Duplex_Strainers-Appendix_A.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- Duplex Strainers Federal contract opportunity
- Solicitation number
- N65540-15-T-5418
About this file
Appendix A (Deliverables Matrix)
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N65540-15-T-5418-0001.pdf | ||
| Duplex_Strainers_Q A.docx | DOCX document | |
| Approx._Duplex_Strainer_Inlet_ _Outlet_Dimensions.docx | DOCX document | |
| N65540-15-T-5418_Redacted.pdf | ||
| SOW_-_Duplex_Strainers_(17_Aug_2015).docx | DOCX document | |
| Duplex_Strainers_Appendix_C_-_Spec_8035_0002.docx | DOCX document | |
| Duplex_Strainers_Appendix_D_-_Spec_8036_0003.docx | DOCX document | |
| Duplex_Strainers_Appendix_F_-_Spec_8038_0003.docx | DOCX document | |
| Duplex_Strainers_Appendix_E_-_Spec_8037_0003.docx | DOCX document | |
| CDRLS DUPLEX_STRAINERS_1.PDF |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| CLIN | CDRL | Title | Subtitle / Description | Required Date of Submission / Delivery |
| 0001 | E001 | Design Data and Calculations | As-built Design Datasheet and Dimensions of Each Duplex Strainer | Submit NLT 20 days after completion of manufacture |
| 0002 | A001 | Conference Minutes | Preliminary submittal NLT 7 Days After Conference. Subsequent submittals NLT 7 Days After additional Conferences | |
| 0003 | E002 | Commercial Drawings/Models And Associated Lists | Certified Outline and Detail Drawing of Each Duplex Strainer | Preliminary submittal NLT 15 days prior to Preliminary Design Review or combined PDR/CDR. Final submittal NLT 25 days prior to Final Design Review. |
| 0004 | E003 | Commercial Drawings/Models And Associated Lists | 3-D Solid Model of Each Duplex Strainer (CAD Files) | Submit NLT 25 days prior to Final Design Review |
| 0005 | A002 | Contractor's Progress, Status and Management Report | Submit NLT 30 Days After Contract Award. As required by the SOW in paragraphs 4.8, 4.10, and 4.17.1. | |
| 0006 | E004 | Test Procedures | Test Procedure Documentation | Submit NLT 30 Days Prior To Test |
| 0007 | E005 | Test/Inspection Report | Test Reports | Submit NLT 15 Days After Test Completion |
| 0008 | E006 | Calibration Certificates | Submit NLT 15 days prior to delivery of equipment | |
| 0009 | E007 | Commercial Off the Shelf (COTS) Manuals and Associated Supplemental Data | Installation, Operating, and Maintenance (IO&M) Manuals | Submit NLT 15 days prior to delivery of equipment |
| 0010 | E008 | Special Equipment Tools and Test Equipment List | Submit NLT 30 days prior to delivery of equipment | |
| 0011 | - | Special Tools and Test Equipment | Submit NLT 135 days after contract award | |
| 0012 | E009 | Proposed Spare Parts List | Spare Parts and Price List | Submit NLT 30 days prior to delivery of equipment |
| 0013 | - | Spare Parts and Consumables | Submit NLT 135 days after contract award | |
| 0014 | A003 | Packaging Plan | Preservation, Packaging, and Shipping Procedures | Submit NLT 15 days prior to delivery of equipment |
| 0015 | - | Duplex Strainer 1 (3") - Closed Loop Cooling Water | Submit NLT 135 days after contract award | |
| 0016 | - | Duplex Strainer 2 (12") - Closed Loop Cooling Water | Submit NLT 135 days after contract award | |
| 0017 | - | Duplex Strainer 3 (12") - Closed Loop Cooling Water | Submit NLT 135 days after contract award | |
| 0018 | - | Duplex Strainer 4 (8") - DI Water | Submit NLT 135 days after contract award | |
| 0019 | - | Duplex Strainer 5 (3") - Lube Oil | Submit NLT 135 days after contract award | |
| 0020 | - | Duplex Strainer 6 (6") - Lube Oil | Submit NLT 135 days after contract award |