgeTech side scan sonar with the SSAM2 payload. This sensor provides enhanced performance compared to the baseline EdgeTech by increasing sonar resolution and range while adding an additional low frequency sonar. The SSAM2 configured MK 18 Mod 2 UUV is pictured in Figure 2; note this figure is not to scale relative to other UUV images.

Figure 2 SSAM2 Configured MK 18 Mod 2 UUV A second sensor upgrade to the baseline MK 18 Mod 2 system is the ATLAS Forward Looking Sonar (FLS). This sensor provides a large area coverage capability for Intelligence Preparation of the Operational Environment (IPOE) missions as well as in-volume mine hunting capability. The ATLAS FLS is packaged as a field-configurable plug-and-play module for the baseline vehicle that is installed in front of the EdgeTech sidescan payload section (Figure 3).

Figure 3 ATLAS Configured MK 18 Mod 2 UUV

Detailed System Description The MK 18 Mod 2 UUV system is comprised of seven groups of equipment: the UUV group, the UUV auxiliary group, the UUV information technology (IT) group, the mission support group, the power distribution group, the UUV outfitting spares, and the boat group.

The UUV group contains the hull sections that comprise the UUV itself. Each MK 18 Mod 2 system consists of three individual vehicles, and each vehicle can be broken down into four sections for transportation. The front nose section of the vehicle, the dry payload section, the acoustic doppler current profiler/main housing, and the tail components are assembled using a v-band clamp system.

The MK 18 Mod 2 UUV is equipped with a host of sensors, which provide data that is critical to complete a variety of missions. Primary system sensors include an EdgeTech side scan sonar, downward looking video camera, ADCP, beam attenuation meter (BAM) to measure turbidity, and a conductivity temperature depth (CTD) sensor. The vehicle also contains subsystems to support navigation, communications, and propulsion.

The UUV auxiliary group includes auxiliary equipment required to operate the vehicle. This includes the surface communication stations, underwater transponders, ruggedized laptops, underwater communication systems, antennas, and gateway buoys. Equipment is packed into six containers for transportation.

The UUV information technology (IT) group includes all the IT equipment required to operate the vehicle. This includes the Common Operator Interface (COIN) laptop, monitors and associated computer peripherals. Also included in this group is a data archival unit (DAU) utilized for mission data set storage. The MK 18 Mod 2 sensors can produce a large quantity of data, and the DAU provides the storage space necessary to retain this data during an operation. Upon concluding an operation, the data stored on the DAU is transferred to a storage system located at the base of operations, and the DAU is cleared for the next operation.

The mission support group includes a few large pieces of support equipment required to operate and maintain the vehicle. The expandable small airmobile shelter (ESAMS) is used for mission planning and data analysis, and can be used for ship-based or shore-based mission monitoring. Figure 4 shows the ESAMS in a shipping configuration and Figure 5 shows it in an operational configuration.

Figure 4 MK 18 ESAMS Portable Shelter Transportation Configuration

Figure 5 MK 18 ESAMS Portable Shelter Operational Configuration The power distribution group includes a 56.6 kW generator, a 20 kW generator, a shore-side power distribution unit (PDU), a transformer PDU for afloat operations, and all the associated power generation and transmission cable equipment required to operate the equipment in an expeditionary manner.

The MK 18 Mod 2 system boat group primarily includes the RHIB used to launch and recover the UUVs. The RHIB is an 11-meter Zodiac that completes launch and recovery (L&R) with a side launch and recovery system (SLRS); also part of the boat group. Figure 6 shows a trailered RHIB with the SLRS carrying a MK 18 on the starboard side. The SLRS consists of an A-frame with trolleys and rigging for lifting, launching, and recovering the vehicles over the side of the 11-meter RHIB. The specialized SLRS also includes shock-isolating cradles to secure and protect the vehicles during transit. A RHIB equipped with the SLRS is capable of simultaneously operating two MK 18 Mod 2 UUVs.Figure 6 MK 18 Mod 2 RHIB

SSAM2

The SSAM2 payload consists of two Synthetic Aperture Sonar (SAS) systems: a high- frequency (HF) SAS and a low-frequency (LF) SAS. The LFSAS (also referred to as BBLF for Broadband Low Frequency) extends existing PMS 408 Explosive Ordnance Disposal (EOD) capabilities by providing detection and classification for heavily scoured and some buried targets, while the combination of HF/LF SAS extends their capability to achieve the original objective parameters for false alarm rejection in their requirements documents. The SAS is designed to provide detection and classification capabilities of proud and buried targets in the highly cluttered, dynamic, and harsh environment of the SW and VSW zones.

The SSAM2 systems are also comprised of auxiliary equipment to support their missions and maintenance, and computer software for pre-mission programming. Post-processing of MK 18 Mod 2 UUV system data is accomplished using a Data Control Processor (DCP) server with Network Embedded Real-time Distributed Synthetic Aperture Sonar (NERDS) beamforming and image processing software developed by the Naval Surface Warfare Center Panama City Division (NSWC PCD).Figure 7 SSAM2 Sensor System Configuration

Figure 8 SSAM2 Auxiliary Equipment

ATLAS

The ATLAS system refers to the ATLAS FLS module installed on an MK 18 Mod 2A UUV, the Post Mission Analysis (PMA) Workstation, and the Mission Management Laptop (MML), with transit cases, as depicted in Figure 9. Additionally, the PMA Workstation and MML include a classified and unclassified hard drive transfer station, respectively.

Figure 9 MK 18 Mod 2A IPOE UUV System Level Diagram The MK 18 Mod 2A IPOE UUV consists of the ATLAS FLS module replacing the nose section of the MK 18 Mod 2A UUV system. This will include the subsections of the nose, wet payload, and forward endcap. Additionally, the system includes the Post-Mission Analysis (PMA) workstation and Mission Management Laptop, plus transit cases.

GENERAL REQUIREMENTS

Non-Personal Services The Government shall neither supervise contractor employees (or any of their partnered sub-contractors) nor control the method by which the contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Procuring Contracting Officer (PCO) immediately.

Business Relations The expectation for this effort for the contractor Program Manager (PM) and Test Engineer coordinate execute and formally report a consolidated final report to the government. The contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The contractor shall manage the timeliness, completeness, and quality of problem identification. The contractor shall provide corrective action plans, proposal submittals, timely identification of issues, and effective management of subcontractors. The contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all contractor personnel. The contractor shall coordinate with other contractors to formulate the best common solutions to meet collective requirements. During formal testing, a government representative and contract operator will be observing and performing vehicle operational check-outs in between testing events.

Contract Administration and Management The following subsections specify requirements for contract, management, and personnel administration.

Contract Administration and Management The contractor shall establish processes and assign appropriate resources to effectively administer tasks outlined in this performance work statement (PWS) in San Diego, and other locations as assigned. The nature of this contract requires a close working relationship between Government and contractor personnel. The contractor shall assign work effort and maintain proper and accurate time keeping records of personnel assigned to work on the requirement. The contractor shall respond to Government requests for contractual actions in a timely fashion.

Personnel Administration The contractor shall provide all administrative and management support for their personnel, as required. These support functions include, but are not limited to:

· Pay and personnel support

· Travel and TAD management

· Training and certification

· Personnel administration and record keeping

· Connectivity and accessibility, including cell phones, email addresses and computer support Subcontract Management The contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor performance on this requirement. The prime contractor will manage work distribution to ensure there are no organizational conflict of interest (OCI) considerations.

Contractor Personnel, Disciplines, and Specialties Contractor Personnel Qualifications.

The contractor shall provide properly trained and qualified people to perform the tasks covered by this PWS. The contractor is responsible for obtaining and maintaining all personnel training, qualifications, clearances, pass/access, or other individual requirements. The contractor shall match personnel skills to the work or task with a minimum of under/over employment of resources. Qualification and training records shall be maintained by the contractor and be available for review by Government personnel.

Contractor Identification in the Government Workplace.

All contractor and subcontractor personnel shall be required to wear company picture identification badges so as to distinguish themselves from Government employees. When conversing with Government personnel during business meetings, over the telephone, or via electronic mail contractor and subcontractor personnel shall identify themselves as such to avoid situations arising where sensitive topics might be better discussed solely between Government employees. Contractors and subcontractors shall identify themselves on any attendance sheet or any coordination documents they may review. Electronic mail signatures shall identify company affiliation.

Contractors shall be required to wear government-issued identification as specified. Both an SSC PAC picture badge and a Department of Defense (DoD) Common Access Card (CAC) are required to work on-site at SSC PAC.

PERFORMANCE REQUIREMENTS

Basic Requirements The contractor shall furnish all work, management, supervision, labor, and materials necessary to ensure the effective and efficient performance of functions identified throughout this PWS, which make up this requirement. The contractor shall provide flexible, responsive, and high quality services and support. The contractor will conduct travel and reviews that are necessary to ensure the effective and efficient performance of functions identified throughout this PWS, which make up this requirement.

The contractor shall maintain accurate and up-to-date training and qualification completion records, available for government review at any time.

The contractor shall provide environmental and E3 testing support to the MK 18 program. Tasks may include, but are not limited to:

1. Preform the environmental and E3 tests listed in Section 3.2

2. Collaborate with SSC PAC test personnel on test plan creation.

3. Prepare resulting test reports for the required tests.

Products must be considered “final” without editing or re-work by the Government representative or other end-user.

Testing has been divided into three segments according to the type of facility and testing equipment that is required: thermal, shock and vibration, and electromagnetic environment effects (E3).

Specific Tests to be Conducted

The contractor shall conduct the tests listed in Table 1 to the specified thresholds in accordance with the specified MIL STD. Test order will be determined by facility availability and funding.

Table 1 List of Tests

Test #
Test Name
Test Parameters
MIL STD
Pass Criteria
1
Cold Temperature Storage
-20°C (-4°F) for 72 hours
810 G w/ Change 1 – 502.6
System must operate and show no signs of significant internal or external physical damage after test.
2
Hot Temperature Storage
30°C (86°F) to 62.8°C (145°F) over 24 hour cycles , 7 times
810G w/ Change 1 – 501.6
System must operate and show no signs of significant internal or external physical damage after test.
3
Transportation Shock
Highways, mission/field transport, aircraft, and sea vessels
810G w/ Change 1 – 516.7 Procedure IV Material to be Packaged
System must operate and show no signs of significant internal or external physical damage after test.
4
Transportation Vibration
Highways, mission/field transport, aircraft, and sea vessels
810G w/ Change 1 – 514.7 Annex C, Test I
System must operate and show no signs of significant internal or external physical damage after test.
5
Radiated Emissions, Electric
10 kHz to 18 GHz
461G – RE102
System/component must remain below emissions thresholds given in MIL-STD-461G [8].
6
Radiated Susceptibility, Electric
2 MHz to 18 GHz
461G – RS103

System/component must remain below emissions thresholds given in MIL-STD-461G [8].

7
Conducted Emissions, Power Leads
120 Hz – 10 kHz
461G – CE101
System/component must remain below emissions thresholds given in MIL-STD-461G [8].
8
Conducted Emissions, Power Leads
10 kHz – 10 MHz
461G – CE102
System/component must remain below emissions thresholds given in MIL-STD-461G [8].
9
Conducted Susceptibility, Power Leads
50 Hz – 150 kHz
461G – CS101
System/component must remain below emissions thresholds given in MIL-STD-461G [8].
10
Conducted Susceptibility, Bulk Cable Injection, Interconnects, and Power Leads
10 kHz – 200 MHz
461G - CS114
System/component must remain below emissions thresholds given in MIL-STD-461G [8].
11
Conducted Susceptibility, Damped Sinusoidal Transients, Power Leads
10 kHz – 100 MHz
461G – CS116
System/component must remain below emissions thresholds given in MIL-STD-461G [8].

Equipment Under Test

As detailed in the System Description section, the MK 18 Mod 2 system is comprised of a large variety of equipment. Portions of the system have been previously evaluated against environmental requirements, and thus will not be included in this test. Table 2 lists only equipment that is included in this test event. Each test listed in Sections 3.5 – 3.7 will further detail the equipment required for each test procedure.

Table 2 List of equipment under test

Item
System Group
Surface Communications Station (SCS)
UUV Auxiliary Group
SCS Accessories
UUV Auxiliary Group
Power Cables
UUV Auxiliary Group
Topside Communications Mast Bottle
UUV Auxiliary Group
Communications Gateway Buoy
UUV Auxiliary Group
Charging Container
UUV Power/Charging Group
Resource Control Unit (RCU)
UUV Power/Charging Group
Transformer Power Distribution Unit (TPDU)
UUV Power/Charging Group
Spider Box
UUV Power/Charging Group
COIN PMA Dell 6800 Laptop
UUV IT Group
COIN PMA Dell Monitor
UUV IT Group
SSAM2 PMA Station
UUV IT Group
SSAM2 PMA UPS
UUV IT Group
SSAM2 DAU
UUV IT Group
SSAM2 Hard Drive Docking Station
UUV IT Group

Performance Requirements The contractor shall provide a monthly progress report summarizing delivery order status. This report shall include services provided during the report period, significant accomplishments or events, the status of any on-going efforts, including any problems or areas of concern, areas where government intervention is required and upcoming events. Financial status shall be provided to include funds expended during the reporting period and during the order to date, as well as funds remaining on the order. Expenditures shall be reported for labor by category/hours, materials, travel, and ODC.

The contractor shall develop appropriate test procedures. Testing will be in accordance with the applicable MIL STD. A schedule for the work to be carried out will be delivered following discussions with the Government Technical Point of Contact (TPOC) and Engineering Test Lead.

Component Level Tests The first segment of environmental testing will be thermal testing of individual system components in operational and transportation configurations to determine the effects of extreme temperatures on system safety, integrity, and performance as detailed below. The tests will be conducted in accordance with the MIL standard cited.

Thermal:

Test 1-2: Transportation and Storage Temperature Objective This test is to determine if the MK 18 Mod 2 and its auxiliary components can operate properly after being transported/stored in its storage configuration (in the un-powered state) in harsh temperatures. The Performance Specification defines the storage temperature as a range from -4°F (-20°C) to 145°F (63°C).

Procedure The hot temperature storage of the system will be tested in accordance to MIL-STD-810G, Method 501.5, Procedure I, while the low temperature storage will be tested in accordance to MIL-STD-810G, Method 502.5, Procedure I. The test articles listed in Table 3 and Table 4 will be placed inside their respective transit cases and then placed inside the temperature chamber. The temperature will then be raised or lowered to the test temperature at no more than 5°F/min. The hot temperature exposure for this test will be a 24-hour cycle over the temperature range of 86°F to 145°F. The temperature will be cycled for a total of seven cycles. The cold temperature exposure for this test will be three 24-hour cycles at a constant low temperature of -20°F.

After the equipment listed in Table 3 and Table 4 have experienced all cycles of the respective test, the components will be returned to room temperature at no more than 5°F/min. Once room temperature is reached, the equipment will be removed and let sit for 2 hours to ensure steady state temperature has been reached and any latent heat is dissipated. A physical audit will be conducted to determine if any damage or material distortion has been caused by the temperature tests.

All test articles will then be unpacked, requiring a workbench of at least 15 feet, and a complete system checkout (pre-mission checkout) of the auxiliary equipment will be conducted.

Table 3. Cold Temperature Storage - Test 1 Test 1: Cold Temperature Storage: MIL STD 810-G 502.5 Procedure I [-20 C (-4 F) for 72 Hours]

Transport Case
Included Test Articles
Case Length (in)
Case Width (in)
Case Height (in)
Case Weight (lb.)
Cables
Cables
N/A
N/A
N/A
25
PMA Monitor
PMA Monitor
27.5
24
8
10
SSAM 2 HD Docking Station
SSAM HD Docking Station
24
16
28
15
Rack Assembly Workstation-DCP
SSAM DCP/COIN Workstation
37
26
20
200
Rack Assembly UPS
SSAM UPS
37
26
10
150
SSAM DAU Case
SSAM DAU
16
6
12
25
TPDU
TPDU
56
34
47
115
Portable Charging Container
Portable Charging Container
189.32
39.13
39.13
1200
Spider Box
Spider Box
14.25
14.25
14.15
40
RCU
RCU
42
35
60
300

Table 4. Hot Temperature Storage - Test 2 Test 2: Hot Temperature Storage: MIL STD 810-G 502.5 Procedure I [30 C (86 F) to 62.8 C (145 F). 24 hour cycles, 7 times.]

Transport Case
Included Test Articles
Case Length (in)
Case Width (in)
Case Height (in)
Case Weight (lb.)
Cables
Cables
N/A
N/A
N/A
25
PMA Monitor
PMA Monitor
27.5
24
8
10
SSAM 2 HD Docking Station
SSAM HD Docking Station
24
16
28
15
Rack Assembly Workstation-DCP
SSAM DCP/COIN Workstation
37
26
20
200
Rack Assembly UPS
SSAM UPS
37
26
10
150
SSAM DAU Case
SSAM DAU
16
6
12
25
TPDU
TPDU
56
34
47
115
Portable Charging Container
Portable Charging Container
189.32
39.13
39.13
1200
Spider Box
Spider Box
14.25
14.25
14.15
40
RCU
RCU
42
35
60
300

Shock and Vibration: Test 3-4 Test 3-4: Transportation Shock and Vibration Objectives The Transportation Shock and Vibration tests will verify that the test articles can physically and functionally withstand the relatively infrequent, non-repetitive shocks encountered in handling and transportation.

Test 3 will be repeated for the following modes of transportation:

· Truck transportation over US highways

· Mission/field transportation

· Aircraft- Jet

· C-17

· C-5

· Aircraft – Propeller

· C-130

· Watercraft – Navy Ships Procedure The Transportation Shock test will be conducted in accordance with MIL-STD-810G 516.7 Procedure II – “Materiel to be Packaged” [9] using the test articles listed in Table 5. The Transportation Vibration test will be conducted in accordance with MIL-STD-810G 514.7 Annex C, Test I to simulate mission/field transportation including, ground vehicle, fixed wing, and rotary wing aircraft transportation. Test articles will be in a shipping configuration.

Table 5. Transportation Shock - Test 3 Test 3: Transportation Shock: Highways, mission/field transport, aircraft, and sea vessels. MIL-STD-810G 516.6 Procedure II, Material to be packaged

Transport Case
Included Test Articles
Case Length (in)
Case Width (in)
Case Height (in)
Case Weight (lb.)
SSAM 2 HD Docking Station
SSAM HD Docking Station
24
16
28
15
Rack Assembly Workstation-DCP
SSAM DCP/COIN Workstation
37
26
20
200
Rack Assembly UPS
SSAM UPS
37
26
10
150
SSAM DAU Case
SSAM DAU
16
6
12
25
PMA Monitor
PMA Monitor
27.5
24
8
10
TPDU
TPDU
56
34
47
115
Portable Charging Container
Portable Charging Container
189.32
39.13
39.13
1200
Spider Box
Spider Box
14.25
14.25
14.15
40
RCU
RCU
42
35
60
300

Table 6. Transportation Vibration - Test 4 Test 4: Transportation Vibration: Highways, mission/field transport, aircraft, and sea vessels. MIL-STD-810G 514.6 Annex C, Test I

Transport Case
Included Test Articles
Case Length (in)
Case Width (in)
Case Height (in)
Case Weight (lb.)
SSAM 2 HD Docking Station
SSAM HD Docking Station
24
16
28
15
Rack Assembly Workstation-DCP
SSAM DCP/COIN Workstation
37
26
20
200
Rack Assembly UPS
SSAM UPS
37
26
10
150
SSAM DAU Case
SSAM DAU
16
6
12
25
PMA Monitor
PMA Monitor
27.5
24
8
10
Portable Charging Container
Portable Charging Container
189.32
39.13
39.13
1200
Spider Box
Spider Box
14.25
14.25
14.15
40
RCU
RCU
42
35
60
300

E3 Tests: Tests 5-11 The purpose of the E3 tests is to characterize the electromagnetic (EM) emissions and susceptibility of the Baseline, ATLAS, SSAM, MSE, and support equipment.

Tests 5-6: Radiated Emission and Susceptibility Objectives The data collected will characterize the electromagnetic signatures of the listed equipment using the limits defined in MIL-STD-461G [8] as required by the Performance Specification. Specifically, this event will verify:

· The electric field emitted by the EUT are below the topside limit level for surface ships, defined in Test Method RE102, Radiated Emissions, Electric Field

· The EUT shall not exhibit any malfunction or degradation of performance when exposed to electric fields at the above deck frequency and levels for ships defined in Test Method RS103, Radiated Susceptibility, Electric Field.

Procedures The Radiated Emissions test will be conducted in accordance with MIL-STD-461F Method RE102 – “Radiated Emissions, Electric Field” [3] using the test articles listed in Error! Reference source not found.. Each test article will be powered on at a set distance from the measurement antennas. The measurement receiver will then scan each applicable frequency range and emissions will be plotted.

The Radiated Susceptibility test will be conducted in accordance with MIL-STD-461F Method RS103 – “Radiated Susceptibility, Electric Field” [3] using the test articles listed in Error! Reference source not found.Error! Reference source not found.. Each test article will be powered on at a set distance from the transmission antennas and electric field probe. The system susceptibility will be monitored using a closed circuit television camera. In the event that a susceptibility is identified, thresholding will be performed to identify levels and frequency ranges for all susceptibilities, including the level and frequency of the greatest observed susceptibility.

Table 8. Radiated Emissions, Electric - Test 5 Test 5: Radiated Emissions, Electric: Electric field emissions do not exceed MIL-STD-461G limit 10 kHz to 18 GHz. MIL-STD-461G-RE102

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Number of Power Leads
SCS
16
19
9
33
2
SCS Accessories
24
20
13
32
1
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
2
Gateway Buoy
43
28
21
190
0
PMA Monitor
27.5
24
8
10
2
PMA Laptop
15
16.5
11
8
1
SSAM2 PMA Workstation
37
26
20
200
2
SSAM2 DAU
16
6
12
25
2
SSAM2 HD Docking Station
24
16
28
15
2
SSAM2 UPS
37
26
10
150
1
Portable Charging Container
189.32
39.13
39.13
1200
4
RCU
42
35
60
300
6

Table 9. Radiated Susceptibility, Electric - Test 6 Test 6: Radiated Susceptibility, Electric: System shall not exhibit any malfunction or degradation of performance when exposed to electric fields 2 MHz to 18 GHz. MIL-STD-461G-RS103

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
SCS
16
19
9
33
SCS Accessories
24
20
13
32
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
Gateway Buoy
43
28
21
190
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

Test 7-11: Conducted Emissions and Susceptibility Objectives The secondary objective of this event is to characterize the conducted emissions and susceptibility of the power leads, interconnection cables, and TPDU using the limits and frequencies defined in MIL-STD-461G [9] as required by the Performance Specification using the following tests:

· The conducted emissions in the power leads from the source into the EUT are below the limits at the frequencies defined in Test Method CE101 & CE102, Conducted Emissions, Power Leads.

· The susceptibility of the EUT when the power leads are exposed to test signals at frequencies and levels defined in Test Method CS101, Conducted Susceptibility, Power Leads.

· The susceptibility of the EUT when the power leads are exposed to transient test signals at levels defined in Test Method CS106, Conducted Susceptibility, Transients, Power Leads.

· The susceptibility of the EUT when the power leads and interconnecting cables are exposed to test signals at frequencies and levels defined in Test Method CS114, Conducted Susceptibility, Bulk Cable Injection.

· The susceptibility of the EUT when the power leads and interconnecting cables are exposed to the waveforms and frequencies defined in Test Method CS116, Conducted Susceptibility, Damped Sinusoidal Transients.

Procedures To characterize the conducted emissions of the power leads into the equipment Test Methods CE101, CE102, CS101, CS114, CS116 will be conducted twice over the entire frequency range. Once with the equipment deenergized and once with the equipment powered on and in an operational state.

Table 10. Conducted Emissions, Power Leads - Test 7 Test 7: Conducted Emissions, Power Leads: Conducted emissions on power leads shall not exceed applicable levels at frequencies from 120 Hz – 10 kHz. MIL-STD-461G-CE101

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

Table 11. Conducted Emissions, Power Leads - Test 8 Test 8: Conducted Emissions, Power Leads: Conducted emissions on power leads shall not exceed applicable levels at frequencies from 10 kHz – 10 MHz MIL-STD-461G-CE102

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

Table 12. Conducted Susceptibility, Power Leads - Test 9 Test 9: Conducted Susceptibility, Power Leads: System shall not exhibit any malfunction or degradation of performance when exposed to conducted emissions from 30 Hz – 150 kHz for all power leads. MIL-STD-461G-CS101

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

Table 14. Conducted Susceptibility, Bulk Cable Injection, Interconnects, and Power Leads - Test 10 Test 10: Conducted Susceptibility, Bulk Cable Injection, Interconnects, and Power Leads: System shall not exhibit any malfunction, degradation of performance when exposed to 10kHz - 200MHz. MIL-STD-461G-CS114

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

Table 15. Conducted Susceptibility, Damped Sinusoidal Transients, Power Leads - Test 11 Test 11: Conducted Susceptibility, Damped Sinusoidal Transients, Power Leads: System shall not exhibit any malfunction, degradation of performance when exposed to 10 kHz – 100MHz. MIL-STD-461G-CS116

Test Article
Length (in)
Width (in)
Height (in)
Weight (lbs.)
Mast Bottle w/ Power Adapter
71
18.3
17.1
101
PMA Monitor
27.5
24
8
10
PMA Laptop
15
16.5
11
8
SSAM2 PMA Workstation
37
26
20
200
SSAM2 DAU
16
6
12
25
SSAM2 HD Docking Station
24
16
28
15
SSAM2 UPS
37
26
10
150
Portable Charging Container
189.32
39.13
39.13
1200
RCU
42
35
60
300

SPECIAL REQUIREMENTS

This section describes the special requirements for this effort. The following sub-sections provide details of various considerations on this effort.

Security and Safety

Contractor personnel performing under this task order will be U.S. Citizens or lawful permanent resident (Green Card holder).

Work performed by the contractor requires access to information that is:

|X|UNCLASSIFIED
|_|CONFIDENTIAL
|_|SECRET
|_|TOP SECRET

The contractor will be required to attend meeting classified at:

|X|UNCLASSIFIED
|_|CONFIDENTIAL
|_|SECRET
|_|TOP SECRET

Contractor Furnished Material.

The contractor is responsible for providing equipment necessary to facilitate the completion of the listed tests (e.g., work tables for assembly and testing of UUV components, lifting devices, remote monitoring devices for operational tests).

For the RCU tests (Test 1-11), the contractor shall provide 480 VAC 60 Hz 4-wire 3-phase power and 220V 3-phase power as well.

For all tests the contractor shall provide access to 220V 1-phase power with a NEMA 5-30R type connector in between testing periods for battery charging.

Applicable Documents/References

In the event of a conflict between the text of this PWS, and the specifications/references cited herein, the text of the PWS shall take precedence. Nothing in the documents/references however, shall supersede applicable laws and regulations, unless a specific exemption has been obtained. The following are for reference only, except where invoked for a specific section of this PWS.

a. Performance System Specification for the MK 18 Mod 2 Increment I Unmanned Underwater Vehicle (UUV) 1.0

b. MIL-STD-810G w/ Change 1, Department of Defense Test Method Standard: Environmental Engineering Considerations and Laboratory Tests

c. MIL-STD-461G, Department of Defense Interface Standard: Requirements for the Control of Electromagnetic Interference Characteristics of Subsystems and Equipment

d. MK 18 Mod 2 Increment I UUV Environmental Test Plan with ATLAS and SSAM Addendums

DELIVERABLES

The Contractor shall provide deliverables within the timeframe specified in accordance with the Task Order CDRL. Copies of all deliverables shall be submitted to the Government representative and the COR. The COR is responsible for tracking and acceptance.

1. A001: Monthly Progress Reports. Shall contain content adhering to DID DI-MGMT-80227 to include testing status, services provided, work accomplished, and schedule/cost risks.

2. A002: Contract Summary Report. DI-ADMN-80447A

3. A003: Test Procedure. DI-NDTI-80603A

4. A004: Scientific and Technical Reports. DI-MISC-80711A Delivery Schedule

1. Deliverable A001 shall be due monthly, ten days after the reporting period.

2. Deliverable A002 shall be due no later than 30 days after end of contract.

3. Deliverable A003 shall be due 30 days after contract award.

4. Deliverable A004 shall be due within 30 days of completion of each test event.

(End of SOW) image3.jpeg image4.jpeg image5.png image6.jpeg image7.png image8.jpeg image9.jpg image10.jpg image11.png image1.png image2.png